You are on page 1of 10

Journal of Loss Prevention in the Process Industries 25 (2012) 166e175

Contents lists available at ScienceDirect

Journal of Loss Prevention in the Process Industries


journal homepage: www.elsevier.com/locate/jlp

Risk-based inspection for large-scale crude oil tanks


Jian Shuai*, Kejiang Han, Xuerui Xu
College of Mechanical and Transportation Engineering, China University of Petroleum-Beijing, 18 Fuxue Road, Changping, 102249 Beijing, China

a r t i c l e i n f o a b s t r a c t

Article history: Periodic Internal Inspection Method often results in under-inspection or over-inspection for large-scale
Received 8 June 2011 crude oil tank. Therefore, how to determine reasonable internal inspection interval (INTII) has great
Received in revised form significance on balancing the safe operation requirement and inspection cost for crude oil tanks. Here,
7 August 2011
RBI (risk-based inspection) technology is used to quantitatively assess the risk of crude oil tanks in an oil
Accepted 8 August 2011
depot in China. The risk comparison between tank shell and bottom shows that the risk of tank depends
on the risk of tank bottom. The prediction procedure of INTII for crude oil tanks is also presented. The
Keywords:
INTII predicted by RBI method is gradually extended with the increasing of the acceptable risk level. The
Internal inspection interval
Risk
method to determine the acceptable risk of crude oil tanks is proposed, by which 3.54Eþ04 are taken as
RBI the acceptable risk of the oil depot. The safety factor of 0.8 is proposed to determine the final INTIIs for 18
The acceptable risk crude oil tanks. The INTII requirement in China code SY/T 5921, 5e7 years, is very conservative and lower
Gumbel extreme value distribution than predicted service life of tanks. The INTIIs predicted by Gumbel method are smaller than by RBI
method for tanks with short INTII. Therefore, this paper recommends RBI method to predict the INTII for
crude oil tanks.
Ó 2011 Elsevier Ltd. All rights reserved.

1. Introduction two short-comings for tanks management. On the one hand, due to
the high-capacity of crude oil tank, it is expensive and time-
With the rapid development of petroleum and chemical consuming to clear and inspect tank, which can influence the
industry, storage tank plays an increasing role in the storage of normal production of oil depot. If the tanks without severe corro-
crude oil. Owing to the advantages of saving steel, saving occupied sion defects are opened to inspect, it will cause unnecessary
area and cost-effective construction, large-scale atmospheric inspection cost and business interruption loss. On the other hand, if
storage tanks are widely used (Bai & Liu, 1995; Jiang & Li, 2005; Li, the tanks with high risk are not timely inspected and repaired, it
1996). However, these large-scale crude oil tanks have high will bring potential safety hazard, and even in some cases crude oil
potential risk. Once the leakage of large-scale crude oil tank leakage may happens (Dai, Li, & Long, 2002; Guo et al., 2010).
happens, it not only causes serious environmental pollution, but Therefore, the determination of a reasonable inspection interval
also in some cases causes fire and even casualties. not only can reduce inspection costs and financial loss for business
Inspection of tank is intended to assess the tank integrity and interruption, but also avoid environmental cost, component
identify the problem that may lead to future loss of integrity. The damage caused by the leak of tank.
inspection can provide the information of deterioration state of RBI is a risk assessment and management process which
tank plates and reduce risk uncertainty of crude oil tank. Currently, provides a methodology for determining the optimum inspection
Periodic Internal Inspection is widely used by China’s petroleum methods and frequencies. According to the fact that a large percent
and chemical industry for the management of crude oil tanks. In of the total risk concentrate on a relatively small percent of the
China, the code SY/T 5921 (Oil and Gas Storage and Transportation equipment items or units, RBI can identify the high-risk and low-
Standardization Technical Committee in China, 2000) has specific risk tanks, and focus inspection resource on high-risk tanks. On
requirement for INTII: for crude oil tank it is generally 5e7 years; the premise of ensuring the safe operation of tanks, RBI can extend
the maximum INTII for the new tank cannot exceed 10 years. the INTII of low-risk tanks, which reduce the shutdown frequencies
However, the Periodic Internal Inspection Method often results in and improve the economic efficiency of oil depot. Therefore, the RBI
method is better to balance the safe operation requirement of crude
oil tanks and inspection costs. RBI method has been successfully
* Corresponding author. applied on refinery and processing piping (Chang, Chang, Shua, &
E-mail address: shuaij@cup.edu.cn (J. Shuai). Lin, 2005) and pressure safety valves (Chien, Chen, & Chao, 2009).

