Professional Documents
Culture Documents
∙
install the required equipment
12. Commission the equipment Engineering design is always based in
13. Commission the process and verify that the heuristics, professional judgment, and reli-
plant performs as designed ance on approaches that are known from
14. Commence routine production the designer’s experience to be highly
∙
15. Improve process efficiency based on the likely to work.
data and experience gained during routine First-principles design is avoided as much
production as possible by professional engineers,
16. Increase the plant capacity based on data because an initial design based on first
principles almost always has some
∙
and experience gained
unforeseen problem.
17. Decommission the plant at the end of the
product life cycle Process plants are too complex to be com-
pletely understood, but the designer does
The pharmaceutical industry operates more not need to completely understand the
stages in parallel than other industries and uses plant. It is only necessary to understand
more laboratory and pilot plant work, but this is it well enough to have a high degree of
the general model followed in all industries and certainty that it meets reliably its
countries [1]. specification.
Different design activities are undertaken
throughout the plant’s life. In the early stages, 1.3.1. Stages of Plant Design
the plant to be designed is very poorly
specified, and as the lifetime of the plant The design of a chemical plant is an expensive
continues, more and more is known about process and many designs do not prove practi-
the plant. cal. Therefore potential designs are often devel-
In addition, a situation in which the plant is oped to the extent necessary to establish whether
essentially underspecified prevails throughout they are sufficiently promising to warrant fur-
most of its lifecycle. A substantial body of ther development.
data on the plant has only developed by stage This has resulted in a staged approach to
15 at which point it is possible to create a highly design, which essentially proceeds from an
accurate model. This allows the effect of a inexpensive initial and conceptual evaluation of
modification to be known with some certainty options through to a detailed design stage that
in advance. accounts for a significant proportion of the build
Therefore, during the majority of a plant’s cost of the plant, via intermediate evaluations.
lifecycle, finding reliable, just creative enough This formal staged design process is fol-
solutions to ill-defined problems is the essence lowed by two further stages, i.e., modification
of plant design. of the as-built design during the commissioning
4 Chemical Plant Design and Construction
stage and the post-handover redesign by the FEED, detailed design, and design for con-
plant owners’ engineers, which are usually struction design are mostly completed by EPC
not undertaken by the original plant design companies, possibly with some assistance from
team. design consultants and ideally with operating
The design process might therefore be split company input.
into six stages as follows [1]: Site-level redesign is led by the commission-
∙∙
design (FEED) assistance from design consultants and EPC
Detailed design companies or equipment suppliers [1].
∙∙
Design for construction
1.3.2. Elements of Process Plant Design
Site-level redesign
Post-handover redesign or optimization Process plant design has a number of integrated
elements [1]:
∙
Procurement and construction of the plant
proceed along its design to varying degrees. Analysis of needs, data, specifications,
Orders for long lead-time items, for example, etc., to generate a clear description of
∙
are commonly placed as early as the detailed the design envelope of the plant
design stage.
System level design, which is concerned
Various types of companies are involved in
with making all of the unit operations
∙
the design process. Conceptual design usually
work together
involves some combination of an operating
company and design consultant and possibly Process control, as specified by docu-
an engineering, procurement, construction ments, such as the functional design spec-
∙
(EPC) company. ification (FDS) for software
Design and specification of the individual
An Operating Company is a company whose processing steps, such as reactors and
business is the operation of process plants. Such distillation columns (known as unit oper-
companies are usually the ultimate clients of the ations in chemical engineering, see
∙
companies who design and construct process below)
plants.
Hydraulic design (concerned with moving
Consultant. Consulting companies offer a fluids around the plant) and the associated
∙
range of services, usually mainly centering on specification of pumps, compressors, etc.
design, project management, or a combination Plant layout, in which the equipment
of the two. They may be single-discipline (espe- and buildings are laid out on the site in
cially if they are design focused) or multidisci- such a way as to produce a cost-effec-
plinary. It is rare for consultants to take on tive, safe, operable, aesthetically pleas-
∙
contractual responsibility for whether the design ing whole
works, and their design input is usually at a Risk and safety analysis using techniques,
∙
conceptual level. such as HAZOP (hazard operability) [3]
Economic analysis, which uses tools, such
∙∙
Contracting or EPC Company. Contracting
as costing and sensitivity analysis
companies engineer, procure, and construct pro-
cess plants. EPC is one of many common contrac- Project programming
tual arrangements including EPCM (engineering, Production of key project deliverables
procurement, construction, management) and defining the design, such as mass and
EPCI (engineering, procurement, construction, energy balances, layout drawings, piping
installation). Contracting companies design and and instrumentation diagrams, process
build plants and usually offer a guarantee that the flow diagrams, Gantt charts, and various
process works. schedules.
Chemical Plant Design and Construction 5
∙∙
concept of unit operations is agreed to be the Isitreliablypossibletomeetthespecification?
foundation of the discipline of chemical engi- Is it publically acceptable?
neering. This concept is simple but powerful. A
Is it safe?
unit operation is a stage of processing, such as
reaction, mixing, separation, or heat exchange,
It is not possible to answer these questions
where a single significant change is made. By
with the required degree of certainty unless a
splitting the process into unit operations, it is
rough design (or, more likely, multiple designs)
possible to analyze it more readily, using tools,
has been carried out. However, for the concep-
such as mass and energy balance.
tual designer, the required degree of certainty to
allow design to progress to the next stage is
1.3.3. Disciplines Involved in Process Plant
far lower than that produced by a rigorous
Design
(but expensive and time-consuming) scientific
analysis.
The key skill of the process designer is to make
Therefore engineering is not applied science,
all of the parts of the plant (and indeed the
but professional art informed by science [1].
associated design process) work together
properly.
Process designers are, generally speaking, 2.2. The Design Envelope
chemical engineers, but there are other disci-
plines that need to be involved in the plant The first task in the conceptual design of a process
design process. As a minimum, electrical, soft- plant is the analysis of the available design data to
ware, and civil engineers are required to design establish the design envelope i.e., the multi-
their respective aspects of the plant. dimensional set of constraints on the design.
There is an exchange of ideas between the External constraints determine which
various disciplines as the design progresses. The designs are possible. The proposed design
common language of the various parties to the must be physically and chemically possible.
design is engineering drawings, most notably a However, designs are commonly far less
line drawing of the plant laid out in space known directly constrained by scientific considerations
as a plot plan or general arrangement drawing. than by man-made ones, the effects of which
All these disciplines seek to optimize the only diminish as new commercially-proven
design from their point of view. The lead technologies become available. This, taken
designer needs to manage this to produce the with the innate conservatism of professional
best design. engineers, means that the practice of design
In most industries, the chemistry used is has a slow rate of change.
generally selected from available proprietary Because the aim of design is to produce a
technologies that have previously been suc- plant that generates a profit throughout its life-
cessfully operated at the proposed scale of time, it must work within the economic and
operation. other resources available. The resources differ
Scale-up from bench scale to full scale is no over time and between countries and sectors.
trivial matter and process plant designers place All designs must also be compliant with
far greater emphasis on the reliability, safety, national and international safety legislation,
and cost-effectiveness of the design than on relevant industry and statutory standards, codes,
novelty. and controls. Some of these constraints may
vary from country to country.
Internal constraints determine which designs
2. Feasibility and Conceptual Design are plausible. The companies carrying out a
design have access to just a subset of all design
2.1. Introduction and construction methods, knowledge and expe-
rience, licensed processes, process equipment,
The key questions to consider at the earliest and materials. There are also finance, time, and
stage of design are: personnel constraints on what can be delivered.
6 Chemical Plant Design and Construction
Operating companies and designers both balance and the associated process flow
have preferences for one process over another diagram.
based on their experience. Operating company
staff has experience of a limited number of Mass and Energy Balance. The law of conser-
processes, and there are costs associated with vation of mass states that (unless a nuclear
training them on a new process. reactor is being designed) mass is neither cre-
The more novel a process is, the more likely ated nor destroyed in chemical reactions. By
there are to be unforeseen problems after a extension, this law holds true in a chemical
period of operation. Plant designers and opera- plant. It may be that chemical reaction causes
tors tend therefore to favor just novel enough the chemical elements in the process to be
processes and to be more conservative at the rearranged into new compounds, but the masses
earliest design stage in order not to over-commit of elements in and out are always equal.
resources in developing a design which proves This principle forms the basis of a simple but
impractical at a later stage [1]. powerful tool known as a mass balance. This is a
calculation in which the masses of all of the
substances going into the plant and each of its
2.3. Risk and Safety Analysis unit operations are determined.
An assumption of steady state is probably
Safety first! Before progressing with a design, made at the earliest stage of design, such that the
chemical engineers must consider whether the mass balance is calculated only under the nor-
proposed chemistry and processing steps are mally envisaged operating condition. This is a
inherently safe [4]. The key principles of the simplifying assumption, which takes no account
concept are:
∙
of even the most foreseeable excursions from
the ideal operating conditions [1].
Minimize: Reduce stocks of hazardous One important feature of the mass balance is
∙
chemicals that it is common in plant design to recycle
Substitute: Replace hazardous chemicals materials from the end of a process back to the
∙∙
with less hazardous ones start for reprocessing. This can make a large
Moderate: Reduce the energy of the system difference to the required size of equipment
Simplify: Simple processes are easier to between the point at which the materials are
understand, operate, and control hazards withdrawn and that at which they are reintro-
within duced. Failure to account for such recycle
streams can consequently have a significant
Rather than using, for example, a highly impact upon the size, price, and practicality
flammable solvent and subsequently putting of the plant as a whole; thus they should be
in place the requisite protection measures, con- considered even at this early stage of design.
sideration should be given to employing a less Beside conservation of mass, energy is also
flammable (and therefore less inherently dan- conserved. This allows an energy balance to be
gerous) solvent in the first instance. constructed by a similar method based upon the
This is one of the most important parts of mass balance and the laws of thermodynamics.
conceptual design, because it builds passive
safety into the design at the earliest stage. Process Flow Diagram. The process flow dia-
gram (PFD) is used to show the inter-relation-
ship of the main unit operations in the envisaged
2.4. System-Level Design plant, and the flows of mass and energy between
them. Unlike some other engineering drawings
Process plant design seeks to make a collection (see Sections 3.5 and 3.8), there is consensus
of unit operations work together as a well-con- agreement within the engineering profession on
trolled and unified whole. the nature (and name) of the PFD.
