EARTHWORKS

For Excavation

MH = Productivity Rate (PR) X Total Volume (Cu.M)


MH/DAY = No. of labor X No. of hours/day
Total Working Days = Total MH ÷ Total MH/DAY
Total Rate/Day = Rate/Day X No. of labor
Labor Cost = Total Rate/Day X Total Days

CONCRETING WORKS

For Column Footing CF

VOLUME = L x W x THK or H or DEPTH (use for 1 CF)


Total Volume = Computed Vol. of 1 CF x No. of CF
Total Materials
CEMENT = T. Vol x Conc. Proportion (See Table 1-2)
SAND = T. Vol x Conc. Proportion (See Table 1-2)
GRAVEL = T. Vol x Conc. Proportion (See Table 1-2)
MARK UP = Total Computed Materials + (Total Computed Materials X Mark Up percentage)

For Column

VOLUME = L x W x THK or H or DEPTH (use for 1 column)


Total Volume = Computed Vol. of 1 column x No. of Columns
Total Materials
CEMENT = T. Vol x Conc. Proportion (See Table 1-2)
SAND = T. Vol x Conc. Proportion (See Table 1-2)
GRAVEL = T. Vol x Conc. Proportion (See Table 1-2)
MARK UP = Total Computed Materials + (Total Computed Materials X Mark Up percentage)

For Slab-On-Grade/Concrete Flooring

VOLUME = L x W x THK of slab


Total Materials
CEMENT = T. Vol x Conc. Proportion (See Table 1-2)
SAND = T. Vol x Conc. Proportion (See Table 1-2)
GRAVEL = T. Vol x Conc. Proportion (See Table 1-2)
MARK UP = Total Computed Materials + (Total Computed Materials X Mark Up percentage)

SUMMARY TABLE
COMPUTED TOTAL QTY
ITEMS MARKUP TOTAL UNITS
QUANTITY (whole number)

CEMENT SAY… BAGS


SAND SAY… CU.M
GRAVEL SAY… CU.M
MASONRY WORKS: CHB AND PLASTERING

For CBH: Area Method


AREA = L x H
Note: Subtract the openings of doors and windows to the total computed wall area.
1 SQ.M = 12.5 pcs of CHB
Total CHB = Total Area x 12.5
Total Materials
CEMENT = T. Area x CHB Mortar Per Sq.M (See Table 2-2)
SAND = T. Area x CHB Mortar Per Sq.M (See Table 2-2)
MARK UP = Total Computed Materials + (Total Computed Materials X Mark Up percentage)

SUMMARY TABLE
COMPUTED TOTAL QTY
ITEMS MARKUP TOTAL UNITS
QUANTITY (whole number)

(CHB SIZE) CHB SAY… PCS


CEMENT SAY… BAGS
SAND SAY… CU.M

For Plastering: Area Method


Single face AREA = Total Computed AREA
Two face AREA = Total Computed AREA x 2
Total Materials
CEMENT = T. Area x Plaster Per Sq.M (See Table 2-4)
SAND = T. Area x Plaster Per Sq.M (See Table 2-4)
MARK UP = Total Computed Materials + (Total Computed Materials X Mark Up percentage)

SUMMARY TABLE
COMPUTED TOTAL QTY
ITEMS QUANTITY
MARKUP TOTAL (whole number)
UNITS
CEMENT SAY… BAGS
SAND SAY… CU.M
REBARS

For Column Footing

Total G.I. Tie Wire in Kilogram (KG)


KG/M = (Steel bar Diameter) ² / 162.20
G.I./KG = TOTAL KG/M (Total No. of Rebar x RSB Length) X 2% or 0.02
MARK UP = Total Computed Materials + (Total Computed Materials X Mark Up percentage)
SUMMARY TABLE
COMPUTED TOTAL QTY
ITEMS QUANTITY
MARKUP TOTAL (whole number)
UNITS
(BAR DIA) MM Ø DEF. BAR SAY… PCS
G.I. TIE WIRE SAY… KG

For Slab-On-Grade
Total G.I. Tie Wire in Kilogram (KG)
KG/M = (Steel bar Diameter) ² / 162.20
G.I./KG = TOTAL KG/M (Total No. of Rebar x RSB Length) X 2% or 0.02
MARK UP = Total Computed Materials + (Total Computed Materials X Mark Up percentage

SUMMARY TABLE
COMPUTED TOTAL QTY
ITEMS MARKUP TOTAL UNITS
QUANTITY (whole number)

(BAR DIA) MM Ø DEF. BAR SAY… PCS


G.I. TIE WIRE SAY… KG