0950-4230/$ e see front matter Ó 2011 Elsevier Ltd. All rights reserved.
doi:10.1016/j.jlp.2011.08.004
J. Shuai et al. / Journal of Loss Prevention in the Process Industries 25 (2012) 166e175 167

Less work is reported on the prediction of INTII for crude oil RiskðtÞ ¼ Pf ðtÞ  FC (1)
storage tank. Most of them focus on Corrosion Rate Method (Li,
Wang, & Yang, 2005) and Reliability Analysis (Liu, 2005; Shuai & where the POF (Pf(t)) is a function of time, and increases as the
Han, 2010; Xiao, Liu, & Qu, 2005). In this paper, RBI technology damage in the component due to thinning or other damage
is used to predict the INTII of crude oil tanks in an oil depot in mechanisms accumulate with time. The COF (FC) is the financial
China. consequence based on economic losses. Only component damage,
product loss, and environmental penalties are considered in the
consequence analysis of failure for atmospheric storage tank.
2. Risk assessment method of RBI
In RBI, the POF is computed by Equation (2). The procedure in
Fig. 1 is used to determine the POF for crude oil tank.
American Petroleum Institute (API) issue two standards for RBI:
API 580 (API, 2002) “risk-based inspection” and API 581 (API, 2008) Pf ðtÞ ¼ gff  Df ðtÞ  FMS (2)
“Risk-Based Inspection Base Resource Document”. Recently, The
European Committee for Standardization (2008) develops risk- where gff (Generic Failure Frequency) represents a POF developed
based inspection and maintenance procedures for European for specific component types, but do not reflect the true failure
Industry (RIMAP). frequency for a specific component subject to a specific damage
In RBI, the risk is the product of the probability of failure (POF) mechanism. Df(t) (damage factor) is an adjustment factor applied to
and the consequence of failure (COF), and also is a function of time. account for damage mechanisms that are active in a component,
The equation for risk calculation is showed as following: which modifies the industry gff and makes it specific to the

Fig. 1. The calculation procedure for POF.


168 J. Shuai et al. / Journal of Loss Prevention in the Process Industries 25 (2012) 166e175

Table 1 1.8601Eþ05$, respectively, which correspond to consequences


Probability and financial-based consequence categories in API RBI. category D and C in Table 1; the COFs of the tanks with capacity of
Probability category Consequence category 50 000 m3 are 5.5968Eþ05$ and 1.0039Eþ05$, respectively, which
Category Range Category Range ($)
correspond to consequences category C.
It can be seen from Table 3 that POF of tank bottom is higher
1 Df(t)  2 A FC  10 000
2 2 < Df(t)  20 B 10 000 < FC  100 000 than that of tank shell. The main reason is that the tank shell has
3 20 < Df(t)  100 C 100 000 < FC  1 000 000 larger plate thickness and lower corrosion rate than that of tank
4 100 < Df(t)  1000 D 1 000 000 < FC  10 000 000 bottom. Fig. 3 and Table 3 presents that the risks of tank shell for all
5 Df(t) > 1000 E FC > 10 000 000
tanks are Medium Risk in Risk Matrix. Due to high COF (conse-
quence category D), the risks of bottom plate for Tank 36, 37 and 38
in risk matrix are Medium High risks, which account for 4.8% of
component under evaluation. FMS (Management Systems Factor) total items.
represents the effect of the facility’s management system on the
mechanical integrity of the plant equipment. 3.3. The ranking for crude oil tanks
Probability and Consequence Categories in API 581 are shown in
Table 1, in which Probability Categories are divided by the magni- One of the purposes of risk analysis based on RBI is to rank the
tude of the total damage factor. API 581 uses a risk matrix showed relative risks of facilities, units, systems, equipment or components
in Fig. 2 to present the risk distribution of different components. in a plant. Based on the result of risk ranking, RBI can identify high,
medium and low-risk items, and then determine equipment that
3. Risk assessments and ranking for crude oil tanks does not require inspection or select risk mitigation measure for
high-risk equipment. So inspection and maintenance activities can
3.1. Brief description of large-scale crude oil tanks be concentrated and more cost-effective. According to the calcu-
lation procedure of POF showed in Fig. 1, wall thickness, in-service
Much data were collected to assess the risk of crude oil tanks, time and corrosion rate of crude oil tank are main influence factors
such as, original design and construction drawings, previous of POF. The start-runtime, in-service time and corrosion rate for
inspection reports and modifications/repairs records of crude oil most of crude oil tanks in oil depot are different, so the calculated
tanks. The basic information for crude oil tanks are showed in POF and risk levels for 38 crude oil tanks are different. The POFs and
Table 2. There are a total of 38 crude oil tanks in an oil depot in risks of all crude oil tanks in this paper are the POFs and risks in
China marked as Tank 1e38, in which Tank 35, 36, 37 and 38 have June 2010.
the capacity of 100 000 m3 and the others 34 tanks have the The POF ranking of tank bottom for all crude oil tanks is showed
capacity of 50 000 m3. 19 Tanks were inspected and repaired at in Fig. 4. The POFs of tank bottom for 19 uninspected tanks are
different time (Tank 3 and 6 with twice inspections), in which the higher than that of the inspected tanks. The POF for bottom plate of
inspection data of Tank 8 was lost. Digital ultrasonic thickness Tank 16 is the highest in all tanks, and reaches up to 20.8  103.
gauge were used to measure the wall thickness of tank plates. The The in-service time of Tank 16 has reached 13 years, which is longer
tank bottom plates also were scanned by Floormap VS MFL. As the than inspection interval requirement of 10 years specified by code
inspection data of crude oil tanks are very huge, it is not introduced SY/T 5921 in China. While, the in-service time of Tank 19, 20, 21 and
in this paper. 22 is 11 years, and the remaining uninspected tanks are 10 years. In
all inspected tanks, the POFs of bottom plate for Tank 4, 11, 2, 7, 9, 13,
18 and 32 are ranged from 1.3  103 to 6.5  103. Because of
3.2. Risk assessment result of crude oil tanks
relatively high corrosion rate or long in-service time, the proba-
bility of leakage for those tanks is relatively high. Due to low
Table 3 and Fig. 3 show the risk assessment results of 37 crude
corrosion rate and repair work taken in recent years, the POFs for
oil tanks in risk matrix. The tanks with the same capacity in the oil
the others tanks are less than 9  104.
depot have the same design geometry, underground structure, the
The POF ranking of tank shell in Fig. 5 is basically similar with
surrounding environment and management method, so the
that of tank bottom. Due to long in-service time and uncertainty
calculated COFs for these tanks are the same. The COFs of bottom
in deterioration rate, the predicted POFs for tank shell of unin-
and shell for Tank 35, 36, 37 and 38 are 1.1137Eþ06$ and
spected tanks are higher than that of inspected tanks. The POFs
for Tank 19e22 are 5.1 104; Tank 23e31, 33 and 34 are
2.1 104; the most of other tanks are 3.59  105. Compared
with the POFs of tank bottom in Fig. 4, POFs of tank shell are
much smaller.
Risk ranking for tank bottom and shell are shown in Figs. 6 and 7,
respectively. As can be seen from Fig. 6, the risks of 19 uninspected
tanks are higher than that of all inspected tanks. The primary
reasons for that are: firstly, for uninspected tanks, it is impossible to
know damage or corrosion state of crude oil tank before inspection.
So the risk of uninspected tank has a large uncertainty. Secondly,
those tanks have been serving for 10e13 years, which also result in
a high risk. The risks of bottom plate for Tank 36, 37, 38 and 16 are
almost the same, and reach up to 1.17  104. But the risk source for
those 4 tanks are different, the COFs of bottom plate for Tank 36, 37
and 38 are higher than Tank 16. Compared with the risk of tank
bottom, the risk of tank shell is much smaller, and almost negli-
gible, so the risk of crude oil tank is determined mainly by the risk
Fig. 2. Risk matrix. of tank bottom.
J. Shuai et al. / Journal of Loss Prevention in the Process Industries 25 (2012) 166e175 169

