You are on page 1of 198

PMI-ACPSM Examination

Boot Camp
Study Guide

42600SG_5.0 2019

aspetraining.com
877-800-5221
 

PMI‐ACP  
Agile Certified Practitioner Examination 
Boot Camp 

Study Reference and


Practice Exams
Version 5.0, May 2019

2019, ASPE Inc.

ALL RIGHTS RESERVED.

 
All trademarks are owned by their respective companies 
and referred to herein for identification purposes only. 

   
PMI‐ACP Study Guide 
©2019 ASPE, Inc. 
 
 
ii/Table of Contents 

Table of Contents

 
PMI‐ACPSM Study Reference and Practice Exams ..................................................... 3 
Abbreviations for Referenced Texts ....................................................................................... 5 
Examination Structure ............................................................................................................ 6 
Preparing for and Taking the PMI‐ACP Exam ......................................................................... 7 
Domains and Tasks ............................................................................................................... 13 
Tools and Techniques ............................................................................................ 25 
Student Guide Index ............................................................................................................. 25 
Tools and Techniques (Q&A) ................................................................................................ 26 
Knowledge and Skills .............................................................................................. 31  
Student Guide Index ............................................................................................................. 31 
Knowledge and Skills (Q&A) ................................................................................................. 33 
Final Practice Exam 1 ............................................................................................. 49  
Final Practice Exam 1 ............................................................................................................ 50 
Final Practice Exam 1 Correct Responses ............................................................................. 79 
Final Practice Exam 2 ........................................................................................... 125 
Final Practice Exam 2 .......................................................................................................... 126 
Final Practice Exam 2 Correct Responses ........................................................................... 154 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /3 

PMI-ACPSM Study Reference and


Practice Exams
 

 Welcome to the PMI‐ACPSM Study Reference and 
Practice Exams!  We’re excited to have you with 
us.  This journey will take you through the tools, 
 
techniques, knowledge, and skills you will need 
to analyze and study in order to pass the exam. 
 
As with any preparation materials for a 
certification; it is impossible to be 100 percent 
comprehensive of all the literature available.  
We encourage you to consider additional 
resources, such as the references noted in this 
study reference to help you prepare to pass the 
exam.   
 
We wish you success on this endeavor!   
 
 

 
   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
4/PMI‐ACP Examination Boot Camp 
 
 

Project Management Institute – Agile Certified 
Practitioner 
PMI‐ACP Examination Boot Camp 
June, 2016   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /5 

Abbreviations for Referenced Texts


 
 
 Lean‐Agile Software Development: Achieving Enterprise Agility (Lean) by 
Alan Shalloway, Guy Beaver, and James R. Trott 
 User Stories Applied: For Agile Software Development (User Stories) by 
Mike Cohn 
 Agile Estimating and Planning (Estimating) by Mike Cohn 
 The Software Project Manager’s Bridge to Agility (Bridge) by Michele Sliger 
and Stacia Broderick 
 Agile Retrospectives: Making Good Teams Great (Retrospectives) by Esther 
Derby and Diana Larsen 
 Agile Software Development: The Cooperative Game – Second Edition 
(Game) by Alistair Cockburn 
 Coaching Agile Teams (Coaching) by Lyssa Adkins 
 Agile Project Management: Creating Innovative Products – Second Edition 
(Creating) by Jim Highsmith 
 Exploring Scrum: The Fundamentals (Exploring) by an Rawsthorne 
 Kanban in Action (Action) by Marcus Hammarberg 
 Effective Project Management: Traditional, Agile, Extreme (Effective) by 
Robert K. Wysocki 
 Kanban: Successful Evolutionary Change for Your Technology Business 
(Kanban) by David J. Anderson 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
6/PMI‐ACP Examination Boot Camp 

Examination Structure
 
Domain  Percentage of 
Items on the Test 
Domain I.  Agile Principles and Mindset  16% 

Domain II.  Value‐Driven Delivery  20% 

Domain III.  Stakeholder Engagement  17% 

Domain IV.  Team Performance   16% 

Domain V.  Adaptive Planning  12% 

Domain VI.  Problem Detection and Resolution  10% 

Domain VII.  Continuous Improvement  9% 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /7 

Preparing for and Taking the PMI-ACP Exam


Timeline of the PMI-ACP Certification Process
• 90 days to complete the application once you start 
• 10 day application completeness review (if submitted online) 
• 90 days to submit materials for an audit; PMI processes audit materials in 5‐7 business days 
• 1 year examination eligibility from application acceptance date 
• 3 times to take the exam during the 1 year examination eligibility timeframe 
• 3 years to earn and report 30 PDUs to maintain certification once exam is passed.  Must pay 
renewal fee. 

