Organising
Tracking
A guide for Engineers, Estimators, Planners and Students
David H. Moloney
Foreword
The aim of this book is to show construction information relevant to planning, organising and
tracking progress, graphically, focusing on the essential facts that can be easily discussed,
communicated and implemented.
Gantt type chart programmes show the sequence and durations. Storyboards can show the
sequence, durations along with how to build an operation graphically in a way that all team
members along with operatives on site can understand leading to a collaborative effort.
This book deals mainly with heavy Civils and structures, the details and outputs are for
guidance, each case should be evaluated separately allowing for particular site conditions.
Front Engineering Period- At time of contract award, the design to be such, that it can be
used for procurement and to produce temporary works designs, method statements, safety
statements and a construction programme.
Procurement time periods vary and could take up to eight weeks from issue of construction
information, depending on the material, hire plant item or sub-contract. Plus delivery and
mobilising periods.
Approval Periods- A maximum of four working days should be set for approval of technical
submissions and to answer queries.
ISBN xxxxxxxxxxxxxxxxxxxxxx
davmol.moloney@gmail
☎ 00353 87 317 6815
There is truth in the old saying that a picture is worth a thousand words.
Storyboards can be used for the following:
• Presentations to Clients and third parties to explain proposed construction methods,
durations and sequences.
• To familiarize junior staff and workers with proposed work as required by health and safety
regulations.
• For foremen to see what plant and equipment is required and what is expected production
wise.
• To monitor progress.
• For Pricing, Costings, Programming, Execution, preparing Method Statements with Risk
Assessments.
• Improve efficiency by getting a better understanding of the process involved in
transforming resources into work, improvements can be made.
1 Excavate, Cart & Place Fill
2 Rock Escavatability, Rock Breaking &
Soils Classification
3 Rock: Drill, Blast & Crush
4 Pipelaying
5 Ground Improvement by Vibro Compaction
6 Basement: Dewatering & Construction
7 Piles: Board
8 Piles: Testing
9 Piles: Breakout & Waterproofing
10 Highrise: Construction Sequence
11 Highrise: Plant Selection
12 Highrise: Planning
Concrete frames have short lead-in times and with modern falsework and formwork systems, floor-to-floor
construction periods of 500m2/week/crane on large and straightforward flat slabs can be achieved. Week =
6 x 10hr shifts.
A typical floor slab size is 30m x 30m = 900sm with columns @ 8m c’c
To reduce the demand for the Tower crane “Hook Time” concreting will be by Pump and Placement Boom.
Core Walls shuttered using a climbing system, Falsework & deck formwork man handled (Peri Skydeck) so
it can be moved vertically between floors by goods hoist. (further advantage wind can restrict movement of
tableforms)
Early striking and reduced backpropping will speed up floor to floor construction cycle times.
13 Reservoir
14 Rail Underpass
15 Bridge (with beams, double span)
16 Bridge Deck Insitu
(with void formers and post-tensioned)
17 Metro Viaduct
Construction Method Outline
Bridge viaduct decks with spans from 25m to 72m were formed with precast concrete segments that were
match-casted to ensure perfect joints. The segments were lifted into position by the launching gantry. Cables were
threaded through the segments and tensioned by jacks. Output: every two days a 36m span was constructed.
18 Quay Wall
19 Temporary Sheetpile Shaft
(with internal bracing to support 10m excavation)
20 Micro Tunneling
21 Marine Plant & Dredging
Jack Up Barge
Generally used as a platform in tidal water
22 Organogram
Shown are the line and lateral relationships between the various team
members and their relative position in the site organisation.
23 Programme & Cashflow
The cash flow chart below shows the monthly and accumulative value of work to be completed for
the project using a combination graph with monthly amounts shown on the left vertical axis and
accumulative amounts on the left axis.
24 Tracking: Progress
Below is an example of how to track progress of an operations, by tabulating programmed against
actual resources, shifts per week and outputs per shifts. A combination graph with trend line is
used, to give a visual presentation, as it is easier to interpret and discuss figures shown pictorially.
