PROJECTED CASH FLOW SCHEDULE

Project: Proposed 10 Units Trellis


Location:
Owner:
Contract Amount: 1345030

SN Paymet No. Work No. Payment Description Payment Date % Accomplishment


1 1st Payment ------------20% downpayment Sept. 30, 2019 0.000%
2 2nd Payment 1 1st Progress Billing
Oct. 13, 2019 0.818%
3 3rd Payment 2 2nd Progress BillingOct. 20, 2019 3.650%
4 4th Payment 3 3rd Progress Billing
Oct. 27, 2019 30.473%
5 5th Payment 4 4th Progress BillingNov. 3, 2019 58.654%
6 6th Payment 5 5th Progress BillingNov. 10,2019 80.743%
7 7th Payment 6 6th Progress Billing
Nov. 17, 2019 89.786%
8 8th Payment 7 7th Progress Billing
Nov. 23, 2019 94.489%
9 9th Payment 8 8th Progress Billing
Nov. 30, 2019 97.584%
10 10th Payment 9 9th Progress BillingDec. 7, 2019 100.000%
W SCHEDULE

This Wk. Accomplishment Amount of Payment Balance


0.000% 269006 1076024
0.818% 8802 1067222
2.832% 30473 1036749
26.823% 288622 748127
28.181% 303234 444893
22.089% 237683 207210
9.043% 97305 109905
4.703% 50605 59300
3.095% 33303 25997
2.416% 25997 0
TOTAL = 1345030