You are on page 1of 15

WORK SIMPLIFICATION FOR PRODUCTIVITY IMPROVEMENT

A case study: Kaliti Metal Products Factory

Daniel Kitaw
Mechanical Engineering Department
Addis Ababa University
and
Tibebe Belachew
TBA Engineering PLC Addis Ababa
ABSTRACT It is a well-known fact that the most productive
companies and government productivity-oriented
The tools and techniques of work simplification are policies are strongly committed to the promotion of a
used increasingly in industries, utilities, private and better quality of working life, participation, market
government institutions, and in all process involving economy principles, individual initiative and
tasks including paper works. Articles in the popular creativity, and human-oriented management styles
press concerning the work simplification techniques and practices.
state that Productivity shall improve upon
intelligently developed and improved work methods The manufacturing industries in Ethiopia whose
by elimination of waste of any kind in a process. establishment dates back to the 1950 are using the
This article introduces the tools and techniques of early 20th century techniques with slight renovation
work simplification, implementation strategies for and slow build up of recent technological know-how.
productivity improvement and its application in The productivity has not improved significantly, and
Kaliti Metal Products Factory. The outcome of the in some cases it was observed that there is a decrease
research has indicated an encouraging result. The in productivity further aggravating to "unproductive"
probable annual net profit gain by use of the situation. The effect of such "unproductive" situation
simplified work method developed, as applied to in some sectors and reduction in productivity
tube production only, is estimated to be Birr 3 improvement in almost all manufacturing industries
million. This profit gain would have increased the have been reflected through failure in
1993 E. C. declared profit by over 55% Application competitiveness due to high cost of production, less
of the same principles for other types of production, quality and limited output.
Secco profile, Cut-to-size plates, etc., is likely to
generate more profit gain. To improve productivity in general, one has to be
aware of all the critical factors (forces or impacts)
INTRODUCTION that change the productivity level and its rate of
growth, such as inputs-related factors: Capital, Plant,
For many years, productivity has been a key issue for Technology, etc.; Process-related factors: Work
all government and private companies. This is methods, Organizational style, etc., in order to
because of the impact of productivity on economic influence them by adopting different sets of actions.
and social development and its importance as a
source of income and an integrative objective, One approach in productivity improvement requires
encompassing as it does improved labor-management high investment in renovation of the old plants and
cooperation, workers' participation, the criteria for introduction of new equipment, technology, and
enterprise competitiveness and the formulation of a qualified manpower. But due to the economic and
long-term strategy for governments, employers and financial problems encountered in the local industries
employees in alleviating poverty and promoting the need for productivity improvement using this
human rights and economic democracy [1]. approach is none too practicable.

Journal of EEA, VoL 24, 2007


44 Daniel Kitaw and Tibebe Belachew

The alternative, approach to productivity results in the elimination of wasteful application of


improvement is the promotion (strengthening) of the human effort, materials, equipment, and facilities as
impacts of the positive productivity factors and the well as in the maximum return for each unit of effort,
elimination (reduction) of the impact of negative money, or time expended [2].
productivity factors (barriers) at minimal Work Simplification is an old tool. The name was
expenditure. actually given by Erwin H. Schell ofM.LT. Allen H.
Mogensen (1930's) with his Lake Placid, NY
Mostly considered productivity barriers are the conferences popularized it [3].
uneconomical and inefficient work methods, loss of
energy, materials and manpower. Productivity A fundamental premise of Work Simplification is
improvement gains are certain, as justified by records that any work that does not add value to material, or
of those who implemented the principles, teclmiques service is reducible waste. There are four types of
and tools of work simplification. reducible waste: transportation, delay-storage-idle,
inspection, and failure to use known faster devices.
This article covers work simplification and
productivity issues and provides current WORK SIMPLIFICATION PROCEDURES
technological findings, the state of the art in work
simplification concepts, theories, techniques and The most important productivity factors in work
tools in general, its application and results of simplification process are linked with: human
implementation of the techniques in the Metal resources (workers, specialists and managers);
Industries like the Kaliti Metal Products Factory. Product design; Technology; Plant and equipment;
Materials and energy; Work methods; and
PRODUCTIVITY IMPROVEMENT & WORK Organization and management styles.
SIMPLIFICATION CONCEPTS
Improved work methods, involving scarce capital,
Productivity in its broad sense is a measure of how intermediate technology and labor-intensive methods
efficiently and effectively resources are used as constitute the most promising area for productivity
inputs to produce outputs, products or services ofthe improvement.
quality needed by society. Productivity means
creating more benefit for consumers, workers, The systematic approach to work simplification
employers, enterprise owners and society at large involves seven steps. They are described as follows.
from the processes and resources employed in the
activities of the organization. Step 1 Identification of the Problem

