You are on page 1of 8

Construction Activities

1 Ocular Inspection
2 Mobilization
3 Staking Out
Excavation
Pouring of Lean Concrete
Footing & Column Rebar Fabrication
4 Installation of Rebars
5 Concreting of footing
6 Placing of column formworks (below wall footing)
7 Concreting of Column (below wall footing)
8 Installation of Rebars for wall footing & Formworks
9 Concreting of Wall footing & Column (Below Footing Tie beams)
10 Curing (depends on needed Strength)
Footing Tie Beam & Slab on Grade Rebar Fabrication
11 Stripping of Formworks
Backfill (Below Footing Tie Beams)
Installation of Rebars (Footing Tie Beams) w/ Formworks & Slab on Grade
12 Concreting of Footing Tie Beam and Slab on Grade
13 Curing (depends on needed Strength)
Rebar Fabrication for other Column Stirrups
Girders and Suspended Slab Rebar Fabrication
14 Stripping of Formworks
Installation of Column Stirrups
Installation of Scaffolding and Formworks from Columns to Suspended Slab
Installation of Girders and Slab Rebars
15 Concreting of Column, Girder, Suspended Slab (2nd Floor)
Stripping of Formworks
16 Curing (depends on needed Strength)
Rebar Fabrication for Columns, Beams & Girder
Girders and Suspended Slab Rebar Fabrication
17 Installation of Column Stirrups
Installation of Scaffolding and Formworks from Columns to Suspended Slab
Installation of Girders and Slab Rebars
Concreting of Column, Girder, Suspended Slab (3rd Floor)
Stripping of Formworks
18 Curing (depends on needed Strength)
Rebar Fabrication for Columns, Beams & Girder
Girders and Suspended Slab Rebar Fabrication
19 Installation of Column Stirrups
Installation of Scaffolding and Formworks from Columns to Suspended Slab
Installation of Girders and Slab Rebars
Concreting of Column, Girder, Suspended Slab (Roof Deck)
Stripping of Formworks
20 Curing (depends on needed Strength)
21 Laying of CHB Walls and Installation of Rebars (Mortar and Plaster)
22 Installation Roofing
Installation of Stairs
25 Demobilization

Schedule of Equipment
1st Month
List of Equipment 1 2 3 4
Concrete Mixer
Bar Bending Machine
Welding Machine
Vibrator
Pumpcrete
1st Month
Workers Involved
Man Days Allocated Man Days 1 2 3
Surveyor Laborer Mason
1 day 2
4 days 6 7
1 day 1 2
2 days 1 5
1 day
1 day 6 3
2 days 5
1 day 7 2
1 day 1 3
1 day 1 7 2
5 days 5 7
1 day 1 7 2
2-3 weeks
3 days 3
1 day 7 1
7
1 day 1 2
4 days 3
1 day 7 2
2-3 weeks
1 day 7 2
2 days 3
1 day 3 1
1 day 4
7 days 4 2
6
7 days 2
1 day 7 2

2-3 weeks * Independent


3 days 3 days 2

2-3 weeks * Independent


3 days 3 days 2
2-3 weeks * Independent
7 days 7 days 3 1
5 days 2
5 days 2
4 days 4 days 7
Total 2 7 4
40 Surveyor Laborer Mason

2nd Month 3rd Month


1 2 3 4 1 2 3 4
onth 2nd Month 3rd Month
4 1 2 3 4 1 2 3 4
4th Month 5th Month
Total Working Todays
1 2 3 4 1 2 3 4
7 days
15 days
15 days
7 days
5 days
4th Month 5th Month
1 2 3 4 1 2 3 4
Total Working Todays

7 days
15 days
15 days
7 days
5 days