Chemical engineers are trained to address Standards used in PFDs vary from country to
this at the earliest stages of design mainly country but, internationally, the most commonly
with two tools, namely the mass and energy used standard is ISO 10628 [5]. There is also a
Chemical Plant Design and Construction 7
commonly used (though now withdrawn) U.S. It is therefore good practice to allow space
standard, ANSI Y32.11 [6]. for these additional requirements when estimat-
There can be no valid design of unit opera- ing plant footprint. This is achieved by multi-
tions before a mass balance and PFD have been plying the footprint for the key unit operations
produced, since flows to individual unit opera- by a factor of four or more. Alternatively, it is
tions are not necessarily obvious from whole- possible to estimate the sizes of these key items,
plant throughput, largely due to the presence of an approach that is especially worthwhile if the
recycle streams in the plant. client wishes to have some idea of what the plant
Chemical or process engineers (the terms are will look like on the site at the earliest stage of
almost interchangeable) therefore tend to pro- design.
duce at least a rough PFD as part of their initial If pumps or compressors are to take up a
deliberations on the various potential process significant proportion of the site, it is best to size
options. them approximately even at the earliest stage,
At this earliest stage of design, the rough using the roughest kind of hydraulic design
PFD is likely to be hand sketched on paper or techniques (see Section 2.6). Similarly, in
shown in the spreadsheet or other computer some industries heat exchangers can have a
program used to produce the mass balance very significant capital and running cost as
rather than developed into a proper engineering well as site footprint, and consequently an initial
CAD drawing. However, a properly CAD- heat exchanger design is undertaken at concep-
drafted version of the rough PFD may be pro- tual design stage.
duced at the earliest stage of design to illustrate The inherent conservatism of professional
proposals to the client. In this manner, engineer- engineers screens out many options at the con-
ing drawings serve as tools for explanation and ceptual design stage in a way that may be
review as much as they are tools for thinking [1]. frustrating to neophiles. Much of professional
engineering know-how however, consists of
knowing what is not likely to work.
2.5. Unit Operation Level Design
Erring on the Side of Caution: The Conserva-
It is usually necessary to design unit operations tism of Engineers.
to some extent at the earliest stage, if only to
provide a rough approximation of their physical
size and cost. This can be completed relatively
∙ A general rule in plant design is to err very
much on the side of caution at earlier
∙
quickly by experienced engineers, based upon stages of design.
approximate heuristics. These heuristics may Plants are always bigger, cost more, and
take the form of rules of thumb, design guides, have more design challenges than seemed
or manuals, or they may be built into specialist likely before embarking upon the detailed
∙
black-box computer software. Thus, even at stages of design.
conceptual design stage, it is helpful to be The urge to optimize a plant design at the
able to size rectangles, circles, etc., representing conceptual design stage should therefore
the footprint on the site of the unit operations be strongly resisted [1].
that are the heart of the plant [1].
Frequently, reaction and separation pro-
cesses of the plant do not represent a significant 2.6. Hydraulic Design
proportion of the whole-plant footprint. The
required separation (for safety and operational When sizing the pumps for liquids or the com-
reasons) between these processes as well as the pressors for gases used to transfer fluids around
pumps, compressors, buildings, etc., probably a process plant, there are three key information
requirements:
∙∙
accounts for far more of the site than the unit
operations. In addition, ancillary processes,
such as steam-raising plant and pollution abate- Composition of the fluid to be moved
∙
ment measures can account for a considerable Required flow
amount of space. Pressure required to move it
8 Chemical Plant Design and Construction
The composition and flow of the fluid to be design at an early stage resulting in an increased
moved come from the mass balance and its early consideration of layout issues.
temperature from the energy balance. The Even an initial layout might show that the
required pressure, however, has to be deter- plant envisaged cannot fit on the proposed site
mined by hydraulic calculations [1]. resulting in a need to return to the very earliest
It is essentially impossible to calculate this stage of design definition and reconsider the
pressure rigorously from first principles, and it is choices made there [1].
in any case pointless to attempt to generate a
precise value for a calculation based upon very
vague information. Engineers therefore employ 2.8. Economic Analysis
a range of techniques that facilitate the rapid
generation of approximate values for the pres- The fundamental objective of conceptual design
sure required of pumps and compressors. is to generate an idea of how much it costs to
Even at conceptual design stage, approxi- build and operate a plant. Around 98% of
mate pipe internal sizes can be established using conceptual designs prove uneconomic, which
a rule of thumb based on average velocity of is why engineers develop potential designs only
fluid through the pipe. For example, velocities to the extent necessary to generate a sufficiently
of 1.5 m/s for water-like liquids, and 15 m/s for robust cost estimate allowing a decision to be
air-like gases can be used to generate approxi- made on whether to proceed further.
mate pipe sizes. At conceptual design stage, professional
The key pumps and compressors can then be engineers often price the main plant items
sized approximately, using charts which give (roughly analogous to the unit operations) and
the amount of pressure required per meter of then calculate the whole plant cost by multi-
pipeline to transfer a given flow of material plying the total main plant items cost by a factor.
through a pipe of a given diameter. The most established factorial costing
The flow and pressure estimate can then be method is that of LANG [8], which offers a factor
used to determine the number and size of the to multiply main plant item costs to account for
required pumps and compressors, with the aid of costs of:
manufacturers’ product catalogues (frequently
available online). ∙∙ Design and engineering costs
∙∙
The above would be the most rigorous cal- Contractors’ fees
culation employed at conceptual design stage, Contingency
∙∙
and it would be common for even such rough Equipment erection
calculations not to be used at this early stage.
Piping
They are, however, necessary to generate an
∙∙
initial plant layout. Electrical
Instrumentation
∙∙
Structures and buildings
2.7. Plant Layout [7] Storage
∙∙
Laying a process plant out in space is not a Utilities
trivial matter, and the process or chemical engi- Site preparation
neer is always involved. Most obviously, the Site work
relative positions of equipment affects the pres-
sure requirements for pumps and compressors, There are other sets of factors (for example
but there is also a series of complex considera- GUTHRIE’s [9]), but the ratio of the main plant
tions associated with safety and operability, items to the cost of the complete working plant
aesthetics, etc. cost is approximately 1 : 5.
It is unusual for engineer-led design to give Alternatively, if the plant designer has access
substantial consideration to plant layout at the to whole plant costs, they might adjust these
conceptual design stage, but there is a growing costs for the size of the proposed plant using the
trend for architects to be involved in plant 0.6 rule [10], which holds that the ratio of the
Chemical Plant Design and Construction 9
cost of the proposed plant to the known one is possibly by drawings of the appearance of the
the ratio of the production volumes of the two plant on site.
plants raised to the power of 0.6. The same In some cases, piping, instrumentation, and
approach can be used to extrapolate from known general arrangement drawings might also be
equipment costs to unknown ones. included, though these are indicative only,
intended for explanatory purposes rather
than as contractually binding design
2.9. Project Programming deliverables.
The FEED designers should record their 3.3. Risk and Safety Analysis (→ Plant
choice of standards and philosophies, together and Process Safety, 6. Risk Analysis)
with any underlying assumptions and justifica-
tions for their design selection. This record By the end of the FEED stage, there is enough
should include items, such as: information to allow formal risk analysis tools,
∙
safety has been applied) relatively informal techniques that require
Isolation philosophies (how the designer examination of the proposed design from the
has designed in safe access to equipment point of view of operation, maintenance, con-
during maintenance activities as well as struction, and commissioning to identify which
∙
the assumptions made in that design) hazards it presents. The hazards identified can
Safety and loss prevention philosophy be prioritized by risk matrices.
(the way in which the designer has HAZOP studies are highly rigorous, detailed,
addressed the safety and loss prevention time-consuming reviews of the design under-
aspects of the design and the underlying taken by a panel of engineers intended to iden-
∙
assumptions) tify possible hazards arising due to unforeseen
Operating and environmental conditions interaction of parts of a process plant.
(the range of internal and external condi- There are various degrees of resolution in
tions under which the plant is designed to risk matrices, but they all permutate the proba-
operate, including foreseeable accident or bility (the risk) of an adverse event occurring (a
∙
incident conditions) hazard) with the severity of consequences if it
does occur. Figure 1 gives a typical example of a
Feedstock and product qualities (the spec- risk matrix.
ification of the feedstocks and product,
∙
Using the matrix in Figure 1, it is common to
which the plant will work with) design out any hazards considered intolerable.
Acceptable range of technologies (the list It would be desirable to design out those con-
of technologies which were considered at sidered moderate. Any remaining moderate
conceptual and FEED stage, with cost, hazards, plus any tolerable hazards are then
safety, or robustness justifications for controlled through standard operating proce-
the exclusion of other technologies) dures and/or passive safety devices. Trivial
hazards may be numerous, but do not generally readings. Off-line measurement may also be
necessitate special measures. used, which involves taking a sample from
the process and carrying out some field or
3.4. System-Level Design laboratory analysis and measurement of param-
eters. Online measurement is generally pre-
At FEED stage the tools of mass and energy ferred so that systems can be updated with
balance are used again, but they are applied at a the status of the measured parameter as often
higher resolution. Smaller streams are consid- as it is useful to obtain the required degree of
ered as well as the design of pollution abatement control.
measures that have been left out of the concep- Both the measuring devices and the control
tual stage design. Significant design problems devices may be referred to as instrumentation,
that had previously been identified but not but it is common and less confusing, to refer
resolved are addressed. to the measuring instruments alone as instru-
The mathematical model of the mass and mentation and the control devices as actuators
energy balance is most commonly produced [1].
using a spreadsheet program, such as Microsoft The most commonly used online instrumen-
Excel, but process simulation packages, such as tation measures pressure, flow, and temperature.
