You are on page 1of 40

Chemical Plant Design and Construction

S. MORAN, Expertise Limited, Wirksworth, Matlock, United Kingdom

1. Introduction to Plant Design . . . . . 2 4.7. Hydraulic Design. . . . . . . . . . . . . . 17


1.1. General. . . . . . . . . . . . . . . . . . . . . 2 4.8. Plant Layout . . . . . . . . . . . . . . . . . 17
1.2. Plant Lifecycle. . . . . . . . . . . . . . . . 2 4.9. Economic Analysis. . . . . . . . . . . . . 17
1.3. Plant Design . . . . . . . . . . . . . . . . . 3 4.10. Project Programming . . . . . . . . . . 18
1.3.1. Stages of Plant Design. . . . . . . . . . . 3 4.11. Deliverables. . . . . . . . . . . . . . . . . . 18
1.3.2. Elements of Process Plant Design . . . 4 4.12. Design Reviews . . . . . . . . . . . . . . . 18
1.3.3. Disciplines Involved in Process Plant 4.13. Site Selection . . . . . . . . . . . . . . . . . 19
Design . . . . . . . . . . . . . . . . . . . . . . 5 5. Design for Construction . . . . . . . . . 20
2. Feasibility and Conceptual Design . 5 5.1. Introduction . . . . . . . . . . . . . . . . . 20
2.1. Introduction . . . . . . . . . . . . . . . . . 5 5.2. The Design Envelope . . . . . . . . . . . 21
2.2. The Design Envelope . . . . . . . . . . . 5 5.3. Risk and Safety Analysis . . . . . . . . 21
2.3. Risk and Safety Analysis . . . . . . . . 6 5.4. System-Level Design . . . . . . . . . . . 21
2.4. System-Level Design . . . . . . . . . . . 6 5.5. Process Control . . . . . . . . . . . . . . . 21
2.5. Unit Operation Level Design . . . . . 7 5.6. Unit Operation Level Design . . . . . 21
2.6. Hydraulic Design. . . . . . . . . . . . . . 7 5.7. Hydraulic Design. . . . . . . . . . . . . . 22
2.7. Plant Layout . . . . . . . . . . . . . . . . . 8 5.8. Plant Layout . . . . . . . . . . . . . . . . . 22
2.8. Economic Analysis. . . . . . . . . . . . . 8 5.9. Economic Analysis. . . . . . . . . . . . . 22
2.9. Project Programming . . . . . . . . . . 9 5.10. Project Programming . . . . . . . . . . 22
2.10. Deliverables. . . . . . . . . . . . . . . . . . 9 5.11. Deliverables. . . . . . . . . . . . . . . . . . 22
3. Basic Design or Front End 5.12. Design Reviews . . . . . . . . . . . . . . . 23
Engineering Design (FEED) . . . . . . 9 5.13. Site Selection . . . . . . . . . . . . . . . . . 23
3.1. Introduction . . . . . . . . . . . . . . . . . 9 6. Site Level Redesign . . . . . . . . . . . . 23
3.2. The Design Envelope . . . . . . . . . . . 9 7. Post-Handover Redesign and
3.3. Risk and Safety Analysis . . . . . . . . 10 Optimization . . . . . . . . . . . . . . . . . 23
3.4. System-Level Design . . . . . . . . . . . 11 8. Health, Safety, Environmental and
3.5. Process Control . . . . . . . . . . . . . . . 11 Sustainability Issues in Design . . . . 23
3.6. Unit Operation Level Design . . . . . 11 8.1. General. . . . . . . . . . . . . . . . . . . . . 23
3.7. Hydraulic Design. . . . . . . . . . . . . . 12 8.2. Pollution Control . . . . . . . . . . . . . . 23
3.8. Plant Layout . . . . . . . . . . . . . . . . . 12 8.2.1. Air Pollution Control . . . . . . . . . . . . 23
3.9. Economic Analysis. . . . . . . . . . . . . 14 8.2.2. Water Pollution Control . . . . . . . . . . 24
3.10. Project Programming . . . . . . . . . . 14 8.2.3. Ground Pollution Control . . . . . . . . . 24
3.11. Deliverables. . . . . . . . . . . . . . . . . . 15 8.2.4. Noise and Odor Nuisance Control . . . 24
3.12. Design Reviews . . . . . . . . . . . . . . . 15 8.3. Sustainability in Chemical Plant
3.13. Site Selection . . . . . . . . . . . . . . . . . 15 Design. . . . . . . . . . . . . . . . . . . . . . 25
4. Detailed Design . . . . . . . . . . . . . . . 15 9. Mechanical Engineering Aspects of
4.1. Introduction . . . . . . . . . . . . . . . . . 15 Chemical Plant Design . . . . . . . . . . 26
4.2. Design Envelope . . . . . . . . . . . . . . 15 9.1. General. . . . . . . . . . . . . . . . . . . . . 26
4.3. Risk and Safety Analysis . . . . . . . . 16 9.2. Materials Selection . . . . . . . . . . . . 26
4.4. System-Level Design . . . . . . . . . . . 16 9.3. Mechanical Design. . . . . . . . . . . . . 26
4.5. Process Control . . . . . . . . . . . . . . . 16 10. Civil Engineering Aspects of
4.6. Unit Operation Level Design . . . . . 17 Chemical Plant Design . . . . . . . . . . 27

 2016 Wiley-VCH Verlag GmbH & Co. KGaA, Weinheim


10.1002/14356007.b04_477.pub2
2 Chemical Plant Design and Construction

11. Plant Layout . . . . . . . . . . . . . . . . . 27 16. Legal Issues. . . . . . . . . . . . . . . . . . 32


12. Costing . . . . . . . . . . . . . . . . . . . . . 28 16.1. Regulatory Framework . . . . . . . . . 32
12.1. General. . . . . . . . . . . . . . . . . . . . . 28 16.2. Contract Writing and Forms of
12.2. Price Indices . . . . . . . . . . . . . . . . . 29 Contracts . . . . . . . . . . . . . . . . . . . 33
12.3. Electronic Data Processing 17. Quality Assurance and Management
Approaches . . . . . . . . . . . . . . . . . . 29 Systems. . . . . . . . . . . . . . . . . . . . . 35
12.4. Availability Analysis . . . . . . . . . . . 29 17.1. Introduction . . . . . . . . . . . . . . . . . 35
12.5. Accountancy . . . . . . . . . . . . . . . . . 29 17.2. ISO 9000 Series . . . . . . . . . . . . . . . 35
13. Simulation and Modeling . . . . . . . . 30 17.3. ISO 14000 . . . . . . . . . . . . . . . . . . . 35
14. Design Optimization, Synthesis, 17.4. OHSAS 18001/ISO 45001. . . . . . . . 36
Intensification, and Similar 18. Plant Start-up and Performance
Techniques . . . . . . . . . . . . . . . . . . 30 Testing . . . . . . . . . . . . . . . . . . . . . 36
14.1. General. . . . . . . . . . . . . . . . . . . . . 30 18.1. Safety During Plant Start-up and
15. Project Management during Plant Commissioning . . . . . . . . . . . . . . . 36
Construction . . . . . . . . . . . . . . . . . 31 18.2. Stages of Plant Start-up and
15.1. Project Team. . . . . . . . . . . . . . . . . 31 Commissioning . . . . . . . . . . . . . . . 36
15.2. Project Manager . . . . . . . . . . . . . . 31 19. Operating and Maintenance Manuals 36
15.3. Technical Support . . . . . . . . . . . . . 32 20. Training of Plant Personnel . . . . . . 38
15.4. Project Progression . . . . . . . . . . . . 32 References. . . . . . . . . . . . . . . . . . . 39

1. Introduction to Plant Design 3. Generate options providing potential solu-


tions to the problem
1.1. General 4. Evaluate and eliminate the options that do
not meet agreed selection criteria
Chemical plants (also called process plants) are
5. Generate a conceptual process design for
used to produce a specified product, largely by a
the selected options
combination of mixing and/or separation of mix-
tures and by chemical, biological, or nuclear 6. In parallel:
reaction. They manufacture a wide variety of prod- a. Commence development work at the
ucts, such as bulk chemicals, drinking water, phar- laboratory scale to provide more data
maceuticals, cosmetics, paraffin, and electricity. to refine the business, engineering, and
The key point is that chemical plants make a science basis of the options
specified quantity of a substance or substances b. Commence conceptual design study to
to a specified quality. evaluate the possible locations, project
Those designing and constructing such plants timescale, and order of magnitude of
need to make sure that the product is made cost- cost
effectively, safely, and reliably [1]. c. Develop the business case at the stra-
tegic level
1.2. Plant Lifecycle 7. Based on the outcomes of step 6, reduce the
number of options to those carried forward
The details of project lifecycles vary between to the next level of detail
industries, but there is a common core. For 8. In parallel:
example, the following list summarizes the a. Continue the development work at the
key stages in the product lifecycle for a phar- pilot plant scale
maceutical project: b. Based initially on data from the labo-
ratory scale, develop the design of the
1. Identify the problem to be addressed remaining options to allow a front end
2. Define the problem in business, engineer- engineering design (FEED) study to be
ing, and science terms undertaken
Chemical Plant Design and Construction 3

c. Continue to develop the business 1.3. Plant Design


scale leading to a project sanction
request at the appropriate corporate Those designing process plants need to ensure
level that their design produces the desired product
9. Based on the outcomes of step 8, select the reliably, safely and cost-effectively and meets
lead option to be designed and installed the specified composition and quantity.
10. In parallel: Plants are designed in a commercial environ-
a. Continue the development work at ment. Thus, the ultimate objective of plant
pilot scale design is to generate a profit for both the
designer and the plant owner (which are nearly
b. Carry out the detailed design of the
always separate entities) rather than for research
lead option
purposes. This has a key influence on the way in
11. Construct the required infrastructure and which plants are designed [2]:


install the required equipment
12. Commission the equipment Engineering design is always based in
13. Commission the process and verify that the heuristics, professional judgment, and reli-
plant performs as designed ance on approaches that are known from
14. Commence routine production the designer’s experience to be highly


15. Improve process efficiency based on the likely to work.
data and experience gained during routine First-principles design is avoided as much
production as possible by professional engineers,
16. Increase the plant capacity based on data because an initial design based on first
principles almost always has some


and experience gained
unforeseen problem.
17. Decommission the plant at the end of the
product life cycle Process plants are too complex to be com-
pletely understood, but the designer does
The pharmaceutical industry operates more not need to completely understand the
stages in parallel than other industries and uses plant. It is only necessary to understand
more laboratory and pilot plant work, but this is it well enough to have a high degree of
the general model followed in all industries and certainty that it meets reliably its
countries [1]. specification.
Different design activities are undertaken
throughout the plant’s life. In the early stages, 1.3.1. Stages of Plant Design
the plant to be designed is very poorly
specified, and as the lifetime of the plant The design of a chemical plant is an expensive
continues, more and more is known about process and many designs do not prove practi-
the plant. cal. Therefore potential designs are often devel-
In addition, a situation in which the plant is oped to the extent necessary to establish whether
essentially underspecified prevails throughout they are sufficiently promising to warrant fur-
most of its lifecycle. A substantial body of ther development.
data on the plant has only developed by stage This has resulted in a staged approach to
15 at which point it is possible to create a highly design, which essentially proceeds from an
accurate model. This allows the effect of a inexpensive initial and conceptual evaluation of
modification to be known with some certainty options through to a detailed design stage that
in advance. accounts for a significant proportion of the build
Therefore, during the majority of a plant’s cost of the plant, via intermediate evaluations.
lifecycle, finding reliable, just creative enough This formal staged design process is fol-
solutions to ill-defined problems is the essence lowed by two further stages, i.e., modification
of plant design. of the as-built design during the commissioning
4 Chemical Plant Design and Construction

stage and the post-handover redesign by the FEED, detailed design, and design for con-
plant owners’ engineers, which are usually struction design are mostly completed by EPC
not undertaken by the original plant design companies, possibly with some assistance from
team. design consultants and ideally with operating
The design process might therefore be split company input.
into six stages as follows [1]: Site-level redesign is led by the commission-

∙∙ Feasibility or conceptual design


Basic design or front end engineering
ing team of the EPC companies.
Process optimization is led by process engi-
neers in the operating company, possibly with

∙∙
design (FEED) assistance from design consultants and EPC
Detailed design companies or equipment suppliers [1].

∙∙
Design for construction
1.3.2. Elements of Process Plant Design
Site-level redesign
Post-handover redesign or optimization Process plant design has a number of integrated
elements [1]:


Procurement and construction of the plant
proceed along its design to varying degrees. Analysis of needs, data, specifications,
Orders for long lead-time items, for example, etc., to generate a clear description of


are commonly placed as early as the detailed the design envelope of the plant
design stage.
System level design, which is concerned
Various types of companies are involved in
with making all of the unit operations


the design process. Conceptual design usually
work together
involves some combination of an operating
company and design consultant and possibly Process control, as specified by docu-
an engineering, procurement, construction ments, such as the functional design spec-


(EPC) company. ification (FDS) for software
Design and specification of the individual
An Operating Company is a company whose processing steps, such as reactors and
business is the operation of process plants. Such distillation columns (known as unit oper-
companies are usually the ultimate clients of the ations in chemical engineering, see


companies who design and construct process below)
plants.
Hydraulic design (concerned with moving
Consultant. Consulting companies offer a fluids around the plant) and the associated


range of services, usually mainly centering on specification of pumps, compressors, etc.
design, project management, or a combination Plant layout, in which the equipment
of the two. They may be single-discipline (espe- and buildings are laid out on the site in
cially if they are design focused) or multidisci- such a way as to produce a cost-effec-
plinary. It is rare for consultants to take on tive, safe, operable, aesthetically pleas-


contractual responsibility for whether the design ing whole
works, and their design input is usually at a Risk and safety analysis using techniques,


conceptual level. such as HAZOP (hazard operability) [3]
Economic analysis, which uses tools, such

∙∙
Contracting or EPC Company. Contracting
as costing and sensitivity analysis
companies engineer, procure, and construct pro-
cess plants. EPC is one of many common contrac- Project programming
tual arrangements including EPCM (engineering, Production of key project deliverables
procurement, construction, management) and defining the design, such as mass and
EPCI (engineering, procurement, construction, energy balances, layout drawings, piping
installation). Contracting companies design and and instrumentation diagrams, process
build plants and usually offer a guarantee that the flow diagrams, Gantt charts, and various
process works. schedules.
Chemical Plant Design and Construction 5

Unit Operation [1]. The development of the ∙∙ Is it economically viable?