As an efficient measure, high productivity implies Locating work problems and properly identifying the
that production inputs are fully utilized and waste is various factors involved is the only reliable method
minimized. Effectiveness, on the other hand, means of determining where improvements can be made,
that outputs (and activities and processes) contribute how much effort is justified in developing an
to the attainment ofthe organization's specific goals, improved work method that can most effectively be
whether these be meeting customers' demands, the developed.
achievement of business aims or a contribution to
attaining the social, economic and ecological Defining a problem in precise terms, and
objectives of the society. Productivity Improvement identification of the various factors involved is
is an increase in productivity and involves the use of extremely helpful. Finally, the critical factors will be
high quality resources to produce outputs that are of identified and listed. These factors will be used to
constant or better quality [1]. judge the worth of the proposed solutions to the
problem.
Work Simplification is a tool of cost reduction and
finding a better way, making the best use of existing The proper identification of work problem may be
tools, equipment and human energy. It is a systematic facilitated by a preliminary survey. As a guide in
analysis of all factors that influence job performance, determining the type of job to select consider jobs
the application of principles of improvement, and the that:
design of correct work procedures. Improvement

Journal of EEA, VoL 24, 2007


Work Simplification for Productivity Improvement 45

• Involve the greatest cost (labor, material,


burden); Knowing what questions to ask of the job or its
• Are continually behind schedule (bottlenecks); details is crucial. The six questions used in work
• Will be running for several months or years; simplification are what, why, when, how, where and
• Is time consuming (red tape); who. Each of these questions is vital to the complete
• Involve hazardous condition, understanding of the situation. The question "why"
especially has been credited with effecting the greater
Step 2 Method Analysis improvements. Applying these questions to each
detail of the job maintains an open mind in order to
Getting the facts of the problem requires objective visualize the possibilities for improvement [4]. The
thinking in terms of functions. Determine the main open-minded approach requires to looking for
reasons and not excuses.
objectives of the work under study, and how these
objectives can be attained.
Step 4 Develop a Better Method
The flow Process Chart helps to reduce a complicated
operation or process to a comprehensive word picture The many possibilities for improving the individual
[ANNEX 1]. work steps and the entire task, which have been
developed in step three, should be carefully re-
With a detailed description of each step in examined. With clear thinking one can assess the
chronological order, the possibilities for merits of the individual possibilities, and with
improvement become obvious. Rules and defmitions imagination can visualize how these individual
to follow in using the chart, in order to obtain the best possibilities can be utilized and related to the overall
results are indicated below [3]: job.

• Determine the job and decide on the subject This detailed consideration of each and every
selected for analysis. In most instances an possibility for improvement should lead to the
selection of the several most meritorious and
operation involves a person, a product, and/or a
paper form. One of the three is picked as a promising suggestions for improvement.
subject and every entry on the chart refers to that
specific subject. Applying the questioning attitude with an open-
minded approach reveals many possibilities for
• Record every detail as it occurs. Avoid the improvement. When an inlprovement is made on a
tendency ofleaving out details even they seam to shop or an office operation, the improvement is made
be minor. All details are important and should be by: Eliminating unnecessary jobs, Combining jobs
recorded in the sanle order as they occur. wherever possible and Rearranging sequence of
operations for more effective results and Simplifying
• Make several short charts than a long single
the operation.
chart. Make sure you have a fixed starting and
stopping place. Record only the necessary steps in the operation.
Once all the possibilities for improvement have been
• Understand the symbols used in the flow process considered, it is ready to reconstruct the job in a way
that will produce the best results.
chart properly. The action-taking place must fit
the description of the symbol applied on the
chart. Step 5 Review the Problem and Analysis

If one ot more improved methods have been


Step 3 Challenge Every Detail & List all
Possibilities for Improvement developed, the next logical step is to subject these
proposals to a critical review and to evaluate the
effectiveness of the proposals as solutions to the
The third step in the work Simplification pattern is
when the job is put on the witness stand and original problem. The most advantageous proposal
can be selected as a result of this examination and
questions are asked that lead to possibilities for
improvement. evaluation if more than one proposed method has
been developed.

Journal of EEA, VoL 24, 2007


46 Daniel Kitaw and Tibebe Belachew

The final selection of one of the alternative proposals Effective and complete use of the improved method
may be deferred until after the validation of the is the only way to achieve any of the benefits
proposals by trail under typical conditions of work. associated with the improved method. One must
The soundness, accuracy, and completeness of all make certain that the improved method is properly
work done up to this point should be checked. Any installed, that it functions as predicted, and that it
errors, or omission should be rectified by appropriate continues to function as intended.
corrective action.
Some sort of standard operating procedure should be
When the proposed method or methods have been prepared to provide a record of the correct job
thoroughly checked, then one is ready to evaluate method and conditions. This record will most likely
these proposals. This evaluation is made in terms of be based upon the chart of the improved method as
the same considerations made in step one when the previously prepared in the preceding steps. Cost
problem was defined and the factors involved in the reduction reports may be used to check the operating
problem identified. effectiveness of the improved method.

