You are on page 1of 30

Drainage System

•Drainage is the natural or


artificial removal of a surface's
water and sub-surface water
from an area with excess of
water. The internal drainage of
most agricultural soils is good
enough to prevent severe
waterlogging, but many soils
need artificial drainage to
improve production or to
manage water supplies.
Drainage System
 (Catch Basin)
Catch Basin
•A catch basin is an underground
pit or receptacle at the entrance of
a drain designed to trap debris and
hence prevent them from clogging
the drainpipe farther away. The
solids settle at the bottom of the
basin while the clear liquids flow
out into the drainpipe.
Different Types of
Catch Basin;
Yard Catch Basin

•A catch basin is a large drain,


usually placed in low areas of a
yard, to catch surface runoff
water. It usually consists of a
surface drain that leads to an
enlarged box beneath that is
then tied to an underground
drainage system that finally
leads to downspout drains or
storm sewers.
Garage Catch Basin

•Garage floor drains or catch basins are


a must-have if your garage is sloped,
and the nearby road collects a lot of
water. They drain the excess rainwater
into a sewage system so that it doesn’t
deposit onto the garage floor.  Garage
floor drains closely resemble catch
basins. The only major difference is the
design. In most cases, floor drains are
round holes that look like your shower
drain hole
•Garage floor drains closely resemble
catch basins. The only major difference
is the design. In most cases, floor
drains are round holes that look like
your shower drain hole
Grease Basin
•A grease trap (also known
as grease interceptor, grease
recovery device, grease
capsule and grease converter) is a 
plumbing device (a type of trap)
designed to intercept most greases
 and solids before they enter a
wastewater disposal system.
Component
of Catch
Basin
Detailed Drawing
of Catch Basin
Computation for Cement,
Sand and Gravel of 10pcs
Catch Basin
CONCRETE PROPORTION

CLASS MIXTURE CEMENT CU.M CU.M


40KG/BAG 50KG/BAG

AA 1:11/2: 3           12.0  9.5 .50 1.0


TABLE 1-2 A 1: 2 : 4            9.0     7.0 .50 1.0
B 1:21/2: 5            7.5        6.0 .50 1.0
C 1 : 3 :  6            6.0 5.0 .50 1.0
CONCREATING PROPORTION:

1. Find the overall volume of the Catch


Basin

V= T x W x H                         
V= .10 x .30 x .50
V= 0.015cu.m
= 0.015 x 10
=0.15 cu.m
2. Refer to the Table 1-2

Cement = 0.15 x 9(40kg/bag) =


1.35 or 2 bags 

Sand = 0.15 x 0.50 = 0.075 cu.m 

Gravel = 0.15 x 1.0 = 0.15 cu.m 


MASONRY
WORKS
TOTAL AREA = .30 X .50 = 0.15 sq. m X 4 faces = 0.6 sq. m
CHB:

MASON .6 sq.  m X 12.5 = 7.5 or 8 pcs CHB per catch basin


PLASTERING

RY CEMENT: .6 sq.  m X 0.288 = 0.1728 or 1 bag 


SAND: .6  sq.  m X 0.016 = 0.0096 

WORKS
WHOLE CATCH BASIN:
CHB: 8pcs X 10 = 80 pcs
CEMENT: 1 bag X 10 = 10 bags
SAND: 0.0096 cu. m X 10 = 0.096 cu. m 
MORTAR:
CEMENT: .6 sq. m X 0.792 = 0.4752 or 1 BAG
SAND: .6 sq. m X 0.0435 = 0.0261 cu.  m

SUMMARY
CHB: 8pcs X 10 =80 pcs
CEMENT: 0.4752 bag X 10 = 4.752 or 5 bags
SAND: 0.0261 cu. m X 10 = 0.261 cu. m 
REINFORCEMENT FOR
CHB WALL OF CATCH
BASIN
TABLE 3-5 LENGTH OF REINFORCING BARS
FOR CHB IN METERS

SPACING VERTICAL REINFORCEMENT  SPACING HORIZONTAL


LENGTH OF BARS IN METERS
LAYER REINFORCEMENT 
LENGTH OF BARS IN METERS

CM PER BLOCK PER SQ. M PER BLOCK PER SQ. M

40 0.235 2.93 2 0.264 3.30


60 0.171 2.13 3 0.172 2.15
80 0.128 1.60 4 0.138 1.72
1. FIND THE AREA OR THE CATCH BASIN
A = .30 X .50 = 0.15 sq. m X 4 faces = .6 pcs

