VOLUME PEKERJAAN
JALAN PANDANSARI
A. STA 0.00
a. Lapisan AC-WC tb 5cm
V = (3,50+3,55)/2 x 0,05 x 2 x 50
= 17,63 m3
b. LPA Kelas A tb 15cm
V = (3,55+3,70)/2 x 0,15 x 2 x 50
= 54,38 m3
c. Sirtu Bahu Jalan
V = (1+0,80)/2 x 0,20 x 2 x 50
= 18 m3
d. Galian
V = (0,80 x 0,30 x 2 x 50)
= 24 m3
e. Pasangan batu kali
V = (0,80 x 0,50 x – 0,40 x 0,30) x 2 x 50
= (0,4 – 0,12 ) x 2 x 50
= 3,2 m3
C. STA 0.150
a. Lapisan AC- WC tb 5cm
V = (2,50 + 2,54)/2 x 0,05 x 2 x 50
= 12,6 m3
b. LPA A tb 15cm
V = (2,64+ 2,54)/2 x 0,15 x 2 x 50
= 38,85 m3
c. Sirtu bahu jalan
V = (1,00+0,856)/2 x 0,20 x 2 x 50
= 18,56 m3
d. Galian
V = 0,80 x 0,30 x 2 x 50
= 24 m3
e. Pasangan batu kali
V = (0,80 x 0,50 – 0,40 x 0,30) x 2 x 50
= (0,4 – 0,12) x 2 x 50
= 28 m3
TOTAL VOLUME
A. Lapisan AC-WC = 230 m3
= 230 x 2,3
= 529 Ton
B. LPA A tb 15cm = 706,62 m3
C. Sirtu
a. Bahu jalan = 329,8 m3
b. Leveling sirtu = 26,4 m3
Total sirtu = 329,8 + 26,4
= 355,4 m3
D. Galian = 427,2 m3
E. Pasangan batu kali = 498,4 m3
4 PENINGKATAN JALAN PANDANSARI
ANALISA
PENINGKATAN JALAN PANDANSARI
TAHUN 2019
GALIAN
HARGA
ITEM BAHAN
NO PEERKIRAAN JUMLAH
PEMBAYARAN SAT URAIAN UPAH
KUANTITAS
Rp
C PERALATAN
55.352,00
1 E.10 0,0256 Excavator
Jam 660.000,00 16.896,00
2 E.08 0,3344 Dump Truck
Jam 115.000,00 38.456,00
3 1,00 Ls Alat Bantu -
-
Jumlah A + B
D 56.301,57
+C
Keuntungan dan
E 10%
Overhead Kantor 5.630,16
Harga Satuan
F Pekerjaan (D
61.931,73
+ E)
7 PENINGKATAN JALAN PANDANSARI
TIMBUNAN SIRTU
PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS HARGA JUMLAH
A. TENAGA
1. Pekerja (L01) Jam 1,7363 12.857,14 22.323,35
2. Mandor (L03) Jam 0,4341 11.428,57 4.960,74
JUMLAH HARGA TENAGA 27.284,09
B. BAHAN
1. sirtu M3 1,2686 180.000,00 228.348,00
JUMLAH HARGA BAHAN 228.348,00
C. PERALATAN
Wheel
1. Loader (E15) Jam 0,0136 280.000,00 3.810,06
Dump
2. Truck (E08) Jam 0,4341 115.000,00 49.917,49
Motor
3. Grader (E13) Jam 0,0020 640.000,00 1.269,84
3. Tandem (E17) Jam 0,0289 375.000,00 10.854,23
Water
4. Tanker (E23) Jam 0,0070 150.000,00 1.054,22
Alat
5. Bantu Ls 1,0000 0,00 0,00
JUMLAH HARGA PERALATAN 66.905,84
LPA KLAS A
LAPIS PONDASI AGREGAT
5.1 (1) 1 M3 313.599,71
KELAS A
A TENAGA 862,14
L.01 0,0595 Jam Pekerja 12.857,14 765,00
L.03 0,0085 Jam Mandor 11.428,57 97,14
B BAHAN 213.962,00
M.26 1,2586 m3 Agregat A 170.000,00 213.962,00
C PERALATAN 70.266,50
E.15 0,0085 Jam Wheel Loader 280.000,00 2.380,00
E.08 0,5043 Jam Dump Truck 115.000,00 57.994,50
E.13 0,0043 Jam Motor Grader 640.000,00 2.752,00
E.17 0,0134 Jam Tandem Roller 375.000,00 5.025,00
E.23 0,0141 Jam Water Tank Truck 150.000,00 2.115,00
Ls Alat Bantu
D Jumlah A + B + C 285.090,64
Keuntungan dan Overhead
E 10% 28.509,06
Kantor
Harga Satuan Pekerjaan (D +
F 1 M3 313.599,71
E)
HARGA SATUAN
PENINGKATAN JALAN PANDANSARI
TAHUN 2019
REKAPITULASI
PENINGKATAN JALAN PANDANSARI
TAHUN 2019