Table 2
Basic information of crude oil tanks.

Tank no. Last inspection Capacity Tank Last inspection Capacity Tank Last inspection Capacity
interval (years) (1  104 m3) no. interval (years) (1  104 m3) no. interval (years) (1  104 m3)
1 11 5 14 12 5 27 / 5
2 15 5 15 13 5 28 / 5
3 10/8 5 16 / 5 29 / 5
4 15 5 17 10 5 30 / 5
5 16 5 18 11 5 31 / 5
6 6/12 5 18 / 5 32 5 5
7 9 5 20 / 5 33 / 5
8 6 (No data) 5 21 / 5 34 / 5
9 8 5 22 / 5 35 7 10
10 10 5 23 / 5 36 / 10
11 11 5 24 / 5 37 / 10
12 9 5 25 / 5 38 / 10
13 9 5 26 / 5

Note: / indicate that tank hasn’t been inspected.

According to the INTII requirement in code SY/T 5921 and risk uninspected tanks. If we pay attention to 25.68%equipment items,
ranking above, uninspected tanks should be immediately inspected the 91.2% risk can effectively be controlled, which can greatly
to identify the tank corrosion state and reduces risk uncertainty; in optimize the inspection resources and increase economic efficiency
particular, Tank 36, 37, 38 and 16 should take priority for inspection. of crude oil depot.
Fig. 8 presents Pareto analysis for the risk distribution of all
tanks. The sum of risks for tank bottom of 19 uninspected tanks, 4. INTII predictions of crude oil tank
which is 25.68% of all equipment items (not include Tank 8),
account for 91.2% of the total risk of the oil depot. In other word, Internal inspection is one of the main means to keep the
most of risks in oil depot concentrate on tank bottom of 19 integrity of crude oil tanks, which require tank must be out of

Table 3
Risk assessment results of crude oil tanks.

