Professional Documents
Culture Documents
Control of Formwork
Control of Formwork
1. SCOPE
.2 After studying the structural drawings, the Project Engineer will Project Shop
plan for sizes, numbers and type of formwork to be used in Engineer Drawings
consultation with the Structural Engineer, if required. Depending
upon the programme, the number of repetitions will be decided.
.6 Ensure that the props, shores, waling, bearers, clamps and tie
rods are the right size and at the correct spacings. The
Gen.
Formwork designer shall check the falsework system with Foreman/
respect to load imposed on it and design parameters as laid Designer
down in the specification.
.10 Tie - rod holes to be made in the formwork shall be neat so that Gen.
they can be patched or plugged later on. Foreman
.12 Particular attention will be paid to the rigidity and line of stop Gen.
ends and joint formers. Foreman
.13 Remove all tie-wire clippings and nails, which may stain both Gen.
the formwork and the concrete. Foreman CONC/04/A
.14 Ensure that adequate access and working platforms are in place Gen.
for the concreting gang and that toe boards and guardrails are Foreman
provided.
Gen.
.15 A spreader or lifting beam shall be used to prevent distortion Foreman
when placing formwork.
Gen.
.16 Adjustable steel props shall be erected in plumb and verticality Foreman
of props checked using a spirit level.
Gen.
.17 A prop should not be used if it is bent, creased or, rusted or has Foreman
a bent head or base plate, damaged pin etc.
Gen.
.18 Proper release of agent shall be used so that it can be removed Foreman CONC/04/A
without damaging the surface finish of the concrete.
.19 New timber and plywood forms shall be given first coat of the Gen.
appropriate release agent 36 hours in advance, then a second Foreman
coat just before they are used. Avoid excessive use of release
agent as this can cause staining or retardation of the concrete.
Gen.
.20 A close watch should be kept on all wedges and fastenings. Foreman
Make sure that they do not work loose. Grout loss is an
indication that some movement has occurred.
WORK PROCEDURE
PROJECT: PROJECT NAME Ref No. CONC/01
PAGE 3 OF 3
SECTION: DATE OF ISSUE:
CONCRETING Dec. 2012
SUBJECT: BY:
QA/QC ENGINEER
CONTROL OF FORMWORK APPROVED BY:
QEHS MANAGER
ACTION VERIFY
.21 When unsleeved tie bars are being used, ease them slightly Gen.
before the concrete sets, and remove them as soon as it is safe. Foreman
iii) Where lifting is done by the vertical soldiers, check that Gen.
they are adequately connected to the walings. Foreman
Project
iv) Fire extinguishers in working order shall be in close Gen. Safety
proximity to the stored formwork. Foreman/ Plan
Safety
Officer