DAFTAR HARGA BAHAN SIPIL

NAMA PROYEK : ……………………………………………………………


PEKERJAAN : ……………………………………………………………
TAHUN ANGGARAN : ……………………………………………………………

HARGA BAHAN
NO NAMA BAHAN SATUAN
Rp.
A BATU
1 Batu Kali M3 155,300.00
2 Batu Pecah 1 - 2 Cm M3 271,200.00
B PASIR
1 Pasir Pasang M3 169,100.00
2 Pasir Beton M3 182,400.00
C KAYU
1 Kayu Meranti Papan 2/25 X 4 M' M3 1,890,000.00
2 Kayu Kamper Usuk 5/7, 4/6 X 4 M' M3 3,498,000.00
3 Kayu meranti usuk M3 3,498,000.00
4 Kayu Begisting M3 1,890,000.00
5 Balok Kayu Meranti M3 4,161,000.00
6 Multiplek tebal 12 mm lbr 175,400.00
7 Dolken Kayu Gelam 8-10/400 cm btg 15,000.00
D PORTLAND CEMENT ( PC )
1 Semen 40 Kg Zak 42,500.00
2 Semen PC Kg 1,200.00
E BESI
1 Besi beton polos U24 Kg 12,930.04
2 Besi beton ulir U39 Kg 13,245.04
3 Kawat Beton Kg 17,600.00
4 Kawat Beton Berderat Kg 17,600.00
5 Besi Hollow 4 x 6 x 2 m1 17,900.00
F Air
1 Air Tanki ltr 20.00
G Cat
1 Kuas Bh 10,500.00
2 Cat Meni Besi Kg 39,200.00
3 Cat besi Kg 49,100.00
H PAKU
1 Paku biasa 2" - 5 " Kg 15,900.00
2 Paku Skrup Bh 1,000.00
J TRIPLEK
1 Playwood 9 mm Lbr 119,800.00
2 Meni Besi/Flincote Kg 39,200.00
K KUAS
1 Alang - Alang / Saput Ikat -
L ASBES + ALUMUNIUM
1 Nok Standart 40 cm 18 SWG 22 M2 88,000.00
M PIPA
1 Pipa Besi 3" (Medium) M' 63,583.33
N Seng
Seng Galvalum 7,5x3,5 cm t= 0,75 mm M' 19,600.00
Seng Plat 3"x 6" BJLS 28 M' 88,000.00

Harga Bahan Proyek ....... 09/01/2019 HAL : 1


HARGA SATUAN UPAH SIPIL
NAMA PROYEK : ……………………………………………………………
PEKERJAAN : ……………………………………………………………
TAHUN ANGGARAN : ……………………………………………………………

NO. NAMA PERSONIL UPAH / HARI

1 Mandor Lapangan Rp. 219,800.00


2 Kepala Tukang Rp. 146,600.00
3 Tukang Batu Rp. 131,200.00
4 Tukang Kayu Rp. 134,300.00
5 Tukang Besi Rp. 128,800.00
6 Tukang Gali Rp. 131,200.00
7 Tukang Listrik Rp.
8 Tukang Cat Rp. 107,400.00
9 Tukang Las Rp.
10 Sopir Material / Truck Rp.
11 Pembantu Sopir / Kernet Rp.
12 Pekerja Rp. 104,400.00