A balanced sheet listing the pros and cons for each APPLICATION OF WORK SIMPLIFICATION
factor for the present and the proposed methods may INKMPF
be prepared. This may take the form of a cost
reduction report based on the concepts of engineering For work simplification application a government
economy. owned metal industry, the KaIiti Metal Products
Factory, KMPF, was selected. KMPF is one of the
Step 6 Validate the New Proposal metal producing factories by making use of cold
forming process with relatively old machineries and
The previous steps have been designed to ensure the low level of technology.
development of sound and workable methods for
improvement. These methods must now be tested to Kaliti Metal Products Factory produces five distinct
make certain that they are feasible. This testing types of products. These include: the
should be done in such a manner that any and all Square/Rectangular/Circular hollow tubes; the Cut-
assumptions are verified. to-size plates; the EGA 300 roofing sheets; the Secco
doors & windows frame profiles; and the Corrugated
Validation may involve extensive experimentation galvanized sheet.
and research to test assumptions or to develop
equipment, processing, or materials, or it may Systematic data collection and analysis is required to
involve a simple trail run for the proposed methods. improve the productivity of the existing plant using
The main objective of the testing is to gather work simplification techniques and tools. This is the
information about the workability of the proposed first step in work simplification.
methods and to supply verification for the
information presented in the comparative analysis of In problem identification process evaluation of the
step five. work procedures, work site conditions, etc., of the
existing factory are done based on group discussions,
Step 7 Install the New Method Effectively video motion pictures, and production records.
Committees were organized to work in collaboration
This is the final step, armed with the facts and ready with the authors for identifying problem areas. Data
to face the challenge. How to do it? How to get sheets were prepared for data collection. The
people to accept the change? How to get respective supervisors and foremen completed the
cooperation? There are three common ways of data sheets as per the training given by the authors at
getting results: telling, selling and consulting. Tell site [5].
them about the change, without a show of authority.
Sell them by explaining why, and consult them for
their opinions on how further improvement can be
made [4].

Journal of EEA, Vol. 24, 2007


Work Simplification for Productivity Improvement 47

Identification and Selection of Productivity The tube production in Kaliti Metal products Factory
Improvement Problems (\Vork simplification amounts to 60 % of the total production capacity of
stepl) the plant. The broad categories of products varying in
dimension, from the smallest 15 x 15 x 1.2 mm to the
A number of techniquesl are in use for problem largest 100 x 100 x 4.5 mm tubes, dictates frequent
identification and selection. Weakness analysis is change of dies and setting up of the machine.
widely implemented and the relevant detailed
questionnaire on workflow, workplace layout, work As recorded in the 1993 E.C. budget year Armual
methods and procedures are used for screening Report, the down time due to the die change,
possible problem areas. miscellaneous set-up and machine trial of the tube
production machine amounts to 1011.29 hours. The
Some of the identified major problems are: high die annual work-hours is estimated to be 3136. This
change and machine setup time, improper market indicates that over 30 % of work-hours was in
analysis; low performances due to old productjon wastage.
machinery and quality of the raw feed stock,
improper plant & machinery layout; lack of initiative Analysis of the Identified Critical Problems
in developing new service and products; machine (Work simplification step 2)
breakdown; and improper materials management
system. Among the classical techniques for detailed analysis
of selected critical problem areas the Method study
The production process for each type of production is analysis technique is implemented for analysis of the
studied and subsequently data was collected to "High Die Change and Machine Setup Time".
determine the time consumed for "Make ready",
"Do", and "Put away" operations. After problems The relative time consumed by machine setup arid die
have been identified, selection of critical problems change time is considerably high because of,
and priorities of action are determined. For the according to the authors' opinion, the small order
selection of certain critical problems and setting quantity produced. Such manufacturing condition is
priorities the work simplification techniques were not viable from the economic point of view. Thus, it
utilized. is required to define the minimum order quantity, the
brake-even-point, for each size of product to be used
Accordingly, one of the selected problems for further as a reference.
analysis is the "High Die Change and Machine Setup
Time". The selection of this critical problem is On the other hand, the time consumed in machine
justified for the following reasons. [The remaining setup and die change operation involves unnecessary
critical problems are not considered in this article). work/job components. These unnecessary job
components were identified through motion study, by
Machine setup and die change in three types of fractionating the job into smaller units, elements, the
products, the Tube, the Cut-to-Size Plate and TherbJigs, according to the function of those units
Corrugated Sheet Production, is found to be about and have been eliminated to reduce the total time
77% higher than the production time. According to [Armex 1 to 5).
the principles of work simplification the "Make ready
a)ld put away" portion need to be minimized to the Motion Study, the Flow Process Chart (Work
lowest possible time and increase the "Do" portion simplification step 2 & 3)
that add value to the product. Therefore, further data
collection and analysis is done to minimize the In the survey conducted the tube-forming machine
"Make ready" and "Put away" operation and set a was producing 50x50 mm square hollow section
Break-Even-Point for each type an~ size of product. tube. After the required quantity had been attained,
there was a need to change the dies for the next
scheduled production of 60x40 mm rectangular
These include Weakness analysis; SWOT, Strength, hollow section. Records were made on the die change
Weakness, Opportunities and Threats analysis; Portfolio
and setup process breaking it down to 69 work
analysis; Pareto analysis; Sensitivity analysis; and Force-field
analysis. components [ANNEX 1).