Aspen Hysys are increasingly applied [1]. Many other parameters can, however, be meas-
ured using online instruments.
The most common actuator on a process
3.5. Process Control plant is some kind of control valve. There are
many types of valve, some more suited for on/
Although process control is a complex subject off control, and some more suited for more
in its own right, the key issue is to control the precise modulating control. The valve can be
processes either manually or (more commonly) moved using an electrical, pneumatic, or steam
automatically to maximize profitability while power supply, and the control signal itself
maintaining safety. is almost always electrical or electronic
Irrespective of the control mode, the condi- nowadays.
tions inside the process need to be measured, The process designers develop the control
and depending on the measurements, the opera- philosophy of the plant using two key docu-
tion of the process may need to be adjusted. ments, the piping and instrumentation diagram
For example, a plant designer needs to produce (most commonly known as P+ID) and the
a stream of water at around pH 7 from a water feed functional design specification (FDS).
stream with a variable pH. The pH of the outgoing Numerous standards are used in P+ID pro-
water can be measured with an in-line pH probe. duction but ISO 14617-6:2002 [12] and ANSI/
If the pH is higher than 7, a metering pump can be ISA 5.1 (2009) [13] are those most commonly
used to add acid. If it is lower than 7, a similar employed.
pump can be used to add alkali. The functional design specification [also
The addition of the acid or alkali moves the called URS (user requirement specification) or
pH towards the desired value (set point), which a control philosophy, though all of these terms
the pH probe registers. The signal from the may also be used for other documents] is a
probe goes into the controller, which sends description in words of how the process
out a control signal to an actuator (in this designer wants the control system to work.
case a metering pump) to dose a little less of This document and the P+ID tell the software
the acid or alkali. engineer what is required of the software.
This process, whereby feedback is taken by
an instrument of a parameter to control an
actuator, which modifies the parameter, is 3.6. Unit Operation Level Design
known as feedback control [1].
Measurements are normally taken using At FEED stage, it is usual to send procurement
online instruments, inserted into the process enquiries out to specialist suppliers for any
equipment (in-line) and taking continuous significant items of equipment. Although plant
12 Chemical Plant Design and Construction
designers may well have a basic knowledge of tables, such as the nomogram reproduced in
the design of such items, they do not have the Figure 2, which are available from process
specialist knowledge required to design them pipe suppliers
sufficiently realistic. The plant designer’s role is 2. Dynamic head due to fittings: The pressure
therefore to specify unit operations rather than drop due to friction while fluid is flowing
to design them. from bends, tees, valves, etc., can be esti-
The plant designer may, however, use heu- mated using the K-value method:
ristics to produce a rough design for such items
while awaiting supplier information. An Loss of head due to fittings = K v2 2 1
g 1
∙
between flows through the plant being driven
purely by gravity or using smaller or larger
Any vertical height difference, pipe
pumps to generate flow.
lengths, number of bends, tees, etc. (which
∙
There is an interplay between hydraulic
can be taken from the layout drawing)
design, economics, and plant layout.
Number of valves, constrictions, etc.
∙
(which can be taken from the P+ID)
The pressure in process vessels (which can 3.8. Plant Layout [7]
be taken from the PFD)
Regardless of whether plant layout has
Once this information and the range of flows been considered at the conceptual design stage,
required through each pipe is known, the it is always considered at FEED stage, where
designer can calculate the three components layout drawings, known as general arrangement
of the required pressure to push flow through (GA) or plot plan drawings are produced. As a
the pipe: minimum, these drawings show, in plan and
elevation, the unit operations, pipes, pumps,
1. Dynamic head due to straight run pipe: The buildings, roadways, and other access arrange-
pressure drop due to friction while fluid is ments of the proposed plant.
flowing in straight pipe per meter of pipe These layout drawings are given to civil and
can be estimated using various charts and electrical engineering designers to allow them to
Chemical Plant Design and Construction 13
Figure 2. ABS pipe nomogram for water at 10°C (approximate values only). (Reproduced with permission of Durapipe ABS)
14 Chemical Plant Design and Construction
Table 1. K-values for common fittings [8] the main plant items method described in
Fitting type Bend radius, ° K-Value
Section 2.8.
Professional engineers normally refer to cur-
Short radius bends 22.5 0.2 rent supplier quotations for the cost of main
45 0.4
90 0.8
plant items. During evaluation, it is important
Long radius bends 22.5 0.1 that the engineer has an understanding of the
45 0.2 accuracy of their cost estimates, so that he/she
90 0.4 can assess the significance (or otherwise) of any
Open isolation valve 0.4
Open control valve 10.8
apparent differences in price.
Side entry tee 1.2 In addition, the engineer considers estimates
Through tee 0.1 of time and other resources required for site
Swing check NRV 1 installation, generated by someone who is expe-
Sharp entry 0.5
rienced in such matters. Thus, the time required
to procure and install the equipment can also be
determined. If the project program is tight,
required equipment may not be available in
progress their own layout drawings and the time to meet it.
design of buildings, slabs, cabling, etc. This This stage of the design process might loop
is, however, not a one-way information transfer. back to several previous points in the process. It
The civil and electrical engineers may return certainly involves iteration through the previous
with suggestions on how the design could be two stages of FEED, and often involves
improved to save costs or facilitate construction reconsideration of unit operation level design.
in their areas. The plant designer needs then to If the conceptual design stage was not well
take an overall view of such suggestions and articulated, iteration may even revert back to
decide if the process design can be modified to reconsideration of design envelope. This itera-
incorporate them in such a way that the overall tive process, with its loops within loops, is
design is improved. However, experienced characteristic of all design and is particularly
designers use well-established mutual arrange- common in process plant design due to its great
ments of equipment with inbuilt consideration complexity [1].
of hydraulics, civil, and electrical implications The design activities described so far have
in their design. Therefore they usually encounter largely required preceding stages for comple-
far less redesign at this stage than less experi- tion. However, this gives a misleadingly linear
enced designers [1]. impression of the design process. There are
many points in the process where a problem
can only be resolved by going back a few stages
3.9. Economic Analysis in the process to redefine the design being
considered.
The preceding two stages generate a wide range This process of iteration is more characteris-
of choices, and even the most experienced tic of the design process than any linear model.
designers need to make a rapid selection. The
key benefit of experience is knowledge of what
does not work and of where good design com- 3.10. Project Programming
promises are likely to lie.
Even the most experienced engineer gener- There may be options which would be viable,
ates numerous plausible alternatives to achieve but for the fact that they cannot be delivered
a design objective. A choice must be quickly within the available timescale. Such options
made between these on the grounds of cost, need to be identified and eliminated at FEED
safety, and process robustness. stage.
In particular, the cost element of this selec- To be accurate, the costing of the plant needs
tion process needs to be sufficiently accurate to also to take into consideration indirect, time-
serve as a tool to differentiate between options. dependent costs. For example, costs associated
Thus it is necessarily more rigorous than with the provision of the site compound used
Chemical Plant Design and Construction 15
and ancillaries also need to be fully considered at model) that the designers understand than to have
this stage. a more complex one which they do not.
By the end of it, there should be no signifi- Whichever software is used, there needs to
cant design issues left unresolved. Signifi- be a detailed mass and energy balance, inte-
cance, in this context, means having serious grated with less detailed unit operation design.
safety implications, the potential to incur addi- The detailed design of unit operations is under-
tional costs in excess of the permitted contin- taken by equipment suppliers, which are nor-
gency, the potential to miss project program mally different companies from the process
milestones, and, most importantly, the poten- plant design company.
tial to prevent the plant meeting its perform- The detailed whole-plant design yields
ance specification [1]. detailed specifications for unit operation
design companies to work from, though the
4.3. Risk and Safety Analysis (→ Plant system-level design is checked to make sure
that the approximate unit operation designs
and Process Safety, 6. Risk Analysis) within it are similar to commercially available
unit operation designs. It is always better to use
A HAZOP study on the detailed design docu-
a commercially available unit operation in a
mentation is almost certainly undertaken
design, because a model from a supplier’s
(although different industries may employ other
standard range is both cheaper and more likely
analyses, such as hazard area zoning, safety
to be well-characterized than a one-off special
integrity levels (SIL) for instrumentation,
design [1].
etc.). Although HAZOP is not intended as a
design review, it should identify any unintended
safety consequences of design choices that 4.5. Process Control [15]
make it through to the final design.
There may also be statutory considerations, Process control is always considered at detailed
such as control of major accident hazards design stage, and a detailed FDS is produced by
(COMAH) legislation [14] that need to be the process engineer in conjunction with the
integrated into the design at this stage as P+ID. Instrumentation and actuators to be used
well as a numerous safety related design codes. are specified down to the level of a particular
Experienced designers should have automati- manufacturer’s model at this stage.
cally considered much of this at earlier stages, The highest level of control is usually
but there should be explicit consideration at achieved by some kind of industrial computer.
this stage. These are usually programmable logic control-
lers (PLCs), or personal computers (PCs). PLCs
4.4. System-Level Design run a simple operating system, with a somewhat
basic input and output screen known as a human
Detailed system level design is undertaken using machine interface (HMI). PCs are essentially
some kind of computer program. This is most the familiar desktop computers running Micro-
commonly a bespoke Microsoft Excel spread- soft Windows, as well as specialized system
sheet created by the process engineer [1]. control and data acquisition (SCADA) or dis-
Although it is reasonably commonplace in tributed control system (DCS) software. Often
many industries for process simulation and both PLCs and PCs are used together in various
modeling programs to be used at this stage (if ways across a site.
not sooner) to ensure the whole system design There can also be field-mounted local control
works, it is by no means universal practice and by various means ranging from smart instru-
is still more common in consultancies than in ments that carry out control actions to field-
EPC companies. mounted PLCs.