The Certification Exam Tests…


• Knowledge of 12 Agile books 
• Terms used in Agile 
• Your application of Agile knowledge in a variety of situations 
• Your understanding of how the code of ethics applies to Agile work 
• Your ability to read, parse, and understand a question 

Referenced Texts
• Lean‐Agile Software Development: Achieving Enterprise Agility (Lean) by Alan Shalloway, Guy 
Beaver, and James R. Trott 
• User Stories Applied: For Agile Software Development (User Stories) by Mike Cohn 
• Agile Estimating and Planning (Estimating) by Mike Cohn 
• The Software Project Manager’s Bridge to Agility (Bridge) by Michele Sliger and Stacia Broderick 
• Agile Retrospectives: Making Good Teams Great (Retrospectives) by Esther Derby and Diana 
Larsen 
• Agile Software Development: The Cooperative Game – Second Edition (Game) by Alistair 
Cockburn 
• Coaching Agile Teams (Coaching) by Lyssa Adkins 
• Agile Project Management: Creating Innovative Products – Second Edition (Creating) by Jim 
Highsmith 
• Exploring Scrum: The Fundamentals (Exploring) by Dan Rawsthorne 
• Kanban in Action (Action) by Marcus Hammarberg 
• Effective Project Management: Traditional, Agile, Scrum (Effective) by Robert K. Wysocki 
• Kanban: Successful Evolutionary Change for Your Technology Business (Kanban) by David J. 
Anderson 
• The Agile Practice Guide, PMI 2017 

The Certification Exam Doesn’t Test…


• General intelligence 
• Common sense 
• Your Agile experience 
• Knowledge of industry practices 
• Knowledge of software tools 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
8/PMI‐ACP Examination Boot Camp 

Requirements for PMI-ACPSM Certification


Requirements 

Educational Background  Secondary degree (high school diploma, associate’s degree, or global 
equivalent). 
General Project  *2,000 hours (12 months) working on team projects earned in the past 5 years. 
Experience 
Agile Project Experience  1,500 hours (8 months) working on project teams using agile methodologies in 
the past 3 years.  These hours are in addition to the 2,000 hours above. 
Training in Agile Practices  21 contact hours earned in Agile practices. 
PMI Code of Ethics and  Read and agree during the application process 
Professional Conduct 

PMI-ACP Application Process


• Document your general project experience (if applicable) and Agile project experience 
• Contact hours of training on Agile practices – 21 PDUs 
• Fill out online or paper – 10 business days process time (20 business days for paper applications 
by corporations) 

Certification Fees
CBT – Member  $435 

CBT – Nonmember  $495 
PBT – Member  $385 
PBT – Nonmember  $445 
   
Reexamination CBT – Member  $335 
Reexamination CBT – Nonmember  $395 
Reexamination PBT – Member  $285 
Reexamination PBT – Nonmember  $345 
   
Certification Renewal – Member   $60 
Certification Renewal – Nonmember   $150 
   
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /9 

After the Application is Submitted


• Exam eligibility timeframe – one year 
• Member vs. Non‐Member fees – must be a member in good standing 
• Scheduling the exam 
– Try to schedule 6 weeks ahead or your preferred test date 
– Sit for the exam at least 3 months before your eligibility period expires 
– Retain your unique PMI identification code 

PMI Exam Security & Confidentiality


• The exam, answer sheets, worksheets, and any other test or test‐related materials remain the 
sole and exclusive property of PMI. 
• Pass/fail results are confidential 
• When you submit your application, you agree: “…Furthermore, I agree not to discuss, debrief or 
disclose, in any manner, the specific content of PMI examination questions and answers, to 
any individual.” 