Journal of EEA, VoL 24, 2007


48 Daniel Kitaw and Tibebe Belachew

This case, for instance, indicates the smallest possible Factor analysis2, the most effective general method of
die change process time that involves changing five evaluating alternatives has been employed for this
sets of finish forming dies. The largest possible die purpose of alternatives evaluation. [ANNEX 5]. Due
change time is observed when there is a change of up consideration is given to those functions that
to 18 sets ofroll forming dies, up to 20 sets of guide consumed relatively long time and alternative
rollers, and 5 sets of finish forming dies (usually methods are generated.
when there is a jump from smaller size to larger size
tube production). In the process of the elapsed time analysis the time
takerl for each job component is, whether done
It is observed that, the time taken to complete the die sequentially or in parallel, added up to calculate the
change process was 225 minutes. Each step of total time taken under both the present method and
activity with the corresponding elapsed time is the recommended method for comparison purpose
recorded in the flow process chart prepared for such using the traditional Flow Process Chart. For more
analysis. clarity and more accurate comparison the gang flow
chart is developed [ANNEX 2] by dividing the whole
Analysis is made, using the recorded flow process process in five gangs working in parallel and found
chart, to identify which step has consumed a lot of the result fairly identical to that of the traditional flow
time, and for duplication of effort, backtracking, process chart [ANNEX 3,4]. This chart reflects the
excessive handling, costly delays, hazardous actual process done in the die change and set-up
conditions, fatigue, etc. operations.

The Break-Even-Point Analysis (Work CONCLUSION


simplification step 3)
The new developed method for die change and set-up
The break-even-point is defined as the quantity of of the tube production process resulted in substantial
products required to be produced to cover the costs of reduction in time and effort of human energy
production and all factory and overhead expenses expended in the process.
including depreciation, property tax, insurance, rent,
etc. and any other related costs. The break-even-point The recommended method:
is calculated as the ratio of fixed cost to the • Saves about 59% or, in terms of actual work
difference of the unit-selling price and unit variable time, the improved die change and setup time
cost. runs for 92.25 min. (1.54 hrs.) instead of 225
min. (3.75 hrs);
Based on the information obtained form the financial
department of the factory and the data from the • Thereby reduces the relative time consumed by
observation made, the Break-I;<:ven-Pointis calculated "Make ready" and "Put away" operations to
to be 650 Pcs. The amount produced while under 48.5% mstead of 87% [5].
study was 384 Pcs [5].
One of the merits of the proposed method is
Flow Process Chart Analysis (Work simplitication envisaged in the possible saving of the downtime,
step 4 & 5) disclosed in 1993 E.C. Annual Report, by proper
implementation of the proposed improved method
For work simplification analysis each work amOlmts to 596.66 hours.
component recorded in the flow process chart is
studied separately considering the possibilities for
Elimination; Combination; Rearranging; and
Simplitying in sequential order. Based on this work 2 It follows the engineering concept of breaking down the problem
simplitying procedure, recommended methods are into its elements and analyzing each one. The procedure involves
proposed for each work component. The proposal for • Identifying the alternatives to be evaluated,
recommended work methods is done after a 1hrough Establishing the factors or considerations,
study and analysis of possible alternative methods Arranging a rating sheet,
Determining the relati ve importance of each factor,
using Charts for Evaluation of alternatives.
Rating each factor for different alternati ves, and
Calculating the weighted value and total.

Journal of EEA, Vol 24, 2007


Work Simplification for Productivity Improvement 49

Assuming that "only" 50% of the saved time is Sincere 1hanks are expressed to 1he following KMPF
utilized for the production of tubes, the amount of Management and Senior staff:
tubes produced, at 1he rate of 30 meters per min (This
is 1he average capacity of the tube machine and that Matiwos Assele, General Manager,
experienced during data collection.), shall be 89,499 Endeshaw Zenebe, Tech. Prod. Manager,
pcs. The gross profit (sales-cost), for 89,499 pes of Yared Efrem, Standard Products Division Head,
tube amounts to Birr 4,547,444.19. Fixed cost and
payable while producing 1his product, at 1he rate of Aschalew Worku, Tube & Secco Production
2417.83 Birrlhr. (Data obtained from Break-Even- Foreman.
Point analysis) becomes Birr 1,442,622.45 [5].
REFERENCES
The net profit gain by use of the simplified work
method, as applied to the tube production only, is [1] Joseph Prokopenko and Klaus North,
estimated to be Birr 3,104,821.74. This additioIfal Productivity and Quality Management. Modular
profit may have increased the 1993 E.C. declared Programme, 1997.
profit of Birr 5,599,000.00 by over 55%. Application
of the same principles for other types of pro duet ion is [2] Frank B. Gilbre1h Motion Study,
likely to generate substantial profit gain higher than
the indicated figures. [3] David Ferguson CSP; The Gilbreth Network,
http://gilbrefunetwork. com,
Here it is to be noted that in 1he application of work
simplification steps 1he first five steps were [4] liThe Journal of Methods-- Time Measurement
considered. The authors hope to see the validation Volume X; Number 3 --Update of the Basic
and implementation of this new method, Step 6 and Techniques. Work Simplification ",1997.
7, for the benefit of the employee and management of
KMPF in particular and the country as a whole. [5] Tibebe Belachew Productivity Improvement on
the basis of Work Simplification, Ergonomics &
ACKNOWLEDGEMENT Industrial Sqfety. MSc. Thesis, Addis Ababa
University, Mechanical Engineering Department.
Full supports have been extended by quite a number (Advisor: Dr.-lng. Daniel Kitaw) July 2002.
of institutions. Among many, 1he authors are
indebted to the management of 1he Basic Metals
Agency, management and employees of the Kaliti
Metal Products Factory for the assistance offered
during the research work upon which 1his article has
been developed.