It is both easy and quick to use simulation Software engineers are frequently involved
programs badly; expensive, and time consuming at this stage to comment on the implications of
for anyone other than the most expert users. It is the chosen control philosophy for the price and
better to have a simpler model (e.g., an Excel practicality of the control system.
Chemical Plant Design and Construction 17
Choosing between the numerous possible design methodology is the same as that used in
options to give a cost effective, robust, and previous stages. The pumps, compressors, etc.,
safe control system is best done in conjunction needed to deliver the required flows are speci-
with software control and instrumentation spe- fied as described in Section 4.6. At this stage,
cialists [1]. consideration may be given to the effects of pipe
networks with their numerous entry and exit
4.6. Unit Operation Level Design points [1].
The detailed design of the whole plant involves 4.8. Plant Layout [7]
advice from equipment suppliers about their
standard range of units. Ideally, more than one The layout drawings at the detailed design stage
equipment supplier is able to supply the specified need to be highly detailed, with accurate place-
unit, so that competitive quotations may be ment and dimensioning of all equipment in three
obtained at design for construction stage. dimensions. It is increasingly common to use
While it may be possible for whole plant 3D modeling software, especially if architects
designers to design unit operations from first are involved in the design.
principles, these designs are bespoke one-off The importance of buildings to the overall
units. It is often as much as three times as costly design predicts to some extent whether archi-
to purchase a one-off special item as it is to buy a tects are involved at this stage. Pharmaceutical
stock item. Furthermore, a special item does not processes, for example, are often indoors for
have the supplier’s know-how built into it, nor containment and confidentiality reasons, which
do they have prior experience with it. puts them at the forefront of this trend.
Stock items are usually available in an over-
lapping range of sizes, with minimum and
maximum unit sizes. Thus the designer may 4.9. Economic Analysis
be constrained as to the number of units to be
specified. A very accurate estimate of costs is possible at
There is a further consideration in this the detailed design stage. Equipment has been
respect. Process-critical unit operations need specified down to the manufacturer’s model
to be duplicated, such that there are duty and number, and it is therefore possible to obtain
standby units. If the required duty cannot be three firm fixed quotations for every item.
achieved by a single unit, duty–duty–standby, The civil and electrical engineering design
duty–assist–standby (and so on) arrangements should also have progressed to the point where
are needed [1]. firm prices and timescales can be obtained
from potential civil and electrical partner
companies.
4.7. Hydraulic Design The discipline managers in the EPC com-
pany should now be able to produce firm esti-
The layout drawing shows the actual equipment mates of how many man-hours of each
to be used at an accuracy of around ±100 mm in discipline are required for design of construc-
this stage. With this greater accuracy of the tion, procurement, site installation, site supervi-
detailed design it is now possible to complete sion, commissioning, etc.
more precise hydraulic calculations. In addition, a program, fed with this infor-
The main methodological difference is mation, can be produced in enough detail such
that straight-run headloss is calculated rather that an accurate estimate of the costs associated
than estimated less precisely from charts. with the setup of office- and site-based teams
This is normally done using Excel spread- can be established.
sheets purpose-written by the plant designer It should therefore be possible to produce an
or by the company’s process engineering estimate to AACE Class 2, ±5% accuracy (see
department. Table 3). This estimate should be in line with
The pipe lengths, elevations, number of fit- those produced at earlier stages, otherwise a
tings, etc., are known more accurately, but the project which appeared promising at the
18 Chemical Plant Design and Construction
FEED stage might yet prove unviable at the engineer or buyer. This is done using a
detailed design stage [1]. data sheet similar to that illustrated in
∙
Figure 3.
4.10. Project Programming Schedules serve a similar function, but
check for completeness and cross
The information on delivery periods for equip- referencing. The design team produces
ment, man-hours estimates, etc., available at drive schedules listing all motors on the
detailed design stage means that a detailed design used primarily to transfer informa-
and accurate project program can now be con- tion to electrical equipment suppliers,
structed [1]. valve schedules used to check that all
There may well be a need for iteration valves shown on the drawings are being
involving programming, design, and costing purchased, etc.
to resolve design issues that become apparent
when the details of design are considered, such There may also be a number of written
as accommodating long-delivery items or allow- technical documents, addressing the planning,
ing for any temporary works required. safety, environmental, and other studies
At detailed design stage, the use of more required to progress the document to this stage.
sophisticated tools, such as critical path analysis Since the design has now been progressed
becomes worthwhile. Critical path analysis is to the point where it is sufficiently well char-
useful for showing project managers, which acterized that it is ready to be built, deliver-
parts of a project are most important for main- ables will include the documentation, costing,
taining project deadlines: etc., used to define an offer to build the plant to
∙
a purchaser.
Once a project program has been con-
structed, showing the dependencies of 4.12. Design Reviews
tasks on those preceding them, it is possi-
ble to establish the critical path of the At the detailed stage of design, more formal
project, the longest linked chain of depen- design reviews are required. These basically
dencies. This, in turn, determines the min- involve a set of experienced engineers review-
imum possible time in which the project ing what has been designed based on their
∙
can be completed. collective experience.
Items which are not on the critical path are A typical review may involve as many as
said to be float. They can be fitted in eight senior engineers and may take many hours
anywhere without delaying the project. or days. Reviews are expensive, but they are
essential at later stages of design to ensure that
as much know-how as possible is built into the
4.11. Deliverables design.
There are three main kinds of technical
Deliverables packages for detailed design review. Value engineering reviews address
include more detailed versions of the PFDs, costs, safety reviews, such as HAZOP, address
P+IDs, GAs, etc. Because of the greater level safety and operability issues, and design
of details each of these drawings needs to be reviews usually center on process robustness
drawn on multiple sheets to maintain clarity. and technical feasibility.
There are also detailed FDS as well as data If this stage of design is associated with the
sheets and schedules: production of a commercial bid, there may be a
Supplier
Client Prepared by STM Date Nov-03
Site Checked by Date
Project Example Contract ref C2265 C2295 Rev 0
Section Skid mounted pumps Section X of Y Rev
Compressor Item P16,P17
One air compressor, pressurised air storage reservoir and associated controls and ancellaries to provide air for oil water separator (if required) continuous
sand filter {if required}, DAF unit {if required}, air actuated valves, and instruments. Current duty is estimated from preliminary calculations, Suppliers
should satisfy themselves that the duty specified is correct and make any adjustments as necessary to the sizing. Supply should be for complete, free
standing unit. Dryer to be provided if supplier considers this to be beneficial. System will be located inside control building
Any infromation not requested which the supplier believes will add to his offer to be provided on separate sheets
Performance parameter Description Pipework Valves Option1 Option2 Option3 Option4
Compressor
Manufacturer
Model
Type
Materials of construction
Noise levels (dBA)
Length (mm)
Width (mm)
Height (mm)
Weight (kg)
Enter here any additional notes, details of additional equipment or facilities required
∙
It may be that the site is fixed by the operating available
company at the very start of the design process, Degree of leveling and filling needed to
∙
but there is often a process of evaluation of meet process requirements
possible sites for grassroots designs at a later
Load-bearing qualities and acidity of the
stage. In considering possible sites, account
soil
must be taken of layout factors, such as:
20 Chemical Plant Design and Construction
∙
surroundings Consideration must be given to any adjacent
Direction and maximum velocity of pre- fire hazards, such as buildings, factories, plants,
∙∙
vailing winds and aspect tips, and vegetation. Adequacy of local or
Seismic activity regional firefighting and other emergency ser-
vices must be checked against foreseeable major
Existence of old mineshafts and work-
accidents.
ings, culverts, pipelines, or old chemical
∙∙
Government incentives for investment and
dumps
employment in certain areas, assistance with
Ease of obtaining planning permission buildings and developments of the social infra-
∙
Nature of adjacent land and activities structure, such as roads, airports, and railways
Any future developments being consid- may be available. Their value is directly calcu-
ered by other bodies adjacent to the pro- lable, but their tangible benefits to site invest-
posed site that could have beneficial or ment prospects must not be allowed to override
harmful interactions. less tangible negative considerations. The
AICheE or IChemE sustainability metrics (see
However, some important criteria for site Section 8.3) [16] may be of use in such
selection are independent of the layout within situations.
the site boundary. These reflect, instead, the It is crucial to enter into consultation with
relationship of the site to its surroundings. planning and other local authorities as well as
Some key examples of such criteria include any other key stakeholders as early as possible,
the proximity of the site to raw material supplies possibly with the assistance of professional
and product markets and the available means of consultants with expert knowledge of the local
transport to and from of the site. legal, safety, environmental, and social prac-
An optimum combination of distance, diffi- tices. Such discussions should not only estab-
culty, or reliability of transport should be lish which effects the site may have on the
sought, bearing in mind any legal requirements locality but also should reveal if the planning
for transport of materials, particularly hazardous authorities have any other plans or proposals
or flammable ones. that may affect or even inhibit future
The availability of suitably-skilled local expansion.
labor and the existence of local subcontractors
should be considered. In addition, the nature of
the local community and the quality of local 5. Design for Construction
infrastructure (e.g., schools, housing, etc.) may
influence the willingness of key staff to move to 5.1. Introduction
the new site.