Harga Satuan Upah Proyek .......................09/01/2019 Hal : 2


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN
JUMLAH HRG. SATUAN
NO JENIS PEKERJAAN KOEF STN HRG. BAHAN
(Rp) (Rp)
1 ANALISA BIAYA KONSTRUKSI PEK. PERSIAPAN
1.1 1 M' Pengukuran dan pemasangan bouwplank
Bahan
Kayu Meranti Papan 2/25 X 4 M' 0.012 M3 1,890,000.00 22,680.00
Paku biasa 2" - 5" 0.020 Kg 15,900.00 318.00
Jumlah 22,998.00
Tenaga
Tukang kayu 0.100 Oh 134,300.00 13,430.00
Pekerja 0.100 Oh 104,400.00 10,440.00
Kepala Tukang 0.010 Oh 146,600.00 1,466.00
Mandor 0.005 Oh 219,800.00 1,099.00
Jumlah 26,435.00
Total 49,433.00
1.2 1 M2 Membersihkan lapangan dan perataan
Tenaga
Pekerja 0.100 Oh 104,400.00 10,440.00
Mandor 0.050 Oh 219,800.00 10,990.00
Jumlah 21,430.00
Total 21,430.00

Analisa SNI Standart Sipil Proyek .....................09/01/2019 Hal : 3


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN
JUMLAH HRG. SATUAN
NO JENIS PEKERJAAN KOEF STN HRG. BAHAN
(Rp) (Rp)
2
ANALISA BIAYA KONSTRUKSI PEKERJAAN TANAH
2.1 1 M3 Galian tanah biasa sedalam 1 meter
Tenaga
Pekerja 0.750 Oh 104,400.00 78,300.00
Tukang gali - Oh 131,200.00 -
Kepala Tukang - Oh 146,600.00 -
Mandor 0.025 Oh 219,800.00 5,495.00
Jumlah 83,795.00
Total 83,795.00
2.2 1 M3 Galian tanah biasa sedalam 2 meter
Tenaga
Pekerja 0.900 Oh 104,400.00 93,960.00
Mandor 0.045 Oh 219,800.00 9,891.00
Jumlah 103,851.00
Total 103,851.00
2.3 1 M3 Galian tanah biasa sedalam 3 meter
Tenaga
Pekerja 1.050 Oh 104,400.00 109,620.00
Tukang gali - Oh 131,200.00 -
Kepala Tukang - Oh 146,600.00 -
Mandor 0.067 Oh 219,800.00 14,726.60
Jumlah 124,346.60
Total 124,346.60
2.4 1 M3 Urugan pasir
Bahan
Pasir urug 1.200 M3 169,100.00 202,920.00
Jumlah 202,920.00
Tenaga
Pekerja 0.300 Oh 104,400.00 31,320.00
Tukang gali - Oh 131,200.00 -
Kepala Tukang - Oh 146,600.00 -
Mandor 0.010 Oh 219,800.00 2,198.00
Jumlah 33,518.00
Total 236,438.00

2.5 1 M3 Urugan kembali


Tenaga
Pekerja 0.064 Oh 104,400.00 6,681.60
Tukang gali - Oh - -
Kepala Tukang - Oh - -
Mandor 0.006 Oh 219,800.00 1,392.07
Jumlah 8,073.67
Total 8,073.67

Analisa SNI Standart Sipil Proyek .....................09/01/2019 Hal : 4


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN
JUMLAH HRG. SATUAN
NO JENIS PEKERJAAN KOEF STN HRG. BAHAN
(Rp) (Rp)
ANALISA BIAYA KONSTRUKSI PEKERJAAN KAYU
3
3.1 1 M' Pasang lisplang ukuran ( 3 x 25 ) Cm kayu kelas I atau II
Bahan
Kayu papan 0.0108 M3 1,890,000.00 20,412.00
Paku biasa 5 cm - 7 cm 0.100 Kg 15,900.00 1,590.00
Jumlah 22,002.00
Tenaga
Pekerja 0.1000 Oh 104,400.00 10,440.00
Tukang kayu 0.200 Oh 134,300.00 26,860.00
Kepala Tukang 0.0200 Oh 146,600.00 2,932.00
Mandor 0.005 Oh 219,800.00 1,099.00
Jumlah 41,331.00
Total 63,333.00

Analisa SNI Standart Sipil Proyek .....................09/01/2019 Hal : 5


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN
JUMLAH HRG. SATUAN
NO JENIS PEKERJAAN KOEF STN HRG. BAHAN
(Rp) (Rp)