∙∙
concept of unit operations is agreed to be the Isitreliablypossibletomeetthespecification?
foundation of the discipline of chemical engi- Is it publically acceptable?
neering. This concept is simple but powerful. A
Is it safe?
unit operation is a stage of processing, such as
reaction, mixing, separation, or heat exchange,
It is not possible to answer these questions
where a single significant change is made. By
with the required degree of certainty unless a
splitting the process into unit operations, it is
rough design (or, more likely, multiple designs)
possible to analyze it more readily, using tools,
has been carried out. However, for the concep-
such as mass and energy balance.
tual designer, the required degree of certainty to
allow design to progress to the next stage is
1.3.3. Disciplines Involved in Process Plant
far lower than that produced by a rigorous
Design
(but expensive and time-consuming) scientific
analysis.
The key skill of the process designer is to make
Therefore engineering is not applied science,
all of the parts of the plant (and indeed the
but professional art informed by science [1].
associated design process) work together
properly.
Process designers are, generally speaking, 2.2. The Design Envelope
chemical engineers, but there are other disci-
plines that need to be involved in the plant The first task in the conceptual design of a process
design process. As a minimum, electrical, soft- plant is the analysis of the available design data to
ware, and civil engineers are required to design establish the design envelope i.e., the multi-
their respective aspects of the plant. dimensional set of constraints on the design.
There is an exchange of ideas between the External constraints determine which
various disciplines as the design progresses. The designs are possible. The proposed design
common language of the various parties to the must be physically and chemically possible.
design is engineering drawings, most notably a However, designs are commonly far less
line drawing of the plant laid out in space known directly constrained by scientific considerations
as a plot plan or general arrangement drawing. than by man-made ones, the effects of which
All these disciplines seek to optimize the only diminish as new commercially-proven
design from their point of view. The lead technologies become available. This, taken
designer needs to manage this to produce the with the innate conservatism of professional
best design. engineers, means that the practice of design
In most industries, the chemistry used is has a slow rate of change.
generally selected from available proprietary Because the aim of design is to produce a
technologies that have previously been suc- plant that generates a profit throughout its life-
cessfully operated at the proposed scale of time, it must work within the economic and
operation. other resources available. The resources differ
Scale-up from bench scale to full scale is no over time and between countries and sectors.
trivial matter and process plant designers place All designs must also be compliant with
far greater emphasis on the reliability, safety, national and international safety legislation,
and cost-effectiveness of the design than on relevant industry and statutory standards, codes,
novelty. and controls. Some of these constraints may
vary from country to country.
Internal constraints determine which designs
2. Feasibility and Conceptual Design are plausible. The companies carrying out a
design have access to just a subset of all design
2.1. Introduction and construction methods, knowledge and expe-
rience, licensed processes, process equipment,
The key questions to consider at the earliest and materials. There are also finance, time, and
stage of design are: personnel constraints on what can be delivered.
6 Chemical Plant Design and Construction

Operating companies and designers both balance and the associated process flow
have preferences for one process over another diagram.
based on their experience. Operating company
staff has experience of a limited number of Mass and Energy Balance. The law of conser-
processes, and there are costs associated with vation of mass states that (unless a nuclear
training them on a new process. reactor is being designed) mass is neither cre-
The more novel a process is, the more likely ated nor destroyed in chemical reactions. By
there are to be unforeseen problems after a extension, this law holds true in a chemical
period of operation. Plant designers and opera- plant. It may be that chemical reaction causes
tors tend therefore to favor just novel enough the chemical elements in the process to be
processes and to be more conservative at the rearranged into new compounds, but the masses
earliest design stage in order not to over-commit of elements in and out are always equal.
resources in developing a design which proves This principle forms the basis of a simple but
impractical at a later stage [1]. powerful tool known as a mass balance. This is a
calculation in which the masses of all of the
substances going into the plant and each of its
2.3. Risk and Safety Analysis unit operations are determined.
An assumption of steady state is probably
Safety first! Before progressing with a design, made at the earliest stage of design, such that the
chemical engineers must consider whether the mass balance is calculated only under the nor-
proposed chemistry and processing steps are mally envisaged operating condition. This is a
inherently safe [4]. The key principles of the simplifying assumption, which takes no account
concept are:


of even the most foreseeable excursions from
the ideal operating conditions [1].
Minimize: Reduce stocks of hazardous One important feature of the mass balance is


chemicals that it is common in plant design to recycle
Substitute: Replace hazardous chemicals materials from the end of a process back to the

∙∙
with less hazardous ones start for reprocessing. This can make a large
Moderate: Reduce the energy of the system difference to the required size of equipment
Simplify: Simple processes are easier to between the point at which the materials are
understand, operate, and control hazards withdrawn and that at which they are reintro-
within duced. Failure to account for such recycle
streams can consequently have a significant
Rather than using, for example, a highly impact upon the size, price, and practicality
flammable solvent and subsequently putting of the plant as a whole; thus they should be
in place the requisite protection measures, con- considered even at this early stage of design.
sideration should be given to employing a less Beside conservation of mass, energy is also
flammable (and therefore less inherently dan- conserved. This allows an energy balance to be
gerous) solvent in the first instance. constructed by a similar method based upon the
This is one of the most important parts of mass balance and the laws of thermodynamics.
conceptual design, because it builds passive
safety into the design at the earliest stage. Process Flow Diagram. The process flow dia-
gram (PFD) is used to show the inter-relation-
ship of the main unit operations in the envisaged
2.4. System-Level Design plant, and the flows of mass and energy between
them. Unlike some other engineering drawings
Process plant design seeks to make a collection (see Sections 3.5 and 3.8), there is consensus
of unit operations work together as a well-con- agreement within the engineering profession on
trolled and unified whole. the nature (and name) of the PFD.
Chemical engineers are trained to address Standards used in PFDs vary from country to
this at the earliest stages of design mainly country but, internationally, the most commonly
with two tools, namely the mass and energy used standard is ISO 10628 [5]. There is also a
Chemical Plant Design and Construction 7

commonly used (though now withdrawn) U.S. It is therefore good practice to allow space
standard, ANSI Y32.11 [6]. for these additional requirements when estimat-
There can be no valid design of unit opera- ing plant footprint. This is achieved by multi-
tions before a mass balance and PFD have been plying the footprint for the key unit operations
produced, since flows to individual unit opera- by a factor of four or more. Alternatively, it is
tions are not necessarily obvious from whole- possible to estimate the sizes of these key items,
plant throughput, largely due to the presence of an approach that is especially worthwhile if the
recycle streams in the plant. client wishes to have some idea of what the plant
Chemical or process engineers (the terms are will look like on the site at the earliest stage of
almost interchangeable) therefore tend to pro- design.
duce at least a rough PFD as part of their initial If pumps or compressors are to take up a
deliberations on the various potential process significant proportion of the site, it is best to size
options. them approximately even at the earliest stage,
At this earliest stage of design, the rough using the roughest kind of hydraulic design
PFD is likely to be hand sketched on paper or techniques (see Section 2.6). Similarly, in
shown in the spreadsheet or other computer some industries heat exchangers can have a
program used to produce the mass balance very significant capital and running cost as
rather than developed into a proper engineering well as site footprint, and consequently an initial
CAD drawing. However, a properly CAD- heat exchanger design is undertaken at concep-
drafted version of the rough PFD may be pro- tual design stage.
duced at the earliest stage of design to illustrate The inherent conservatism of professional
proposals to the client. In this manner, engineer- engineers screens out many options at the con-
ing drawings serve as tools for explanation and ceptual design stage in a way that may be
review as much as they are tools for thinking [1]. frustrating to neophiles. Much of professional
engineering know-how however, consists of
knowing what is not likely to work.
2.5. Unit Operation Level Design
Erring on the Side of Caution: The Conserva-
It is usually necessary to design unit operations tism of Engineers.
to some extent at the earliest stage, if only to
provide a rough approximation of their physical
size and cost. This can be completed relatively
∙ A general rule in plant design is to err very
much on the side of caution at earlier


quickly by experienced engineers, based upon stages of design.
approximate heuristics. These heuristics may Plants are always bigger, cost more, and
take the form of rules of thumb, design guides, have more design challenges than seemed
or manuals, or they may be built into specialist likely before embarking upon the detailed


black-box computer software. Thus, even at stages of design.
conceptual design stage, it is helpful to be The urge to optimize a plant design at the
able to size rectangles, circles, etc., representing conceptual design stage should therefore
the footprint on the site of the unit operations be strongly resisted [1].
that are the heart of the plant [1].
Frequently, reaction and separation pro-
cesses of the plant do not represent a significant 2.6. Hydraulic Design
proportion of the whole-plant footprint. The
required separation (for safety and operational When sizing the pumps for liquids or the com-
reasons) between these processes as well as the pressors for gases used to transfer fluids around
pumps, compressors, buildings, etc., probably a process plant, there are three key information
requirements:

∙∙
accounts for far more of the site than the unit
operations. In addition, ancillary processes,
such as steam-raising plant and pollution abate- Composition of the fluid to be moved


ment measures can account for a considerable Required flow
amount of space. Pressure required to move it
8 Chemical Plant Design and Construction

The composition and flow of the fluid to be design at an early stage resulting in an increased
moved come from the mass balance and its early consideration of layout issues.
temperature from the energy balance. The Even an initial layout might show that the
required pressure, however, has to be deter- plant envisaged cannot fit on the proposed site
mined by hydraulic calculations [1]. resulting in a need to return to the very earliest
It is essentially impossible to calculate this stage of design definition and reconsider the
pressure rigorously from first principles, and it is choices made there [1].
in any case pointless to attempt to generate a
precise value for a calculation based upon very
vague information. Engineers therefore employ 2.8. Economic Analysis
a range of techniques that facilitate the rapid
generation of approximate values for the pres- The fundamental objective of conceptual design
sure required of pumps and compressors. is to generate an idea of how much it costs to
Even at conceptual design stage, approxi- build and operate a plant. Around 98% of
mate pipe internal sizes can be established using conceptual designs prove uneconomic, which
a rule of thumb based on average velocity of is why engineers develop potential designs only
fluid through the pipe. For example, velocities to the extent necessary to generate a sufficiently
of 1.5 m/s for water-like liquids, and 15 m/s for robust cost estimate allowing a decision to be
air-like gases can be used to generate approxi- made on whether to proceed further.
mate pipe sizes. At conceptual design stage, professional
The key pumps and compressors can then be engineers often price the main plant items
sized approximately, using charts which give (roughly analogous to the unit operations) and
the amount of pressure required per meter of then calculate the whole plant cost by multi-
pipeline to transfer a given flow of material plying the total main plant items cost by a factor.
through a pipe of a given diameter. The most established factorial costing
The flow and pressure estimate can then be method is that of LANG [8], which offers a factor
used to determine the number and size of the to multiply main plant item costs to account for
required pumps and compressors, with the aid of costs of:
manufacturers’ product catalogues (frequently
available online). ∙∙ Design and engineering costs

∙∙
The above would be the most rigorous cal- Contractors’ fees
culation employed at conceptual design stage, Contingency

∙∙
and it would be common for even such rough Equipment erection
calculations not to be used at this early stage.
Piping
They are, however, necessary to generate an

∙∙
initial plant layout. Electrical
Instrumentation

∙∙
Structures and buildings
2.7. Plant Layout [7] Storage

∙∙
Laying a process plant out in space is not a Utilities
trivial matter, and the process or chemical engi- Site preparation
neer is always involved. Most obviously, the Site work
relative positions of equipment affects the pres-
sure requirements for pumps and compressors, There are other sets of factors (for example
but there is also a series of complex considera- GUTHRIE’s [9]), but the ratio of the main plant
tions associated with safety and operability, items to the cost of the complete working plant
aesthetics, etc. cost is approximately 1 : 5.
It is unusual for engineer-led design to give Alternatively, if the plant designer has access
substantial consideration to plant layout at the to whole plant costs, they might adjust these
conceptual design stage, but there is a growing costs for the size of the proposed plant using the
trend for architects to be involved in plant 0.6 rule [10], which holds that the ratio of the
Chemical Plant Design and Construction 9

cost of the proposed plant to the known one is possibly by drawings of the appearance of the
the ratio of the production volumes of the two plant on site.
plants raised to the power of 0.6. The same In some cases, piping, instrumentation, and
approach can be used to extrapolate from known general arrangement drawings might also be
equipment costs to unknown ones. included, though these are indicative only,
intended for explanatory purposes rather
than as contractually binding design
2.9. Project Programming deliverables.