Exam Overview
• CBT is the standard and you get instant feedback 
• 120 multiple choice questions – 20 are pre‐test and 100 are scored test questions 
• 3 hours 
• Answer every question 
• Optional online tutorial before the exam and optional survey after the exam do not count 
toward the 3 hours. 
• No scheduled breaks 

Exam Blueprint
Topic Areas  Percentage of Questions 
Agile Tools and Techniques  50% 
Agile Knowledge and Skills  50% 
 

The Day of the Exam


• Arrive 30 minutes early 
• Bring identification – examples of ID are listed on the PMI Website 
• You cannot bring into the exam area: 
 
• Food  • Beverages  • Book bags 
• Coats  • Sweaters  • Luggage 
• Calculators  • Eyeglass cases  • Pagers 
• Cellular telephones    • Tape recorders    • Dictionaries 
• Any other personal 
items 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
10/PMI‐ACP Examination Boot Camp 
• No children 
• Calculators are built into the CBT exam 
• Scrap paper  and pencil are provided by testing center administrator 
Or 
• Erasable boards and marker are provided by testing center administrator 

Best Practice Studying Tips


• Take the entire practice exam and grade yourself. 
• Take the practice exams until you consistently score 85‐90 percent. 
• When reviewing your practice tests, examine the reasoning behind both your right and wrong 
answers.  
• Be careful of downloading test questions from the web.  Verify the sample test questions are 
from reliable sources.  
• Determine how to prep yourself based on your learning style.  You can use self‐study, study 
groups, flash cards, private tutors, coaches, additional classes, etc. 
• Schedule the exam date based on your learning style. 
• Schedule the exam time when you are at your best – morning or afternoon. 
• Schedule the exam based on the day of the week when you will have the most time to review 
the information. 
• If you do not plan on taking the exam shortly after completing this workshop, try to study every 
day, even if it is for 15‐30 minutes.  It is very difficult to regain momentum once you lose it. 

Understanding the Test Questions


• Read the question and think about it thoroughly before looking at the answers. Look for key 
words in the question that will lead you to the right answer (e.g., principal, major, primary, best, 
nearest, incorrect). 
• Try to anticipate the correct answer before you review the responses. 
• Read the answers from the bottom up.  This prevents you from keying in on the first answer. 
• Practice eliminating the completely unlikely options first. 
• Beware of answers that represent true statements but are not relevant. 
• Beware of answer choices that represent generalizations, for example always, never, must, or 
completely; these are often the incorrect choices. 
• Watch for choices that represent special cases. These choices tend to be correct and are 
characterized by words such as often, sometimes, may, generally, and perhaps. 
• The correct answer might not be grammatically correct in relation to the stem question. 
• You will probably run across a few questions that were not in any of the materials you used to 
prepare for the test or you have no idea what the question is asking. Use educated guessing to 
select the most appropriate option. 
• If you do not know the answer of a question, flag it and move on so you can revisit it later if you 
have time. 
• Some of the questions have diagrams, charts, or other exhibits associated with them.  Be 
prepared that you might be asked more than one question about the diagram, chart, or other 
exhibit.   
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /11 

During the Exam


• Use the 15 minute tutorial time in the way that suits you best. 
• Do Not Panic if you don’t know the first answer on the exam.  Look for scoring opportunities. 
• When marking test questions, write the test question number down on your scrap paper and 
write down the two responses you think are correct.  
• Most successful candidates say the first guess is your best guess. 
• Try not to mark test questions you are confident you answered correctly.  
• You will have to refer to information you learned during your exam preparation. 
• Before responding to a question, always analyze the other alternatives just in case these, too, 
have valid points. 
• Try not to linger on one question just because you are determined to answer it, no matter what. 
Sometimes it takes time to establish rhythm during the test. 
• Sometimes the answer to a question will be found in another question on the exam.  
• You will need to prepare yourself mentally for this event. Refresh yourself at regular intervals. 
• When taking breaks the time clock will keep ticking during your break.  It is helpful to develop 
your break strategy during your mock practice exams. 
• When you are finished with the relatively easy questions, go back to the unanswered ones.  If 
you have narrowed the responses down to the two you think are correct, you will have a 50‐50 
chance of getting the answer right.   

General Tips
• Eat foods that will digest well with you and drink fluids that will not upset your stomach on the 
day of your exam. 
• Dress in layers since you will not know the temperature comfort level in the testing room. 
• There may be several people taking tests at the same time as you.  Not all of the tests are of 
equal length, so do not panic if you see people coming and going during your exam. 
• Try not to focus on getting an “A” on the test.  The test is difficult and no one gets rewarded for 
their overall score, they get rewarded for passing. 
• Consider only telling a few select people that you are taking the exam.  If you tell everyone you 
are sitting for the exam, this creates extra pressure to pass and you do not need that feeling.  
There is nothing wrong with taking the test in secret and then revealing to everyone that you 
passed it!  
• Many people take a ½ day or full day of vacation the day before the exam so they are not 
distracted by work the day before. 
• It is not the end of the world if you do not pass the exam. 