Tank no. Tank bottom Tank shell

Probability Consequence Risk Probability Consequence Risk


category (Pf) category category category (Pf) category category
1 1 C Medium / C /
2 2 C Medium 1 C Medium
3 2 C Medium 1 C Medium
4 3 C Medium 1 C Medium
5 2 C Medium 1 C Medium
6 1 C Medium 1 C Medium
7 2 C Medium 1 C Medium
9 2 C Medium 1 C Medium
10 2 C Medium 1 C Medium
11 2 C Medium 1 C Medium
12 1 C Medium / C /
13 2 C Medium 1 C Medium
14 2 C Medium 1 C Medium
15 1 C Medium 1 C Medium
16 3 C Medium 2 C Medium
17 1 C Medium 1 C Medium
18 2 C Medium 1 C Medium
18 3 C Medium 2 C Medium
20 3 C Medium 2 C Medium
21 3 C Medium 2 C Medium
22 3 C Medium 2 C Medium
23 3 C Medium 2 C Medium
24 3 C Medium 2 C Medium
25 3 C Medium 2 C Medium
26 3 C Medium 2 C Medium
27 3 C Medium 2 C Medium
28 3 C Medium 2 C Medium
29 3 C Medium 2 C Medium
30 3 C Medium 2 C Medium
31 3 C Medium 2 C Medium
32 2 C Medium 1 C Medium
33 3 C Medium 2 C Medium
34 3 C Medium 2 C Medium
35 1 D Medium 1 C Medium
36 3 D Medium high 1 C Medium
37 3 D Medium high 1 C Medium
38 3 D Medium high 1 C Medium
170 J. Shuai et al. / Journal of Loss Prevention in the Process Industries 25 (2012) 166e175

Fig. 3. The result of risk matrix for all crude oil tanks.

service to clear gas and oil for inspection and repair work. By the The predicted INTIIs of crude oil tanks are showed in Table 4.
internal inspection, the real deterioration rate of crude oil tank can When the acceptable risk is 1.42Eþ04, INTIIs for all tanks are higher
be determined, and following repair works also can ensure long- than 5e7 years specified by code SY/T 5921 except Tank 3 with that
time safe operation of tanks in the future. As showed in Fig. 9, of 6.4 years. The INTII of Tank 1, 5, 6, 12, 15, 17 and 35 are larger than
corrosion rates of tank bottom for all crude oil tanks are higher than 15 years; especially Tank 1 is 70 years. The corrosion rates of all
that of tank shell except Tank 6. Due to lower corrosion rate and these 7 tanks are smaller than 0.3 mm/a. After in-service time of 11
thicker thickness of tank shell, the tank shells are eroded more years, maximum corrosion depth of Tank 1 is only 1 mm. The
slightly than that of tank bottom. By the POF and risk calculation for inspection data of Tank 3 show that: intensive corrosion pitting was
many tanks, Guo et al. (2010) and Yuan, Xu, Wang and Li (2009) found on the part of bottom plates of Tank 3; there are 20 bottom
draw a conclusion that the POF and risk of tank bottom are much plates with serious corrosion, in which the maximum corrosion
larger than that of tank shell. Figs. 4e7 also present the consistent depths of 12 bottom plates are larger than 4 mm; the maximum
conclusion with Guo et al. (2010) and Yuan et al. (2009). Therefore, corrosion depth for all bottom plates is 7.4 mm.
the INTII of crude oil tank depends on INTII of tank bottom. Due to The predicted INTIIs of tanks gradually increase with the
lack of corrosion information about uninspected tanks, the INTIIs of increasing of acceptable risk level. When the acceptable risk is
uninspected tanks are not predicted in this paper. 3.54Eþ04, in addition to INTIIs of Tank 3 and Tank 11 are 8.1 and
10.8 years respectively, the others are larger than 12 years. If the
4.1. INTII prediction based on RBI acceptable risk of oil depot reaches to 7.08Eþ04, predicted INTIIs of
all tanks are larger than the requirements specified by code SY/T
In this method, the INTII is defined as the in-service time from 5921, in which that of Tank 3 is 9.7 years, and the others are larger
last inspection until the risk of tank bottom reach the acceptable than 12 years. Therefore, the reasonable acceptable risk is of the
risk of oil depot. The procedure in Fig. 10 is used to predict INTII utmost importance to accurately predict INTIIs of crude oil tanks.
based on RBI technology. 1.42Eþ04, 3.54Eþ04 and 7.08Eþ04 are
respectively taken as the acceptable risk to predict INTII, which 4.2. The determination of the acceptable risk of oil depot
correspond to damage factor Df(t) ¼ 100, 250 and 500 for tanks
with capacity of 50 000 m3. The damage factor Df(t) ¼ 100 is tran- The acceptable risk is one of main factors which affect predic-
sition value from Medium Risk to Medium High Risk in risk matrix. tion result of INTII based on RBI technology. If the acceptable risk is

Fig. 4. POF ranking of tank bottom for all crude oil tanks. Fig. 5. POF ranking of tank shell for all crude oil tanks.
J. Shuai et al. / Journal of Loss Prevention in the Process Industries 25 (2012) 166e175 171

Fig. 6. Risk ranking of tank bottom for all crude oil tanks.
Fig. 8. Pareto analysis for the risk distribution of all tanks.