Journal of EEA, Vol. 24, 2007


50 Daniel Kitaw and Tibebe Belachew

ANNEXl DIE CHANGE AND SETUP, FLOW PROCESS CHART

the 2nd roller dies set , Pipe


,
OSItime
t--i
j(
~.
~,
Removal
Measuring
~ ~ 11=~
lOnIDg
•.
0:;]
0:
j(f-aJ-.
Removal 0: ~
Elapsed
Untightening
Cleaning
Cutting
Hoisting
Removal
Washing
Inspection
•.
~~.
~~, o~
o~
5U,.J;Vmd.'f
id.aJ ""
,
Ij:;]
1j:1j5
5:
5:
Ij:;]
5:
5:22
5:26
.4;>u:t09
5:00
•.cutting,
Positioning
Measuring 0: ~
time
Ij:
Ending 05
08
i/f(mill.)
5of
Of
05
0{ 05
8
509
05
{7
2Event
{6
of
finished5Cut
.?oo.?
1j0
{Ij
machine
and
of
"""" q0V'D
ganuy
Method
Recommended
XaM;
(A!..!..
{2nd
"'"
~••.
each
6.is,;.
of 1st
5.· Ij:
decoder0:52
off
installed
m(5;
bolts
removed
crane
4:38
lubrication
length
fdies
5:section
dies
manually,
thickness
d.m...ap-
I.M. bed 1:42
a.lIad..d.
3:41 1j0
PROPOSED
XYlZt1"Y
4set
6of
roller
PRESENT
SAVINGS
0:050:13
used
8:13
d.m...laJo
a.t52:34 :32
f:27
Start
Description
58.20
machine
m.i.I.
0
5.·
0:18%set
8ckz."7< ,~"~\V
:(
IOr
bearing
TRANSPORT
{6 from
~for
I.M.
5:
dies
~<
/' )(,/.-iI'$,
bearing,
from
to
jJ.=Jto
of
from
of Ij:
scale
fIx
DELAY f7
to
tube
71st
disco-
6installed
d.m...laJo
I.M.50% 50%
Ij:
Ij:;]
5:
5:
11:05
,)...t
OPERATION ;]TIME
Ij:{5
{7
;]1zI.ja;f-
SYMBOLS
fa1j5
i ./
C. EVENT
--.....
INSPECTION
............
j(..t;, ""'Fin<o.d
.11~?",~~
:A~~~
J-nM.aJ.
41.80Ij:;] METHODS
8~/"'f.l1IJ.."."diu<-
>vm.a1l "'r ~
a{
TIME ANALYSISU""'<>I~~"'"
ANALYSIS 1&,~
1&,¥~
81i/mimcM ••..~t.y. .11~
&. a.i4'
""

Dv 5:
5:00 09time t.I...-
tL on machine bed
/0
s, using crane) and
a",kw-
from the 1st roller dies set roller stands.
remove cut outusing
piececrane, and
saving
ng it on machine bed