Examination Report
• Proficient – indicates performance is above the average level of knowledge in this domain. 
• Moderately Proficient – indicates performance that is at the average level of knowledge in this 
domain. 
• Below Proficient – indicates performance is below the average level of knowledge in this 
domain. 
When you pass, the performance information will help identify specific chapters to focus on for 
continuing education purposes. If you fail, the performance information will identify specific 
chapters where improvement or further study may be required in order to successfully complete the 
examination in the future. 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
12/PMI‐ACP Examination Boot Camp 

Certificate Package
Within six to eight weeks, you will receive a credential package that includes: 
– Congratulatory letter 
– Information on how to maintain and/or renew your credential 
– Credential certificate 
 Both of these documents list your: 
– Credential number – a unique identification number used by PMI to maintain your 
individual certification records 
– Your credential cycle dates 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /13 

Domains and Tasks

Domain I. Agile Principles and Mindset (9 tasks)  
Explore, embrace, and apply agile principles and mindset within the context of the project team and 
organization.  
 
 
Domain I   Agile Principles and Mindset  
Task 1   Advocate for agile principles by modeling those 
principles and discussing agile values in order to 
develop a shared mindset across the team as well 
as between the customer and the team.  

Task 2   Help ensure that everyone has a common 
understanding of the values and principles of 
agile and a common knowledge around the agile 
practices and terminology being used in order to 
work effectively.  

Task 3   Support change at the system or organization 
level by educating the organization and 
influencing processes, behaviors, and people in 
order to make the organization more effective 
and efficient.  

Task 4   Practice visualization by maintaining highly visible 
information radiators showing real progress and 
real team performance in order to enhance 
transparency and trust.  

Task 5   Contribute to a safe and trustful team 
environment by allowing everyone to experiment 
and make mistakes so that each can learn and 
continuously improve the way he or she works.  

Task 6   Enhance creativity by experimenting with new 
techniques and process ideas in order to discover 
more efficient and effective ways of working.  

Task 7   Encourage team members to share knowledge by 
collaborating and working together in order to 
lower risks around knowledge silos and reduce 
bottlenecks.  

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
14/PMI‐ACP Examination Boot Camp 

Domain I   Agile Principles and Mindset  
Task 8   Encourage emergent leadership within the team 
by establishing a safe and respectful environment 
in which new approaches can be tried in order to 
make improvements and foster self‐organization 
and empowerment.  

Task 9   Practice servant leadership by supporting and 
encouraging others in their endeavors so that 
they can perform at their highest level and 
continue to improve.  

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /15 

Domain II. Value‐Driven Delivery (4 sub‐domains, 14 tasks)  
Deliver valuable results by producing high‐value increments for review, early and often, based on 
stakeholder priorities. Have the stakeholders provide feedback on these increments, and use this 
feedback to prioritize and improve future increments.  

Domain II  Value‐Driven Delivery  
Define Positive Value   
Task 1   Define deliverables by identifying units that can 
be produced incrementally in order to maximize 
their value to stakeholders while minimizing non‐
value added work.  

Task 2   Refine requirements by gaining consensus on the 
acceptance criteria for features on a just‐in‐time 
basis in order to deliver value.  

Task 3   Select and tailor the team’s process based on 
project and organizational characteristics as well 
as team experience in order to optimize value 
delivery.  
Avoid Potential Downsides   
Task 4   Plan for small releasable increments by 
organizing requirements into minimally 
marketable features/minimally viable products in 
order to allow for the early recognition and 
delivery of value.  

Task 5   Limit increment size and increase review 
frequency with appropriate stakeholders in order 
to identify and respond to risks early on and at 
minimal cost.  

Task 6   Solicit customer and user feedback by reviewing 
increments often in order to confirm and 
enhance business value. 
Prioritization   
Task 7   Prioritize the units of work through collaboration 
with stakeholders in order to optimize the value 
of the deliverables.  

Task 8   Perform frequent review and maintenance of the 
work results by prioritizing and maintaining 
internal quality in order to reduce the overall cost 
   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
16/PMI‐ACP Examination Boot Camp 

Domain II  Value‐Driven Delivery  
of incremental development.  