too high, it allow crude oil tanks to continue operation under the
condition of high risk, which may cause the leakage of tank; if the 3.54Eþ04, but lower when the acceptable risk is 7.08Eþ04. Table 5
acceptable risk is too low, it decrease the inspection interval of tank, also shows that the MARs for all tanks are higher than 3.54Eþ04, in
which increase the inspection cost and business interruption loss. which Tank 4, 5, 6, 11 and 12 are close to 3.54Eþ04. The determi-
Therefore, the basic principle on the determination of the accept- nation of the acceptable risk for crude oil tank should not be
able risk for oil depot is: on the premise of ensuring safe operation allowed to deteriorate to a point where the minimum acceptable
of crude oil tanks, as far as possible to extend the inspection thickness or fitness-for-service could be threatened. In order to
interval. ensure safe operation of all tanks, an identical acceptable risk for
When minimum remaining thickness of tank bottom is less than the whole oil depot should be lower than the minimum value in
the minimum acceptable bottom thicknesses, the tank bottom MARs of all tanks. Therefore, the acceptable risk of the oil depot
should be repaired or replaced. So the risk at the time when the cannot be higher than 3.54Eþ04.
thickness of tank bottom is eroded to the minimum acceptable Mai, Zhang, and Li (2011) took the damage factor Df(t) ¼ 300 as
bottom thickness is considered as the Maximum Acceptable Risk the target damage factor for large-scale atmospheric storage tanks.
(MAR) of tank. In standard API 653 (American Petroleum Institute, The damage factor Df(t) ¼ 300 correspond to risk value of 4.25Eþ04
2009), if tank bottom/foundation are designed with means or no for crude oil tanks in this paper, which is larger than 3.54Eþ04.
means for detection and containment of a bottom leak, the Based on the comprehensive comparison analysis above and
minimum acceptable bottom thicknesses at next inspection are inspection experience, it is reasonable to take risk of 3.54Eþ04 as
0.05 (1.27 mm) or 0.1 in (2.54 mm), respectively. The minimum the acceptable risk of the whole oil depot.
acceptable thickness of 2.54 mm is selected in this paper. When the
minimum remaining thickness of tank bottom is 2.54 mm, The
4.3. Comparison between RBI and Gumbel method
MARs assessed by API RBI and INTIIs predicted by corrosion rate
procedure of all tanks are showed in Table 5.
According to corrosion characteristics of crude oil storage tank,
It can be seen from Table 5 that the INTIIs for all tanks are higher
corrosion defects can be categorized into general corrosion, local
than 5e7 years specified by code SY/T 5921. The INTII of Tank 3 is
corrosion and pit corrosion. The primary factors affecting service
9.71 years, while the others are higher than 11 years. The INTIIs for
life of crude oil tank are local corrosion and pit corrosion. Much
Tank 1, 2, 3 and 35 are slightly higher than that obtained by RBI
research (Cao, 1988; Liang, Zhuang, & Jiang, 2000) have shown that
method at acceptable risk of 7.08Eþ04 in Table 4; the remaining
the maximum corrosion depths obeys the extreme value distribu-
tanks are higher than that of RBI method with the acceptable risk of
tion of Gumbel type I e maximum extreme value distribution

Fig. 7. Risk ranking of tank shell for all crude oil tanks. Fig. 9. The corrosion rate comparisons between tank shell and bottom.
172 J. Shuai et al. / Journal of Loss Prevention in the Process Industries 25 (2012) 166e175

Fig. 10. Flow chart of INTII prediction.

(MEVD), its distribution function and probability density function where x is the random variable of maximum corrosion depth, k is
as shown below the location parameter and h is the scale parameter.
   In Gumbel method, the INTII is defined as the in-service life
xk from last inspection or initial service time until the thickness of
FðxÞ ¼ R ¼ exp  exp  (3)
h bottom plate is eroded to minimum acceptable bottom thicknesses
of 2.54 mm specified by API 653. The calculation formula of the
    
1 xk xk inspection interval prediction for large-scale crude oil storage tank
f ðxÞ ¼ exp   exp  (4)
h h h is showed as following