If a more accurate costing is required, the likely


duration of the project needs to be known, and it
can be useful to have an idea of project program
3. Basic Design or Front End
length even at the earliest stages of design Engineering Design (FEED)
evaluation. Thus, engineers need to estimate
how long it takes to build a plant as part of 3.1. Introduction
their consideration of whether it is worth build-
ing, and to choose between the different design Only around 2% of projects progress beyond the
possibilities. Experienced engineers can usually conceptual design stage. The next stage for
generate a reliable estimate based on experience those progressing is the basic design or front
of how long it takes to procure an item of end engineering design FEED study [1].
equipment, deliver it to site, erect, and commis- Design consultants or EPC companies work
sion it. with operating companies to produce a FEED
Formally, the duration and interrelationship study, though the lead organization may vary.
of all the individual activities which form the At FEED stage, the operating company needs to
project of designing and building a process be involved in the process to ensure that the
plant is often expressed using a Gantt chart, proposed design meets their specific situation
also known as a project program or schedule. and needs. Design consultants may not be
The project program shows the start and required, but if they are used, they assist the
finish dates and duration of tasks, such as operating company to manage the EPC com-
site preparation, dependencies between tasks pany, carry out some high-level design activi-
as links, and key events as milestones. The ties, and/or contribute some proprietary process
program is quite simple at the conceptual or technology. The EPC company has the
design stage. detailed design and construction know-how
However, the interrelationships between and access to accurate pricing data to ascertain
tasks are particularly important; for example, that the design and pricing aspects of the study
some items can be installed concurrently, are realistic [1].
whereas others are reliant on other activities,
which have already taken place before they can
be erected [1]. 3.2. The Design Envelope

Whereas, during the conceptual design stage, a


2.10. Deliverables first rough consideration of the constraints on
the system design has been undertaken, at
The deliverables for a conceptual design study FEED stage, these assumptions are investi-
normally include a narrative report, setting out gated in more detail, and design philosophies
the considered design, the technology options are clearly set out in writing. If the design
possible at the plant, and a comparison of those proceeds further, those responsible for the next
options from the perspective of cost, safety, and stage of design have a clear statement of the
practicality. design basis of the plant, which minimizes the
The report usually identifies any options risk of wasting resources on redesign based on
worthy of further design development and is a different set of assumptions or a different
supported by process flow diagrams and design philosophy [1].
10 Chemical Plant Design and Construction

The FEED designers should record their 3.3. Risk and Safety Analysis (→ Plant
choice of standards and philosophies, together and Process Safety, 6. Risk Analysis)
with any underlying assumptions and justifica-
tions for their design selection. This record By the end of the FEED stage, there is enough
should include items, such as: information to allow formal risk analysis tools,

∙ Overpressure, vent, flare, and blowdown


philosophies (how the designer has
such as HAZID (hazard identification), risk
matrices, and HAZOP (hazard operability) to
be used, in addition to checking whether inher-
handled the residual possibility of over- ent safety has been properly applied [3].
pressurization of equipment after inherent HAZID techniques are quick, early stage,


safety has been applied) relatively informal techniques that require
Isolation philosophies (how the designer examination of the proposed design from the
has designed in safe access to equipment point of view of operation, maintenance, con-
during maintenance activities as well as struction, and commissioning to identify which


the assumptions made in that design) hazards it presents. The hazards identified can
Safety and loss prevention philosophy be prioritized by risk matrices.
(the way in which the designer has HAZOP studies are highly rigorous, detailed,
addressed the safety and loss prevention time-consuming reviews of the design under-
aspects of the design and the underlying taken by a panel of engineers intended to iden-


assumptions) tify possible hazards arising due to unforeseen
Operating and environmental conditions interaction of parts of a process plant.
(the range of internal and external condi- There are various degrees of resolution in
tions under which the plant is designed to risk matrices, but they all permutate the proba-
operate, including foreseeable accident or bility (the risk) of an adverse event occurring (a


incident conditions) hazard) with the severity of consequences if it
does occur. Figure 1 gives a typical example of a
Feedstock and product qualities (the spec- risk matrix.
ification of the feedstocks and product,


Using the matrix in Figure 1, it is common to
which the plant will work with) design out any hazards considered intolerable.
Acceptable range of technologies (the list It would be desirable to design out those con-
of technologies which were considered at sidered moderate. Any remaining moderate
conceptual and FEED stage, with cost, hazards, plus any tolerable hazards are then
safety, or robustness justifications for controlled through standard operating proce-
the exclusion of other technologies) dures and/or passive safety devices. Trivial

Potential severity of harm


slightly harmful harmful extremely harmful
1 2 3
highly unlikely trivial tolerable moderate
1 1 2 3
Likelihood of unlikely tolerable moderate substantial
harm occurring 2 2 4 3
likely moderate substantial intolerable
3 2 6 9

Figure 1. Example of a risk matrix [11]


Chemical Plant Design and Construction 11

hazards may be numerous, but do not generally readings. Off-line measurement may also be
necessitate special measures. used, which involves taking a sample from
the process and carrying out some field or
3.4. System-Level Design laboratory analysis and measurement of param-
eters. Online measurement is generally pre-
At FEED stage the tools of mass and energy ferred so that systems can be updated with
balance are used again, but they are applied at a the status of the measured parameter as often
higher resolution. Smaller streams are consid- as it is useful to obtain the required degree of
ered as well as the design of pollution abatement control.
measures that have been left out of the concep- Both the measuring devices and the control
tual stage design. Significant design problems devices may be referred to as instrumentation,
that had previously been identified but not but it is common and less confusing, to refer
resolved are addressed. to the measuring instruments alone as instru-
The mathematical model of the mass and mentation and the control devices as actuators
energy balance is most commonly produced [1].
using a spreadsheet program, such as Microsoft The most commonly used online instrumen-
Excel, but process simulation packages, such as tation measures pressure, flow, and temperature.
Aspen Hysys are increasingly applied [1]. Many other parameters can, however, be meas-
ured using online instruments.
The most common actuator on a process
3.5. Process Control plant is some kind of control valve. There are
many types of valve, some more suited for on/
Although process control is a complex subject off control, and some more suited for more
in its own right, the key issue is to control the precise modulating control. The valve can be
processes either manually or (more commonly) moved using an electrical, pneumatic, or steam
automatically to maximize profitability while power supply, and the control signal itself
maintaining safety. is almost always electrical or electronic
Irrespective of the control mode, the condi- nowadays.
tions inside the process need to be measured, The process designers develop the control
and depending on the measurements, the opera- philosophy of the plant using two key docu-
tion of the process may need to be adjusted. ments, the piping and instrumentation diagram
For example, a plant designer needs to produce (most commonly known as P+ID) and the
a stream of water at around pH 7 from a water feed functional design specification (FDS).
stream with a variable pH. The pH of the outgoing Numerous standards are used in P+ID pro-
water can be measured with an in-line pH probe. duction but ISO 14617-6:2002 [12] and ANSI/
If the pH is higher than 7, a metering pump can be ISA 5.1 (2009) [13] are those most commonly
used to add acid. If it is lower than 7, a similar employed.
pump can be used to add alkali. The functional design specification [also
The addition of the acid or alkali moves the called URS (user requirement specification) or
pH towards the desired value (set point), which a control philosophy, though all of these terms
the pH probe registers. The signal from the may also be used for other documents] is a
probe goes into the controller, which sends description in words of how the process
out a control signal to an actuator (in this designer wants the control system to work.
case a metering pump) to dose a little less of This document and the P+ID tell the software
the acid or alkali. engineer what is required of the software.
This process, whereby feedback is taken by
an instrument of a parameter to control an
actuator, which modifies the parameter, is 3.6. Unit Operation Level Design
known as feedback control [1].
Measurements are normally taken using At FEED stage, it is usual to send procurement
online instruments, inserted into the process enquiries out to specialist suppliers for any
equipment (in-line) and taking continuous significant items of equipment. Although plant
12 Chemical Plant Design and Construction

designers may well have a basic knowledge of tables, such as the nomogram reproduced in
the design of such items, they do not have the Figure 2, which are available from process
specialist knowledge required to design them pipe suppliers
sufficiently realistic. The plant designer’s role is 2. Dynamic head due to fittings: The pressure
therefore to specify unit operations rather than drop due to friction while fluid is flowing
to design them. from bends, tees, valves, etc., can be esti-
The plant designer may, however, use heu- mated using the K-value method:
ristics to produce a rough design for such items
while awaiting supplier information. An Loss of head due to fittings = K v2 2 1
g 1

approximate idea of the power, utility and con-


trol requirements, physical size and mass of Where
these items is required to allow design to prog- v = average velocity of fluid
ress. The plant designer may therefore be g = acceleration due to gravity (9.81 m/s2)
required to make such estimates in anticipation K = sum of K-values
of more accurate information from the supplier.
The K-values for a number of common
fittings are provided in Table 1.
3.7. Hydraulic Design 3. The static head: Independent of fluid flow,
there is a pressure in the line from any
Whereas hydraulic design is relatively unusual
pressurized process vessels attached to it,
at the conceptual stage, it is mandatory at the
as well as a pressure exerted by the fluid
FEED stage. Since the completion of hydraulic
uphill of the entry point to the pipe. These
design calculations requires knowledge of the
two components are added together to form
size, length, and shape of pipework, a layout
the static head.
drawing must first be produced [1].
Hydraulic design progresses iteratively by
The designer calculates the amount of pressure
increasing the degree of rigor. The next most
required at the inlet of the pipe to give a certain
rigorous approach (after the average velocity
flow as the sum of these three components.
method outlined in Section 2.6) is as follows:
Since length and internal diameter of the
The equipment is laid out in space and
pipe, number of fittings, and vertical height
connected by pipes on a layout drawing (as
difference between process vessels are key var-
described in Section 3.8). For each of these
iables, the designer can to some extent choose
pipes, the designer needs to know:


between flows through the plant being driven
purely by gravity or using smaller or larger
Any vertical height difference, pipe
pumps to generate flow.
lengths, number of bends, tees, etc. (which


There is an interplay between hydraulic
can be taken from the layout drawing)
design, economics, and plant layout.
Number of valves, constrictions, etc.


(which can be taken from the P+ID)
The pressure in process vessels (which can 3.8. Plant Layout [7]
be taken from the PFD)
Regardless of whether plant layout has
Once this information and the range of flows been considered at the conceptual design stage,
required through each pipe is known, the it is always considered at FEED stage, where
designer can calculate the three components layout drawings, known as general arrangement
of the required pressure to push flow through (GA) or plot plan drawings are produced. As a
the pipe: minimum, these drawings show, in plan and
elevation, the unit operations, pipes, pumps,
1. Dynamic head due to straight run pipe: The buildings, roadways, and other access arrange-
pressure drop due to friction while fluid is ments of the proposed plant.
flowing in straight pipe per meter of pipe These layout drawings are given to civil and
can be estimated using various charts and electrical engineering designers to allow them to
Chemical Plant Design and Construction 13

Figure 2. ABS pipe nomogram for water at 10°C (approximate values only). (Reproduced with permission of Durapipe ABS)
14 Chemical Plant Design and Construction

Table 1. K-values for common fittings [8] the main plant items method described in
Fitting type Bend radius, ° K-Value
Section 2.8.
Professional engineers normally refer to cur-
Short radius bends 22.5 0.2 rent supplier quotations for the cost of main
45 0.4
90 0.8
plant items. During evaluation, it is important
Long radius bends 22.5 0.1 that the engineer has an understanding of the
45 0.2 accuracy of their cost estimates, so that he/she
90 0.4 can assess the significance (or otherwise) of any
Open isolation valve 0.4
Open control valve 10.8
apparent differences in price.
Side entry tee 1.2 In addition, the engineer considers estimates
Through tee 0.1 of time and other resources required for site
Swing check NRV 1 installation, generated by someone who is expe-
Sharp entry 0.5
rienced in such matters. Thus, the time required
to procure and install the equipment can also be
determined. If the project program is tight,
required equipment may not be available in
progress their own layout drawings and the time to meet it.
design of buildings, slabs, cabling, etc. This This stage of the design process might loop
is, however, not a one-way information transfer. back to several previous points in the process. It
The civil and electrical engineers may return certainly involves iteration through the previous
with suggestions on how the design could be two stages of FEED, and often involves
improved to save costs or facilitate construction reconsideration of unit operation level design.
in their areas. The plant designer needs then to If the conceptual design stage was not well
take an overall view of such suggestions and articulated, iteration may even revert back to
decide if the process design can be modified to reconsideration of design envelope. This itera-
incorporate them in such a way that the overall tive process, with its loops within loops, is
design is improved. However, experienced characteristic of all design and is particularly
designers use well-established mutual arrange- common in process plant design due to its great
ments of equipment with inbuilt consideration complexity [1].
of hydraulics, civil, and electrical implications The design activities described so far have
in their design. Therefore they usually encounter largely required preceding stages for comple-
far less redesign at this stage than less experi- tion. However, this gives a misleadingly linear
enced designers [1]. impression of the design process. There are
many points in the process where a problem
can only be resolved by going back a few stages
3.9. Economic Analysis in the process to redefine the design being
considered.
The preceding two stages generate a wide range This process of iteration is more characteris-
of choices, and even the most experienced tic of the design process than any linear model.
designers need to make a rapid selection. The
key benefit of experience is knowledge of what
does not work and of where good design com- 3.10. Project Programming
promises are likely to lie.
Even the most experienced engineer gener- There may be options which would be viable,
ates numerous plausible alternatives to achieve but for the fact that they cannot be delivered
a design objective. A choice must be quickly within the available timescale. Such options
made between these on the grounds of cost, need to be identified and eliminated at FEED
safety, and process robustness. stage.
In particular, the cost element of this selec- To be accurate, the costing of the plant needs
tion process needs to be sufficiently accurate to also to take into consideration indirect, time-
serve as a tool to differentiate between options. dependent costs. For example, costs associated
Thus it is necessarily more rigorous than with the provision of the site compound used
Chemical Plant Design and Construction 15

during construction accrue on a weekly basis, 3.13. Site Selection [1]


irrespective of how much progress is made with
construction. FEED stage would usually be the first point at
For these reasons, it is common to produce which site selection is seriously considered.
at least an outline project program at FEED Any proposed plant, whether it is an extension
stage, with input from the civil, electrical, and of an existing plant or an all-new grassroots
process engineers involved in the design design, needs to be able to fit onto the available
development. land.
Projects are usually programmed using soft- Since this consideration can affect such basic
ware, such as Microsoft Project or, more com- factors as choice of technology, it is wise to
monly, Oracle’s Primavera, and a project consider site selection at an early stage, along
programming specialist often joins the project with factors, such as proximity of housing,
team at this stage. MS Project is, however, utilities, etc.
sufficiently intuitive that most engineers can For more detailed listing of the factors that
produce a simple program for themselves at should be considered see Section 4.13.
FEED stage.
4. Detailed Design
3.11. Deliverables
4.1. Introduction
From a technical perspective, a FEED document
package usually includes as a minimum PFDs, Detailed design of process plants is an expen-
P+IDs, GAs, project program, detailed costing, sive process, which can cost up to 10% of the
and specifications for the main plant items, whole value of the plant as constructed. It is
pumps, pipework, valves, and instrumentation. therefore only undertaken for projects identified
There are also corresponding civil and electrical by the FEED study as strongly viable [1].
drawings and documentation. The detailed design stage produces deliver-
Usually there are also contractual documen- ables close to the design for construction docu-
tation as well as safety and quality assurance ments, involving in depth discussion with
scheme details and other certifications. equipment suppliers, construction companies,
FEED studies can be produced by consul- planning authorities, operating companies,
tants, in which case they are almost entirely and consultants.
technical in nature, and their costing basis may New disciplines, such as architects, software,
be less reliable. and piping engineers not involved in earlier
Alternatively, design and build-capable con- stages, may be introduced, and the management
tracting companies can produce competitive of the design team starts to become a significant
tenders incorporating a FEED study. Such ten- task in itself.
ders are likely to include detailed legal docu- The requirement for a close link between
mentation but may be less forthcoming in their detailed design and design for construction
articulation of the design due to commercial means that this stage of design always involves
confidentiality [1]. construction companies, and if the FEED study
was undertaken as part of a competitive tender-
ing exercise, it takes place almost entirely within
3.12. Design Reviews an EPC company.