Task 9   Continuously identify and prioritize the 
environmental, operational, and infrastructure 
factors in order to improve the quality and value 
of the deliverables.  
Incremental Development   
Task 10   Conduct operational reviews and/or periodic 
checkpoints with stakeholders in order to obtain 
feedback and corrections to the work in progress 
and planned work.  

Task 11   Balance development of deliverable units and risk 
reduction efforts by incorporating both value 
producing and risk reducing work into the 
backlog in order to maximize the total value 
proposition over time.  

Task 12   Re‐prioritize requirements periodically in order to 
reflect changes in the environment and 
stakeholder needs or preferences in order to 
maximize the value.  

Task 13   Elicit and prioritize relevant non‐functional 
requirements (such as operations and security) 
by considering the environment in which the 
solution will be used in order to minimize the 
probability of failure.  

Task 14   Conduct frequent reviews of work products by 
performing inspections, reviews, and/or testing 
in order to identify and incorporate 
improvements into the overall process and 
product/service. 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /17 

Domain III. Stakeholder Engagement (3 sub‐domains, 9 tasks)  
Engage current and future interested parties by building a trusting environment that aligns their needs 
and expectations and balances their requests with an understanding of the cost/effort involved. 
Promote participation and collaboration throughout the project life cycle and provide the tools for 
effective and informed decision making.  
 

Domain III   Stakeholder Engagement  
Understand Stakeholder Needs   
Task 1   Identify and engage effective and empowered 
business stakeholder(s) through periodic reviews 
in order to ensure that the team is 
knowledgeable about stakeholders’ interests, 
needs, and expectations.  

Task 2   Identify and engage all stakeholders (current and 
future) by promoting knowledge sharing early 
and throughout the project to ensure the 
unimpeded flow of information and value 
throughout the lifespan of the project.  
Ensure Stakeholder Involvement   
Task 3   Establish stakeholder relationships by forming a 
working agreement among key stakeholders in 
order to promote participation and effective 
collaboration.  

Task 4   Maintain proper stakeholder involvement by 
continually assessing changes in the project and 
organization in order to ensure that new 
stakeholders are appropriately engaged.  

Task 5   Establish collaborative behaviors among the 
members of the organization by fostering group 
decision making and conflict resolution in order 
to improve decision quality and reduce the time 
required to make decisions.  
Manage Stakeholder Expectations   
Task 6   Establish a shared vision of the various project 
increments (products, deliverables, releases, 
iterations) by developing a high level vision and 
supporting objectives in order to align 
stakeholders’ expectations and build trust.  

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
18/PMI‐ACP Examination Boot Camp 

Domain III   Stakeholder Engagement  
Task 7   Establish and maintain a shared understanding of 
success criteria, deliverables, and acceptable 
trade‐offs by facilitating awareness among 
stakeholders in order to align expectations and 
build trust.  

Task 8   Provide transparency regarding work status by 
communicating team progress, work quality, 
impediments, and risks in order to help the 
primary stakeholders make informed decisions.  

Task 9   Provide forecasts at a level of detail that balances 
the need for certainty and the benefits of 
adaptability in order to allow stakeholders to 
plan effectively.  
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /19 

Domain IV. Team Performance (3 sub‐domains, 9 tasks)  
Create an environment of trust, learning, collaboration, and conflict resolution that promotes team self‐
organization, enhances relationships among team members, and cultivates a culture of high 
performance.  
 
 
Domain IV   Team Performance  
Team Formation   
Task 1   Cooperate with the other team members to 
devise ground rules and internal processes in 
order to foster team coherence and strengthen 
team members’ commitment to shared 
outcomes.  

Task 2   Help create a team that has the interpersonal 
and technical skills needed to achieve all known 
project objectives in order to create business 
value with minimal delay.  
Team Empowerment   
Task 3   Encourage team members to become 
generalizing specialists in order to reduce team 
size and bottlenecks, and to create a high‐
performing cross‐functional team.  

Task 4   Contribute to self‐organizing the work by 
empowering others and encouraging emerging 
leadership in order to produce effective solutions 
and manage complexity.  