D
Nf ¼  (5)
Table 4 yx 1  Cx ½0:7797 lnðln Ra Þ þ 0:4501
INTIIs predicted by API RBI for crude oil tanks.
where Nf is predicted inspection interval, years; D is corrosion
Tank no. The acceptable risk
allowance, mm; yx is corrosion rate, mm/a; Cx is the coefficient of
1.42Eþ04 3.54Eþ04 7.08Eþ04 variation for corrosion depth, mm; Ra is reliability, which is 0.999 in
1 70.06 87.99 104.28 this paper.
2 12.26 15.56 18.55 Fig. 11 presents the INTIIs comparison between Gumbel and RBI
3 6.40 8.12 9.69
4 8.80 11.17 13.32
method with the acceptable risk of 3.54Eþ04. For Tank 2, 6, 15 and
5 15.68 19.90 23.73
6 37.57 47.68 56.86 Table 5
7 9.46 12.01 14.32 Predicted INTIIs and MARs with bottom plate thickness of 2.54 mm.
9 13.07 16.59 19.79
Tank no. INTIIs MARs Tank no. INTII MAR
10 13.10 16.63 19.83
(years) (years)
11 8.55 10.85 12.94
12 34.13 43.32 51.66 1 105.16 7.33Eþ04 11 11.04 3.77Eþ04
13 14.50 18.40 21.94 2 18.64 7.20Eþ04 12 43.56 3.61Eþ04
14 8.77 11.13 13.27 3 9.71 7.13Eþ04 13 20.33 5.20Eþ04
15 15.26 19.37 23.10 4 11.44 3.86Eþ04 14 12.64 5.86Eþ04
17 23.55 29.88 35.64 5 20.84 4.24Eþ04 15 21.23 5.06Eþ04
18 9.99 12.68 15.12 6 49.66 4.15Eþ04 17 34.27 6.08Eþ04
32 12.51 15.88 18.93 7 13.21 5.13Eþ04 18 14.36 5.78Eþ04
35 16.74 21.53 25.74 9 18.67 5.62Eþ04 32 18.57 6.57Eþ04
10 18.44 5.28Eþ04 35 30.10 1.31Eþ05
Note: the dimension of INTII is year.
J. Shuai et al. / Journal of Loss Prevention in the Process Industries 25 (2012) 166e175 173

Table 6
Suggested INTIIs of crude oil tanks.

Tank no. Internal inspection Tank Internal inspection


interval (years) no. interval (years)
1 20 11 8.7
2 12.5 12 20
3 6.5 13 14.7
4 8.9 14 8.9
5 15.9 15 15.5
6 20 17 20
7 9.6 18 10.1
9 13.2 32 12.7
10 13.3 35 17.2

might be loaded in crude oil from different area or with different


corrosivity in the future, which result in the alteration of corrosion
Fig. 11. INTIIs comparison between Gumbel method and RBI method.
rate for tank bottom. For example, the predicted INTIIs of Tank 1, 6
and 12 are higher than 40 years. It is impossible to keep tanks
35, the INTIIs predicted by the Gumbel method are higher than by serving without internal inspection for such a long time. In stan-
RBI method; it is quite the contrary with that of the others tanks. dard API 653 also have a provision for INTII: the maximum intervals
There are two reasons for that: the first is the difference between shall not exceed 25 years for RBI assessment procedures. Because
the measured maximum corrosion rate and the maximum corro- corrosion rate is not constant over time, and the magnitude of local
sion rate predicted by Gumbel MEVD; the second is the difference corrosion rate and pit corrosion rate has certain randomness, the
caused by the principle of two prediction methods. determination of INTII for crude oil tanks should be based on
Fig. 12 shows the comparison between predicted corrosion rate conservative assumptions, and contain adequate margins to allow
and measured corrosion rate. It can be seen that the corrosion rates for uncertainties.
of all tanks predicted by Gumbel MEVD are higher than the Based on the operation and inspection experience and standard
measured corrosion rate except Tank 2, 6, and 15. Due to relatively requirements, safety factor of 0.8 is applied on the INTII prediction
low corrosion rate of Tank 2, 6 and 15, the inspection intervals of crude oil tanks. After the correction by the safety factor of 0.8, if
predicted by two methods are both higher than 15 years. However, the INTII of crude oil tanks is still higher than 20 years, it will be set
in this paper more attention is paid to crude oil tanks with short as 20 years. The suggested INTIIs of 18 inspected tanks are showed
inspection interval. The inspection interval of Tank 3, 4, 7, 10, 11, 14 in Table 6.
and 18 predicted by Gumbel method is lower than 10 years, and the
corresponding ratios between predicted corrosion rate and 5. Discussions
measured corrosion rate are 1.64, 1.31, 1.71, 2.36, 2.67, 1.44 and 2.10,
respectively. The predicted corrosion rates of Tank 3, 11 and 18 are Different countries or industry associations have different
higher than the others, and up to 1.52 mm/a, 1.22 mm/a and requirements on INTII. In China, the code SY/T 5921 has provisions
1.05 mm/a, respectively. Therefore, by the comparison of two for INTII: for crude oil tank it is generally 5e7 years; the maximum
methods, it can be drawn that Gumbel method is more conserva- of initial inspection interval for the new tank cannot exceed 10
tive than RBI method for tanks with short INTII. RBI method is years.
recommended to predict the INTII of tank. In United States, in standard API 653 (American Petroleum
Institute, 2009) the INTII is required as following: The interval
from initial service until the initial internal inspection shall not
4.4. The determination of the INTII for crude oil tanks exceed 10 years. When the tank has one of following conditions:
bottom thickness 5/16 inch or greater, cathodic protection or lining,
In practice, we can’t manage crude oil tanks completely in initial INTII shall be extended to 12e15 years. The interval between
accordance with the prediction result of INTII in Table 4. A tank subsequent internal inspections shall be determined in accordance
with either the corrosion rate procedures or the RBI procedures. For
using corrosion rate and RBI assessment procedures, maximum
intervals shall not exceed 20 and 25 years, respectively; for using
RBI assessment procedures and tank with a release prevention
barrier, maximum intervals shall not exceed 30 years.
In Europe, the standard EEMUA 159 (The Engineering
Equipment and Material Users Association, 2003a, 2003b) also
have specific requirement: For crude oil tank under warm and
humid climate (e.g. tropical and subtropical areas) or temperate
climate with frequent rain and wind, INTII is suggested to be 8
years; for warm and dry climate (e.g. desert locations), INTII is
suggested to be 10 years.
By the comparison of three standards, it can be concluded that
the INTII of 5e7 years in standard SY/T 5921 in China is more
conservative than that in standard API 653 and EEMUA 159, and
also more conservative than the predicted INTIIs above. Based on
Fig. 12. The comparisons between predicted corrosion rate and measured corrosion statistical analysis of corrosion data and inspection interval
rate. prediction for a lot of tanks, Shuai and Han (2010) and Shuai, Xu,
174 J. Shuai et al. / Journal of Loss Prevention in the Process Industries 25 (2012) 166e175