4 ANALISA BIAYA KONTRUKSI PEKERJAAN BETON


4.1 1M3 Membuat beton bertulang K 225
Bahan
Semen Portland 40 kg 9.275 Kg 1,200.00 11,130.00
Pasir beton 0.436 M3 182,400.00 79,526.40
Batu pecah mesin 1/2 0.551 M3 271,200.00 149,431.20
Air (biaya air tawar) 215.000 lt 20.00 4,300.00
Jumlah 240,087.60
Tenaga
Pekerja 1.650 Oh 104,400.00 172,260.00
Tukang Batu 0.275 Oh 131,200.00 36,080.00
Kepala Tukang 0.028 Oh 146,600.00 4,104.80
Mandor 0.083 Oh 219,800.00 18,243.40
Jumlah 230,688.20
Total 470,775.80
4.2 1M3 Membuat beton bertulang K 300
Bahan
Semen Portland 40 kg 10.325 zak 1,200.00 12,390.00
Pasir beton 0.426 M3 182,400.00 77,702.40
Batu pecah mesin 1/2 0.537 M3 271,200.00 145,634.40
Air (biaya air tawar) 215.000 lt 20.00
Jumlah 235,726.80
Tenaga
Pekerja 1.650 Oh 104,400.00 172,260.00
Tukang Batu 0.275 Oh 131,200.00 36,080.00
Kepala Tukang 0.028 Oh 146,600.00 4,104.80
Mandor 0.083 Oh 219,800.00 18,243.40
Jumlah 230,688.20
Total 466,415.00
4.3 1 m3 Beton Kolom 15/15
Bahan
Beton K300 1.000 M3 466,415.00 466,415.00
Besi beton polos U24 36.036 Kg 12,930.04 465,946.92
Besi beton ulir U39 138.667 Kg 13,245.04
Jumlah 465,946.92
Tenaga
Pekerja 2.000 Oh 104,400.00 208,800.00
Tukang Batu 0.350 Oh 131,200.00 45,920.00
Kepala Tukang 0.035 Oh 146,600.00 5,131.00
Mandor 1.000 Oh 219,800.00 219,800.00
Jumlah 479,651.00
Total 479,651.00
4.4 10 Kg Pembesian dengan besi polos atau besi ulir
Bahan
Besi beton (polos/ulir) 10.500 Kg 12,930.04 135,765.42
Kawat beton 0.150 Kg 17,600.00 2,640.00
Jumlah 138,405.42
Tenaga
Pekerja 0.070 Oh 104,400.00 7,308.00 0.007
Tukang Besi 0.070 Oh 128,800.00 9,016.00 0.0007
Kepala Tukang 0.007 Oh 146,600.00 1,026.20
Mandor 0.004 Oh 219,800.00 879.20
Jumlah 18,229.40
Total 156,634.82
4.5 1 M2 Pasang bekisting untuk kolom
Bahan
Kayu meranti usuk 0.040 M3 3,498,000.00 139,920.00
Paku biasa 2" - 5 " 0.400 Kg 15,900.00 6,360.00
Balok Kayu Meranti 0.015 M3 4,161,000.00 62,415.00
Multiplek tebal 12 mm 0.350 Lbr 175,400.00 61,390.00
Dolken Kayu Gelam 8-10/400 cm 2.000 Btg 15,000.00 30,000.00
Jumlah 300,085.00
Tenaga
Pekerja 0.660 Oh 104,400.00 68,904.00
Tukang kayu 0.330 Oh 134,300.00 44,319.00
Kepala Tukang 0.033 Oh 146,600.00 4,837.80
Mandor 0.033 Oh 219,800.00 7,253.40
Jumlah 125,314.20
Total 425,399.20
4.6 1 M2 Pasang bekisting untuk lantai
Bahan

