You are on page 1of 9

REKAPITULASI ANGGARAN BIAYA

PAGAR BATAKO DAN BRC BAGIAN SELATAN


PALU CITY SQUARE TAHUN 2015
No. Uraian Pekerjaan Jumlah Harga
1 2 3

I Pekerjaan Persiapan 7,250,000.00


II Pekerjaan Tanah / Pasir 7,217,763.00

III Pekerjaan Pagar Batako Type I = 60 mtr 92,843,870.61

IV Pekerjaan Pagar Batako Type II = 32,50 mtr 56,643,936.30


V Pekerjaan Pagar Batako Type III = 140 mtr 211,229,242.24
VI Pekerjaan Pagar BRC Ø 8 = 277,5 mtr 266,755,959.30

VII Pekerjaan Lain-lain 1,000,000.00

Total Harga Pekerjaan 642,940,771.45


PPn 10% 64,294,077.15
Total Harga Pekerjaan + PPn 10% 707,234,848.60
Dibulatkan 707,234,000.00

Terbilang : " Tujuh Ratus Lima Belas Juta Tujuh Ratus Delapan Puluh Ribu Rupiah "
RINCIAN ANGGARAN BIAYA (RAB)
PAGAR BATAKO DAN BRC BAGIAN SELATAN
PALU CITY SQUARE

No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga


1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Ls 1.00 1,500,000.00 1,500,000.00
2 Pengukuran dan Pasang Buowplank Ls 1.00 2,250,000.00 2,250,000.00
3 Administrasi dan Dokumentasi Ls 1.00 3,500,000.00 3,500,000.00
Sub Total 7,250,000.00
II Pekerjaan Tanah / Pasir
1 Galian Tanah Kontruksi M³ 113.20 46,900.00 5,309,080.00
2 Urugan Kembali Bekas Galian M³ 28.30 21,350.00 604,205.00
3 Urugan Pasir Bawah Galian M³ 15.30 85,260.00 1,304,478.00
Sub Total 7,217,763.00
III Pekerjaan Pagar Batako Type I = 60 mtr
1 Pasangan Batu Kosong M³ 7.20 438,408.00 3,156,537.60
2 Pasangan Pondasi Batu Kali M³ 18.90 800,799.00 15,135,101.10
3 Pasangan Dinding Batako M² 103.68 139,535.00 14,466,988.80
4 Plesteran Dinding M² 207.36 45,800.00 9,497,088.00
5 Acian Dinding M² 207.36 27,325.00 5,666,112.00
6 Plesteran Pondasi M² 36.00 45,800.00 1,648,800.00
7 Acian Pondasi M² 36.00 27,325.00 983,700.00
8 Sloof 15/20 beton K 225 M³ 1.73 5,371,858.30 9,293,314.86
9 Kolom 20/20 beton K 225 M³ 3.90 6,077,670.10 23,702,913.39
10 Ring Balok 15/20 beton K 225 M³ 1.73 5,371,858.30 9,293,314.86
Sub Total 92,843,870.61
IV Pekerjaan Pagar Batako Type II = 32,50 mtr
1 Pasangan Batu Kosong M³ 3.90 458,134.20 1,786,723.38
2 Pasangan Pondasi Batu Kali M³ 13.16 838,734.00 11,037,739.44
3 Pasangan Batako M² 56.16 125,617.00 7,054,650.72
4 Plesteran Dinding M² 112.32 55,784.00 6,265,658.88
5 Acian Dinding M² 112.32 32,383.00 3,637,258.56
6 Plesteran Pondasi M² 26.00 55,784.00 1,450,384.00
7 Acian Pondasi M² 26.00 32,383.00 841,958.00
8 Sloof 15/20 beton K 225 M³ 0.94 5,445,373.36 5,118,650.95
9 Kolom 20/20 beton K 225 M³ 2.33 6,151,185.16 14,332,261.41
10 Ring Balok 15/20 beton K 225 M³ 0.94 5,445,373.36 5,118,650.95
Sub Total 56,643,936.30
V Pekerjaan Pagar Batako Type III = 140 mtr
1 Pasangan Batu Kosong M³ 16.80 458,134.20 7,696,654.56
2 Pasangan Pondasi Batu Kali M³ 56.70 838,734.00 47,556,217.80
3 Pasangan Batako M² 239.40 125,617.00 30,072,709.80
4 Plesteran Dinding M² 478.80 55,784.00 26,709,379.20
5 Acian Dinding M² 478.80 32,383.00 15,504,980.40
6 Plesteran Pondasi M² 98.00 55,784.00 5,466,832.00
7 Acian Pondasi M² 98.00 32,383.00 3,173,534.00
8 Sloof 15/20 beton K 225 M³ 3.57 5,445,373.36 19,439,982.88
9 Kolom 20/20 beton K 225 M³ 5.88 6,151,185.16 36,168,968.72
10 Ring Balok 15/20 beton K 225 M³ 3.57 5,445,373.36 19,439,982.88
Sub Total 211,229,242.24
No. Uraian Pekerjaan Satuan Volume Harga Satuan Jumlah Harga
1 2 3 4 5 6