Attitudes of local authorities and pressure Design for construction is always completed
groups can affect the responses of both the local within the organization constructing the plant.
community and society to the new site. The This stage is controlled by the EPC company’s
most immediately measurable negative impacts project managers, as it is an integral part of the
of the site are probably its consumption of construction activity.
public utilities and its generation of process This final stage of design is the least forgiv-
and sanitary waste, odor, and noise nuisance. ing and usually starts late from the point of view
Local services must be checked for their capac- of the critical path, due to the delays which have
ity to cope with the new demand and for their almost always accrued in earlier stages. It there-
standards of quality and tolerance. Fears of fore often takes place concurrently with pur-
major plant accidents impinging on the commu- chasing and construction activities.
nity may also arise. In addition, if the site Design for construction involves applying
development requires a large temporary influx the organization’s knowledge of what works
of construction workers, their impact on a com- and what does not. Small design changes, based
munity can be considerable. Other nuisance on experience, can have a large impact on the
Chemical Plant Design and Construction 21
of pipework for fabricators, and the completion integrated with design at this stage, and long
of associated stress analyses. Thus, moving lead-time items may be purchased while final
items at this stage involves significant additional design continues.
work.
The delivery time needs also to be consid-
ered. The design is often progressed in a direc- 5.10. Project Programming
tion and to the point where long-delivery items,
such as large gas compressors, can be ordered The programs produced at this stage are more
preferentially. project management tools than design aids. The
It is an essential part of process plant design project manager is therefore far more likely to
that the specification of every part depends to be driving their production than any design
some extent on the specification of other parts. leader.
Fixing the part of the design surrounding these Specific resources are allocated to each task,
long delivery items with a design freeze is and tasks are split into sub-tasks, knowing
therefore done as late as possible, since revers- which staff members are available, and how
ing an unwise design freeze, or revising the much of their time is allocated to the project,
specification of equipment already on order, as well as an accurate start and finish date,
costs time and money. equipment delivery, and installation timetables,
etc.
5.7. Hydraulic Design
5.11. Deliverables
There should be very little change to the layout
at design for construction stage, so any hydrau-
There are large quantities of deliverables at this
lic design activity should mostly be a checking
stage, and the version of the design approved for
operation.
construction has to be right. Good document
However, occasionally a particularly com-
change control and QA therefore becomes
plex element of hydraulic design requiring an
essential:
expensive computational flow dynamics (CFD)
study (→ Computational Fluid Dynamics) by a
third party expert consultant is left until this final
stage.
∙ Each deliverable item (drawing, sched-
ule etc.) depends upon others. If an
instrument on a P+ID is changed, this
requires the modification of instrument
5.8. Plant Layout schedules, the PLC I/O schedule, FDS,
∙
etc., to suit.
In many industries the very detailed layout
In the past, the drawings were stored in a
required at this stage is undertaken by specialist
drawing chest to which access was con-
piping engineers with loose oversight by pro-
trolled. Now that drawings are kept in
cess designers.
electronic format, new techniques have
It is relatively common for such engineers,
been developed to ensure that everyone
or, in some industries, specialized process archi-
is working from the same, current, set of
∙
tects, to use 3D modeling software and building
drawings and other deliverables.
information modeling (BIM) systems.
At this stage of design, QA and change
control systems usually mandate that any
5.9. Economic Analysis changes to drawings are sanctioned via the
signature of one or more key staff. Deliv-
Discussions with suppliers at this stage are erables are marked with a revision number
largely final negotiations on price, delivery, and cross-referenced to the revision num-
and specification with a view to purchase rather ber of other deliverables upon which they
than a pricing exercise. Purchasing may well be rely to avoid confusion.
Chemical Plant Design and Construction 23
Once a plant is in full operation, it is common- In addition to limits on the release to atmosphere
place for a plant operator to wish to reduce its of poisonous and obnoxious gases, most coun-
production costs per unit of product to increase tries have strict controls on the release of acid
profits. This may entail a partial redesign of the gases, such as sulfur oxides (SOx) and nitrogen
plant to optimize production efficiency. oxides (NOx) to prevent acid rain. Most also
The design of modifications to an existing restrict greenhouse gases, such as CO2, and
plant is very different to grassroots design of a volatile organic compounds (VOCs).
complete new plant because there is a substantial SOx, NOx, and CO2 are scrubbed out by
body of information on plant operation and per- water or alkali. VOCs are removed by scrubbing
formance that can be taken into consideration. with an aqueous oxidizing agent, by adsorption,
There is consequently far less uncertainty; fur- or by removal with catalytic oxidation (→ Air,
thermore, the data can be used in conjunction 7. Waste Gases, Separation and Purification).
24 Chemical Plant Design and Construction
8.2.2. Water Pollution Control even out or otherwise cope with greater
inconsistency.
Large quantities of water are used in process
plants in various grades as a solvent, heat Changes in Main Process. Not only may the
transfer medium, etc. Water may also be pro- main process or processes be highly variable,
duced as a reaction product. It is also used by the but the processes carried out might also occur on
staff in sanitary and food applications, and any a seasonal or campaign basis. The effluent
rainwater falling on the site needs to be managed produced may thus vary widely in composition
and often treated prior to discharge. and strength throughout the year. Such changes
Industrial effluent treatment has a number of may be on a timescale too long to handle by
key design problems. buffering capacity. In such cases, it is therefore
advisable to consider operation of the effluent
Batching. Many processes, especially in the treatment plant as part of the preparations for
pharmaceutical and fine chemical sectors, utilize changes to be made. In the case of campaign
a batch production process. Effluents are there- manufacture, where there may be unique events
fore also produced batchwise. This can be over- and contaminants, pilot trials may be advisable.
come by either providing a large in-line buffer
capacity prior to the treatment plant or by 8.2.3. Ground Pollution Control
treating the wastes on a batch-by-batch basis
as they are produced. Ground pollution is often of lesser concern than
the groundwater pollution that it can cause.
Toxic Shocks. There may be wide variations, Liquid wastes or liquids leached from solid
such as production of certain substances, pro- wastes by rain or groundwater can be transferred
cesses that are carried out infrequently, or emer- a long way from the site and enter drinking
gency situations, which might lead to the water supplies with adverse effects on human
occasional release of high concentrations of health.
toxic materials to the effluent treatment plant. The disposal of solid wastes by burial is
Such situations may be handled in different therefore highly regulated in most countries,
ways. The operation can be designed with and the disposal of wastes containing free
(online or off-line) buffering capacity; the pro- liquids by burial is banned in the European
cess selected can be designed to handle the full Union, United States, and many other countries.
loading; or alternative arrangements can be Control measures (other than prohibiting the
made for dealing with the toxic shock. on-site burial of waste, and permitting its
Nutrient Balance. Although industrial efflu- disposal only via suitable carriers to licensed
ents may have very high BOD (biological oxy- disposal facilities) therefore consist of keeping
gen demand) levels, nutrients may be limited. potential pollutants away from the ground by
Appropriate levels of N, P, S, etc., are needed keeping liquid storage tanks on impermeable
for biological processes to work. Various pro- standing and within secondary bunds.
prietary formulations are available, but it is In some cases, liquid and solid wastes are
questionable whether the majority of them offer disposed of on-site by incineration, but this is a
significant advantages over commercially avail- highly regulated (and publicly unpopular) pro-
able agricultural fertilizers. cess in most countries. Incineration therefore
tends only to be a worthwhile option if the site is
Sludge Consistency. Industrial process plants located far from human habitation, or if the
frequently experience problems with obtaining volumes of waste are very significant.
consistent sludges. There may be a greater
proportion of chemical sludges, and there 8.2.4. Noise and Odor Nuisance Control
may be a greater number of different sludge (→ Noise and Vibration)
types. There is almost certainly less sludge
inventory to smooth out any inconsistencies. Nuisance differs from the preceding categories
As a result, it may be necessary to design of pollution because it is subjective. Different
consolidation and thickening facilities to people have different tolerances, certain types of
Chemical Plant Design and Construction 25
noise and odor can be far more annoying to ■ Net water consumed per unit value added
people than other equally loud noises and emo- ■ Total land occupied and affected for
tional factors all come into play. value added
Noise pollution can be controlled by speci- ■ Rate of land restoration (restored per
fying low-noise equipment, by fitting noise year/total)
abatement measures to equipment, or by locat-
2. Emissions, effluents, and waste (impact on
ing noisy equipment as far as possible from the
atmosphere, water, and land)
potential complaints. In addition, night-time
■ Atmospheric acidification burden per
noise levels should be considered, because a
unit value added
noise level acceptable against a high back-
■ Global warming burden per unit value
ground level may not be acceptable against a
lower night-time baseline. added
Odor nuisance, even when it is entirely ■ Human health burden per unit value added
harmless, can cause great perceived nuisance ■ Ozone depletion burden per unit value
added
Sustainability is a highly contested term, the ■ Eutrophication per unit value added
meaning of which can be subject to political
■ Hazardous solid waste per unit value
influence. To a plant designer, however, sus-
tainability issues entails consideration of the added
■ Nonhazardous solid waste per unit value
environmental indicators outlined in the UK
IChemE’s sustainability metrics [16], which added
are divided into three main areas: 3. Additional environmental items
■ Duty of care with respect to products and
9. Mechanical Engineering Aspects design choices before they are finalized. This
of Chemical Plant Design may lead to a requirement to modify selec-
tions, based on their experience of what may or
9.1. General may not work.
Item Responsibility
Civil engineering design is frequently the work On a new or greenfield plant, the site layout
of specialist civil and structural engineering needs to reflect the known needs of the process
design companies and consultants. Such com- plant to be constructed. Alternatively, a plant
panies design the reinforced concrete slabs on may have to be laid out on an existing site
which process plants sit as well as water retain- where the requirements of a future plant may
ing concrete tanks, buildings, etc. not have been foreseen at the time of the
Civil engineers may also have environmental original site layout. In this second case, at
engineering skills allowing them to design water least some of the access arrangements that
and pollution abatement equipment, although would normally be provided on a new site
such design falls increasingly into the main have to be provided by the plant layout
plant design. engineers.
The key aspects of civil design are the selec- There are three main elements to layout:
tion of type and thickness of concrete and sizing
of required reinforcing steel to construct slabs 1. Site layout: Consideration of plots in relation
and tanks. The determination of these selections to each other within the site and to activities
is dependent on: outside the site
∙
location to resist applied forces
3. Equipment layout: Consideration of acces-
The weight of the items of the process sories around a process unit
∙
plant
Whether their weight is constant or A complete set of process units (i.e., a plant)
∙
variable fits onto a plot, although bigger plants may need
The type of process fluid or water that the two or more plots.