Analisa SNI Standart Sipil Proyek .....................09/01/2019 Hal : 6


Kayu meranti usuk 0.040 M3 3,498,000.00 139,920.00
Paku biasa 2" - 5 " 0.400 Kg 15,900.00 6,360.00
Balok Kayu Meranti 0.015 M3 4,161,000.00 62,415.00
Multiplek tebal 12 mm 0.350 Lbr 175,400.00 61,390.00
Dolken Kayu Gelam 8-10/400 cm 6.000 Btg 15,000.00 90,000.00
Jumlah 360,085.00
Tenaga
Pekerja 0.660 Oh 104,400.00 68,904.00
Tukang Batu 0.330 Oh 131,200.00 43,296.00
Kepala Tukang 0.033 Oh 146,600.00 4,837.80
Mandor 0.033 Oh 219,800.00 7,253.40
Jumlah 124,291.20
Total 484,376.20
4.7 1 M2 Pasang bekisting untuk dinding
Bahan
Kayu meranti usuk 0.040 M3 3,498,000.00 139,920.00
Paku biasa 2" - 5 " 0.400 Kg 15,900.00 6,360.00
Balok Kayu Meranti 0.020 M3 4,161,000.00 83,220.00
Multiplek tebal 12 mm 0.350 Lbr 175,400.00 61,390.00
Dolken Kayu Gelam 8-10/400 cm 2.000 Btg 15,000.00 30,000.00
Formtie/ penjaga jarak bekisting/ spacer 4.000 Btg
Jumlah 320,890.00
Tenaga
Pekerja 0.660 Oh 104,400.00 68,904.00
Tukang Batu 0.330 Oh 131,200.00 43,296.00
Kepala Tukang 0.033 Oh 146,600.00 4,837.80
Mandor 0.033 Oh 219,800.00 7,253.40
Jumlah 124,291.20
Total 445,181.20
4.8 1 M3 Membuat pondasi
Bahan
Batu Kali 1.100 M3 155,300.00 170,830.00
Semen Portland 136.000 Kg 15,900.00 2,162,400.00
Pasir Pasang 0.544 Kg 169,100.00 91,990.40
Jumlah 2,425,220.40
Tenaga
Pekerja 1.500 Oh 104,400.00 156,600.00
Tukang Batu 0.750 Oh 131,200.00 98,400.00
Kepala Tukang 0.075 Oh 146,600.00 10,995.00
Mandor 0.075 Oh 219,800.00 16,485.00
Jumlah 282,480.00
Total 2,707,700.40
4.9 1 M3 Membuat dinding beton bertulang K300
Bahan
Beton K300 1.000 M3 466,415.00 466,415.00
Besi beton ulir U39 3.200 Kg 13,245.04 42,384.13
Jumlah 508,799.13
Tenaga
Pekerja 5.300 Oh 104,400.00 553,320.00
Tukang Batu 0.275 Oh 131,200.00 36,080.00
Tukang kayu 1.300 Oh 134,300.00 174,590.00
Tukang besi 1.050 Oh 128,800.00 135,240.00
Kepala Tukang 0.262 Oh 146,600.00 38,409.20
Mandor 0.265 Oh 219,800.00 58,247.00
Jumlah 995,886.20
Total 1,504,685.33
4.10 1 M3 Beton plat dasar tandon t= 15 cm
Bahan
Beton K300 1.000 M3 1,890,000.00 1,890,000.00
Besi beton ulir U39 101.000 Kg 15,900.00 1,605,900.00
Jumlah 3,495,900.00
Tenaga
Pekerja 5.300 Oh 104,400.00 553,320.00
Tukang Batu 0.275 Oh 131,200.00 36,080.00
Tukang kayu 1.300 Oh 134,300.00 174,590.00
Tukang besi 1.050 Oh 128,800.00 135,240.00
Kepala Tukang 0.262 Oh 146,600.00 38,409.20
Mandor 0.265 Oh 219,800.00 58,247.00
Jumlah 995,886.20
Total 4,491,786.20
4.11 1 M' Pengecoran Tiang Atap
Bahan
Pipa Galvanis 1.200 M' 63,583.33 76,300.00
Perlengkapan 35.000 % 22,254.17 22,254.17
Jumlah 98,554.17
Tenaga
Pekerja 0.054 Oh 104,400.00 5,637.60
Tukang Batu 0.090 Oh 131,200.00 11,808.00
Kepala tukang 0.009 Oh 134,300.00 1,208.70