2. DETERMINE THE NUMBER OF CHB


0.6 X 12.5 = 8pcs

REINFORCE 3. REFER TO TABLE 5


MENT FOR A. VERTICAL REINFORCEMENT @ 40cm SPACING

CHB WALL   8pcs X .235 = 1.88 or 2m long


B. HORIZONTAL REINFORCEMENT @ EVERY 2 LAYERS
OF CATCH   8pcs X 0.264 = 2.112 or 3m long

BASIN
4. ADD THE RESULTS FROM NO. 3

REINFORCE 2m long + 3m long = 5m long

MENT FOR 5. CONVERT THE LENGTH TO 6M LONG


CHB WALL 5m long/6m = 0.8333 pc OF 10 mm Ø of 6 m
long
OF CATCH 0.8333 X 10 = 8.33 or 9 pcs 10 mm Ø of 6 m long
BASIN
G.I TIE
WIRE
KILOGRAMS PER SQUARE METER
VERTICAL HORIZONTAL
SPACING LAYER SPACING 25CM TIE 30CM TIE 40CM TIE

40 2 .054 .065 .066


TABLE 3-6  NO. 16 G.I 40 3 .039 .047 .063
40 4 .024 .029 .039
TIE WIRE FOR CHB
REINFORCEMENT
PER SQ. METER 60 2 .036 .044 .057
60 3 .026 .032 .042
60 4 .020 .024 .032

80 2 .027 .033 .044


80 3 .020 .024 .032
80 4 .015 .018 .024
1. FIND THE AREA OF THE CATCH
BASIN
  A= .30 X .50 = 0.15 sq. m 

2. ALONG 40 CM VERTICAL SPACING


AND 2 LAYERS HORIZONTAL SPACING
OF REINFORCEMENT AT 30 CM LONG
TIRE WIRE:
  .15 sq. m X .065 = 0.00975 or 1 KG
#NO. 16- G.I TIE WIRE
REINFORCEMENT
BAR FOR BOTTOM
SLAB AND COVER
OF CATCH BASIN
BAR LENGTH = L + 4 (7.5 cm)
          = 35cm + 30cm
          = 65 cm or .65m
BOTTOM SLAB
NO. OF BARS ALONG .50 M @ 0.15 M spacing no. of bars : 
= .50m / spacing + 1
= .50m / 0.15 + 1
= 4.33 / 5 pcs @ .65 m long
= 3.25 m long
COVER OF CATCH BASIN
NO. OF BARS ALONG .50 M @ 0.15 M spacing
no. of bars : 
= .50m / spacing + 1
= .50m / 0.15 + 1
= 4.33 / 5 pcs @ .65 m long
= 3.25 m long
BOTTOM SLAB + COVER
= 3.25 m long + 3.25 m long
= 6.5 m long/ 6m
= 1.08 pc.  12 mm ø of 6 m long    
= 1.08 pc x 7 = 7.56 or 8 pcs. 12 mm ø 6 m long
1. NO. OF WIRE x NO. OF INTERSECTION OF REBARS
  = 5 pcs x 5pcs
  = 25 pcs
2. TOTAL TIES NEEDED FOR 10 CATCH BASIN
  = 25 pcs x 10
  = 250 pcs
3.  
  = 250 pcs x .30 m 

G.I TIRE WIRE   = 75 m long 


4. CONVERT TO KG. 
  = 75 m long/ 53(1kg. Of tire wire is 53 m)
  = 1.4150 or 2 kg. of #16-G.I TIRE WIRE
BILLS OF MATERIALS
ITEM DESCRIPTION QTY UNIT MATERIAL COST TOTAL COST
I. Earthworks
Excavation 1 cub. m. 500 500
II. Concreting Works
A. Masonry
      Concrete Hollow Blocks- 4” 88 pcs 12 1056
      Cement 3 bag 230 690
      Sand .08 cub. m. 1000 80
      Gravel .17 cub. m. 600 102
      10 mm ø (6 m long) 10 pcs 150 1500
      12 mm ø (6 m long) 9 pcs 220 1,980
      G.I  Tire Wire #16 4 kg 75 300
B. Mortar
      Cement 6 bag 230 1,380
      Sand .29 cub. m. 1000 290
C. Plastering
      Cement 11 bag 230 2530
      Sand .11 cub. m. 1000 110
Total 10518

You might also like