Task 5   Continuously discover team and personal 
motivators and de‐motivators in order to ensure 
that team morale is high and team members are 
motivated and productive throughout the 
project.  
Team Collaboration and Commitment   
Task 6   Facilitate close communication within the team 
and with appropriate external stakeholders 
through co‐location or the use of collaboration 
tools in order to reduce miscommunication and 
rework.  

Task 7   Reduce distractions in order to establish a 
predictable outcome and optimize the value 
delivered.  
   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
20/PMI‐ACP Examination Boot Camp 

Domain IV   Team Performance  
Task 8   Participate in aligning project and team goals by 
sharing project vision in order to ensure the team 
understands how their objectives fit into the 
overall goals of the project.  

Task 9   Encourage the team to measure its velocity by 
tracking and measuring actual performance in 
previous iterations or releases in order for 
members to gain a better understanding of their 
capacity and create more accurate forecasts.  
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /21 

Domain V. Adaptive Planning (3 sub‐domains, 10 tasks) 
Produce and maintain an evolving plan, from initiation to closure, based on goals, values, risks, 
constraints, stakeholder feedback, and review findings.  
 
 
Domain V   Adaptive Planning  
Levels of Planning   
Task 1   Plan at multiple levels (strategic, release, 
iteration, daily) creating appropriate detail by 
using rolling wave planning and progressive 
elaboration to balance predictability of outcomes 
with ability to exploit opportunities.  

Task 2   Make planning activities visible and transparent 
by encouraging participation of key stakeholders 
and publishing planning results in order to 
increase commitment level and reduce 
uncertainty.  

Task 3   As the project unfolds, set and manage 
stakeholder expectations by making increasingly 
specific levels of commitments in order to ensure 
common understanding of the expected 
deliverables.  
Adaptation   
Task 4   Adapt the cadence and the planning process 
based on results of periodic retrospectives about 
characteristics and/or the 
size/complexity/criticality of the project 
deliverables in order to maximize the value.  

Task 5   Inspect and adapt the project plan to reflect 
changes in requirements, schedule, budget, and 
shifting priorities based on team learning, 
delivery experience, stakeholder feedback, and 
defects in order to maximize business value 
delivered.  
Agile Sizing and Estimation   
Task 6   Size items by using progressive elaboration 
techniques in order to determine likely project 
size independent of team velocity and external 
variables.  

Task 7   Adjust capacity by incorporating maintenance 
   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
22/PMI‐ACP Examination Boot Camp 

Domain V   Adaptive Planning  
and operations demands and other factors in 
order to create or update the range estimate.  

Task 8   Create initial scope, schedule, and cost range 
estimates that reflect current high level 
understanding of the effort necessary to deliver 
the project in order to develop a starting point 
for managing the project.  

Task 9   Refine scope, schedule, and cost range estimates 
that reflect the latest understanding of the effort 
necessary to deliver the project in order to 
manage the project.  

Task 10   Continuously use data from changes in resource 
capacity, project size, and velocity metrics in 
order to evaluate the estimate to complete.  
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /23 

Domain VI. Problem Detection and Resolution (5 tasks)  
Continuously identify problems, impediments, and risks; prioritize and resolve in a timely manner; 
monitor and communicate the problem resolution status; and implement process improvements to 
prevent them from occurring again.  
 
 
Domain VI   Problem Detection and Resolution  
Task 1   Create an open and safe environment by 
encouraging conversation and experimentation, 
in order to surface problems and impediments 
that are slowing the team down or preventing its 
ability to deliver value.  

Task 2   Identify threats and issues by educating and 
engaging the team at various points in the project 
in order to resolve them at the appropriate time 
and improve processes that caused issues.  

Task 3   Ensure issues are resolved by appropriate team 
members and/or reset expectations in light of 
issues that cannot be resolved in order to 
maximize the value delivered.  

Task 4   Maintain a visible, monitored, and prioritized list 
of threats and issues in order to elevate 
accountability, encourage action, and track 
ownership and resolution status.  

Task 5   Communicate status of threats and issues by 
maintaining threat list and incorporating 
activities into backlog of work in order to provide 
transparency.  
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
24/PMI‐ACP Examination Boot Camp 

Domain VII. Continuous Improvement (Product, Process, People) (6 tasks)  
Continuously improve the quality, effectiveness, and value of the product, the process, and the team.  
 
 
Domain VII   Continuous Improvement (Product, Process, 
People) 
Task 1   Tailor and adapt the project process by 
periodically reviewing and integrating team 
practices, organizational culture, and delivery 
goals in order to ensure team effectiveness 
within established organizational guidelines and 
norms.  