Engineering is a team activity, and the design 4.2. Design Envelope


work is always checked before it is considered
reliable enough to act upon. At detailed design stage, the design envelope
The costs associated with formal design needs to cover all foreseeable circumstances.
reviews are sufficiently high that, at FEED stage, This includes environmental conditions, varia-
oversight by more senior engineers and/or man- tions in feedstock, utility quality, and availability,
agers is all that is usually undertaken [1]. etc. The interactions between the main process
16 Chemical Plant Design and Construction

and ancillaries also need to be fully considered at model) that the designers understand than to have
this stage. a more complex one which they do not.
By the end of it, there should be no signifi- Whichever software is used, there needs to
cant design issues left unresolved. Signifi- be a detailed mass and energy balance, inte-
cance, in this context, means having serious grated with less detailed unit operation design.
safety implications, the potential to incur addi- The detailed design of unit operations is under-
tional costs in excess of the permitted contin- taken by equipment suppliers, which are nor-
gency, the potential to miss project program mally different companies from the process
milestones, and, most importantly, the poten- plant design company.
tial to prevent the plant meeting its perform- The detailed whole-plant design yields
ance specification [1]. detailed specifications for unit operation
design companies to work from, though the
4.3. Risk and Safety Analysis (→ Plant system-level design is checked to make sure
that the approximate unit operation designs
and Process Safety, 6. Risk Analysis) within it are similar to commercially available
unit operation designs. It is always better to use
A HAZOP study on the detailed design docu-
a commercially available unit operation in a
mentation is almost certainly undertaken
design, because a model from a supplier’s
(although different industries may employ other
standard range is both cheaper and more likely
analyses, such as hazard area zoning, safety
to be well-characterized than a one-off special
integrity levels (SIL) for instrumentation,
design [1].
etc.). Although HAZOP is not intended as a
design review, it should identify any unintended
safety consequences of design choices that 4.5. Process Control [15]
make it through to the final design.
There may also be statutory considerations, Process control is always considered at detailed
such as control of major accident hazards design stage, and a detailed FDS is produced by
(COMAH) legislation [14] that need to be the process engineer in conjunction with the
integrated into the design at this stage as P+ID. Instrumentation and actuators to be used
well as a numerous safety related design codes. are specified down to the level of a particular
Experienced designers should have automati- manufacturer’s model at this stage.
cally considered much of this at earlier stages, The highest level of control is usually
but there should be explicit consideration at achieved by some kind of industrial computer.
this stage. These are usually programmable logic control-
lers (PLCs), or personal computers (PCs). PLCs
4.4. System-Level Design run a simple operating system, with a somewhat
basic input and output screen known as a human
Detailed system level design is undertaken using machine interface (HMI). PCs are essentially
some kind of computer program. This is most the familiar desktop computers running Micro-
commonly a bespoke Microsoft Excel spread- soft Windows, as well as specialized system
sheet created by the process engineer [1]. control and data acquisition (SCADA) or dis-
Although it is reasonably commonplace in tributed control system (DCS) software. Often
many industries for process simulation and both PLCs and PCs are used together in various
modeling programs to be used at this stage (if ways across a site.
not sooner) to ensure the whole system design There can also be field-mounted local control
works, it is by no means universal practice and by various means ranging from smart instru-
is still more common in consultancies than in ments that carry out control actions to field-
EPC companies. mounted PLCs.
It is both easy and quick to use simulation Software engineers are frequently involved
programs badly; expensive, and time consuming at this stage to comment on the implications of
for anyone other than the most expert users. It is the chosen control philosophy for the price and
better to have a simpler model (e.g., an Excel practicality of the control system.
Chemical Plant Design and Construction 17

Choosing between the numerous possible design methodology is the same as that used in
options to give a cost effective, robust, and previous stages. The pumps, compressors, etc.,
safe control system is best done in conjunction needed to deliver the required flows are speci-
with software control and instrumentation spe- fied as described in Section 4.6. At this stage,
cialists [1]. consideration may be given to the effects of pipe
networks with their numerous entry and exit
4.6. Unit Operation Level Design points [1].

The detailed design of the whole plant involves 4.8. Plant Layout [7]
advice from equipment suppliers about their
standard range of units. Ideally, more than one The layout drawings at the detailed design stage
equipment supplier is able to supply the specified need to be highly detailed, with accurate place-
unit, so that competitive quotations may be ment and dimensioning of all equipment in three
obtained at design for construction stage. dimensions. It is increasingly common to use
While it may be possible for whole plant 3D modeling software, especially if architects
designers to design unit operations from first are involved in the design.
principles, these designs are bespoke one-off The importance of buildings to the overall
units. It is often as much as three times as costly design predicts to some extent whether archi-
to purchase a one-off special item as it is to buy a tects are involved at this stage. Pharmaceutical
stock item. Furthermore, a special item does not processes, for example, are often indoors for
have the supplier’s know-how built into it, nor containment and confidentiality reasons, which
do they have prior experience with it. puts them at the forefront of this trend.
Stock items are usually available in an over-
lapping range of sizes, with minimum and
maximum unit sizes. Thus the designer may 4.9. Economic Analysis
be constrained as to the number of units to be
specified. A very accurate estimate of costs is possible at
There is a further consideration in this the detailed design stage. Equipment has been
respect. Process-critical unit operations need specified down to the manufacturer’s model
to be duplicated, such that there are duty and number, and it is therefore possible to obtain
standby units. If the required duty cannot be three firm fixed quotations for every item.
achieved by a single unit, duty–duty–standby, The civil and electrical engineering design
duty–assist–standby (and so on) arrangements should also have progressed to the point where
are needed [1]. firm prices and timescales can be obtained
from potential civil and electrical partner
companies.
4.7. Hydraulic Design The discipline managers in the EPC com-
pany should now be able to produce firm esti-
The layout drawing shows the actual equipment mates of how many man-hours of each
to be used at an accuracy of around ±100 mm in discipline are required for design of construc-
this stage. With this greater accuracy of the tion, procurement, site installation, site supervi-
detailed design it is now possible to complete sion, commissioning, etc.
more precise hydraulic calculations. In addition, a program, fed with this infor-
The main methodological difference is mation, can be produced in enough detail such
that straight-run headloss is calculated rather that an accurate estimate of the costs associated
than estimated less precisely from charts. with the setup of office- and site-based teams
This is normally done using Excel spread- can be established.
sheets purpose-written by the plant designer It should therefore be possible to produce an
or by the company’s process engineering estimate to AACE Class 2, ±5% accuracy (see
department. Table 3). This estimate should be in line with
The pipe lengths, elevations, number of fit- those produced at earlier stages, otherwise a
tings, etc., are known more accurately, but the project which appeared promising at the
18 Chemical Plant Design and Construction

FEED stage might yet prove unviable at the engineer or buyer. This is done using a
detailed design stage [1]. data sheet similar to that illustrated in


Figure 3.
4.10. Project Programming Schedules serve a similar function, but
check for completeness and cross
The information on delivery periods for equip- referencing. The design team produces
ment, man-hours estimates, etc., available at drive schedules listing all motors on the
detailed design stage means that a detailed design used primarily to transfer informa-
and accurate project program can now be con- tion to electrical equipment suppliers,
structed [1]. valve schedules used to check that all
There may well be a need for iteration valves shown on the drawings are being
involving programming, design, and costing purchased, etc.
to resolve design issues that become apparent
when the details of design are considered, such There may also be a number of written
as accommodating long-delivery items or allow- technical documents, addressing the planning,
ing for any temporary works required. safety, environmental, and other studies
At detailed design stage, the use of more required to progress the document to this stage.
sophisticated tools, such as critical path analysis Since the design has now been progressed
becomes worthwhile. Critical path analysis is to the point where it is sufficiently well char-
useful for showing project managers, which acterized that it is ready to be built, deliver-
parts of a project are most important for main- ables will include the documentation, costing,
taining project deadlines: etc., used to define an offer to build the plant to


a purchaser.
Once a project program has been con-
structed, showing the dependencies of 4.12. Design Reviews
tasks on those preceding them, it is possi-
ble to establish the critical path of the At the detailed stage of design, more formal
project, the longest linked chain of depen- design reviews are required. These basically
dencies. This, in turn, determines the min- involve a set of experienced engineers review-
imum possible time in which the project ing what has been designed based on their


can be completed. collective experience.
Items which are not on the critical path are A typical review may involve as many as
said to be float. They can be fitted in eight senior engineers and may take many hours
anywhere without delaying the project. or days. Reviews are expensive, but they are
essential at later stages of design to ensure that
as much know-how as possible is built into the
4.11. Deliverables design.
There are three main kinds of technical
Deliverables packages for detailed design review. Value engineering reviews address
include more detailed versions of the PFDs, costs, safety reviews, such as HAZOP, address
P+IDs, GAs, etc. Because of the greater level safety and operability issues, and design
of details each of these drawings needs to be reviews usually center on process robustness
drawn on multiple sheets to maintain clarity. and technical feasibility.
There are also detailed FDS as well as data If this stage of design is associated with the
sheets and schedules: production of a commercial bid, there may be a

∙ To facilitate purchasing and project man-


agement, the complete technical specifica-
tender-settling meeting before signing off the
tender documents. Such a meeting touches upon
cost, safety, and robustness issues, but often
tion of the equipment to be purchased has focuses on risk issues based in company-spe-
to be reliably transferred from designer to cific constraints and the quality of supporting
the supplier company via the project documentation [1].
Chemical Plant Design and Construction 19

Equipment Schedule and Pricing

Supplier
Client Prepared by STM Date Nov-03
Site Checked by Date
Project Example Contract ref C2265 C2295 Rev 0
Section Skid mounted pumps Section X of Y Rev
Compressor Item P16,P17
One air compressor, pressurised air storage reservoir and associated controls and ancellaries to provide air for oil water separator (if required) continuous
sand filter {if required}, DAF unit {if required}, air actuated valves, and instruments. Current duty is estimated from preliminary calculations, Suppliers
should satisfy themselves that the duty specified is correct and make any adjustments as necessary to the sizing. Supply should be for complete, free
standing unit. Dryer to be provided if supplier considers this to be beneficial. System will be located inside control building

Any infromation not requested which the supplier believes will add to his offer to be provided on separate sheets
Performance parameter Description Pipework Valves Option1 Option2 Option3 Option4

Min flow {Nm3/hr) 30 10 10 10


Max flow {Nm3/hr) 90 20 25 35
Pressure (bar) 8 8 8 8

Compressor
Manufacturer
Model
Type
Materials of construction
Noise levels (dBA)

Length (mm)
Width (mm)
Height (mm)
Weight (kg)

Inlet connection (mm dia)


Outlet connection (mm dia)
Motor type
Enclosure class (IEC 34-5)
Insulation Class (IEC 85)
Motor Speed {rpm)
Rated power {kW}
Efficiency at design duty (%)
Mains frequency {Hz} 50
Rated voltage 415
Rated current {amp)
Strating (Star delta/DoL)
Strating current (amp)

Price for comlete system, delivered Manchester


Delivery period for complete, tested system (weeks) Target < 10 weeks

Enter here any additional notes, details of additional equipment or facilities required

Figure 3. Example of an equipment datasheet

4.13. Site Selection [7] ∙∙ Desired layout of the proposed complex


Cost, size, shape, and contours of the land


It may be that the site is fixed by the operating available
company at the very start of the design process, Degree of leveling and filling needed to


but there is often a process of evaluation of meet process requirements
possible sites for grassroots designs at a later
Load-bearing qualities and acidity of the
stage. In considering possible sites, account
soil
must be taken of layout factors, such as:
20 Chemical Plant Design and Construction

∙ Water table, flooding history, and natural


drainage patterns of the site and
effects of construction, such as noise and dust
should be minimized.


surroundings Consideration must be given to any adjacent
Direction and maximum velocity of pre- fire hazards, such as buildings, factories, plants,

∙∙
vailing winds and aspect tips, and vegetation. Adequacy of local or
Seismic activity regional firefighting and other emergency ser-
vices must be checked against foreseeable major
Existence of old mineshafts and work-
accidents.
ings, culverts, pipelines, or old chemical

∙∙
Government incentives for investment and
dumps
employment in certain areas, assistance with
Ease of obtaining planning permission buildings and developments of the social infra-


Nature of adjacent land and activities structure, such as roads, airports, and railways
Any future developments being consid- may be available. Their value is directly calcu-
ered by other bodies adjacent to the pro- lable, but their tangible benefits to site invest-
posed site that could have beneficial or ment prospects must not be allowed to override
harmful interactions. less tangible negative considerations. The
AICheE or IChemE sustainability metrics (see
However, some important criteria for site Section 8.3) [16] may be of use in such
selection are independent of the layout within situations.
the site boundary. These reflect, instead, the It is crucial to enter into consultation with
relationship of the site to its surroundings. planning and other local authorities as well as
Some key examples of such criteria include any other key stakeholders as early as possible,
the proximity of the site to raw material supplies possibly with the assistance of professional
and product markets and the available means of consultants with expert knowledge of the local
transport to and from of the site. legal, safety, environmental, and social prac-
An optimum combination of distance, diffi- tices. Such discussions should not only estab-
culty, or reliability of transport should be lish which effects the site may have on the
sought, bearing in mind any legal requirements locality but also should reveal if the planning
for transport of materials, particularly hazardous authorities have any other plans or proposals
or flammable ones. that may affect or even inhibit future
The availability of suitably-skilled local expansion.
labor and the existence of local subcontractors
should be considered. In addition, the nature of
the local community and the quality of local 5. Design for Construction
infrastructure (e.g., schools, housing, etc.) may
influence the willingness of key staff to move to 5.1. Introduction
the new site.
Attitudes of local authorities and pressure Design for construction is always completed
groups can affect the responses of both the local within the organization constructing the plant.
community and society to the new site. The This stage is controlled by the EPC company’s
most immediately measurable negative impacts project managers, as it is an integral part of the
of the site are probably its consumption of construction activity.
public utilities and its generation of process This final stage of design is the least forgiv-
and sanitary waste, odor, and noise nuisance. ing and usually starts late from the point of view
Local services must be checked for their capac- of the critical path, due to the delays which have
ity to cope with the new demand and for their almost always accrued in earlier stages. It there-
standards of quality and tolerance. Fears of fore often takes place concurrently with pur-
major plant accidents impinging on the commu- chasing and construction activities.
nity may also arise. In addition, if the site Design for construction involves applying
development requires a large temporary influx the organization’s knowledge of what works
of construction workers, their impact on a com- and what does not. Small design changes, based
munity can be considerable. Other nuisance on experience, can have a large impact on the
Chemical Plant Design and Construction 21

