Costs

Item Description
Labors $

Columns
Vertical Vessels
Horizontal vessels
Shell and tube heat exchanger
Plate heat exchanger
Pumps,Motors

Direct field costs "DFC"


Direct field labor 25%of DFC
Indirect Field Costs "IFC" 115% of DFL
Total Field Costs "TFC"
Home Offfice Costs "HOC" 30% of DFC
Total Field and Home Office Costs
Project Commissioning Costs 3% of DFC
Total Project estimated costs "TPEC"
Contingency 15% of TPEC
Total Project Costs including contingency
Costs
Eqm
Total
Eqmt Factor Multiplier
Eqmt $ Sub Total

650000 2.1 1365000


540000 3.2 1728000
110000 2.4 264000
630000 2.5 1575000
110000 2 220000
765000 3.4 2601000
2805000
7753000 2.7639929
25%of DFC 1938250
115% of DFL 2228987.5
11920238 4.249639
30% of DFC 2325900
14246138 5.0788369
3% of DFC 232590
14478728 5.1617567
15% of TPEC 2171809
31129264
16650537 5.9360202
Total %

46.56%

71.59%

85.56%

86.96%

100.00%