Analisa SNI Standart Sipil Proyek .....................09/01/2019 Hal : 7


Mandor 0.027 Oh 128,800.00 3,477.60
Jumlah 22,131.90
Total 120,686.07

Analisa SNI Standart Sipil Proyek .....................09/01/2019 Hal : 8


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN
JUMLAH HRG. SATUAN
NO JENIS PEKERJAAN KOEF STN HRG. BAHAN
(Rp) (Rp)
5
ANALISA BIAYA KONTRUKSI PEKERJAAN BETON
5.1 Pemasangan Usuk Galvalum 7,5x3,5 cm t= 0,75 mm
Bahan
Usuk Galvalum m1 3 19,600.00 58,800.00
Paku sekrup bh 6 1,000.00 6,000.00
Jumlah 64,800.00
Tenaga
Mandor Oh 0.005 219,800.00 1,099.00
Kepala Tukang Oh 0.001 146,600.00 146.60
Tukang Oh 0.1 128,800.00 12,880.00
Pekerja Oh 0.1 104,400.00 10,440.00
Jumlah 24,565.60
Total 89,365.60
5.2 1 M2 Pasang Atap Nok Seng
Bahan
Seng Plat 3"x 6" BJLS 28 0.300 Lbr 88,000.00 26,400.00
Paku 1/2"-1" 0.040 Kg 15,900.00 636.00
Jumlah 27,036.00
Tenaga
Pekerja 0.150 Oh 104,400.00 15,660.00
Tukang Kayu 0.070 Oh 134,300.00 9,401.00
Kepala tukang 0.008 Oh 146,600.00 1,172.80
Mandor 0.006 Oh 219,800.00 1,318.80
Jumlah 27,552.60
Total 54,588.60

Analisa SNI Standart Sipil Proyek .....................09/01/2019 Hal : 9


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN
JUMLAH HRG. SATUAN
NO JENIS PEKERJAAN KOEF STN HRG. BAHAN
(Rp) (Rp)

6 ANALISA BIAYA KONSTRUKSI PEKERJAAN BESI DAN ALLUMUNIUM


6.1 1Kg Pasang Rangka Atap Baja
Bahan
Besi Hollow 40x60x3,2 mm 2.6 m1 17,900.00 46,540.00
Paku sekrup 6 bh 1,000.00 6,000.00
Jumlah 52,540.00
Tenaga
Tukang besi 0.200 Oh 128,800.00 25,760.00
Pekerja 0.100 Oh 104,400.00 10,440.00
Kepala tukang 0.020 Oh 146,600.00 2,932.00
Mandor 0.0050 Oh 219,800.00 1,099.00
Jumlah 40,231.00
Total 92,771.00

Analisa SNI Standart Sipil Proyek .....................09/01/2019 Hal : 10


ANALISA BIAYA KONSTRUKSI SNI SIPIL STANDAR
BANGUNAN GEDUNG DAN PERUMAHAN
JUMLAH HRG. SATUAN
NO JENIS PEKERJAAN KOEF STN HRG. BAHAN
(Rp) (Rp)