Journal of EEA, VoL 24, 2007


Work Simplification for Productivity Improvement 51

ne,
mg and
lacingIt on
Ov
nspected
rnachme
it on machine
bearing
it on machine bed
bedbed
for next use
I ~.
~~e", from
5 0% the
I."" ",a6/~~,
)\/
~'4•¥~,
Removal
Selection
710.
Cleaning
Hoisting
Assembling
Removal
Inspection
710.
u", 0:
0:
r1o.~~
..........
Steps Removal
Removal.of
Hoi~ti.ng
Cleaning
Hoisting
Washing 0:
U:
0.'
0:
'Unm.u.~5:
5:
5:
5.'
5::1
:J:
'!/.o..c.o-~
0.'
time
6:00
Elapsed
9time,min
'Unm.u.v='4
~~, ~
U-niVm.d'l
U~'t~1oMo
~~~&v.fv
~
~ \---
roller'\--
1\
1/
~

stands, usmg
3rd
05
06
08
~~O{
UI
O{
09
05
08
05
07225
{I/
01/
Ending
0.'
a.&"..,.,.
~.~
{9
"'X
2of
27
35
23
26
of
of
e..",.,
~J,,~,
U,.,I>«;1'~"""
U~AhMv",j'l
5:
roller
27
of5:
1
Event
of
and
of 5:
3Recommended
358of
Y
~~5: 22 'x
375:
5:
crane,
/"w, dies
J(
6{4th
Method
50
(3rd
each
new {8
22
roller
5th
~~
bearin~
roller )\
;;:.
¥0roller
installed
holding
{7
installed
bearings set
dies
bearing:;
~removed
Ii
2dies
dies
rk-nt,
~
5: 22
..' and
50setand
dies
lubrication
dies
~~
of
Description
X;:.
% set
dies
set
()1
;(
into
)\)))
..•
5:
5:of
dies
of
5:
bearing
bearing
into
of
Starting
a.iA.
~~
~~
/"w,50 1a6lc
tadv
2{9
2nd
from
3rd20
22
bearing,3
bearing,
&v.fvfronl
from
~ /
1<
~
1st
{set
from
3rd
the
2ndset
5:
replace-
replace-
set
I.ad.
IoMo
%
&v.fv SYMBOLS
{9
16
{8
:J:42 20
5.' \
5'{92 {/.. ; I,' A~'(~~
5:
5:22
time•

"':
I
A~~e,.~ A~~~ 5: 20
A~,/""",,~""f"
A~.,~~
A~~~
2{8{
71.(..U)- r/I..aI1'lk
?.i.M-

~,~~e",
(l,o'y

e..",.,
int-
50 %
A~~kM,"t"
U,.,~am.d~7'
A~'f=""~

om the 4th roller diesu)~ set roller stands, using crane, %


~

Journal of EEA, VoL 24, 2007


52 Daniel Kitaw and Tibebe Belachew

DDV
inspected bearing for next use
from the 5th roller dies set
/,\-\-\-.\---'"---//¥~,//--
.....---w...U:
Steps IYOSltlOnmg
~'4
uaugmg
\fdugmg
'ri4.~
'ri4.
Removal
Cleaning
Changing
Washing
Removal
Cleaumg
Washing 0:
U:
lDSUiua
I.M.
Gauging U:~:
5.
6:
5:
6:
5.·
5:
5:

~:IIO
J:II~
0:
0:
0:&.".
6:
time
a."
Elapsed
time,min
~~Ca.;J<.
&.".
&.".
~,
'Ik.
lnstallation
Installation
Hoisting
Assembling
Inspection
----
~\~
31UO
~05
08
6:Ending
~~d".."..1ad.
'Ik.
1~
38
07
06
111
05
08
50
10
'"fw;A
~d".."..iado
id..al.
~
'L&vn.u~
~,
-X
on 1st dies set
6: )X
JU
210
==m.<mf UZ
of
and
and
~."..
35
1/5
5.· 2:3
~of
83ana
35
2and
53
2832
55
Event
2of
31/
1/5
of
Ion 55:
555·
of~:
Ia1st
gamry
1
Recommended
8J:
a
of50
Method
/0
%
each
21/
II
roller I1%roller
installed
&.".
w...
bearings
removed
of
fY'<~'
&""50%
d".."..
~:crane
aOJusunem
dies
adjustment
lubrication
lubrication
replacement
replacernent
23 5:JUX
~replacement
"\
f
/
K\/V
.(
dies
of
/
Z ~dies
jf-
if 5:
Description
aaJusunem
0holding
rep 5:50~
tA.
1/7%
acemen.
~I\ *~
) V~')(-i(
t
\ ~'"
5:lOr
bearing
into
21/
Starting
d".~
-mil on22:3
5th
for
/0on
of
4th
of 5:
bearing,5
iado
d".."..
~U
d".=
N
pfad-
: 1/7 5:1/7 6:1/5 time
~
5:
~
1\
lad.
011
<M.
<We 1/7
3Sl
Lno
~:
utes
set
cut-
4th
5th
3rd
4th
replace-
dies
iado dies A1
;<::
5· ~.
5.· 2:3
21/
~.
V
25 ~SYMBOLS
./
'Ik.
A~
A~
w,.
.9rvkJ.
~fY"'"t.-~r
~t.-~e..,
-..am..~f"~
X--
~A~
;r~B-~v..
'f'aM.
~ 'f'aM.
"""A~
Y-..am..~~
~
~ 5: 1/7
~ fY"'"'"''W'"
~ 'f'aM.
fY"'"'-"'''ff''
"""""',
'f'aM.
t.-~e..,&.". 50 %
~f'Y"
~ f'Y" 'Ik. ~/"'''"t.-~r
~
Y-..am.. fY"'"i<>0f< r
~f"'d.vv,.
Y-..am..~f"~

Journal of EEA, VoL 24, 2007


Work Simplification for Productivity Improvement 53

50n..
n..~
n..
n..~%7:
w=luf,
0.·08
0:
0:
O. 7. Recommended
7.·1/5
6:
0:7:09
02
0802
01 05
35
215