VI Pekerjaan Pagar BRC Ø 8 = 277,5 mtr


1 Pekerjaan Pondasi Setempat K 225 M³ 4.00 6,710,014.00 26,840,056.00
2 Pekerjaan Pondasi Menerus M³ 59.00 838,734.00 49,485,306.00
3 Pekerjaan Sloof 15/20 M³ 8.33 5,445,373.36 45,332,733.19
4 Pekerjaan Pagar BRC 240 X 170 Lbr 277.50 522,875.19 145,097,864.12
Sub Total 266,755,959.30
VII Pekerjaan Lain-lain
1 Pembersihan Akhir Lahan Ls 1.00 1,000,000.00 1,000,000.00
0.00
Sub Total 1,000,000.00
Total Harga Pekerjaan 642,940,771.45
ANALISA HARGA SATUAN

PEKERJAAN : PAGAR BATAKO DAN BRC BAGIAN SELATAN


LOKASI : PALU CITY SQUARE
THN. ANGGARAN : 2015

No. Uraian Satuan Volume Hrg. Satuan Upah Jumlah Harga

I Pekerjaan Tanah, Pondasi dan Pasangan Dinding


1 1 M³ Galian Tanah
Pekerja Org 0.550 60,000.00 33,000.00
Mandor Org 0.055 90,000.00 4,950.00
Total Harga Rp. 37,950.00

2 1 M³ Urugan Kembali Bekas Galian


Pekerja Org 0.250 60,000.00 15,000.00
Mandor Org 0.025 90,000.00 2,250.00
Total Harga Rp. 17,250.00

3 1 M³ Urugan Sirtu Bawah Galian


Pekerja Org 0.100 60,000.00 6,000.00
Mandor Org 0.020 90,000.00 1,800.00
Sirtu M³ 1.200 182,000.00 218,400.00
Total Harga Rp. 226,200.00

4 1 M³ Urugan Tanah Bawah Galian


Pekerja Org 0.100 60,000.00 6,000.00
Mandor Org 0.020 90,000.00 1,800.00
Tanah Urug M³ 1.200 63,000.00 75,600.00
Total Harga Rp. 83,400.00

5 1 M³ Urugan Pasir Bawah Pondasi/Lantai


Pekerja Org 0.300 60,000.00 18,000.00
Mandor Org 0.100 90,000.00 9,000.00
Pasir Urug M³ 1.200 175,000.00 210,000.00
Total Harga Rp. 237,000.00

6 1 M³ Pasangan Batu Kosong (Aanstamping)


Batu Kali/Belah M³ 1.200 231,490.00 277,788.00
Pasir urug M³ 0.432 175,000.00 75,600.00
Pekerja Org 0.780 60,000.00 46,800.00
Tukang Org 0.390 80,000.00 31,200.00
Kepala Tukang Org 0.039 90,000.00 3,510.00
Mandor Org 0.039 90,000.00 3,510.00
Total Harga Rp. 438,408.00

7 1 M³ Pasangan Batu Kali 1 : 4


Batu Kali/Belah M³ 1.100 231,490.00 254,639.00
Semen PC Zak 3.260 85,000.00 277,100.00
No. Uraian Satuan Volume Hrg. Satuan Upah Jumlah Harga

Pasir Pasang M³ 0.520 203,000.00 105,560.00


Pekerja Org 1.500 60,000.00 90,000.00
Tukang Batu Org 0.750 80,000.00 60,000.00
Kepala Tukang Org 0.075 90,000.00 6,750.00
Mandor Org 0.075 90,000.00 6,750.00
Total Harga Rp. 800,799.00