∙
concrete is in contact with The initial layout is usually based upon the
The height of the water table at the site PFD sequence, with process units arranged in
the order of processing. Physically adjacent
As these factors vary not only between pos- vessels and equipment are separated by dis-
sible sites but also across sites, an optimal tances that are sufficient to permit access for
design must take into consideration the civil satisfactory operation and maintenance without
engineering implications of placement of pro- wasting space.
cess equipment. The layout of some plants may follow the
process flow sequence closely through to the
final stages, but in practice there are several
11. Plant Layout [7] common features that require the layout
sequence to differ from this default sequence.
Plant layout considers the spatial arrangement These include:
of items, such as process vessels and equipment,
together with their connection by pipes, ducts, ∙∙ Process requirements
∙
conveyors, or vehicles. When developing a Economics
layout, engineers have to satisfy several criteria Ease of operation, maintenance, construc-
∙∙
in their designs:
∙∙
tion, and commissioning
Ease of future expansion and extension
Efficient, reliable, and safe plant operations
∙∙
Ease of escape and firefighting
Safe and convenient maintenance of pro-
∙
cess equipment by removal or in situ repair Operator safety
∙
Acceptable levels of hazard and nuisance Hazard containment
to the public Environmental impact
28 Chemical Plant Design and Construction
Any change to the initial layout as a result of to ±30% and is based on a body of data from
these considerations may result in extra pipe- equipment suppliers as well as key experience
work or transportation costs and additional site on the true costs of plant construction.
or building areas. The changes must therefore be Professionals working in contracting compa-
economically justifiable. Repeated checks nies complete a very detailed design and price
should be made to ensure that layout changes all the goods and services required to supply it,
do not adversely affect another requirement. taking into consideration risks, margins, contin-
A detailed knowledge of the characteristics gency, etc.
of process materials is needed to determine the Engineers have quantified this process into
requirements of hazard containment. This eval- five classes of estimates (Table 3). These are
uation must therefore be carried out by experi- used by public bodies in the United States and
enced process engineers. In particular, they worldwide [19].
must be able to identify and use appropriate The degree of confidence in the performance
statutory and in-house regulations, design stan- of the technical design thus reflects the maxi-
dards and codes of practice; appreciate the needs mum degree of confidence which may be placed
of operation, maintenance and construction; and in a costing. In addition, to develop a robust
apply engineering experience and common pricing, consideration needs to be given to a
sense. number of risk factors:
Alternatively, this work may be carried out
by designers and piping engineers supervised by
engineers experienced in plant layout. Exactly
∙ Process risks: The more novel the process,
the greater the chance it underperforms or
how this is done varies from sector to sector. fails to perform. If the plant fails its per-
Arriving at an optimal layout thus involves formance test, the construction company
close cooperation between the process and lay- incurs daily penalties until the issues are
out engineers. It also requires good cooperation rectified. It is possible to purchase per-
between all the technical and engineering disci- formance bonds, which insure process
plines to incorporate all relevant factors cor- risks, the cost of which are directly related
∙
rectly in the layout design. to the novelty of the design.
Financial risks: Contracts may be subject
12. Costing [17, 18] to fluctuations in foreign exchange, mar-
ket volatility (particularly in the cost of
12.1. General raw materials), and changes in inflation
∙
and taxation.
Engineering is a commercial activity. Engineers Political risks: Political relations between
consider the cost, safety, and robustness impli- nations can affect the price and import of
cations of every choice at every stage of a raw materials, industries may be privat-
project to allow rational decision making ized or nationalized without compensation
whether to proceed to the next stage. and changes in regulations, particularly in
At the conceptual design stage, it is possible the environmental field, may lead to cer-
to get a budget estimate of costs. A budget tain design options becoming illegal or
estimate from a contractor is probably accurate prohibitively expensive.
Chemical Plant Design and Construction 29
Sensitivity analysis is the key to understand- of the programs. They are reliant on curve fitting
ing these risks and deciding how to account for algorithms, but equipment prices are not a con-
them in pricing, but a competitive tender is tinuous variable. Such prices proceed stepwise
unlikely to succeed if all risks are considered from model to model, and it is usual to specify
to have 100% probability of occurrence. the next size model up. There are also maximum
As a rough guide, a reasonable method of and minimum commercially-available unit
pricing risk would be the probability of occur- sizes, affecting the decision on the appropriate
rence, multiplied by the consequential cost of quantity of units.
occurrence. However, some commercial players Secondly, there is an issue of the authority of
may be willing to undercut this considerably to a price estimate generated by software. A firm
gain competitive advantage. fixed price quotation is offered with a legally
At the detailed design stage all of the risk enforceable guarantee that the equipment is
factors are considered, and a price accurate to a available at the quoted price. Computer software
few percent is produced. This price needs to be vendors may offer no such guarantee.
based upon a design, which is optimized to meet
the client evaluation criteria, whether that is the
lowest price that meets the specification, lowest 12.4. Availability Analysis
whole-life cost, best net present value, or fastest
payback period, each of which affects every In deciding the required quantity of each unit
aspect of competitive design. operation, some kind of availability analysis is
necessary to determine the probability if any
given unit operation is available when required.
12.2. Price Indices In an operational environment, sophisticated
tools, such as fault tree analysis and reliability
A number of price indices are produced com- block diagrams are used alongside process sim-
mercially to allow sector specific inflation and ulation software to arrive at very certain esti-
cost escalation to be accounted for in cost mates of availability.
estimation. In the costing stage, only the required
In all cases, there is a baseline date at which standby, assist, and duty units need to be deter-
costs are set at 100%, and cost indices at specific mined. It is common to ensure a higher availa-
dates, which are multiples of 100%. To apply bility for equipment on the main process stream
cost escalation to a historical quotation, the than for less process-critical side-streams.
quotation value is multiplied by the ratio of
the cost index at the date of the quotation and 12.5. Accountancy
the current cost index.
The best known and most widely used pro- A number of accountancy techniques are par-
cess plant specific index in the field of chemical ticularly useful in the economic appraisal of
plant design is the chemical engineering plant plant design because of the long-term nature
cost index (CEPCI) [20]. of such projects: a new process plant requires
significant investment in the present but cash
inflows generated by the project will not arrive
12.3. Electronic Data Processing until well into the future. Two key techniques
Approaches for the appraisal of such projects are payback
period and discounted cash flow analyses [21].
Modeling and simulation programs may offer
integrated costing facilities though these may Payback period works by comparing the
represent, at best, no more than very coarse known initial costs of a project with its esti-
budgetary estimates. There are also commer- mated future cash flows (or savings). The length
cially available spreadsheet based approaches. of time it takes for the cash flows (or savings) to
However, these programs have two disad- cover the initial expenditure is the payback
vantages for the engineering practitioner. period. For example, a project with an initial
Firstly, there is a necessary limit to the realism cost of $10 000 000, which generates cash flows
30 Chemical Plant Design and Construction
∙
setting up the model The majority of real-world plant optimization
Whether the model has been programmed takes place after plant construction, during exer-
properly (validation) cises, such as debottlenecking. These exercises
Chemical Plant Design and Construction 31
are aspects of plant operation rather than plant 15. Project Management during
design. Plant Construction
The availability of detailed information on
plant and unit operation performance collected 15.1. Project Team
from the real plant makes it possible to develop a
plant-specific verified, validated process model. Once the operating company has accepted the
The effect of various modifications and improve- offer by the EPC company to build the designed
ments can thus be assessed in advance using this plant, the project is handed over to a new team
model. The effects of modifications suggested by within the EPC company, responsible for plant
applying various optimization techniques, such construction, commissioning, and handover to
as pinch analysis [23, 24], may then be applied to the client.
the model, and assessed for cost-effectiveness, The focus of the project now changes from
robustness and safety. design to management of resources. There are a
number of engineering disciplines within the
Pinch Analysis (→ Pinch Technology) Origi- EPC company’s project team as well as inter-
nally developed to allow optimization of heat faces with civil and electrical engineering com-
exchanger networks in the 1970s, pinch analy- panies and possibly design houses and various
sis, network analysis, or process integration is specialist consultants.
used widely in academia but far less in profes-
sional engineering practice.
Pinch analysis techniques have been
15.2. Project Manager
expanded to allow the possibility of recovery
of water and hydrogen, but these techniques
There is usually an overall project manager,
have three major flaws in all applications: They
with project engineers working under them.
are very time consuming; they do optimize the
Generally, project management positions are
issues that are most relevant to engineers, and
occupied by graduate engineers, though their
they require too much information input to be of
skills are usually deployed in people and pro-
use during the design stage.
cess management rather than design or technical
However, process synthesis or integration
issues.
(making the parts of the plant work together
The project manager has the key responsi-
as a unified whole) occurs automatically as part
bility for managing a complex range of
of process plant design. It is in fact the essence
resources to ensure that the overall objectives
of process design.
of the project are met. These are usually
Process intensification (→ Process Intensifi-
expressed in three main criteria:
∙
cation, 4. Plant Level), in the sense of making
equipment as small as is practical and some-
Time: The project must be delivered
times combining unit operations is also a feature
within a specified timeframe, with key
of standard process design approaches.
interim deadlines (milestones) to meet
∙
In academia these terms are used to
contractual requirements
describe the approaches of academic research-
ers and modelers, enumerated by, e.g., the Cost: The project must be delivered within
NTNU (Norwegian University of Science budget if it is to be a profitable activity for
∙
and Technology) which are applied to ver- the EPC
sions of process design problems lacking Specification: The finished project must
the uncertainty and lack of definition which meet its contractual performance
make their real world counterparts genuinely specifications
problematic.