1/5
t,7Method
55
87
07 6·53 7:It
85 ItSYMBOLS
I
6~
~
~t,
~,
time,min
~, I.M.26
02
Steps Reinstallation
time
u>~nf
Assembling
Hoisting
e..", 17
wmnnvni
...•.
Event
co-mnm,nf
Assembling
Elapsed
Endingof 5thofreplacement
4th
4th
2nd
3rd
5th
1st
2ud
3rd decoder
Description
replacement
replacement
replacelnellt
replacement dies
Starting dies
mes
dies
dies
7: ,~
1/1/ 1\.I( '/.W,of~&~e"",,-
I 7.
6.57
7: 05
7:
7:27
07 K
...~
17 15 '/.W,~/~·&~e"",,-
'/.W,~/~&~e"",,-
offY"'-~ &~e" ""-
DDV
65
66
crane. from machine bed
crane~
crane,
set onfrom
011 rnachine
machstands,
to roller ine bedusing
machine using

7:287
time '/.W,

Journal of EEA, Vol 24, 2007


54 Daniel Kitaw and Tibebe Belachew

ANNEX 2 DIE CHANGE AND SETUP, GANG PROCESS CHART

V
00150
/~ V')("/
'" *rl'f f
fI1 8/8 5 I ---I5/
tI8/ i'---
1 \
or
/q8
V/0138 13
/(5
9 61
OIIUOn!nCgantry
QSving%
QS
qS
Prop.rim,
Saving %Present
Event
Propoud
oq \6/
~'-...
~~sa
S8
(min.) /51/
~---
q210
~
I~ //~
t86V
8 I---
IV~
888
89
58
Cnu\l'l
08oJutmnto
2267
066223
92
87
*7
)(
215
59
60
fx 210
90
57Pr
~i:
5/
.t' q5
Pr
Sa
.,...
or
S8
f8"" GANG
Description
59 SYMBOLS
22 85
965 122 2
JI:34 SYMBOLS I!~ I~ 85
~t ~
I ':It5Present

\ B'" 65
875
13 35S5
22 '\, "
~ METHODS 15
5
---ANALYSIS ~
8
Pres. 08time
Proposed
(min)217 x., If¢ i"
---
Prop.tim,
Savitlg
156
I¢ op.!iml
op.rim,
ving%
es.
:l.:iS.lOlg:uo .Ou~
(min.)
15/
1/ ~V
(min)
i'--- oq
OC:::>DDv
8/
680154
'-...
S8V ""-70
OC:::>DDvO
1'\1
"*.;
""
1;('8~ x::»0'X';;
~l¢
11-
pc: ~/5/
C:::>DDv
"---- 1/ >K '" (min..)
1\ '-...
Prop.timl
___ ""-
res. time "\J(miff)
------ 10 9~ "'-
I
§ ~ 1\
1492 l'0.5Uioalar
Removal of decoder
1g
ANGI
Clenlag
OJiuonmg
6 m lugtk ganU'y
madlu hd for $calt
J IIftbglstrollerdiesstt
fronl crane lor
25
10 Rtiasta.1hltlol
Removal
Chlg:i_g oUastalled
ofCat
Iaoldi.g
22 B 61
oforrmadille
decoder
~8~
bearllg
dies foreat-
10
\\ 64 ~ \
~

JournalofEEA, VoL 24, 2007 .


Work Simplification for Productivity Improvement 55

ANNEX 3 SINGLE DIE SET CHANGE, FLOW PROCESS CHART

/0
Yihk
0:
0:
0:45 q0
0\]
XaU:
29
0:
{6
58.33
L,~.f}",;d
0:1/2
{:
4t>.d06 Ill~
37Ahh
01.5;
:26
PRESENT
1:03
PROPOSED
SAVINGS
DELAY xmt?y
EVENT
.!OO.! 1:48
INSPECTION
~OPERATION
TRANSPORT 41.67
TIME (min.)
METHODS ANALYSIS
TIME ANALYSIS
saving

V
DD\l S9
- e~~.~ ~
0:
6:53
{ no.
no.
Removal
A~,5.·
5:27
0:
7:
5:
6:
0:
Selection
0(J7.
Steps Inspection
Gauging
Assembling
~
roller
using
EndingRecommended
0:1/3
08
25
Elapsed
Hoisting 5:
21/6
{6
08
{5
08
05
-...d.u..c...~,
time
5:
5:22 21/
2{
0:0205
55
O{
~00
r/..",d,;.~~
Washing
Cleaning
Removal
r/"
dies
craneand
{of
and
of
5:
CA>-~

set
{6
ofof
Methodeach
new
t.-,..
~
~
31
bearings
1st
{7
roller
5: {7
5:{9
set 6: 57
roller
Startof
5(J7.
5(J7.
lubrication
replacement
installed
1st
placing
{0(J7.
adjustment
Event
dies 6:1/5
dies
dies
Description
dies
removable into
from

it
on to roller stands, using crane, from
of
replacement
6:
on
on
5: from
from "6
replacement
of
1st
bearing 1st
roller
17
bearing
53
time
1st
dies
set
dies
from
machine
die

1
SYMBOLS
various
the
stands,
set
seteach /' '"
~ ~~~
~;~ /"ee~~.~
set1st A~,
e~~.~
\ )<e~
e~,~.~
)f:.
Ark~;.,
tR...du.u- A(
~ :::x
5:{5
5:
5."{6
{6 'I1...~to.

Journal of EEA, Vol. 24, 2007


56 Daniel Kitaw and Tibebe Belachew
ANNEX 4 DIE GAUGING & ADJUSTMENT, FLOW PROCESS CHART

:riht.
0:01:20
0:05:20
0:fO:20 b~Xa-M
J!;;,&,,,,,,,
4t>u:t
0: Proposel
01/.·1/0
.fJ,;,. 0U,!
D
V
Q(0, xmt?,y
t3.ta-d.~
Present
INSPECTION
EVENT
DELAY
OPERATION
TRANSPORT
oo,!
.£- 0: 55.'56