and Han (in press) argue that the inspection interval of 5e7 years in reasonable for 18 inspected crude oil tanks. Therefore, deter-
SY/T 5921 should be extended to 8e10 years. In Table 4, INTIIs of all mining the acceptable risk for the oil depot and considering the
tanks predicted by RBI method with the acceptable risk of influence of fire and explosion on risk assessment and INTII
3.54Eþ04 are higher than 8 years. Therefore, the predicted INTIIs prediction of crude oil tank will be our next work.
above correspond with Shuai’s research results.
However, the Periodic Internal Inspection Method has a number 6. Conclusions
of disadvantages for the management of crude oil tanks:
(1) The risk of tank shell is much smaller than the risk of tank
1) The tanks without severe corrosion defects are open to inspect, bottom for all crude oil tanks in an oil depot in China. So the
which will cause unnecessary expenditure in inspection and risk of crude oil tank is determined dominantly by the risk of
business interruption loss, e.g. Tank 1, 6, 12 and 17. tank bottom. 25% Equipment items account for 90% of the total
2) Some tanks with high deterioration rate are not timely risk in crude oil depot.
inspected and repaired, which will lead to potential safety (2) According to risk assessment and risk ranking of 19 unin-
hazard or in some cases may cause leakage accident of tank. spected tanks and the requirement of INTII in code SY/T 5921 in
3) Periodic Internal Inspection Method not only does not consider China, they should be immediately inspected to determine the
the effect of COF on the risk of tanks, but also does not consider corrosion state of tanks and reduces risk uncertainty, in
influence of the plant’s management system on the integrity of particular, Tank 36, 37, 38 and 16 should take priority for
crude oil tanks. A good plant’s management can reduce the POF inspection.
of tank. (3) In RBI method, the predicted INTII of crude oil tank gradually
4) It lacks the freedom to benefit from good operating experience increases with the increasing of the acceptable risk. Based on
and focus finite inspection resources on the areas of the comparison analysis among calculated MARs of 18 inspected
greatest concern (Wintle & Kenzie, 2001). tanks, the acceptable risk proposed by Mai and inspection
experience, 3.54Eþ04 are taken as the acceptable risk. The
RBI is a method which use risk as a basis to prioritize and manage safety factor of 0.8 is used to adjust the INTIIs of 18 inspected
inspection. RBI shift from passive inspection to active inspection. crude oil tanks.
Different crude oil tanks have different inspection intervals, which (4) The INTIIs predicted by Gumbel method are more conservative
can be flexibly determined by the risk of tank. RBI technology not than RBI methods for tanks with short INTII.
only quantitatively assesses the risk of storage tank and improves (5) By the comparison of three standards in inspection interval, it
risk level of oil depot by paying attention to high-risk tanks, but also can be concluded that the INTII requirement of 5e7 years in
can predict inspection interval of crude oil tank. However, in the code SY/T 5921 in china is more conservative than that of
consequence analysis of atmospheric storage tank, API RBI only standard API 653 and EEMUA 159.
considers the influence of leak on storage tank risk, but does not
consider the influence of flammable and explosive consequences.
References
Although the possibility of failure of fire and explosion for crude oil
tanks are very small, it may cause catastrophic accident. API 580 American Petroleum Institute. (2002). Risk-based inspection. Washington,
As we mention above, crude oil tank might be loaded in crude D.C.: API Publishing Services.
oil from different area or with different corrosivity, so the corrosion API 581 American Petroleum Institute. (2008). Risk-based inspection technology.
Washington, D.C.: API Publishing Services.
rate of crude oil tank is not constant over the interval between two API 653 American Petroleum Institute. (2009). Tank inspection, repair, alteration, and
internal inspections. The corrosion rate calculated from the differ- reconstruction. Washington, D.C.: API Publishing Services.
ence of thickness between two inspections is the average corrosion Bai, M., & Liu, Z. W. (1995). Economic benefit analysis of large-scale oil tank.
Petroleum Engineering Construction, 1(6), 8e10.
rate. So the short-term corrosion rate (actual corrosion rate) is
Cao, C. (1988). Statistical analysis of corrosion test data. Beijing: Chemical Industry
significantly different from the long-term corrosion rate (average Press.
corrosion rate). However, it is difficult to measure the actual Chang, M. K., Chang, R. R., Shua, C. M., & Lin, K. N. (2005). Application of risk based
inspection in refinery and processing piping. Journal of Loss Prevention in the
corrosion rate of tank without opening tank. In addition, corrosion
Process Industries, 18, 397e402.
rate of pitting for tank bottom has randomness. The determination Chien, C. H., Chen, C. H., & Chao, Y. J. (2009). A strategy for the risk-based
of corrosion rate of pitting is not the research scope of this paper. In inspection of pressure safety valves. Reliability Engineering and System Safety,
this paper we just focus on the general corrosion in prediction of 94, 810e818.
CWA 15740 e The European Committee for Standardization. (2008). Risk-
INTII for crude oil tank. Therefore, we assume that general corro- based inspection and maintenance procedures for European industry
sion is the dominant damage mechanism and corrosion rate is (RIMAP).
constant over the interval between two internal inspections in all Dai, G., Li, W., & Long, F. F. (2002). An acoustic emission method for the in service
detection of corrosion in vertical storage tanks. Materials Evaluation, 60(8),
crude oil tanks. 976e978.
The determination of reasonable INTII for crude oil tank has EEMUA 159 The Engineering Equipment and Material Users Association. (2003a).
a great significance in balancing the safe operation requirement Users’ guide to inspection, maintenance and repair of aboveground vertical cylin-
drical steel storage tanks, Vol. 1. London: EEMUA.
of crude oil tanks and inspection costs. However, now it is EEMUA 159 The Engineering Equipment and Material Users Association. (2003b).
difficult to confirm that 3.54Eþ04 are the most reasonable Users’ guide to inspection, maintenance and repair of aboveground vertical cylin-
acceptable risk for oil depot. Because there are still 19 unin- drical steel storage tanks, Vol. 2. London: EEMUA.
Guo, B., Shen, G. T., Zhang, W. L., Li, F. H., Wang, W. H., Zhao, Y. X., et al. (2010).
spected tanks with the uncertainty on corrosion rate, and the Application of RBI technology in atmospheric storage tanks. Pressure Vessel
determination of the acceptable risk of 3.54Eþ04 is based on Technology, 27(4), 55e60.
corrosion data of 18 inspected tanks. RBI risk assessment is Jiang, S. Q., & Li, X. X. (2005). Research and development of high strength steel plate
for large oil storage tank. China Steel, 1, 20e23.
a continuous improvement and dynamic process. After several
Li, G. Y., Wang, A. F., & Yang, S. X. (2005). Calculation of the remaining life of
years, all tanks will have at least one internal inspection, and corroded tanks. Journal of Daqing Petroleum Institute, 29(1), 67e68.
then we can obtain more information and have a better Li, H. B. (1996). Development of large-size oil tanks. Petroleum Refinery Engineering,
understanding of deterioration rate for all crude oil tanks. The 26(6), 24e26.
Liang, C. H., Zhuang, S. L., & Jiang, H. F. (2000). Development of corrosion life
nit is possible for us to determine the acceptable risk for the prediction system for petrochemical equipment materials. Petro-Chemical
whole oil depot. But the acceptable risk of 3.54Eþ04 is also Equipment, 17(4), 51e54.
J. Shuai et al. / Journal of Loss Prevention in the Process Industries 25 (2012) 166e175 175