Such approaches do not properly consider Therefore, the project managers have respon-
the cost, safety, and robustness implications of sibility for management and deployment of
design choices (improper trade-off handling) staff, equipment, and raw materials as well as
and are consequently of very limited relevance any other resources. They also need to manage
to engineering practitioners. and control the risks associated with project
32 Chemical Plant Design and Construction
delivery, monitor and report on progress, and Table 4. Summary of construction project activities
control change as the project moves through its Location Activity
delivery milestones. In addition, a good project
manager needs to be able to see beyond the Office based: Project Finalization of design
team Obtaining planning and other
project itself and has a sound commercial permissions
awareness, including an appreciation of the Procurement of equipment
project’s impact on the business of the EPC Project programming and subsequent
company as a whole. tracking
Appointment of mechanical, electrical,
The project managers have various tools and civil and software subcontractors
techniques at their disposal including specialist Site based: Project Establishment of site compound
software for managing each resource and report- team Site preparatory civil works
ing. In addition, many project managers now Mechanical and electrical installation
Mechanical and electrical completion
have professional qualifications in the field. Snagging
Site based: Mechanical and electrical
Commissioning team commissioning
15.3. Technical Support Process commissioning
Snagging
Performance trials
Project management engineers are usually pro- Production of operating and maintenance
vided with technical support either by in-house manuals
or bought-in process and electrical engineers Operator training
Plant acceptance
as well as software, civil, and mechanical Plant handover
engineers.
Bought-in staff resources may come from
external design houses, or more commonly,
they may be freelance individuals, allowing
companies to staff up rapidly to meet demands.
16. Legal Issues
Process plant construction is usually controlled
by a formal contract between vendor and pur-
15.4. Project Progression
chaser. Even if it is not, there is an implied
contract, whose terms are far more expensive to
A plant construction project normally prog-
establish if a problem arises.
resses through the activities as shown in Table 4.
As well as the provisions of commercial
The chronological order given in Table 4 is
contracts, plants have to be built in accordance
only approximate because, by the time an order
with the laws of the jurisdiction in which they
is awarded to construct a plant, less time is
are built and in compliance with national and
available than originally envisaged. Some
international codes and standards, which may or
degree of project acceleration, achieved by run-
may not be specifically referenced in contract
ning activities concurrently, is therefore the
documentation.
norm. Similarly, the office-based activities
always take longer than envisaged, so commis-
sioning is performed under great time pressure. 16.1. Regulatory Framework
Commissioning engineers often commence
work on site having already missed key National regulatory frameworks vary from
deadlines. country to country, but the requirements of
This time pressure is responsible for a very international trade and other considerations
different style of management in commissioning tend to result in some convergence of regula-
teams. Commissioning teams, led by a project tion, especially with respect to health, safety,
commissioning engineer, have a very high and environmental requirements.
degree of aim orientation. Commissioning is a One notable exception is the application of
short, intensive high-pressure campaign usually the precautionary principle. Originally only
undertaken by a team assembled solely for the applied to Health Safety and Environmental
purposes of the particular project. (HSE) legislation, it has become a general
Chemical Plant Design and Construction 33
guiding principle of lawmaking in the European Other contract names commonly used in the
Union [25]. However, the United States do not process industries are:
accept the precautionary principle, and conse-
quently there is a greater disparity between
some aspects of HSE law and regulation in
∙ Turnkey projects: A project which is
handed over to the client in a fully com-
the United States and European Union than in plete and operational state and able to
other areas. generate cash flows immediately. In the
There are also differences in the degree of case of a process plant, a turnkey project
prescription. The United States tend to require would be one where all the client needs to
∙
strict compliance with design codes, whereas do is turn the plant on.
the European Union tends to offer guidance and Design, build and operate contracts: In
place the onus on the designer to ensure a safe this type of contract, a contractor has full
plant has been designed. responsibility for the design and construc-
tion of a plant, and also operates it for a
16.2. Contract Writing and Forms of specified period of time before handover to
the ultimate client.
Contracts There are several variants on this type
of contract, including for example build,
A number of bodies have produced standard
operate, maintain; build, operate, trans-
terms or model forms of contract commonly
fer; and design, build, finance, operate.
used in process plant construction.
Such contracts are often used for public
The IChemE produces standard terms for
sector projects where the contractor has
three types of process plant construction con-
the ability to raise the significant levels of
tract [26]:
∙
finance required, together with appropri-
In a lump sum contract, the contractor ate expertise in facilities management and
contracts to achieve compliance with the construction.
design and performance specifications and
deliver the finished plant on time. In All standard forms of contract contain similar
return, the contractor receives a firm fixed elements. To take the IChemE Red Book as an
exemplar:
∙∙
price.
In this scenario any unforeseen costs
diminish the contractor’s profits, but any Description of the works
∙∙
cost savings are enjoyed by the contractor Documentation
alone. The pricing of lump sum contracts, Responsibilities of purchaser
∙
therefore, requires careful consideration of Health and safety
risk and the inclusion of an appropriate Environmental protection and waste
∙ ∙∙
contingency allowance. disposal
In a cost-reimbursable contract, the con- Quality assurance and validation
∙∙
tractor is reimbursed at agreed rates for all
Subcontracting
of the costs incurred in meeting their
contractual obligations. Specific contrac- Contractor’s named personnel
∙
tual provision is made for the cost of any Training by contractor
corrective works, depending on how these Parts with limited working life and spare
∙ ∙∙
arise. parts
In a target cost contract, the contractor Times of completion
∙∙
also works on a cost-reimbursable basis Liquidated damages for delay
but there is contractual provision for both Preinstallation tests and procedures
∙∙
the purchaser and the contractor to share
either any additional unforeseen costs Criteria for the completion of construction
(pain share) or any unforeseen savings Take over procedures
(gain share). Performance tests and procedures
34 Chemical Plant Design and Construction
∙ Performance guarantees and damages for may thus be considered as guidance rather
∙∙
failure than prescription and if a project is proceeding
Valuation of variations and claims well then minor breaches may well be
∙∙
Contract price and payment overlooked.
The UK’s IChemE has a set of color-coded
Contract coordination
terms specifically intended for use in process
Reports and records plant construction (Table 5).
Each of the IChemE standard forms of con-
The essence of the contract is that the parties tract also has a corresponding international
have decided prior to commencement of works version.
how they are going to work together, whether With the possible exception of the Brown
the project proceeds smoothly or not. They have Book, all the forms of contract explicitly
agreed their roles and responsibilities as well as recognize that a process plant is not just a
the penalties and procedures in the event of collection of equipment, but has a specifically
noncompliance. defined purpose and a minimum required
Business culture varies from country to performance.
country and so does the ease of enforcing The UK Institute of Engineering and Tech-
agreed contract conditions. In some countries, nology (IET) produce the MF/1 model form of
(e.g., India) the time and effort involved in contract [27], which is arguably more suited to
initiating court action to enforce a contract may mechanical and electrical equipment without
be so onerous that the signing of a contract specified process performance requirements
may have very little practical significance. In than the IChemE Forms.
others, the goodwill and friendship between The International Federation of Consulting
parties may be considered more important than Engineers (FIDIC) [28] produces standard
the precise details of the contract which has terms, which are commonly used in interna-
been signed. tional construction contracts but are less suited
These considerations are also important in to process plant construction. They also have a
countries where contract enforcement is rela- color-coded selection:
tively well-defined, since business culture
may interpret strict enforcement of every
aspect of the letter of the contract as sharp
∙ Red Book: Conditions of contract for
construction for building and engineering
practice and a breach of goodwill. Contracts works designed by the employer
Title Features
Red Book for lump sum contracts Used in a wide range of process industries
Used for fixed-sum contracts
Particularly useful for turnkey projects with significant technical elements in design and construction
and where a performance specification has been set for the finished plant
Green Book for reimbursable Used for similar projects to the Red Book but where the contract is cost-reimbursable rather than fixed-
contracts sum
Burgundy Book for target cost Used for projects where a target cost is defined
contracts Target costs may be defined either at the outset or at a later date once there is more clarity on the scope
of works
Orange Book for minor works Used for modifications to existing plant
contracts Less detailed than the Red, Green and Burgundy Books
Yellow Book for subcontracts Used to govern mechanical electrical or process subcontract relationships in the design and construction
of process plant
Design to work in concert with the Red, Green or Burgundy Books for main contracts
Brown Book subcontract for civil Used to govern subcontract relationships for any necessary civil engineering works that precede the
engineering works construction of process plant (e.g., laying slabs, access ways, etc.)
Design to work in concert with the Red, Green or Burgundy Books for main contracts
Chemical Plant Design and Construction 35
∙ Yellow Book: Conditions of contract for The 9000 series are the most popular standard
∙
plant and design-build of this type, with over one million subscribers
Silver Book: Conditions of contract for worldwide.
∙
EPC and turnkey projects The concept of ISO 9000 systems is to set out
Green Book: Conditions of short form of how a company intends to control its design or
∙
contract product quality, and how it intends to monitor
and correct and deviations from the plan.
Blue Book: Contract for dredging and
ISO 9000 series systems are not necessarily
reclamation works; MDB/FIDIC contract:
benchmarked against an external quality stan-
FIDIC conditions incorporated in the stan-
dard. They ensure consistency with a predeter-
dard bidding documents of multilateral
∙
mined internally-set standard rather than an
development banks
absolute standard.