I f5: 00Time
~",d~ 0: 08:
06:1/0
2 a
(min.) ANALYSIS
TIME ANALYSIS
d
d.tad.. "'r'
STORAGE to. A~~~
PercentageSavings .1. (min.)
(

Steps Event Description time


5: 1/6:
35: 00
Ending Start Elapsed Alternative
5:3f:00
5:time
3f: 00
odYDOD~ time
0: f 5: 00 rP__d.=.
Method

47 Gauging and adjustment on 1st die set


47-1 Positioning dies 0: 01/: OO?"",I..-,*" •.
47-2 Calibration of gauge tool using iF ~w.

Veruity Caliper 5: 35: 00 0: 01/: 00 ~n

47-3 IChecking clearnce of slot in three di... •• wn.d.

spots in line using calibrated tool 5: 89: 001 5: I/O: 1/01 0: Of: I/O ~
47-4ITightening the bolts to reduce clearance r,.,.u... :J~"
between slot and gauging tool 5: 1/ 0: 1/ 0 0: 00: 2 a d..a.-.a."""",

47-4IChecking clear nee of slot in lhree spots uM. f-dL."


in line using calibrated tool 5: 1/ f: 00 0: Of: 2 a F"'t"" "'•.
47-5lUntightening the bolts to increase ~J.
clearance hetween slot .nd gauging tool
5:1/2:201 5:1/3: 00 0: 00:1/0 {R.d.=.
47-6IMeasurillg c1earnce between die shaft side f.vm,.~
5:1/3: O:Of:OO ~

47-7lTightening the bolts to reduce clearance ~I 50 %

and gauging tool 5: 1/1/: 0: 00: 50

47-8 IChecking clearnce of slot in three spots


in line using between slol calibrated tool 5:1/1/:5015:1/5:3010:00:1/0

47-9 Finish tightening


to make bolts
ready for and counter
assembly nuts J(1
onto sunds . V 5:1/5:3015:1/6:0010:00:30

Journal of EEA, VoL 24, 2007


Work Simplification for Productivity Improvement 57

ANNEX 5 SAMPLE CHARTFOREVALUATINGALTERNATIVES

•..
.,
.•.. -<
=0)
0)
A~U-",
I6.uJ;~
.8~
B ~
ct.~,
U~.••
~& te~u-.
Score
E
tI!~u.. _t
.8~
'\.f.1'n.o.LLt.,
CD
~,
11JJ.,t~.~,
~,
,J". _t6-""""""1'
.•• 56.13
~.
,J". .••

> 1.8~_t ~U-r.. IAlternative A

6,56
,36 0,16
556,6,56
ii,8
6,67
3,33
,28
fO,C
D
,51
if. U8
E
6,67
3,33
96
0B
00 6,67
6,67
ii,8
if.
28,f
6,56
if,8
ff.8
53,33
Ratings I3}}co-
Factor/Consideration
03,33
,56
oa51.79
6,7f
51/,35
1/6,61
i,f8 830
80O"",~
0iOO
9,3
IM...) = Weighted
6/and
•..•
('fTlan" 1M...-
('fTlan" IM...). 6,67
A.J...ol 3,33 U8
7 5 3,33
6,56
3,33
6,67
6,67
3,33
if. {I8 0]
Wt[f0]
3,28
Ratings
[I/O]
[30] CommentstI!..t.>~
availability
tools Standard
Full
lotals
Highly tools
satisfaction
skilled

Remark:
Cost include arrangement of spare bearing and shaft, Shaft fabricated in the workshop and bearing
bought Birr 200,00, Expected lifetime 3136 hours operation, records, depreciation cost amounts to
Birr 1.40 per hour, for 20 bearings, For a die change time of24 minutes, max, saving by
reinstalling removed bearing and shaft is Birr 0,56 per change,

Legend
Subject: Dies are removed from dies holders. Each die consisits of a bearing and a shaft.
Removed dies will be stored and new replacement dies are installed in the die holders for
the next operation. The usuall method is to remove die with bearing and shaft and
dismantle, clean and inspect, store die, replace bearing and shaft into replaceable die.

Alternative processes proposed for die and bearing change


A Clean and store die as assembled and install replaceable assembled die readily prepared,
B Store die as removed from die holder and install replaceable assembled die readily prepared,
C Clean, inspect and store die as assembled and install replaceable die readily prepared,
D Disassemble die, clean, inspect, store and install replaceable assembled die readily prepared,
E Disassemble die, clean, inspect, store and install replaceable die with bearing fixed,

Journal of EEA, VoL 24, 2007

You might also like