Professional Documents
Culture Documents
Prerana Dhumale
Contents
Lesson 0: Introduction
SAP PS
SAP PS is a project management tool that assists you throughout all the phases of
your project. Through the high level of integration between SAP PS and other SAP
functions, such as Logistics, Accounting, and Human Resources, SAP PS ensures
that the necessary business processes are handled quickly and efficiently.
Project Types
Internal Projects
Projects financed internally with in the Organization for their New, Expansions, Overheads, R&D
and so on. These project types are:
Overhead Cost Projects (Ex: Maintenance, shutdown and R&D projects)
Capital Investment Projects (Ex: Building a factory, Expanding existing facility)
External Projects
Projects financed from external organizations or Agencies and creating revenue’s to the
executing/undertaking Organization.
Customer Projects (Ex: Building a Cell Tower, building roads and Bridges etc)
Key Functions:
To carry out complex, unique, and high degree of risk activities
in a structured manner.
To monitor dates and schedules.
To monitor costs and revenues.
To Control of budget .
To trigger Billing schedules, cash flow plans.
Resource allocation and monitoring.
To monitor, track and control Project purchases.
To monitor the Project progress w.r.t. Cost, Time, Revenue and
% of completion.
Simulations and Flexible reporting
Approval
PS
Planning
“Pre-Investment” Budgeting
Replacement
investment
Implementation
Retirement
Settlement and
capitalization
Maintenance
and use
Proj. Planning
Create Enquiry Proj. Creation
Budgeting &
Approvals
Create Quotation
Project Close
Create Sales Order
Procurement
Settlement
Billing & Invoicing
Proj. Execution
Delivery
SD
SD PS
Standard WBS
Create Project
Enquiry to Proj.
Standard Network
Vendor Quotations
Release Execution
Project Close
- Internal Order
- IM Program
CO controlling
- Settlement
- Cost Centre
- Position ID
- AR IM
- Budget Distribution
-Sales promotion accounting
- Proj. Creation
Proj - Settlement CC
SD -Sales Campaign
- ETO process - Assembly PP
- Milestone Billing Project Systems processing
MM - reservations PS - Purchasing
- Contract
- Material issue
- Material Value
- Goods receipt
- Invoice receipt MM
- Direct Capitalization -Capitalisation
History
FI
- Invoice receipt - Depreciation
- Revenue recognition - AuC
- Asset balances
AM
- Person Responsible - Order Creation - Financial Statements
- Workflow - Planning
HR - Partner functions
- Confirmation with P - Budgeting
- Order Cost control
M
personnel number - AuC, Fixed Asset
Contents
Lesson 0: Introduction
Depending on the type of project and the monitoring needs, projects in the Project System can
be structured using:
Networks/Activities
We can use either Operative Projects or Standard projects for structuring the Project. Standard
WBS and standard networks allow you to standardize and reuse structures and sequences of
events in a project.
WBS divides the project step-by-step into structure elements, these elements are called
work breakdown structure elements (WBS Elements). The various work packages in the
project are described in individual work breakdown structure elements (WBS elements).
You can further divide these elements at various levels until you reach the level of detail
you require.
Project Definitions
Project Definitions
WBS Elements
Project Definition
WBS Element
CP-0001
Cell Tower
Work Breakdown
Structure
Periodic Processing:
Overheads “WBS Structure”
Settlement
Earned Value Analysis Budget:
Original Budget
Budget Updates
Release Budgets
Availability Control
Execution:
Confirmation
Goods Issue
Resource usage
Commitments:
Purchase Requisition
Purchase Order
Control
Field Key
Simulation
Status Profile
Validation
Substitution
Organization Controlling
Controlling Area Object Class
Company Code Planner Profile
Business Area Budget Profile
Profit center
Plant
Project Profile Settlement Profile
investment Profile
Proj Currency …
Coding Mask
I
Key 0 = number
X= Alphanumerical
4
3
2 1
1. Operative indicators
2. Responsibilities
3. Org. Assignments
5 4.
5.
Controlling Profiles
WBS Dates
6 6. User Fields
1 Hierarchy Graphic
2
Manual
Project Builder
4
3 Incorporate
Copy
= Operative Structure
= Standard Structure
Current
project
Overviews of
selected Object
Selected
Object
Template Operative
XX-9999 CP-0001
1 1
Include
Template
Finish
CRTD PREL
SYSTEM STATUS
The following status are set by the system/user as the project progress through
different stages:
…
A status set by the user to complement the system status for a given status object. You can
use only a user status belonging to a status profile (defined in Customizing) and assigned to
the relevant status object.
User statuses enable you to extend the control of business processes managed by the
system status. You can set and delete user statuses manually when carrying out business
transactions.