White Book: Client and consultant model When well written and administered, ISO
∙
services agreement 9000 systems can ensure the production of a
Gold Book: FIDIC design, build, and consistently good design and product. However,
operate projects they have therefore been criticized for over-
looking continuous improvement considera-
17. Quality Assurance and tions and for their resource-intensive nature.
The series comprises:
∙
Management Systems
ISO 9001 Model for quality assurance in
17.1. Introduction
design, development, production, installa-
∙
tion, and servicing
The ISO standards are the most commonly used
international standards, although there are other ISO 9002 Model for quality assurance in
∙
standards in use worldwide, most notably in the production, installation, and servicing
United States. ISO 9003 Model for quality assurance in
The three most popular international stan- final inspection and test
dards covering the management and control of
quality, environment, and occupational health
17.3. ISO 14000 [30]
and safety are soon to be produced to a common
ISO format as follows:
∙∙
The ISO 14000 series was developed from
ISO 9000 as an environmental management
Scope system. Unlike ISO 9000, ISO 14000 defines
∙∙
Normative references both absolute minimum standards and a com-
Terms and definitions mitment to continuous improvement. The series
∙∙
Context of the organization comprises:
Leadership
∙
∙∙
ISO 14001: Environmental management
∙
Planning
systems—requirements
Support
ISO 14004: Environmental management
∙∙
Operation systems—principles, systems and support
∙
Performance evaluation techniques
Improvement ISO 14006: Environmental management
∙
systems—incorporating eco-design
17.2. ISO 9000 Series ISO 14015: Environmental assessment of
∙
sites and organizations
The ISO 9000 [29] series of international quality ISO 14020 series (14020 to 14025): Envi-
∙
assurance and quality management systems ronmental labels and declarations
are derived from a British Standard, BS5750, ISO 14030: Post-production environmen-
itself based on 1960s U.S. military standards. tal assessment
36 Chemical Plant Design and Construction
∙ ISO 14031: Environmental performance systems are eventually filled with gas when in
∙
evaluation service. This is because a leak or rupture in a
ISO 14040 series (14040 to 14049): Life liquid-containing vessel or pipe is far less haz-
∙
Cycle Assessment ardous than a pressurized gas-containing one,
ISO 14046: Requirements for water foot- since liquids do not have the stored energy of
print assessments pressurized gases. The liquid might be water, or
it might be a less-flammable hydrocarbon, such
17.4. OHSAS 18001/ISO 45001 [31] as fuel oil, depending on the nature and materi-
als of construction of the plant.
British Standard OHSAS 180001 is an interna- Where gases are charged in start-up and
tionally-applied British standard for the man- commissioning exercises, less hazardous gases
agement of occupational health and safety. A are often used initially in place of any flammable
version of OHSAS, restyled to match ISO 9000 or toxic ones used when the process is running.
and ISO 14000, is due to be published as ISO
45001 in October 2016. 18.2. Stages of Plant Start-up and
Commissioning
18. Plant Start-up and Performance
Testing There are a number of discrete and consecutive
stages of process plant commissioning. This
A process plant is more than a loose collection area is well covered in the IChemE’s Chemical
of equipment. It is a single integrated working and Process Plant Commissioning Handbook
machine, which reliably and safely produces a [32] but an outline is provided in Table 6.
given quantity of a specified product.
This integrated whole is not achieved by
completing mechanical and electrical installa- 19. Operating and Maintenance
tion alone. At this point, there exists only a Manuals
collection of equipment fixed to a slab and
interconnected with pipes and cables. This col- Operating and maintenance (O & M) manuals are
lection is not yet a single integrated working produced by those responsible for plant construc-
machine, and it is not safe to operate. tion. O & M manuals are written for the plant as a
Thus, before the plant can be handed over single integrated machine rather than as if it was a
there must be a phase of commissioning and collection of independent equipment.
performance trials, which converts the collec- Thus, they usually contain detailed explan-
tion of equipment into a single integrated oper- ations of what the objectives of the plant are, the
ational plant functioning in accordance with its limits on its performance, how the automatic
specification. controls systems work, and how operators
should operate maintain and troubleshoot the
plant as a whole.
18.1. Safety During Plant Start-up and A generic O & M manual has usually the
Commissioning following sections in the approximate order given:
∙∙
measures which protect operators during normal Emergency procedures and contact numbers
operation are not in place. Risk assessments are HSE information
undertaken, and detailed descriptions of how the General description of the process and plant
∙
plant is started up (known as method statements) including design and operating envelope
are written to control these risks.
The plant is probably filled, initially, with a Standard operating procedures for routine
∙∙
less harmful fluid than the process materials. operation
Acids and alkalis are for example often replaced Faultfinding guidance
by water. The fluid is often a liquid, even if the Maintenance schedule and procedures
Chemical Plant Design and Construction 37
Task Notes
Ensure adequate safety precautions and services available for activities in this and Completed by mechanical installers before process
ensuing phases: Risk assessment and method statement in place, all safety commissioning engineer arrives
equipment available.
Install service gland packing in all minor machinery and drivers. Completed by mechanical installers before process
commissioning engineer arrives
Install service gland packing and lubricate all types of valves as required Completed by mechanical installers before process
commissioning engineer arrives
Check alignment and lubrication of all minor rotating machinery and drivers: Completed by mechanical installers before process
Pumps to be checked commissioning engineer arrives
Lock-off or isolate all equipment before line flushing and testing Completed by mechanical installers before process
commissioning engineer arrives
Correct any construction errors or omissions Inspected by process commissioning engineer and snag list
produced
Phase B Construction and pre-commissioning
Check electrical installations for power, lighting, and instrumentation for Inspected by process commissioning engineer and snag list
operability and safety produced
Check for correct rotation of minor rotating machinery drivers and carry out Inspected by process commissioning engineer and snag list
uncoupled run produced
Hydraulic and/or pneumatic pressure test equipment to specification requirements Carried out by mechanical installers monitored by process
to check connections and joints for pressure tightness commissioning engineer
Clean all lines of loose material by flushing Carried out by mechanical installers monitored by process
commissioning engineer
Hydraulic and/or pneumatic pressure test lines to specification requirements Carried out by mechanical installers monitored by process
commissioning engineer
After completion of line and equipment pressure testing, remove all swing blinds Carried out by mechanical installers observed by process
(slip-plates) from lines other than those required for operation purposes commissioning engineer
Correction of construction errors and omissions Inspected by process commissioning engineer and snag list
produced
Retest after corrective work or alteration Carried out by mechanical installers monitored by process
commissioning engineer
Phase C Construction and pre-commissioning
Check alignment and lubrication of all major drivers assembled on site Carried out by mechanical installers monitored by process
commissioning engineer
Carry out drop tests on pumps with water to ensure satisfactory operation Carried out by process commissioning engineer
Check action of instruments, continuity of connections and instrument circuits Carried out by process commissioning engineer, assisted by
electrical installer
Check control valves and penstocks are correct for direction of flow and action on Carried out by process commissioning engineer
power failure
Test instruments and loop-check control circuits Carried out by process commissioning engineer, assisted by
electrical engineer
Test electrical controls and plant operation systems Carried out by process commissioning engineer, assisted by
electrical engineer
Phase D Construction and pre-commissioning
Check safety equipment and communications Carried out by process commissioning engineer
Calibrate instruments Carried out by process commissioning engineer, assisted by
electrical engineer
Test for leak-tightness of plant-systems Carried out by process commissioning engineer, assisted by
mechanical installer
Check completeness of battery limit connections Carried out by process commissioning engineer
Check battery limits disposal systems are complete and ready for function Carried out by process commissioning engineer
Adjust pipe supports for expansion and loading strains Carried out by process commissioning engineer, assisted by
mechanical fitter
Correct construction errors and repairs Inspected by process commissioning engineer and snag list
produced
38 Chemical Plant Design and Construction
Table 6. (Continued)
Task Notes
Phase E Commissioning
Check supports of all lines Check carried out by process commissioning engineer;
mechanical fitter remedies
Optimize operating adjustments Carried out by process commissioning engineer, assisted by
electrical engineer
Agree procedures for plant performance tests Procedures proposed by process commissioning engineer
proposes if specification does not provide them
Maintenance, routine cleaning and normal adjustments to plant Carried out by process commissioning engineer, assisted by
mechanical fitter
Complete lagging and painting Carried out by mechanical installer
Complete minor construction details Carried out by installers
Record any modifications carried out during commissioning and annotate Carried out by draftsmen from main contractor
drawings/diagrams accordingly
Clean up site Inspected by process commissioning engineer and snag list
produced
∙∙ Spares schedules
Equipment manufacturers brochures and
majority of the training should, however, take
place on the plant itself.
∙∙
contact details Small groups of operators should witness the
Certification of equipment and plant plant operating routinely under the control of the
construction company’s commissioning engi-
Plant drawings including P+IDs, GAs,
neers. The operators should operate the plant
ELDs, etc.
themselves in accordance with the O & M
manual under the supervision of the commis-
A good O & M manual is concise, clear,
sioning engineers.
comprehensive, and correct in all respects. Poor
The operation and maintenance procedures
O & M manuals are, however, commonplace.
of more sophisticated individual items of equip-
ment may be demonstrated by the commission-
20. Training of Plant Personnel ing engineers, or by specialists from the
equipment vendors in the case of unusual or
The personnel to operate the plant are ideally complex items of equipment.
trained during the final stages of commissioning Once the operators are familiar with routine
by the commissioning team. The training should operation, the shutdown, maintenance, and
be carried out in accordance with the O & M start-up procedures can be demonstrated and
manual. practiced. Next, sampling, field testing, and
It is important that the operators gain a other required off-line control actions should
favorable impression of the plant during their be taught to operators.
training, so training should be delayed until the By this point, operators should be confident
plant works reliably, and the O & M manual is in operating the plant. Emergency and fault
correct. situations can then be set up by the commission-
Training should generally proceed from a ing engineers, and the operators can be tasked to
discussion of the general principles of plants use the O & M manual to diagnose and fix them.
of the type being considered, through a discus- Once operators are fully confident in operat-
sion of the specific needs addressed by the new ing the plant, the commissioning engineers
plant, and how it addresses these requirements. should satisfy themselves that all operators
These general discussions can take place in a are competent in plant operation before signing
training room, where audiovisual equipment certificates of competence to operate the plant
might be useful to the presentation, but the for operators.
Chemical Plant Design and Construction 39