7 ANALISA BIAYA KONSTRUKSI PEKERJAAN PENGECATAN


7.1 1 M2 Pengecatan Permukaan Baja dengan Meni Besi
Bahan
Meni besi 0.100 Kg 39,200.00 3,920.00
Kuas 0.010 Bh 10,500.00 105.00
Jumlah 4,025.00
Tenaga
Pekerja 0.020 Oh 104,400.00 2,088.00
Tukang cat 0.200 Oh 107,400.00 21,480.00
Kepala tukang 0.020 Oh 146,600.00 2,932.00
Mandor 0.010 Oh 219,800.00 2,198.00
Jumlah 28,698.00
Total 32,723.00
7.2 1 M2 Pengecatan Permukaan Baja Lapis Seng (galbani) secara Manual
Sistem 1 Lapis Cat Mutakhir dgn tebal 200 um
Bahan
Cat 0.300 Kg 49,100.00 14,730.00
Jumlah 14,730.00
Tenaga
Pekerja 0.006 Oh 104,400.00 626.40
Tukang cat 0.060 Oh 107,400.00 6,444.00
Kepala tukang 0.012 Oh 146,600.00 1,759.20
Mandor 0.006 Oh 219,800.00 1,318.80
Jumlah 10,148.40
Total 24,878.40

Analisa SNI Standart Sipil Proyek .....................09/01/2019 Hal : 11


DAFTAR HARGA SATUAN ANALISA BIAYA KONSTRUKSI SNI SIPIL
BANGUNAN GEDUNG DAN PERUMAHAN
NAMA PROYEK
……………………………………………………………
:
PEKERJAAN
……………………………………………………………
:
TAHUN ANGGARAN
……………………………………………………………
:

HARGA SATUAN HARGA SATUAN


NO JENIS PEKERJAAN AWAL KOREKSI
(Rp) (Rp)

1 ANALISA BIAYA KONSTRUKSI PEK. PERSIAPAN


1.1 1 M' Pengukuran dan pemasangan bouwplank 49,433.00
1.2 1 M2 Membersihkan lapangan dan perataan 21,430.00
2 ANALISA BIAYA KONSTRUKSI PEKERJAAN TANAH
2.1 1 M3 Galian tanah biasa sedalam 1 meter 83,795.00
2.2 1 M3 Galian tanah biasa sedalam 2 meter 103,851.00
2.3 1 M3 Galian tanah biasa sedalam 3 meter 124,346.60
2.4 1 M3 Urugan pasir 236,438.00
2.5 1 M3 Urugan kembali 8,073.67
3 ANALISA BIAYA KONSTRUKSI PEKERJAAN KAYU
3.1 1 M' Pasang lisplang ukuran ( 3 x 25 ) Cm kayu kelas I atau II 63,333.00
4 ANALISA BIAYA KONTRUKSI PEKERJAAN BETON
3.1 1M3 Membuat beton bertulang K 225 470,775.80
3.2 1M3 Membuat beton bertulang K 300 466,415.00
3.3 1 m3 Beton Kolom 15/15 479,651.00
3.4 10 Kg Pembesian dengan besi polos atau besi ulir 156,634.82
3.5 1 M2 Pasang bekisting untuk kolom 425,399.20
3.6 1 M2 Pasang bekisting untuk lantai 484,376.20
3.7 1 M2 Pasang bekisting untuk dinding 445,181.20
3.8 1 M3 Membuat pondasi 445,181.20
3.9 1 M3 Membuat dinding beton bertulang K300 2,707,700.40
3.9 1 M3 Beton plat dasar tandon t= 15 cm 4,491,786.20
3.10 1 M' Pengecoran Tiang Atap 120,686.07
5 ANALISA BIAYA KONTRUKSI PEKERJAAN PENUTUP ATAP
5.1 Pemasangan Usuk Galvalum 7,5x3,5 cm t= 0,75 mm 89,365.60
5.2 1 M2 Pasang Atap Nok Seng 54,588.60
5.3 ANALISA BIAYA KONSTRUKSI PEKERJAAN KAYU
5.4 1 M' Pasang lisplang ukuran ( 3 x 25 ) Cm kayu kelas I atau II 63,333.00
6 ANALISA BIAYA KONSTRUKSI PEKERJAAN BESI DAN ALLUMUNIUM
6.1 1Kg Pasang Rangka Atap Baja 92,771.00
7 ANALISA BIAYA KONSTRUKSI PEKERJAAN PENGECATAN
7.1 1 M2 Pengecatan Permukaan Baja dengan Meni Besi 32,723.00
7.2 1 M2 Pengecatan Permukaan Baja Lapis Seng (galbani) secara Manual 24,878.40
RENCANA ANGGARAN BIAYA
PEKERJAAN :
LOKASI :
TAHUN ANGGARAN : 2019

HARGA STN JUMLAH HRG TOTAL


NO URAIAN PEKERJAAN VOLUME STN
(Rp.) (Rp.) (Rp.)