robustness of a process. The management of the 5.4. System-Level Design


internal handover to the construction teams thus
has to be well handled to limit modifications to The emphasis of design for construction is on a
the design to those absolutely necessary. Those very detailed design, often at a level below unit
responsible for construction have different pri- operation level design rather than on whole
orities from those in design and proposals system design.
departments, and their mutual information There is also more time pressure than in
transfer may often be poor, so this issue may previous stages of design, and even though
require active management. the very detailed design could be entered into
The design for construction stage produces a simulation program and optimized, there is
new documentation, which allows site construc- rarely time to do so.
tion teams without process design skills to build However, 3D walk-through models of the
the designed process plant. plant layout might be used to evaluate operabil-
ity. In this instance, staff operates the plant on a
virtual basis, identifying any small design
5.2. The Design Envelope details, which can be addressed to maximize
safety and ease of correct operation.
The design envelope should have been com-
pletely and accurately set by the end of the
detailed design stage and no rethink should 5.5. Process Control
be required or permissible at design for con-
struction stage other than in extremis. The process control software has probably been
The documentation of the design envelope, compiled during the detailed design stage, and
design philosophies, etc., should make it clear there is, at the very least, a detailed questioning
that this is the case. This is not the time for the of the FDS, as software engineers produce their
design to be re-engineered to suit the prefer- own detailed description of exactly how the
ences of the construction team, unless their very software needs to work.
detailed design shows that the design envelope There are hardware implications to this pro-
which formed the basis of earlier stages contains cess, as the software engineer establishes
a fundamental error. exactly how many inputs and outputs to the
The use of quality assurance, document, and PLC there need to be to accommodate the
change control procedures become extremely envisaged control actions.
important at this stage to ensure that this is If previous stages of design were insuffi-
the case. ciently rigorous, new input and output modules
are required on the PLC, or the PLC needs to be
upgraded to a more sophisticated model. How-
5.3. Risk and Safety Analysis ever, with good software or control and instru-
mentation engineers, design for construction
The design is often subjected to HAZOP at this may yield savings over what was envisaged
stage, which can cause programming problems, at the detailed design stage.
since HAZOP brings together a number of key
people who often operate under time pressure
for an extended period. 5.6. Unit Operation Level Design
Because HAZOP is not a design review, and
the design should have been well reviewed and The exact items of equipment to be used are
fixed by this stage, design and procurement selected and the design revised, if required, to
can proceed alongside the HAZOP process. reflect this. However, this is not just a matter of
HAZOP should ideally show that there are no placing a different item of equipment on the GA
problems with the design of any significance. drawing.
It should, therefore, be a due diligence exercise Design for construction involves the detailed
at this stage, rather than an opportunity to design of items, such as pipe supports and
modify the design. hangers, the production of isometric drawings
22 Chemical Plant Design and Construction

of pipework for fabricators, and the completion integrated with design at this stage, and long
of associated stress analyses. Thus, moving lead-time items may be purchased while final
items at this stage involves significant additional design continues.
work.
The delivery time needs also to be consid-
ered. The design is often progressed in a direc- 5.10. Project Programming
tion and to the point where long-delivery items,
such as large gas compressors, can be ordered The programs produced at this stage are more
preferentially. project management tools than design aids. The
It is an essential part of process plant design project manager is therefore far more likely to
that the specification of every part depends to be driving their production than any design
some extent on the specification of other parts. leader.
Fixing the part of the design surrounding these Specific resources are allocated to each task,
long delivery items with a design freeze is and tasks are split into sub-tasks, knowing
therefore done as late as possible, since revers- which staff members are available, and how
ing an unwise design freeze, or revising the much of their time is allocated to the project,
specification of equipment already on order, as well as an accurate start and finish date,
costs time and money. equipment delivery, and installation timetables,
etc.
5.7. Hydraulic Design
5.11. Deliverables
There should be very little change to the layout
at design for construction stage, so any hydrau-
There are large quantities of deliverables at this
lic design activity should mostly be a checking
stage, and the version of the design approved for
operation.
construction has to be right. Good document
However, occasionally a particularly com-
change control and QA therefore becomes
plex element of hydraulic design requiring an
essential:
expensive computational flow dynamics (CFD)
study (→ Computational Fluid Dynamics) by a
third party expert consultant is left until this final
stage.
∙ Each deliverable item (drawing, sched-
ule etc.) depends upon others. If an
instrument on a P+ID is changed, this
requires the modification of instrument
5.8. Plant Layout schedules, the PLC I/O schedule, FDS,


etc., to suit.
In many industries the very detailed layout
In the past, the drawings were stored in a
required at this stage is undertaken by specialist
drawing chest to which access was con-
piping engineers with loose oversight by pro-
trolled. Now that drawings are kept in
cess designers.
electronic format, new techniques have
It is relatively common for such engineers,
been developed to ensure that everyone
or, in some industries, specialized process archi-
is working from the same, current, set of


tects, to use 3D modeling software and building
drawings and other deliverables.
information modeling (BIM) systems.
At this stage of design, QA and change
control systems usually mandate that any
5.9. Economic Analysis changes to drawings are sanctioned via the
signature of one or more key staff. Deliv-
Discussions with suppliers at this stage are erables are marked with a revision number
largely final negotiations on price, delivery, and cross-referenced to the revision num-
and specification with a view to purchase rather ber of other deliverables upon which they
than a pricing exercise. Purchasing may well be rely to avoid confusion.
Chemical Plant Design and Construction 23

5.12. Design Reviews with modeling and simulation programs to create


an accurate model of the plant. This validated
At design for construction stage, the design is model can then be used to carry out virtual trials
reviewed by those who have to build and com- of proposed modifications to the plant.
mission it. In a company with experienced The use of modeling and simulation pro-
designers and good internal communications, grams in support of design becomes very impor-
the design is not subject to significant changes. tant in this application. This is the stage at which
It is, however, commonplace for the addition such tools can be used realistically to optimize
of a range of small items, which would facilitate operations, such as heat exchanger networks
construction and commissioning, to be pro- and, to a lesser extent, utility usage.
posed at the stage. Good change control proce-
dures are required to limit their inclusion to the
absolute minimum necessary after giving due 8. Health, Safety, Environmental
consideration to the wishes of the installation and Sustainability Issues in Design
and commissioning teams.
8.1. General
5.13. Site Selection
Although this section deals with health, safety,
The site has been selected by this stage, but there environmental, and sustainability issues, these
is ongoing liaison with planning and other issues are not separate from design. Considera-
authorities which can affect the details of site tion of these issues should be embedded in
selection. design from the earliest stages, as described
in previous sections, and any abatement pro-
6. Site Level Redesign cesses should be designed alongside the main
process.
Even with well-controlled design processes,
there can be a lack of feedback from construc-
8.2. Pollution Control
tion and commissioning staff to design teams
about some aspects of design important to The best way to control waste would be not to
installation and commission stages. generate any in the main process. However, it is
Frequently some residual errors in the design not possible to have a zero-waste process. Pre-
have to be corrected by redesign. Examples of venting the waste products from becoming
such minor errors and/or omissions include avoidable pollution is, thus, a matter of contain-
missing valves, instruments, sample points, ing them, removing them from emissions to air,
and connections for temporary services. water, or land, and converting the retained
pollution into harmless substances.
7. Post-Handover Redesign and
Optimization 8.2.1. Air Pollution Control

Once a plant is in full operation, it is common- In addition to limits on the release to atmosphere
place for a plant operator to wish to reduce its of poisonous and obnoxious gases, most coun-
production costs per unit of product to increase tries have strict controls on the release of acid
profits. This may entail a partial redesign of the gases, such as sulfur oxides (SOx) and nitrogen
plant to optimize production efficiency. oxides (NOx) to prevent acid rain. Most also
The design of modifications to an existing restrict greenhouse gases, such as CO2, and
plant is very different to grassroots design of a volatile organic compounds (VOCs).
complete new plant because there is a substantial SOx, NOx, and CO2 are scrubbed out by
body of information on plant operation and per- water or alkali. VOCs are removed by scrubbing
formance that can be taken into consideration. with an aqueous oxidizing agent, by adsorption,
There is consequently far less uncertainty; fur- or by removal with catalytic oxidation (→ Air,
thermore, the data can be used in conjunction 7. Waste Gases, Separation and Purification).
24 Chemical Plant Design and Construction

8.2.2. Water Pollution Control even out or otherwise cope with greater
inconsistency.
Large quantities of water are used in process
plants in various grades as a solvent, heat Changes in Main Process. Not only may the
transfer medium, etc. Water may also be pro- main process or processes be highly variable,
duced as a reaction product. It is also used by the but the processes carried out might also occur on
staff in sanitary and food applications, and any a seasonal or campaign basis. The effluent
rainwater falling on the site needs to be managed produced may thus vary widely in composition
and often treated prior to discharge. and strength throughout the year. Such changes
Industrial effluent treatment has a number of may be on a timescale too long to handle by
key design problems. buffering capacity. In such cases, it is therefore
advisable to consider operation of the effluent
Batching. Many processes, especially in the treatment plant as part of the preparations for
pharmaceutical and fine chemical sectors, utilize changes to be made. In the case of campaign
a batch production process. Effluents are there- manufacture, where there may be unique events
fore also produced batchwise. This can be over- and contaminants, pilot trials may be advisable.
come by either providing a large in-line buffer
capacity prior to the treatment plant or by 8.2.3. Ground Pollution Control
treating the wastes on a batch-by-batch basis
as they are produced. Ground pollution is often of lesser concern than
the groundwater pollution that it can cause.
Toxic Shocks. There may be wide variations, Liquid wastes or liquids leached from solid
such as production of certain substances, pro- wastes by rain or groundwater can be transferred
cesses that are carried out infrequently, or emer- a long way from the site and enter drinking
gency situations, which might lead to the water supplies with adverse effects on human
occasional release of high concentrations of health.
toxic materials to the effluent treatment plant. The disposal of solid wastes by burial is
Such situations may be handled in different therefore highly regulated in most countries,
ways. The operation can be designed with and the disposal of wastes containing free
(online or off-line) buffering capacity; the pro- liquids by burial is banned in the European
cess selected can be designed to handle the full Union, United States, and many other countries.
loading; or alternative arrangements can be Control measures (other than prohibiting the
made for dealing with the toxic shock. on-site burial of waste, and permitting its
Nutrient Balance. Although industrial efflu- disposal only via suitable carriers to licensed
ents may have very high BOD (biological oxy- disposal facilities) therefore consist of keeping
gen demand) levels, nutrients may be limited. potential pollutants away from the ground by
Appropriate levels of N, P, S, etc., are needed keeping liquid storage tanks on impermeable
for biological processes to work. Various pro- standing and within secondary bunds.
prietary formulations are available, but it is In some cases, liquid and solid wastes are
questionable whether the majority of them offer disposed of on-site by incineration, but this is a
significant advantages over commercially avail- highly regulated (and publicly unpopular) pro-
able agricultural fertilizers. cess in most countries. Incineration therefore
tends only to be a worthwhile option if the site is
Sludge Consistency. Industrial process plants located far from human habitation, or if the
frequently experience problems with obtaining volumes of waste are very significant.
consistent sludges. There may be a greater
proportion of chemical sludges, and there 8.2.4. Noise and Odor Nuisance Control
may be a greater number of different sludge (→ Noise and Vibration)
types. There is almost certainly less sludge
inventory to smooth out any inconsistencies. Nuisance differs from the preceding categories
As a result, it may be necessary to design of pollution because it is subjective. Different
consolidation and thickening facilities to people have different tolerances, certain types of
Chemical Plant Design and Construction 25

noise and odor can be far more annoying to ■ Net water consumed per unit value added
people than other equally loud noises and emo- ■ Total land occupied and affected for
tional factors all come into play. value added
Noise pollution can be controlled by speci- ■ Rate of land restoration (restored per
fying low-noise equipment, by fitting noise year/total)
abatement measures to equipment, or by locat-
2. Emissions, effluents, and waste (impact on
ing noisy equipment as far as possible from the
atmosphere, water, and land)
potential complaints. In addition, night-time
■ Atmospheric acidification burden per
noise levels should be considered, because a
unit value added
noise level acceptable against a high back-
■ Global warming burden per unit value
ground level may not be acceptable against a
lower night-time baseline. added
Odor nuisance, even when it is entirely ■ Human health burden per unit value added

harmless, can cause great perceived nuisance ■ Ozone depletion burden per unit value

even at very low concentrations. Odors can be added


treated like VOCs, which they mostly com- ■ Photochemical ozone burden per unit
prise, by scrubbing, catalytic, or biological value added
oxidation. ■ Aquatic acidification per unit value added

■ Aquatic oxygen demand per unit value


8.3. Sustainability in Chemical Plant added
Design ■ Ecotoxicity to aquatic life per unit value

added
Sustainability is a highly contested term, the ■ Eutrophication per unit value added
meaning of which can be subject to political
■ Hazardous solid waste per unit value
influence. To a plant designer, however, sus-
tainability issues entails consideration of the added
■ Nonhazardous solid waste per unit value
environmental indicators outlined in the UK
IChemE’s sustainability metrics [16], which added
are divided into three main areas: 3. Additional environmental items
■ Duty of care with respect to products and

1. Resource usage (energy, material, water, services produced. Environmental


land) impact and mitigating steps taken,
■ Percentage of total net primary energy including issues concerning long-term
sourced from renewables environmental or health problems arising
■ Total net primary energy usage per kilo- from process or product, for which the
gram product solution is not yet known.
■ Issues concerning environmental impact of
■ Total net primary energy usage per unit

value added plant construction and decommissioning.


■ Compliance: Magnitude and nature of
■ Total raw materials used per kilogram

product penalties for noncompliance with any


■ Total raw materials used per unit value
local, national, or international environ-
added mental regulations or agreements.
■ Impacts on protected areas (sites of spe-
■ Fraction of raw materials recycled within

company cial scientific interest, proposed special


areas of conservation, national parks).
■ Fraction of raw materials recycled from
Impacts on local biodiversity or impor-
consumers tant habitats.
■ Hazardous raw material per kilogram
■ Issues concerning long-term supply of raw
product materials from nonrenewable resources.
■ Net water consumed per unit mass of
■ Other possible relevant metrics
product
26 Chemical Plant Design and Construction

9. Mechanical Engineering Aspects design choices before they are finalized. This
of Chemical Plant Design may lead to a requirement to modify selec-
tions, based on their experience of what may or
9.1. General may not work.