25 Filing System
(Computer & Lever Arch Filing System for Site Staff)
Are you losing too much time searching through the clutter on your computer for work files that you need?
Can you file and retrieve information quickly and easily?
A well-organised and user-friendly filing system saves time and stress.
Notes:
• The sub folders are numbers, so when the main contract folder is opened, the sub folders appear in the same
order each time when viewed by name. Therefore the layout is consistent for all contracts.
• An advantage of this filing system, it is easy to find information on a colleague’s computer who may be on
leave or left the company. Or when the QS wants to put together the final account and he refers to a former site
staff members computer for information.
• If this this filing system is started at tender stage then contract information can be passed to site electronically
and distributed. After completion of the contract the information can be passed back to Head Office.
• During a Health & Safety audit it is easy to retrieve relevant information e.g. method statements, risk
assessments, company safety circulars etc.
• Save files with the Filename & Path as the header. So if you are working on a hardcopy and want to know
where you filed it on the computer you can see.
• Labels on Lever Arch Files can have same numbers and titles and be colour coded to assist with placing on
shelves. Both computer and hard copy filing systems are the same.
• On each document under the Contract name show in which contract sub folder it is filed, for example (File in:
Contract Folder / Sub Folder Nr 8.)
26 Procurement: Quotation Enquiry
Below is an example of a Quotation Enquiry Form
By having the Quotation Enquiry Form and the Directory of suppliers as separate worksheets in an excel file,
Suppliers details can easily be transferred into the Quotation Enquiry avoiding errors.
27 Procurement: Directory of Suppliers etc.
Below is an example of a directory.
28 Procurement: Comparison Sheet
On a single excel spreadsheet the quotations for all materials, plant hire and subcontracts
on a project are shown. Ideal summary of quotations for pricing other work.
29 Tracking: Payments
The table and graph below shows amounts and times of payments overdue. Ideally
suitable when chasing late payments to highlight amounts overdue and previous
payments that were late.
30 Tracking: Monthly Certificates v’s Costs
This table and graph is used to see if a contract is making or losing money monthly
and to monitor the trend.
31 Daily Allocations
Keeping Daily Records of what work was done and the resources involved is essential. These records
can be used for tracking outputs, costings and seeking payment.
The Daily Allocation Form below is used to ensure that all the operations are recorded and all the
resources on site are assigned to operations. The format makes the preparation of dayworks easy and
the accompanying photos gives visual meaning.
Nowadays with digital pocket cameras, (or Mobile phones) photographs can easily be taken and
transferred to the form below as an invaluable record of difficulties encountered with operations on site.
32 Dayworks Sheet
The sheet below is user friendly and relevant details can easily be transferred from
the Daily Allocation sheet ensuring that extra work can be costed quickly.
33 Costing: Pipelaying
It is a worthwhile exercise to price major operations on site to check the tender rates
and learn for pricing future work.
34 Outputs: Programming & Estimating
Having a feel for production outputs is vital for estimating, programming and
checking progress. Putting together a table of outputs on which a job was priced
and programmed and checking actual outputs is an important exercise.
35 Plant: Fuel Consumption
The cost of fuel on top of the hire rate of plant is sometimes overlooked in estimates
and costings. This table shows fuel cost per hours for various items of plant.
36 Compaction Table for Rollers
37 Recording: Concrete Orders
If this form is used when ordering concrete, it will help to avoid most of the problems
with concrete deliveries namely: wrong mix, wrong sump, wrong time, non delivery,
insufficient quantity, excessive wastage, uncertainty as to what was said verbally to
the dispatcher. It can be used to reconcile deliveries with paid quantities.
38 Programme: Weekly Look-ahead & Review
Weekly look ahead planning and reviewing of progress is
essential, the form below is used for this purpose.
39 Clip Arts of Plant & Site Team
To use, scan sheet and save as Jpeg picture. Insert Jpeg
into document, select image and crop to size.