Process Area
CRITICAL PATH:
The Critical Path in Upstream Plant project is P&ID.
In this project I have assumed 20 days as the critical path.
P&ID starting in 11-APR-19 after the start of PFD and completes on
25-SEP-19.
The Critical Path flows through sequential order PROCESS
SIMULATION,P&ID,PLOT PLAN,AND E/I CABLE LAYOUTS.
Utility Area
CRITICAL PATH:
The Critical Path in Upstream Plant project is U&ID.
In this project I have assumed 20 days as the critical path.
U&ID starting in 11-APR-19 after the start of UFD and completes on
28-AUG-19.
The Critical Path flows through sequential order PROCESS
SIMULATION,U&ID,PLOT PLAN,AND E/I CABLE LAYOUTS.
Offplot Area
CRITICAL PATH:
The Critical Path in Upstream Plant project is P&ID.
In this project I have assumed 20 days as the critical path.
P&ID starting in 11-APR-19 after the start of PFD and completes on
06-NOV-19.
The Critical Path flows through sequential order PROCESS
SIMULATION,P&ID,PLOT PLAN,AND E/I CABLE LAYOUTS.