The selection of the basic subcomponents of 9.2. Materials Selection


process plants is an essential part of what plant
designers do. Certain types of materials, for Plant designers need to know which materials
example, are more suited to a given range of are suitable for the plant’s intended duty, as well
pressures, temperatures, chemical, and physical as the duties to which the plant might (inten-
compositions than others. tionally or unintentionally) be put.
Matching the ranges of these parameters in This is not determined so much by material
the plant design envelope to suitable materials is science as by practical experience, together with
usually considered to be the responsibility of the a broad qualitative knowledge of available
process plant designer. Similarly, so is the materials and their strengths and limitations.
selection of pumps, heat exchangers, instrumen- There are also traditional default positions in
tation, valves, etc. various process sectors. For example, the
At conceptual design stage it is often generic pipe material in the oil and gas industry
important to know, at a category level, what is carbon steel, whereas plastics are specified
kinds of components are likely to be used. For within the water industry; highly corrosive
example, process plant designers usually water is transported in carbon steel piping in
know whether to use rotodynamic or positive the oil and gas industry.
displacement pumps; membranes or distilla- Although this may seem unusual to a water
tion; globe or butterfly valves; carbon steel or specialist, this selection is not wrong, per se, as
plastic, etc., by the time their initial drawings long as suitable corrosion allowances are made,
are complete. All of these decisions affect and the consequent increased metal ion content
the fundamental characteristics of the design of the water is acceptable from a process point
and have implications for cost, safety, and of view.
robustness.
At the detailed design stage, selection is at
the level of particular specific commercially- 9.3. Mechanical Design
available items of equipment. Datasheets are
produced setting out the detailed specification Process designers probably only address the
of the item and taking account of the selected materials selection aspect of the mechanical
materials of construction. Manufacturers may, design of process plants. Piping engineers,
on sight of these datasheets, provide feedback mechanical engineers, mechanical installers,
that may lead to refinement or reconsideration of and equipment suppliers carry out the mechani-
the selection. cal design of process plant and interconnections.
Design for construction generates signifi- The items requiring design and those usually
cantly more detailed documentation, and expe- responsible for designing them are shown in
rienced engineers are likely to review the Table 2.

Table 2. Responsibilities of mechanical design

Item Responsibility

Pressure vessels Suppliers of pressure equipment


Steel and plastic open-topped tanks Suppliers of tanks
Above-ground pipework, pipework supports, thrust blocks, and bracketry Piping engineers, mechanical installers
Below-ground pipework and thrust blocks, wall penetrations Civil and structural engineers
Chemical Plant Design and Construction 27

10. Civil Engineering Aspects of


Chemical Plant Design
∙∙ Safe and efficient construction
Effective and economical use of space

Civil engineering design is frequently the work On a new or greenfield plant, the site layout
of specialist civil and structural engineering needs to reflect the known needs of the process
design companies and consultants. Such com- plant to be constructed. Alternatively, a plant
panies design the reinforced concrete slabs on may have to be laid out on an existing site
which process plants sit as well as water retain- where the requirements of a future plant may
ing concrete tanks, buildings, etc. not have been foreseen at the time of the
Civil engineers may also have environmental original site layout. In this second case, at
engineering skills allowing them to design water least some of the access arrangements that
and pollution abatement equipment, although would normally be provided on a new site
such design falls increasingly into the main have to be provided by the plant layout
plant design. engineers.
The key aspects of civil design are the selec- There are three main elements to layout:
tion of type and thickness of concrete and sizing
of required reinforcing steel to construct slabs 1. Site layout: Consideration of plots in relation
and tanks. The determination of these selections to each other within the site and to activities
is dependent on: outside the site

∙ The ability of the ground at the proposed


2. Plot layout: Consideration of process units in
relation to each other within a plot


location to resist applied forces
3. Equipment layout: Consideration of acces-
The weight of the items of the process sories around a process unit


plant
Whether their weight is constant or A complete set of process units (i.e., a plant)


variable fits onto a plot, although bigger plants may need
The type of process fluid or water that the two or more plots.


concrete is in contact with The initial layout is usually based upon the
The height of the water table at the site PFD sequence, with process units arranged in
the order of processing. Physically adjacent
As these factors vary not only between pos- vessels and equipment are separated by dis-
sible sites but also across sites, an optimal tances that are sufficient to permit access for
design must take into consideration the civil satisfactory operation and maintenance without
engineering implications of placement of pro- wasting space.
cess equipment. The layout of some plants may follow the
process flow sequence closely through to the
final stages, but in practice there are several
11. Plant Layout [7] common features that require the layout
sequence to differ from this default sequence.
Plant layout considers the spatial arrangement These include:
of items, such as process vessels and equipment,
together with their connection by pipes, ducts, ∙∙ Process requirements


conveyors, or vehicles. When developing a Economics
layout, engineers have to satisfy several criteria Ease of operation, maintenance, construc-

∙∙
in their designs:

∙∙
tion, and commissioning
Ease of future expansion and extension
Efficient, reliable, and safe plant operations

∙∙
Ease of escape and firefighting
Safe and convenient maintenance of pro-


cess equipment by removal or in situ repair Operator safety


Acceptable levels of hazard and nuisance Hazard containment
to the public Environmental impact
28 Chemical Plant Design and Construction

Table 3. AACE classes of cost estimate

Estimate class Name Purpose Project definition level, %

Class 5 order of magnitude screening or feasibility 0–2


Class 4 intermediate concept study or feasibility 1–15
Class 3 preliminary budget, authorization, or control 10–40
Class 2 substantive control or bid/tender 30–70
Class 1 definitive check estimate or bid/tender 50–100

Any change to the initial layout as a result of to ±30% and is based on a body of data from
these considerations may result in extra pipe- equipment suppliers as well as key experience
work or transportation costs and additional site on the true costs of plant construction.
or building areas. The changes must therefore be Professionals working in contracting compa-
economically justifiable. Repeated checks nies complete a very detailed design and price
should be made to ensure that layout changes all the goods and services required to supply it,
do not adversely affect another requirement. taking into consideration risks, margins, contin-
A detailed knowledge of the characteristics gency, etc.
of process materials is needed to determine the Engineers have quantified this process into
requirements of hazard containment. This eval- five classes of estimates (Table 3). These are
uation must therefore be carried out by experi- used by public bodies in the United States and
enced process engineers. In particular, they worldwide [19].
must be able to identify and use appropriate The degree of confidence in the performance
statutory and in-house regulations, design stan- of the technical design thus reflects the maxi-
dards and codes of practice; appreciate the needs mum degree of confidence which may be placed
of operation, maintenance and construction; and in a costing. In addition, to develop a robust
apply engineering experience and common pricing, consideration needs to be given to a
sense. number of risk factors:
Alternatively, this work may be carried out
by designers and piping engineers supervised by
engineers experienced in plant layout. Exactly
∙ Process risks: The more novel the process,
the greater the chance it underperforms or
how this is done varies from sector to sector. fails to perform. If the plant fails its per-
Arriving at an optimal layout thus involves formance test, the construction company
close cooperation between the process and lay- incurs daily penalties until the issues are
out engineers. It also requires good cooperation rectified. It is possible to purchase per-
between all the technical and engineering disci- formance bonds, which insure process
plines to incorporate all relevant factors cor- risks, the cost of which are directly related


rectly in the layout design. to the novelty of the design.
Financial risks: Contracts may be subject
12. Costing [17, 18] to fluctuations in foreign exchange, mar-
ket volatility (particularly in the cost of
12.1. General raw materials), and changes in inflation


and taxation.
Engineering is a commercial activity. Engineers Political risks: Political relations between
consider the cost, safety, and robustness impli- nations can affect the price and import of
cations of every choice at every stage of a raw materials, industries may be privat-
project to allow rational decision making ized or nationalized without compensation
whether to proceed to the next stage. and changes in regulations, particularly in
At the conceptual design stage, it is possible the environmental field, may lead to cer-
to get a budget estimate of costs. A budget tain design options becoming illegal or
estimate from a contractor is probably accurate prohibitively expensive.
Chemical Plant Design and Construction 29

Sensitivity analysis is the key to understand- of the programs. They are reliant on curve fitting
ing these risks and deciding how to account for algorithms, but equipment prices are not a con-
them in pricing, but a competitive tender is tinuous variable. Such prices proceed stepwise
unlikely to succeed if all risks are considered from model to model, and it is usual to specify
to have 100% probability of occurrence. the next size model up. There are also maximum
As a rough guide, a reasonable method of and minimum commercially-available unit
pricing risk would be the probability of occur- sizes, affecting the decision on the appropriate
rence, multiplied by the consequential cost of quantity of units.
occurrence. However, some commercial players Secondly, there is an issue of the authority of
may be willing to undercut this considerably to a price estimate generated by software. A firm
gain competitive advantage. fixed price quotation is offered with a legally
At the detailed design stage all of the risk enforceable guarantee that the equipment is
factors are considered, and a price accurate to a available at the quoted price. Computer software
few percent is produced. This price needs to be vendors may offer no such guarantee.
based upon a design, which is optimized to meet
the client evaluation criteria, whether that is the
lowest price that meets the specification, lowest 12.4. Availability Analysis
whole-life cost, best net present value, or fastest
payback period, each of which affects every In deciding the required quantity of each unit
aspect of competitive design. operation, some kind of availability analysis is
necessary to determine the probability if any
given unit operation is available when required.
12.2. Price Indices In an operational environment, sophisticated
tools, such as fault tree analysis and reliability
A number of price indices are produced com- block diagrams are used alongside process sim-
mercially to allow sector specific inflation and ulation software to arrive at very certain esti-
cost escalation to be accounted for in cost mates of availability.
estimation. In the costing stage, only the required
In all cases, there is a baseline date at which standby, assist, and duty units need to be deter-
costs are set at 100%, and cost indices at specific mined. It is common to ensure a higher availa-
dates, which are multiples of 100%. To apply bility for equipment on the main process stream
cost escalation to a historical quotation, the than for less process-critical side-streams.
quotation value is multiplied by the ratio of
the cost index at the date of the quotation and 12.5. Accountancy
the current cost index.
The best known and most widely used pro- A number of accountancy techniques are par-
cess plant specific index in the field of chemical ticularly useful in the economic appraisal of
plant design is the chemical engineering plant plant design because of the long-term nature
cost index (CEPCI) [20]. of such projects: a new process plant requires
significant investment in the present but cash
inflows generated by the project will not arrive
12.3. Electronic Data Processing until well into the future. Two key techniques
Approaches for the appraisal of such projects are payback
period and discounted cash flow analyses [21].
Modeling and simulation programs may offer
integrated costing facilities though these may Payback period works by comparing the
represent, at best, no more than very coarse known initial costs of a project with its esti-
budgetary estimates. There are also commer- mated future cash flows (or savings). The length
cially available spreadsheet based approaches. of time it takes for the cash flows (or savings) to
However, these programs have two disad- cover the initial expenditure is the payback
vantages for the engineering practitioner. period. For example, a project with an initial
Firstly, there is a necessary limit to the realism cost of $10 000 000, which generates cash flows
30 Chemical Plant Design and Construction

of $2 000 000 in year one and every year


thereafter would have a payback period of
∙ Whether the model matches the real
world plant it is intended to simulate
five years. (verification)
Payback period has the advantage of sim-
plicity, and it is widely used in project appraisal. Modern simulation and modeling programs
It is readily understood by management, who are very powerful, but there is a high potential
may set internal payback time limits. However, for misuse by all but the most skilled users. The
payback period analysis relies heavily on dividing line between use and misuse of simu-
assumptions and overlooks the often critical lation and modeling programs tends to reflect
issue of when exactly cash flows are received whether the IChemE computer aided process
within the payback period time limit. It also fails engineering (CAPE) guidelines [22] are fol-
to take the inflation of money into account. lowed, and particularly whether model verifica-
tion and validation have been undertaken.
Discounted Cash Flows. Discounted cash flow In situations where a body of applicable data
techniques are more sophisticated than simple on the exact plant to be designed already exists,
payback period analysis, because they account and many similar plants are to be designed, it
for the inflation of money, allowing future cash may be worthwhile to invest resources in creat-
flows to be compared with present-day mone- ing a verified model of the proposed plant,
tary values on a like-for-like basis. together with models of the unit operations.
Discounted cash flows work on the basis that Plant design then becomes a question of linking
it is preferable to receive a sum of money today these blocks into an integrated model, and
rather than an equal sum in the future; this is due optimization of the model can serve as a valid
to three reasons. Firstly, there is a risk that proxy for optimizing the plant.
the future sum will not materialize; secondly, If, however, a single one-off plant is
receiving the money now creates an investment designed, there is usually insufficient data avail-
opportunity (and will thus become a greater sum able on the plant to produce anything but an
in a year’s time), and thirdly, due to inflation, the unverified model using generic data. The con-
original sum may be worth less in real terms in a siderable margin of error would thus render such
year’s time. a model worthless.
They are calculated by taking the projected In general, plant operators are the staff most
cash flows for a project and applying a discount likely to hold the information necessary to
factor to each. The sum of the resulting dis- verify and tune modeling software. The con-
counted cash flows can then be compared to the tracting companies, who design the majority of
total costs of the project, giving the net present process plants, do not have this information, and
value of a project. If the net present value is consequently make less use of modeling. There-
positive, then the project is financially viable fore, the most commonly-used modeling soft-
because, the inflows of cash will exceed the ware is employed in the oil and gas industry,
outflows. because these companies are best placed to
invest the data, time, and effort needed to verify
the accuracy of modeling software.
13. Simulation and Modeling
Modeling and simulation programs allow an
approximate computer model of a process plant 14. Design Optimization, Synthesis,
to be assembled and operated on a virtual basis. Intensification, and Similar
The realism of this virtual plant depends on Techniques
three factors:

∙ The skill and experience of the person


14.1. General


setting up the model The majority of real-world plant optimization
Whether the model has been programmed takes place after plant construction, during exer-
properly (validation) cises, such as debottlenecking. These exercises
Chemical Plant Design and Construction 31

are aspects of plant operation rather than plant 15. Project Management during
design. Plant Construction
The availability of detailed information on
plant and unit operation performance collected 15.1. Project Team
from the real plant makes it possible to develop a
plant-specific verified, validated process model. Once the operating company has accepted the
The effect of various modifications and improve- offer by the EPC company to build the designed
ments can thus be assessed in advance using this plant, the project is handed over to a new team
model. The effects of modifications suggested by within the EPC company, responsible for plant
applying various optimization techniques, such construction, commissioning, and handover to
as pinch analysis [23, 24], may then be applied to the client.
the model, and assessed for cost-effectiveness, The focus of the project now changes from
robustness and safety. design to management of resources. There are a
number of engineering disciplines within the
Pinch Analysis (→ Pinch Technology) Origi- EPC company’s project team as well as inter-
nally developed to allow optimization of heat faces with civil and electrical engineering com-
exchanger networks in the 1970s, pinch analy- panies and possibly design houses and various
sis, network analysis, or process integration is specialist consultants.
used widely in academia but far less in profes-
sional engineering practice.
Pinch analysis techniques have been
15.2. Project Manager
expanded to allow the possibility of recovery
of water and hydrogen, but these techniques
There is usually an overall project manager,
have three major flaws in all applications: They
with project engineers working under them.
are very time consuming; they do optimize the
Generally, project management positions are
issues that are most relevant to engineers, and
occupied by graduate engineers, though their
they require too much information input to be of
skills are usually deployed in people and pro-
use during the design stage.
cess management rather than design or technical
However, process synthesis or integration
issues.
(making the parts of the plant work together
The project manager has the key responsi-
as a unified whole) occurs automatically as part
bility for managing a complex range of
of process plant design. It is in fact the essence
resources to ensure that the overall objectives
of process design.
of the project are met. These are usually
Process intensification (→ Process Intensifi-
expressed in three main criteria:


cation, 4. Plant Level), in the sense of making
equipment as small as is practical and some-
Time: The project must be delivered
times combining unit operations is also a feature
within a specified timeframe, with key
of standard process design approaches.
interim deadlines (milestones) to meet


In academia these terms are used to
contractual requirements
describe the approaches of academic research-
ers and modelers, enumerated by, e.g., the Cost: The project must be delivered within
NTNU (Norwegian University of Science budget if it is to be a profitable activity for


and Technology) which are applied to ver- the EPC
sions of process design problems lacking Specification: The finished project must
the uncertainty and lack of definition which meet its contractual performance
make their real world counterparts genuinely specifications
problematic.
Such approaches do not properly consider Therefore, the project managers have respon-
the cost, safety, and robustness implications of sibility for management and deployment of
design choices (improper trade-off handling) staff, equipment, and raw materials as well as
and are consequently of very limited relevance any other resources. They also need to manage
to engineering practitioners. and control the risks associated with project
32 Chemical Plant Design and Construction

delivery, monitor and report on progress, and Table 4. Summary of construction project activities
control change as the project moves through its Location Activity
delivery milestones. In addition, a good project
manager needs to be able to see beyond the Office based: Project Finalization of design
team Obtaining planning and other
project itself and has a sound commercial permissions
awareness, including an appreciation of the Procurement of equipment
project’s impact on the business of the EPC Project programming and subsequent
company as a whole. tracking
Appointment of mechanical, electrical,
The project managers have various tools and civil and software subcontractors
techniques at their disposal including specialist Site based: Project Establishment of site compound
software for managing each resource and report- team Site preparatory civil works
ing. In addition, many project managers now Mechanical and electrical installation
Mechanical and electrical completion
have professional qualifications in the field. Snagging
Site based: Mechanical and electrical
Commissioning team commissioning
15.3. Technical Support Process commissioning
Snagging
Performance trials
Project management engineers are usually pro- Production of operating and maintenance
vided with technical support either by in-house manuals
or bought-in process and electrical engineers Operator training
Plant acceptance
as well as software, civil, and mechanical Plant handover
engineers.
Bought-in staff resources may come from
external design houses, or more commonly,
they may be freelance individuals, allowing
companies to staff up rapidly to meet demands.
16. Legal Issues
Process plant construction is usually controlled
by a formal contract between vendor and pur-
15.4. Project Progression
chaser. Even if it is not, there is an implied
contract, whose terms are far more expensive to
A plant construction project normally prog-
establish if a problem arises.
resses through the activities as shown in Table 4.
As well as the provisions of commercial
The chronological order given in Table 4 is
contracts, plants have to be built in accordance
only approximate because, by the time an order
with the laws of the jurisdiction in which they
is awarded to construct a plant, less time is
are built and in compliance with national and
available than originally envisaged. Some
international codes and standards, which may or
degree of project acceleration, achieved by run-
may not be specifically referenced in contract
ning activities concurrently, is therefore the
documentation.
norm. Similarly, the office-based activities
always take longer than envisaged, so commis-
sioning is performed under great time pressure. 16.1. Regulatory Framework
Commissioning engineers often commence
work on site having already missed key National regulatory frameworks vary from
deadlines. country to country, but the requirements of
This time pressure is responsible for a very international trade and other considerations
different style of management in commissioning tend to result in some convergence of regula-
teams. Commissioning teams, led by a project tion, especially with respect to health, safety,
commissioning engineer, have a very high and environmental requirements.
degree of aim orientation. Commissioning is a One notable exception is the application of
short, intensive high-pressure campaign usually the precautionary principle. Originally only
undertaken by a team assembled solely for the applied to Health Safety and Environmental
purposes of the particular project. (HSE) legislation, it has become a general
Chemical Plant Design and Construction 33

guiding principle of lawmaking in the European Other contract names commonly used in the
Union [25]. However, the United States do not process industries are:
accept the precautionary principle, and conse-
quently there is a greater disparity between
some aspects of HSE law and regulation in
∙ Turnkey projects: A project which is
handed over to the client in a fully com-
the United States and European Union than in plete and operational state and able to
other areas. generate cash flows immediately. In the
There are also differences in the degree of case of a process plant, a turnkey project
prescription. The United States tend to require would be one where all the client needs to


strict compliance with design codes, whereas do is turn the plant on.
the European Union tends to offer guidance and Design, build and operate contracts: In
place the onus on the designer to ensure a safe this type of contract, a contractor has full
plant has been designed. responsibility for the design and construc-
tion of a plant, and also operates it for a
16.2. Contract Writing and Forms of specified period of time before handover to
the ultimate client.
Contracts There are several variants on this type
of contract, including for example build,
A number of bodies have produced standard
operate, maintain; build, operate, trans-
terms or model forms of contract commonly
fer; and design, build, finance, operate.
used in process plant construction.
Such contracts are often used for public
The IChemE produces standard terms for
sector projects where the contractor has
three types of process plant construction con-
the ability to raise the significant levels of
tract [26]:


finance required, together with appropri-
In a lump sum contract, the contractor ate expertise in facilities management and
contracts to achieve compliance with the construction.
design and performance specifications and
deliver the finished plant on time. In All standard forms of contract contain similar
return, the contractor receives a firm fixed elements. To take the IChemE Red Book as an
exemplar:

∙∙
price.
In this scenario any unforeseen costs
diminish the contractor’s profits, but any Description of the works

∙∙
cost savings are enjoyed by the contractor Documentation
alone. The pricing of lump sum contracts, Responsibilities of purchaser


therefore, requires careful consideration of Health and safety
risk and the inclusion of an appropriate Environmental protection and waste

∙ ∙∙
contingency allowance. disposal
In a cost-reimbursable contract, the con- Quality assurance and validation

∙∙
tractor is reimbursed at agreed rates for all
Subcontracting
of the costs incurred in meeting their
contractual obligations. Specific contrac- Contractor’s named personnel


tual provision is made for the cost of any Training by contractor
corrective works, depending on how these Parts with limited working life and spare

∙ ∙∙
arise. parts
In a target cost contract, the contractor Times of completion

∙∙
also works on a cost-reimbursable basis Liquidated damages for delay
but there is contractual provision for both Preinstallation tests and procedures

∙∙
the purchaser and the contractor to share
either any additional unforeseen costs Criteria for the completion of construction
(pain share) or any unforeseen savings Take over procedures
(gain share). Performance tests and procedures
34 Chemical Plant Design and Construction

∙ Performance guarantees and damages for may thus be considered as guidance rather

∙∙
failure than prescription and if a project is proceeding
Valuation of variations and claims well then minor breaches may well be

∙∙
Contract price and payment overlooked.
The UK’s IChemE has a set of color-coded
Contract coordination
terms specifically intended for use in process
Reports and records plant construction (Table 5).
Each of the IChemE standard forms of con-
The essence of the contract is that the parties tract also has a corresponding international
have decided prior to commencement of works version.
how they are going to work together, whether With the possible exception of the Brown
the project proceeds smoothly or not. They have Book, all the forms of contract explicitly
agreed their roles and responsibilities as well as recognize that a process plant is not just a
the penalties and procedures in the event of collection of equipment, but has a specifically
noncompliance. defined purpose and a minimum required
Business culture varies from country to performance.
country and so does the ease of enforcing The UK Institute of Engineering and Tech-
agreed contract conditions. In some countries, nology (IET) produce the MF/1 model form of
(e.g., India) the time and effort involved in contract [27], which is arguably more suited to
initiating court action to enforce a contract may mechanical and electrical equipment without
be so onerous that the signing of a contract specified process performance requirements
may have very little practical significance. In than the IChemE Forms.
others, the goodwill and friendship between The International Federation of Consulting
parties may be considered more important than Engineers (FIDIC) [28] produces standard
the precise details of the contract which has terms, which are commonly used in interna-
been signed. tional construction contracts but are less suited
These considerations are also important in to process plant construction. They also have a
countries where contract enforcement is rela- color-coded selection:
tively well-defined, since business culture
may interpret strict enforcement of every
aspect of the letter of the contract as sharp
∙ Red Book: Conditions of contract for
construction for building and engineering
practice and a breach of goodwill. Contracts works designed by the employer

Table 5. IChemE standard forms of contract

Title Features

Red Book for lump sum contracts Used in a wide range of process industries
Used for fixed-sum contracts
Particularly useful for turnkey projects with significant technical elements in design and construction
and where a performance specification has been set for the finished plant
Green Book for reimbursable Used for similar projects to the Red Book but where the contract is cost-reimbursable rather than fixed-
contracts sum
Burgundy Book for target cost Used for projects where a target cost is defined
contracts Target costs may be defined either at the outset or at a later date once there is more clarity on the scope
of works
Orange Book for minor works Used for modifications to existing plant
contracts Less detailed than the Red, Green and Burgundy Books
Yellow Book for subcontracts Used to govern mechanical electrical or process subcontract relationships in the design and construction
of process plant
Design to work in concert with the Red, Green or Burgundy Books for main contracts
Brown Book subcontract for civil Used to govern subcontract relationships for any necessary civil engineering works that precede the
engineering works construction of process plant (e.g., laying slabs, access ways, etc.)
Design to work in concert with the Red, Green or Burgundy Books for main contracts
Chemical Plant Design and Construction 35

∙ Yellow Book: Conditions of contract for The 9000 series are the most popular standard


plant and design-build of this type, with over one million subscribers
Silver Book: Conditions of contract for worldwide.


EPC and turnkey projects The concept of ISO 9000 systems is to set out
Green Book: Conditions of short form of how a company intends to control its design or


contract product quality, and how it intends to monitor
and correct and deviations from the plan.
Blue Book: Contract for dredging and
ISO 9000 series systems are not necessarily
reclamation works; MDB/FIDIC contract:
benchmarked against an external quality stan-
FIDIC conditions incorporated in the stan-
dard. They ensure consistency with a predeter-
dard bidding documents of multilateral


mined internally-set standard rather than an
development banks
absolute standard.
White Book: Client and consultant model When well written and administered, ISO


services agreement 9000 systems can ensure the production of a
Gold Book: FIDIC design, build, and consistently good design and product. However,
operate projects they have therefore been criticized for over-
looking continuous improvement considera-
17. Quality Assurance and tions and for their resource-intensive nature.
The series comprises:


Management Systems
ISO 9001 Model for quality assurance in
17.1. Introduction
design, development, production, installa-


tion, and servicing
The ISO standards are the most commonly used
international standards, although there are other ISO 9002 Model for quality assurance in


standards in use worldwide, most notably in the production, installation, and servicing
United States. ISO 9003 Model for quality assurance in
The three most popular international stan- final inspection and test
dards covering the management and control of
quality, environment, and occupational health
17.3. ISO 14000 [30]
and safety are soon to be produced to a common
ISO format as follows:

∙∙
The ISO 14000 series was developed from
ISO 9000 as an environmental management
Scope system. Unlike ISO 9000, ISO 14000 defines

∙∙
Normative references both absolute minimum standards and a com-
Terms and definitions mitment to continuous improvement. The series

∙∙
Context of the organization comprises:
Leadership

∙∙
ISO 14001: Environmental management


Planning
systems—requirements
Support
ISO 14004: Environmental management

∙∙
Operation systems—principles, systems and support


Performance evaluation techniques
Improvement ISO 14006: Environmental management


systems—incorporating eco-design
17.2. ISO 9000 Series ISO 14015: Environmental assessment of


sites and organizations
The ISO 9000 [29] series of international quality ISO 14020 series (14020 to 14025): Envi-


assurance and quality management systems ronmental labels and declarations
are derived from a British Standard, BS5750, ISO 14030: Post-production environmen-
itself based on 1960s U.S. military standards. tal assessment
36 Chemical Plant Design and Construction

∙ ISO 14031: Environmental performance systems are eventually filled with gas when in


evaluation service. This is because a leak or rupture in a
ISO 14040 series (14040 to 14049): Life liquid-containing vessel or pipe is far less haz-