Liu, X. N. (2005). Reliability prediction of corrosion residual life of steel pressure SY/T 5921 Oil and Gas Storage and Transportation Standardization Technical
vessel and pipeline. China Petroleum Machinery, 33(2), 35e38. Committee in China. (2000). Code for repair of vertical cylindrical weld steel crude
Mai, Y. S., Zhang, P., & Li, G. H. (2011). A study on the method and application of the oil tanks. Beijing: Petroleum Industry Press.
integrity assessment on large e sized storage tank of Sinopec Guangzhou. Petro- Wintle, J. B., & Kenzie, B. W. (2001). Best practice for risk based inspection as a part
Chemical Equipment Technology, 32(1), 1e7. of plant integrity management. TWI research report.
Shuai, J., & Han, K. J. (2010). The remaining life prediction and INTII analysis for Xiao, J., Liu, L. C., & Ou, Y. H. (2005). Reliability calculation for corrosion of bottom
large-scale crude oil storage tank. In Proceedings of the 8th international pipeline plate of oil tank. Corrosion & Protection, 26(5), 205e207, 219.
conference. Calgary, Alberta, Canada. Yuan, G. J., Xu, C. Y., Wang, W. H., & Li, G. H. (2009). Application of quantitative RBI
Shuai, J., Xu, X. R., & Han, K. J. The study of overhaul period for crude oil tank. Acta technology in large storage tank group. Petrochemical Safety and Environmental
Petrolei Sinica, in press. Protection Technology, 25(3), 23e26.

You might also like