Construction surveys

When building roads, buildings, pipelines and other projects, it is a common task for surveying engineer to
mark locations on the ground according to a project.

The locations for corners of the building have to be found by surveyor

The  marks  placed  are  usually  wooden  stakes.  These  wooden  stakes  serve  as  reference  points  for  either
vertical or horizontal positions, or for both.
The vertical location (elevation) is called grade.
The horizontal location is called line.

The  line  and  grade  must  be  established  in  a  reasonable  distance  (1  to  3  m)  from  proposed  construction
prior contractor starts work. Craft persons (skilled workers) can draw positioning of constructions using
rule and hand level then.

Establishing line
The process of giving line consists of establishing direction (angle) and placing a series of marks along
the line at determined distances. The angle may be set by theodolite. If a great accuracy is requested, then
target wooden stake is re‑measured by theodolite and from observed angle and distance, shift of the target
is computed.
Series of marks can be in need to find out positions for columns

Direction should be established from some backsight line, which is longer than line to be established.

Establishing grade
Marking elevations  (also  called  giving grade, grade staking)  is  setting  marks  by  tops  of  stakes  or  by
nails on stakes.

The wooden stake is driven into the ground to mark requested elevation. Assuming the height of the
instrument is known, elevation is set by means of level instrument.

To  either  push  or  cut  the  wooden  stake  to  comply  with  requested  altitude  in  given  place  according  to  a
project  is  time  consuming.  Thus,  other  method  is  used:  wooden  stake  is  fixed  to  convenient  level  into
ground. Requested height is compared with observed height. The difference is written with the stake as
a cut or fill (letter C or F). That means the target height is below or above the top of the given stake.

Many times it would be not convenient to drive the wooden stake so high to mark the requested level
(42.27 on picture). Thus, wooden stake is driven into convenient height and is labeled by "fill". Fill tells
how much to fill above the stake until requested height.
This is an analogy for fill. But in this case requested level is not above the stake, but below (at 46.94 on
the picture). The stake is labeled by "cut" which tells how much land to cut until requested altitude is
reached.

The cut or fill is found by means of level instrument. Level instrument uses some known level to determine
the height of the instrument and reading is made from rod placed on top of the wooden stake.

Building stakeout
Very common complex task for surveyor is to reference corners and borders for construction of proposed
building.  For  such  purpose,  a  batter  board  is  used  as  shown  on  the  picture.  Important  part  is  a  nail
intended to hold string straight from one batter board to the opposite one. Because batter board is laid at
offset of around 1.5 m from proposed building, the string can be temporarily taken off during construction
while the board is still kept at the place to be used again.

Batter boards

The carpenters and masons can readily take a measurement from established strings by means of rule or
plumb bob. Sometimes all the boards are set at a specific height to the ground floor.
Batter boards made from wood are established around corners of planned building. They should be
placed in a reasonable distance from construction. They serve together with line and grades. If line or
grade is lost by the construction process, batter boards are helpful to re‑establish them.
When the corners are being found by a surveyor, for good accuracy measurements should be taken
rather from longer than shorter baseline.

The  distances  for  proper  locations  of  boards  and  strings  is  taken  from  baseline  according  to  the  project.
Baseline might be the property line taken between monuments.

Column footings

 
Column footings

The column footings must be located with a high degree of accuracy (at most a few millimeters). Because
footing is established in the fresh concrete before it hardens.
The  elevation  of  base  plates  is  critical  also.  Traditional  differential  levelling  methods  are  used  to  set
elevation  of  the  plate.  When  the  final  position  is  established,  cement  is  forced  under  the  plate  to  fill  the
space.
The  construction  surveyor  is  also  called  on  to  ensure  that  the  columns  are  placed  in  a  truly  vertical
position. This can be achieved by using a plumb bob or by instrument.

Slope staking
It is common task—when road or railroad is being built—to align surface and the slope along the road
(see picture below).
1.  Geodetic engineer is required to measure the terrain along proposed path.
2.  Based on observation by geodetic engineer the current situation can be used for preparing a project.
3.  Then geodetic surveyor shows by wooden stakes to contractor the point where to start filling the land
or where to start cutting the land, according to the project:

During the construction process, wooden stakes are pushed into the ground under an angle (slope). These
are marked with the station number so the description of the height needed to fill/cut and stake distance
from road centerline can be read also from protocol. The wooden stakes are established for every cross‑
section at distances of 10 or more metres.

Slope staking illustration (cross‑section at given kilometer):
A) F4.09/11.14: 4.09 m have to be filled (1.69 + 2.40), the stake is 11.14 m (6.14 + 5) from the centerline
B) F4.75/0: 4.75 m have to be filled, the stake is at the centerline
C) F5.85/13.78: 5.85 m have to be filled, the stake is 13.78 (5 + 8.78) from the centerline
The slope stakes are placed along the construction in intervals according to conditions, eg. every 10
metres.

Additional layout procedures
Prolonging a line (double centering)
It  is  often  needed  to  extend  given  line.  For  example,  line  AB  needs  to  be  extended  to  C.  So  called  double
centering method is used to reduce the impact of instrument inaccuracy:
The point C1  is found by means of theodolite and marked. Then the telescope is reversed, and point C2  is
found. If the instrument is in perfect adjustment, C1  and C2  will give the same result.

Double centering used to extend a line

Obstacle in a line
A property line between the marks might be obstructed or blocked by an object. The line needs to be found
across the obstacle.
Line AD can not be established because of the obstacle.
1—(above) The method could be used only on low accuracy surveys; the larger is BC, the larger is error
2—(below) The preferred method: for best accuracy AB, CD and AA' have to be established as long as
practical
3—(below) Fewer angles and distances than in the first method therefore better accuracy is achievable

Line and grade for sewer
The slope is shown on the engineering drawing so that the builder can excavate the ground and place down
the pipe in requested slope.
Whenever the pipeline changes in slope, diameter or direction, a manhole is build to provide access.

Manholes are openings which allows access to a pipe. Manholes are placed for a purpose of cleaning
and inspecting whenever the pipeline changes in slope, diameter or direction.

For  construction,  positions  of  grade  stakes  are  established  by  surveyor.  As  the  ground  is  excavated,  its
depth is being periodically checked by measurements from the grade stakes.
After the ground is open to a depth slightly deeper than that required, a series of batter boards is placed
across the line at uniform intervals.
The batter boards are set at a constant elevation above the proposed pipe flow line, and a string line is run
between  the  boards.  String  line  is  directly  above  the  pipe  centerline  and  has  the  same  slope.  It  is  then
simple for workers to establish pipe into proper position making periodic measurements from the string
line.
The pipeline location is equipped with grade stakes and line stakes (in yellow color) along the path
during construction. These serve as guides for excavating. When the ground is opened, then batter
boards are installed to guide establishing the pipe into proper position.

Use of lasers
A straight beam is useful as a tool for giving a line and grade in construction surveying. The beam can be
observed even under the sun and can be used outdoor. The laser instrument can be mounted on a tripod at
a requested  height:  the  laser  beam  is  oriented  in  the  horizontal  direction  and  can  serve  as  an  electronic
level.
The laser beam can be adjusted to a specific slope. That is useful for lying pipelines such as sewers, which
require placing in slope of determined value according to the project.
A  rotating  laser  beam  is  very  useful  construction  survey  tool.  Instead  of  a  single  line  it  can  generate  flat
reference surface over open area.

 
1—Pipe laser, 2—Rotary laser