8 1 M² Pasangan Dinding Batako


Batu Bata Bh 25.000 3,500.00 87,500.00
Semen PC Zak 0.230 52,000.00 11,960.00
Pasir Pasang M³ 0.043 275,000.00 11,825.00
Pekerja Org 0.300 60,000.00 18,000.00
Tukang Org 0.100 80,000.00 8,000.00
Kepala Tukang Org 0.010 90,000.00 900.00
Mandor Org 0.015 90,000.00 1,350.00
Total Harga Rp. 139,535.00

9 1 M² Plesteran
Semen PC Zak 0.125 52,000.00 6,500.00
Pasir M³ 0.024 275,000.00 6,600.00
Pekerja Org 0.300 60,000.00 18,000.00
Tukang Org 0.150 80,000.00 12,000.00
Kepala Tukang Org 0.015 90,000.00 1,350.00
Mandor Org 0.015 90,000.00 1,350.00
Total Harga Rp. 45,800.00

10 1 M² Acian
Semen PC Zak 0.065 85,000.00 5,525.00
Pekerja Org 0.200 60,000.00 12,000.00
Tukang Org 0.100 80,000.00 8,000.00
Kepala Tukang Org 0.010 90,000.00 900.00
Mandor Org 0.010 90,000.00 900.00
Total Harga Rp. 27,325.00

II Pekerjaan Beton
1 1 M² Rabat Beton
Semen PC Zak 4.360 85,000.00 370,600.00
Pasir M³ 0.520 203,000.00 105,560.00
Batu Pecah 2/3 M³ 0.870 350,000.00 304,500.00
Pekerja Org 1.650 60,000.00 99,000.00
Tukang Org 0.250 80,000.00 20,000.00
Kepala Tukang Org 0.050 90,000.00 4,500.00
Mandor Org 0.080 90,000.00 7,200.00
Total Harga Rp. 911,360.00

2 1 M³ Beton Mutu fc' = 19,3 Mpa (K 225)


Semen PC Zak 7.420 85,000.00 630,700.00
No. Uraian Satuan Volume Hrg. Satuan Upah Jumlah Harga

Pasir M³ 0.499 203,000.00 101,297.00


Batu Pecah 2/3 M³ 0.776 350,000.00 271,600.00
Air M³ 0.215 28,000.00 6,020.00
Pekerja Org 1.650 60,000.00 99,000.00
Tukang Org 0.275 80,000.00 22,000.00
Kepala Tukang Org 0.028 90,000.00 2,520.00
Mandor Org 0.083 90,000.00 7,470.00
Total Harga Rp. 1,140,607.00

3 10 Kg Pekerjaan Pembesian
Besi Beton Kg 11.000 19,500.00 214,500.00
Kawat Beton M³ 0.300 25,000.00 7,500.00
Pekerja Org 0.070 60,000.00 4,200.00
Tukang Besi Org 0.070 80,000.00 5,600.00
Kepala Tukang Org 0.007 90,000.00 630.00
Mandor Org 0.004 90,000.00 360.00
Total Harga Rp. 232,790.00
Per Kg Besi Rp. 23,279.00

4 1 M² Pekerjaan Begesting
Kayu Kelas III M³ 0.030 1,500,000.00 45,000.00
Paku Biasa Kg 0.400 20,000.00 8,000.00
Mould Oil Ltr 0.200 40,000.00 8,000.00
Multiplex 6mm Lbr 0.350 130,000.00 45,500.00
Kayu Doken Btg 0.500 18,000.00 9,000.00
Pekerja Org 0.300 60,000.00 18,000.00
Tukang Org 0.260 80,000.00 20,800.00
Kepala Tukang Org 0.026 90,000.00 2,340.00
Mandor Org 0.005 90,000.00 450.00
Total Harga Rp. 157,090.00

5 1 M³ Pekerjaan Plat Beton Bertulang K 225


Beton Bertulang M³ 1.000 1,140,607.00 1,140,607.00
Bekesting M² 6.000 157,090.00 942,540.00
Pembesian Kg 200.000 23,527.06 4,705,412.00
Total Harga Rp. 6,788,559.00

6 1 M³ Pekerjaan Sloof /Ring Balk K 225


Beton Bertulang M³ 1.000 1,140,607.00 1,140,607.00
Bekesting M² 4.470 157,090.00 702,192.30
Pembesian Kg 150.000 23,527.06 3,529,059.00
Total Harga Rp. 5,371,858.30

7 1 M³ Pekerjaan Kolom K 255


Beton Bertulang M³ 1.000 1,140,607.00 1,140,607.00
Bekesting M² 4.470 157,090.00 702,192.30
Pembesian Kg 180.000 23,527.06 4,234,870.80
No. Uraian Satuan Volume Hrg. Satuan Upah Jumlah Harga