Cycle Assessment ardous than a pressurized gas-containing one,
ISO 14046: Requirements for water foot- since liquids do not have the stored energy of
print assessments pressurized gases. The liquid might be water, or
it might be a less-flammable hydrocarbon, such
17.4. OHSAS 18001/ISO 45001 [31] as fuel oil, depending on the nature and materi-
als of construction of the plant.
British Standard OHSAS 180001 is an interna- Where gases are charged in start-up and
tionally-applied British standard for the man- commissioning exercises, less hazardous gases
agement of occupational health and safety. A are often used initially in place of any flammable
version of OHSAS, restyled to match ISO 9000 or toxic ones used when the process is running.
and ISO 14000, is due to be published as ISO
45001 in October 2016. 18.2. Stages of Plant Start-up and
Commissioning
18. Plant Start-up and Performance
Testing There are a number of discrete and consecutive
stages of process plant commissioning. This
A process plant is more than a loose collection area is well covered in the IChemE’s Chemical
of equipment. It is a single integrated working and Process Plant Commissioning Handbook
machine, which reliably and safely produces a [32] but an outline is provided in Table 6.
given quantity of a specified product.
This integrated whole is not achieved by
completing mechanical and electrical installa- 19. Operating and Maintenance
tion alone. At this point, there exists only a Manuals
collection of equipment fixed to a slab and
interconnected with pipes and cables. This col- Operating and maintenance (O & M) manuals are
lection is not yet a single integrated working produced by those responsible for plant construc-
machine, and it is not safe to operate. tion. O & M manuals are written for the plant as a
Thus, before the plant can be handed over single integrated machine rather than as if it was a
there must be a phase of commissioning and collection of independent equipment.
performance trials, which converts the collec- Thus, they usually contain detailed explan-
tion of equipment into a single integrated oper- ations of what the objectives of the plant are, the
ational plant functioning in accordance with its limits on its performance, how the automatic
specification. controls systems work, and how operators
should operate maintain and troubleshoot the
plant as a whole.
18.1. Safety During Plant Start-up and A generic O & M manual has usually the
Commissioning following sections in the approximate order given:

Plant start-up is dangerous, because the safety ∙∙ Introduction

∙∙
measures which protect operators during normal Emergency procedures and contact numbers
operation are not in place. Risk assessments are HSE information
undertaken, and detailed descriptions of how the General description of the process and plant


plant is started up (known as method statements) including design and operating envelope
are written to control these risks.
The plant is probably filled, initially, with a Standard operating procedures for routine

∙∙
less harmful fluid than the process materials. operation
Acids and alkalis are for example often replaced Faultfinding guidance
by water. The fluid is often a liquid, even if the Maintenance schedule and procedures
Chemical Plant Design and Construction 37

Table 6. Summary of commissioning tasks

Task Notes

Phase A Construction and precommissioning

Ensure adequate safety precautions and services available for activities in this and Completed by mechanical installers before process
ensuing phases: Risk assessment and method statement in place, all safety commissioning engineer arrives
equipment available.
Install service gland packing in all minor machinery and drivers. Completed by mechanical installers before process
commissioning engineer arrives
Install service gland packing and lubricate all types of valves as required Completed by mechanical installers before process
commissioning engineer arrives
Check alignment and lubrication of all minor rotating machinery and drivers: Completed by mechanical installers before process
Pumps to be checked commissioning engineer arrives
Lock-off or isolate all equipment before line flushing and testing Completed by mechanical installers before process
commissioning engineer arrives
Correct any construction errors or omissions Inspected by process commissioning engineer and snag list
produced
Phase B Construction and pre-commissioning

Check electrical installations for power, lighting, and instrumentation for Inspected by process commissioning engineer and snag list
operability and safety produced
Check for correct rotation of minor rotating machinery drivers and carry out Inspected by process commissioning engineer and snag list
uncoupled run produced
Hydraulic and/or pneumatic pressure test equipment to specification requirements Carried out by mechanical installers monitored by process
to check connections and joints for pressure tightness commissioning engineer
Clean all lines of loose material by flushing Carried out by mechanical installers monitored by process
commissioning engineer
Hydraulic and/or pneumatic pressure test lines to specification requirements Carried out by mechanical installers monitored by process
commissioning engineer
After completion of line and equipment pressure testing, remove all swing blinds Carried out by mechanical installers observed by process
(slip-plates) from lines other than those required for operation purposes commissioning engineer
Correction of construction errors and omissions Inspected by process commissioning engineer and snag list
produced
Retest after corrective work or alteration Carried out by mechanical installers monitored by process
commissioning engineer
Phase C Construction and pre-commissioning

Check alignment and lubrication of all major drivers assembled on site Carried out by mechanical installers monitored by process
commissioning engineer
Carry out drop tests on pumps with water to ensure satisfactory operation Carried out by process commissioning engineer
Check action of instruments, continuity of connections and instrument circuits Carried out by process commissioning engineer, assisted by
electrical installer
Check control valves and penstocks are correct for direction of flow and action on Carried out by process commissioning engineer
power failure
Test instruments and loop-check control circuits Carried out by process commissioning engineer, assisted by
electrical engineer
Test electrical controls and plant operation systems Carried out by process commissioning engineer, assisted by
electrical engineer
Phase D Construction and pre-commissioning

Check safety equipment and communications Carried out by process commissioning engineer
Calibrate instruments Carried out by process commissioning engineer, assisted by
electrical engineer
Test for leak-tightness of plant-systems Carried out by process commissioning engineer, assisted by
mechanical installer
Check completeness of battery limit connections Carried out by process commissioning engineer
Check battery limits disposal systems are complete and ready for function Carried out by process commissioning engineer
Adjust pipe supports for expansion and loading strains Carried out by process commissioning engineer, assisted by
mechanical fitter
Correct construction errors and repairs Inspected by process commissioning engineer and snag list
produced
38 Chemical Plant Design and Construction

Table 6. (Continued)

Task Notes

Phase E Commissioning

Check supports of all lines Check carried out by process commissioning engineer;
mechanical fitter remedies
Optimize operating adjustments Carried out by process commissioning engineer, assisted by
electrical engineer
Agree procedures for plant performance tests Procedures proposed by process commissioning engineer
proposes if specification does not provide them
Maintenance, routine cleaning and normal adjustments to plant Carried out by process commissioning engineer, assisted by
mechanical fitter
Complete lagging and painting Carried out by mechanical installer
Complete minor construction details Carried out by installers
Record any modifications carried out during commissioning and annotate Carried out by draftsmen from main contractor
drawings/diagrams accordingly
Clean up site Inspected by process commissioning engineer and snag list
produced

∙∙ Spares schedules
Equipment manufacturers brochures and
majority of the training should, however, take
place on the plant itself.

∙∙
contact details Small groups of operators should witness the
Certification of equipment and plant plant operating routinely under the control of the
construction company’s commissioning engi-
Plant drawings including P+IDs, GAs,
neers. The operators should operate the plant
ELDs, etc.
themselves in accordance with the O & M
manual under the supervision of the commis-
A good O & M manual is concise, clear,
sioning engineers.
comprehensive, and correct in all respects. Poor
The operation and maintenance procedures
O & M manuals are, however, commonplace.
of more sophisticated individual items of equip-
ment may be demonstrated by the commission-
20. Training of Plant Personnel ing engineers, or by specialists from the
equipment vendors in the case of unusual or
The personnel to operate the plant are ideally complex items of equipment.
trained during the final stages of commissioning Once the operators are familiar with routine
by the commissioning team. The training should operation, the shutdown, maintenance, and
be carried out in accordance with the O & M start-up procedures can be demonstrated and
manual. practiced. Next, sampling, field testing, and
It is important that the operators gain a other required off-line control actions should
favorable impression of the plant during their be taught to operators.
training, so training should be delayed until the By this point, operators should be confident
plant works reliably, and the O & M manual is in operating the plant. Emergency and fault
correct. situations can then be set up by the commission-
Training should generally proceed from a ing engineers, and the operators can be tasked to
discussion of the general principles of plants use the O & M manual to diagnose and fix them.
of the type being considered, through a discus- Once operators are fully confident in operat-
sion of the specific needs addressed by the new ing the plant, the commissioning engineers
plant, and how it addresses these requirements. should satisfy themselves that all operators
These general discussions can take place in a are competent in plant operation before signing
training room, where audiovisual equipment certificates of competence to operate the plant
might be useful to the presentation, but the for operators.
Chemical Plant Design and Construction 39

BIM building information modeling catalogue_detail.htm?csnumber=51840 [accessed 15 December


BOD biological oxygen demand 2015].
6 American National Standards Institute (1961) A.N.S.I. Y32.11
CAPE computer aided process 61st ed., Graphical Symbols for Process Flow Diagrams in the
engineering Petroleum and Chemical Industries https://global.ihs.com/
CEPCI chemical engineering plant cost doc_detail.cfm?document_name=ANSI%20Y32.11 [accessed
index 15 December 2015].
7 Mecklenburgh, J.C. (1985) Process Plant Layout, Institution of
CFD computational flow dynamics Chemical Engineers, London.
COMAH control of major accident hazards 8 Green, D. and Perry, R. (2007) Perry’s Chemical Engineers’
DCS distributed control system Handbook, 8th edn, McGraw Hill, New York.
EPC engineering, procurement, con- 9 Guthrie K.M. (1969) Capital Cost Estimating. Chem. Eng.,
76 (6), 114–142.
struction 10 Williams, R. Jr. (1947) Sixth-tenths factor aids in approximat-
EPCI engineering, procurement, con- ing costs, Chem. Eng., 54 (6), 102.
struction, installation 11 Great Britain, Health and Safety Executive, What Are Risk
EPCM engineering, procurement, con- Matrices? http://www.hse.gov.uk/risk/faq.htm (accessed 30
March 2016).
struction, management 12 International Standards Organization (2002) ISO 14617-6 Graph-
FDS functional design specification ical symbols for diagrams – Part 6 Measurement and control
FEED front end engineering design functions http://www.iso.org/iso/iso_catalogue/catalogue_tc/
FIDIC International Federation of catalogue_detail.htm?csnumber=22654 [accessed 15 December
2015].
Consulting Engineers 13 International Society of Automation (2009) ANSI/ISA-5.1-2009
GA General Arrangement Instrumentation Symbols and Identification https://www.isa.
HAZID hazard identification org/templates/two-column.aspx?pageid=124355 (Accessed
HAZOP Hazard and Operability study 15 December 2015).
14 United Kingdom Health and Safety Executive (2015) Control of
HMI human machine interface major accident hazards Regulations 1999 (COMAH) http://
HSE Health Safety and Environmental www.hse.gov.uk/comah/background/comah99.htm (Accessed
IET Institute of Engineering and 15 December 2015).
Technology 15 King, M. (2010) Process Control A Practical Approach, Wiley-
VCH Verlag, Weinheim.
NTNU Norwegian University of Sci- 16 United Kingdon Institution of Chemical Engineers, The Sustain-
ence and Technology ability Metrics: Sustainable Development Progress Metrics Rec-
O&M operating and maintenance ommended For Use in the Process Industries https://www.icheme
P+ID piping and instrumentation .org/communities/subject_groups/sustainability/resources//
~/media/Documents/Subject%20Groups/Sustainability/
diagram Newsletters/
PC personal computer Sustainability%20Metrics.pdf [accessed 30 September 2015].
PFD process flow diagram 17 Peters, M. and Timmerhouse, K. (2002) Plant Design and
PLC programmable logic controller Economics for Chemical Engineers, McGraw-Hill, New
York.
QA quality assurance 18 Sinnot, R.K. and Towler, G. (2005) Chemical Engineering
SCADA system control and data Design: Principles, Practice and Economics of Plant and
acquisition Process Design, 2nd edn, Butterworth-Heinemann, London.
URS user requirement specification 19 United States of America, Association for the Advancement of
Cost Engineering (A.A.C.E. International) (2005) Recom-
VOC volatile organic compounds mended Practice no. 18r-97: cost estimate classification system
– as applied in engineering, procurement and construction for
the process industries.
References 20 Chemical Engineering Magazine (2016) Chemical Engineering
Plant Cost Index http://www.chemengonline.com/pci-home
1 Moran, S. (2015) An Applied Guide to Process and Plant (Accessed 15 December 2015).
Design, Butterworth-Heinemann, London. 21 United Kingdom, Association of Accounting Technicians
2 Branan, C. (2012) Rules of Thumb for Chemical Engineers, (2004) AAT Intermediate Course Companion, Units 6 & 7:
Elsevier, Amsterdam. Costing and Reports and Returns, 4th edn, B.P.P. Professional
3 Kletz, T. (2001) Hazop and Hazan, Institution of Chemical Education, London.
Engineers, London. 22 United Kingdon Institution of Chemical Engineers (1999) The
4 Center for Chemical Process Safety (2009) Inherently Safer Use of Computers by Chemical Engineers: Guidelines for prac-
Chemical Processes, 2nd edn, J. Wiley & Sons, New York. tising engineers, engineering management, software developers
5 International Standards Organization (2014) ISO 10628-1 and teachers of chemical engineering in the use of computer
Diagrams for the chemical and petrochemical industry – software in the design of process plant https://www.icheme.org/
Part 1: Specification of diagrams http://www.iso.org/iso/ ~/media/Documents/Subject%20Groups/CAPE/TheUseof
40 Chemical Plant Design and Construction

ComputersbyChemicalEngineersGuidelines1999.pdf (Accessed 28 International Federation of Consulting Engineers (F.I.D.I.C.)


21 December 2015). (1999) The F.I.D.I.C. Suite of Contracts http://fidic.org/sites/
23 El-Hagawi, M.M. (2006) Process Integration, Academic Press, default/files/FIDIC_Suite_of_Contracts_0.pdf (Accessed 21
New York. December 2015).
24 Reay, D., Ramshaw, C., and Harvey, A. (2013) Process 29 International Standards Organization (2015) I.S.O. 9000 –
Intensification: Engineering for Efficiency, Sustainability and Quality Management http://www.iso.org/iso/iso_9000
Flexibility, 2nd edn, Butterworth-Heinemann, London. (Accessed 21 December 2015).
25 European Commission (2000) Communication from the Com- 30 International Standards Organization (2015) I.S.O. 14000 –
mission on the precautionary principle (COM(2000) 1 final of 2 Environmental Management http://www.iso.org/iso/home/
February 2000) http://eur-lex.europa.eu/legal-content/EN/ standards/management-standards/iso14000.htm (Accessed 21
TXT/?uri=uriserv%3Al32042 (Accessed 21 December 2015). December 2015).
26 United Kingdom, Institution of Chemical Engineers, Forms of 31 British Standards INSTITUTE (2007) BS OHSAS 18001 Occu-
Contract http://www.icheme.org/resources/forms_of_contract/ pational Health and Safety Management http://www.bsigroup.
the%20contracts.aspx (Accessed 15 December 2015). com/en-GB/ohsas-18001-occupational-health-and-safety/
27 United Kingdom, Institution of Engineering and Technology (Accessed 15 December 2015).
(I.E.T.) (2014) Model Form of Contract for the design, supply 32 Kilcross, M. (2011) Chemical and Process Plant Commission-
and installation of electrical, electronic and mechanical plant, ing Handbook, Butterworth-Heinemann, London.
MF/1 (Rev 6).

You might also like