In the following steps you add the system status provided by SAP to your user status.
You can define a user status for:
Project_definitions
WBS elements
Network headers and network activities
CREATED
Created (CRTD)
Use
Initial system status for new WBS elements
Allows project structuring, date and cost planning.
Allows Budgeting
Prerequisites
The superior WBS element MUST have status Created
RELEASED
Released (REL)
Use
Allows costs and revenues to be posted to the project
Passed onto lower level WBS elements
Prerequisites
Created must have been set
….. Cont
Closed (CLSD)
Use
During the life of a project, networks are used as a basis for planning,
analyzing, controlling and monitoring schedules, dates and resources
(such as people, machines, materials, documents and drawings).
You can assign networks to a project.
Network / Activities
A network is a special type of work order that has the same structure
as production orders, maintenance orders, and inspection orders in
the System.
Activities
Individual tasks in the project are mapped as activities in a network.
Activities having the following characteristics:
They have a duration.
They have a defined start and a defined finish.
Resources are needed to execute them.
They incur costs.
Internal Activity:
Work
Dates, Capacities
Costs
External Activity /
Milestones: Service:
April
7 Dates
Milestone Trend analysis Costs
Billing Milestones Commitments
Payments
Material:
Costs Activity: Dates
Dates “Network” Costs
Costs Commitments
Payments Payments
Purchased Parts
Periodic Processing:
Overheads May
Settlement
June
Process Costs
20 Work
Scheduling
30 Procurement
External
Activity Elements
Work
External
Costs
Service
Service
Network
Settlement Rule
Profit Center
Other data
Sub Network
4
5
2
3
7 2.
3.
Dates
Scheduling Parameters
4. Allocation (Header or Activity)
5. Assignment to Org Elements
6. MRP relevant control
8 7.
8.
Costing base from Profile
Purchase Requisition Control
Control
Activity
key
Activity Duration
number
Description
Earliest
finish
Relationship Latest
Floats finish
Documents Materials
Internal Processing
Labor requirements
Capacity requirements
External Processing
Materials
Internal External
Documents, PS Texts
Milestones
PS Texts Milestones
Activity No
Execution
Assignment Constraints
Execution
Work Related
factor
External
Activity
assignments
Unique Milestone
number Activity to which the
milestone is
assigned
Parameter for
Progress Analysis
Manual
planned date
Parameter for
planned date in
relation to activity
WBS1
WBS
Cost Control and Reporting WBS1.1 WBS1.2
Reflects Ownership
Hierarchical Structuring
WBS1.1.1 WBS1.1.2 WBS1.2.1 WBS1.2.2
NETWORK
Work Control
Reflects Execution Process 20
Spread across Different WBS
elements 10 40 Network
30
WBS1
Planning dates
Planning Costs WBS1.1 WBS1.2
Settlement rules
Milestones WBS1.1.1 WBS1.1.2 WBS1.2.1 WBS1.2.2
Billing Plans
20
10 40 Network
30
Network Structure 2
Graphic
Project Builder
Copy 3
Incorporate 4
= Operative Structure
= Standard Structure
Drop here
Click & Hold Result
Drop here
Click & Hold Result
Drop here
Click & Hold
Result
In the Project System there are several different standard structures that you can use as
templates to create operative structures.
Standard networks
Project-neutral network structure, which can be used as a template when creating other
standard networks or operative networks. Creating operative networks by using standard
networks will save the time and increase the consistency of business process.
You can link standard networks with standard work breakdown structures in order to create
project templates, which contain both the project structure and the activities assigned to
the structure.
= Operative Structure
= Standard Structure
= Direct Assignment
= indirect Assignment
While creating operative network using standard While creating operative WBS from standard
network, if the standard Network is linked to standard WBS, if WBS is linked with standard network,
WBS, system will create operative WBS as well. system will not create operative network
Standard milestones
Standard milestones are used for creating milestones and other standard milestones. You
can combine different standard Milestones in a milestone group.
From milestone
3
Use:
Create, change or display all project structure data in one transaction
Graphic views (hierarchy and network graphic)
Project planning board with all its overviews (capacity, costs, component, and
maintenance order overviews)
Can define a user-specific worklist and a user-specific templates pool
Can make user-specific changes to the settings
Selected Project
& Project Tree
Worklist
and
Templates
Proj. Definition
and Structure
Worklists &
templates
Work Area
Worklist Preview Of
last Project
WBS elements
Network activities
Use:
Create Projects and activities
Maintain already created projects
Analysis
Capacity leveling
Cost overviews as for activities
Network View
1. http://help.sap.com/saphelp_46c/helpdata/en/04/926eae46f
311d189470000e829fbbd/frameset.htm