Site Managers’ Dream….
3
Site Managers’ Dream….
4
Site Managers’ Dream….
5
Starting the Project….
Define the project Strategy on the basis of the contractual basis
and constraints
Defining Workfronts, considering:
WBS
Design Activities
Procurement campaign
Site Milestone
Site Prep.;
Civil (Foundations & U/G)
Steel Structure and Equipment,
Piping Prefabrication and Erection
6
Workfront Management
7
Workfront Management by Planning during
Project life
Planning stage
8
Piping Prefabrication work process
A typical case
9
Piping Prefabrication work process
A typical case
Baseline Schedule – Work Process Sequences
10
Piping Prefabrication work process
A typical case
Quantity Plan at Initial Stage
Prefabrication Plan
11
Workfront Management by Planning during
Project life
Control and Review phase
12
Piping Prefabrication work process
A typical case
Workfront Control and Rescheduling - Key Checking Steps
After P&ID’s Last Issue for
Detail Design, about 8
1st MTO done months before Start of Piping TIMELY
→ Material Prefabrication → ISO plan After ISO IFC issue AVAILABILITY
purchasing and Material purchasing / start OF MTL FOR
plan review availability plan review PREFAB
Time
1st PO issued →
Material Piping Prefabrication Subcontract award,
availability plan about 3 ÷ 4 months before Start of Piping
review on the Prefabrication → Prefabrication Plan
basis of actual review to verify if current workload
info from Order availability is supporting the start and
feasibility of Initial Plan, and to freeze
detailed subcontractor plan
13
Piping Prefabrication work process
A typical case
Updated Quantity Plan
Is prefabrication plan
Prefabrication start may still feasible?
be modified
14
FORECAST RUN: process
18
Piping Prefabrication work process
A typical case
Forecast Contractual
Prefabrication Start
date: end January
2009
1st Assessment
positive
19
Piping Prefabrication work process
A typical case
Forecast Contractual
Prefabrication Start
date: end January
2009
2nd Assessment
positive
20
Piping Prefabrication work process
A typical case
Final Quantity Plan
Piping at Site by
SPM
Workfront by
Forecast Runs
Actual
Prefabrication
Input each data one time, at one location, for the use of everybody
Project Data 360° Browser aims at consolidating E P C tools
together and also with planning and project management tools
Make decisions based on more quantitative data quickly
accessible on a single interface
22
Project Data 360° Browser
Provide various browsing capabilities for details or overviews
status and help identifying key from any complex search on a Process review required
23
Thank you