Total Harga Rp. 6,077,670.10

8 1 M³ Pekerjaan Pondasi Beton Bertulang K 225


Beton Bertulang M³ 1.000 1,140,607.00 1,140,607.00
Bekesting M² 5.500 157,090.00 863,995.00
Pembesian Kg 200.000 23,527.06 4,705,412.00
Total Harga Rp. 6,710,014.00

9 1 M³ Pekerjaan Pondasi Beton Bertulang K 175


Beton Bertulang M³ 1.000 1,140,607.00 1,140,607.00
Bekesting M² 5.500 157,090.00 863,995.00
Pembesian Kg 150.000 23,527.06 3,529,059.00
Total Harga Rp. 5,533,661.00

III Pekerjaan BRC


1 1 M¹ Pagar BRC 175
Beton K 175 untuk Pondasi M³ 0.026 5,533,661.00 143,875.19
BRC t = 175 mm + Assesories Lbr 1.000 238,000.00 238,000.00
Tiang Pagar BRC Ø2" Galvanis Unit 1.000 91,000.00 91,000.00
Pekerja Org 0.550 60,000.00 33,000.00
Tukang Batu Org 0.100 80,000.00 8,000.00
Kepala Tukang Org 0.100 90,000.00 9,000.00
Total Harga Rp. 522,875.19

2 1 M² Pintu Pagar BRC t = 2 cm


BRC t = 2 cm + Assesories M² 1.000 450,000.00 450,000.00
Pekerja Org 0.750 60,000.00 45,000.00
Tukang Batu Org 0.350 80,000.00 28,000.00
Kepala Tukang Org 0.350 90,000.00 31,500.00
Total Harga Rp. 554,500.00
A L V A H V Q Total
0.03 5.25 0.1575 1 0.03 2.50 0.0750 17 1.2750

15/20
0.03 3.52 0.1056 2 0.03 4.01 0.1203 2 0.2406
0.03 3.52 0.1056 3 0.03 4.60 0.1380 1 0.1380 1.6536

Kolom basement
0.03 5.05 0.1515 4 15/30 0.05 6.10 0.2745 1 0.2745
Sloof 15/20

0.03 7.00 0.2100 5 0.08 3.80 0.3040 7 2.1280


0.03 7.00 0.2100 6 0.08 4.03 0.3224 1 0.3224

20/40
0.03 3.48 0.1044 7 0.08 5.90 0.4720 2 0.9440
0.03 1.47 0.0441 8 0.08 7.40 0.5920 3 1.7760
0.03 1.47 0.0441 9 0.08 9.50 0.7600 1 0.7600 5.9304
1.1328 m3 7.8585 m3
10 15/20 0.03 3.60 0.1080 4 0.4320
0.06 5.05 0.3030 11 20/40 0.08 4.90 0.3920 16 6.2720
0.06 5.05 0.3030 12 Lt dsr
40/40 0.16 4.90 0.7840 1 0.7840
0.06 13.82 0.8292 7.4880 m3
0.06 13.82 0.8292 13 15/20 0.03 3.60 0.1080 5 0.5400
Sloof 20/30

mezanin

0.06 4.80 0.2880 14 15/30 0.05 3.60 0.1620 16 2.5920


0.06 10.63 0.6378
0.06 10.63 0.6378 3.1320 m3
0.06 6.57 0.3942 15 15/20 0.03 3.60 0.1080 5 0.5400
lt satu

0.06 6.57 0.3942 16 0.03 6.61 0.1983 5 0.9915 1.5315


4.6164 m3 17 15/30 0.05 3.60 0.1620 16 2.5920
18 0.05 6.61 0.2975 2 0.5949 3.1869
19 20/30 0.06 4.08 0.2448 1 0.2448
20 0.06 4.60 0.2760 2 0.5520 0.7968
5.5152 m3

Balok Latei
A L V Q Total Ketrerangan
15/15 0.02 26.05 0.5861 Lt. Dasar
0.02 30.16 0.6786 Lt. Mezanin
0.02 42.41 0.9542 1.6328 Lt. 1

Balok Struktur
15/20 0.03 5.05 0.1515 Lt. Mezanin
20/30 0.06 8.78 0.5268
20/40 0.08 79.00 6.3200

20/30 0.06 21.16 1.2696 Lt. 1


20/40 0.08 102.26 8.1808
A W Q Vol
2.73 0.15 3 1.229 m3

You might also like