I PEK. PERSIAPAN
1 1 M' Pengukuran dan pemasangan bouwplank 4 m' 49,433.00 197,732.00
2 Pembersihan / Pembuangan 5.000 m' 21,430.00 107,150.00
Jumlah 304,882.00

II Galian Tanah Pond


1 Galian Tanah Biasa 26.148 m3 103,851.00 2,715,458.56
2 Urugan Tanah kembali 2.451 m3 8,073.67 19,792.24
3 Urugan Pasir 0.458 m3 236,438.00 108,189.30
Jumlah 2,843,440.10
III PEK. BETON
1 Pemasangan Bagesting Kolom 1.23 m2 425,399.20 523,241.02
2 Pemasangan Bagesting Dinding 20.7 m2 445,181.20 9,217,476.75
3 Pemasangan Bagesting Lantai 7.590 m2 484,376.20 3,676,415.36
Pekerjaan Pembesian 4.205 M3 156,634.82 658,688.58
4 Pengecoran Pengecoran Kolom 0.185 m3 479,651.00 88,495.61
5 Pengecoran Dinding Beton 3.10575 m3 2,707,700.40 8,409,440.52
6 Pengecoran Lantai Beton 0.915 m3 4,491,786.20 4,109,984.37
Jumlah 26,683,742.20
III PEK. PONDASI MOTOR
Pemasangan Pondasi Motor 0.416 M3 445,181.20 185,195.38
Jumlah 185,195.38
VI PEK. ATAP
Pengecoran Tiang Atap 9.28 M1 120,686.07 1,119,966.70
1 Rangka Baja WF 36.652 M' 92,771.00 3,400,242.69
#VALUE! Pemasangan Atap SengnGalvalum 7,5x3,5 cm t= 0,75 mm 20.000 m2 89,365.60 1,787,312.00
#VALUE! Nok 0.879 m' 54,588.60 47,983.38
#VALUE! Lisplank 3/25 0.150 m' 63,333.00 9,499.95
Jumlah 6,365,004.72
VI PEK. Pengecatatn
Pengecatan Rangka Atap dengan Meni Besi 39.080 M2 28,698.00 1,121,517.84
Pengecatan Rangka Atap dan Atap Seng Galvalum 59.080 M2 24,878.40 1,469,815.87

Jumlah 2,591,333.71
REKAPITULASI
RENCANA ANGGARAN BIAYA
PEKERJAAN
LOKASI :
TAHUN ANGGARAN :
: 2019

NO.
URAIAN P E K E R J AA N T O TAL
(Rp.)
I
II PEK. PERSIAPAN 304,882.00
III Galian Tanah Pond 2,843,440.10
1.00 PEK. BETON 26,683,742.20
2.00 PEK. PONDASI MOTOR 185,195.38
3.00 PEK. ATAP 6,365,004.72
4.00 PEK. Pengecatatn 2,591,333.71
5.00 #REF!
6.00 #REF!
#REF! #REF!
#REF!

JUMLAH 38,973,598.11
PPN 10 % 3,897,359.81
JUMLAH TOTAL 42,870,957.92
DIBULATKAN 42,870,000.00

TERBILANG : Tiga ratus lima puluh empat juta lima ratus empat puluh dua ribu rupiah.

Surabaya,
Dibuat Oleh,
Konsultan Perencana
CV.

SATRIO DWINANTO, SE
Direktur