Task 2   Improve team processes by conducting frequent 
retrospectives and improvement experiments in 
order to continually enhance the effectiveness of 
the team, project, and organization.  

Task 3   Seek feedback on the product by incremental 
delivery and frequent demonstrations in order to 
improve the value of the product.  

Task 4   Create an environment of continued learning by 
providing opportunities for people to develop 
their skills in order to develop a more productive 
team of generalizing specialists.  

Task 5   Challenge existing process elements by 
performing a value stream analysis and removing 
waste in order to increase individual efficiency 
and team effectiveness.  

Task 6   Create systemic improvements by disseminating 
knowledge and practices across projects and 
organizational boundaries in order to avoid re‐
occurrence of identified problems and improve 
the effectiveness of the organization as a whole. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /25 

Tools and Techniques


Student Guide Index
 

 
 
Tools and Techniques  Page 
Agile analysis and design  142 
These tools  Agile estimation  147 
illustrate the 
breadth of the  Communications  153 
toolkit, but are not 
meant by PMI to 
Interpersonal skills  178 
provide an  Metrics  188 
exhaustive list of all 
of the techniques  Planning, monitoring, and adapting  207 
and tools that might 
Process improvement  215 
be in the toolkit. 
Product quality  222 
Risk management  231 
Value‐based prioritization  242 
 
Please note: Examples for each of these areas is included 
in the PMI Agile Certified Practitioner (PMI‐ACP)SM 
Examination Content Outline.  The tools and techniques 
identified in this document do not include a complete list 
of the tools and techniques on the exam.   
The page numbers above refer to the student manual 
page numbers.  Use these to find the first slide in the 
student manual corresponding to the topic listed in the 
table. 
  

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
26/PMI‐ACP Examination Boot Camp 

Tools and Techniques (Q&A)


 
Agile Analysis and Design 
 
1.  Correct Response: B 

A user story is a brief description of functionality as viewed by a user or customer of the 
system. 
 
2.  Correct Response: D 

Avoid splitting a user story into the development tasks that will be necessary to 
implement the feature. 
 
3.  Correct Response: D 

The Product Backlog is a list of functional and nonfunctional requirements that, when 
turned into functionality will deliver the project vision. 
 
 
 
Agile Estimation 
 
1.  Correct Response: A 

Story points are a unit of measure for expressing the overall size of a user story, feature, 
or other piece of work. 
 
2.  Correct Response: D 

Ideal time is the amount of time that something takes when stripped of all peripheral 
activities. 
 
3.  Correct Response: C 

The impact of the overhead of the environment in which the team works is not 
considered when performing ideal time estimates. 
 
 
 
 
 
 
   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /27 

 
 
Communications  
 
1.  Correct Response: D 
 
Agile processes attempt to maximize face‐to‐face communications because it is the 
richest form of communications. 
 
2.  Correct Response: C 

An information radiator displays information in a place where passersby can see it 
without having to ask questions. 
 
3.  Correct Response: C 

The ScrumMaster is responsible for moving the reporting along briskly, from person to 
person. 
 
 
Interpersonal Skills 
 
1.  Correct Response: False 
 
2.  Correct Response: B   

Servant leadership includes mentoring, guidance, facilitation, and roadblock removal. 
 
3.  Correct Response: A 

Compromise/Reconcile is used to search for solutions that bring some degree of 
satisfaction to all parties in order to temporarily or partially resolve the conflict. 
 
 
 
 
 
 
 
 
 
 
 
   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
28/PMI‐ACP Examination Boot Camp 

 
Metrics 
 
1.  Correct Response: C 

Velocity is a measure of a team's rate of progress and is calculated by summing the 
number of story points assigned to each user story that the team completed during the 
iteration. 
 
2.  Correct Response: C 

A burndown chart shows the amount of work remaining at the start of each iteration. 
 
3.  Correct Response: A 

When the bottom of the bar is below the horizontal axis at 0, it means that overall work 
has been added to the release. 
 
 
 
 
Planning, Monitoring, and Adapting  
 
1.  Correct Response: C 
 
The team decomposes each story into the tasks necessary to actually deliver the User 
Story’s functionality during the iteration. 
 
2.  Correct Response D 
 
A release plan helps the Agile project manager understand the viability of the project 
 
3.  Correct Response: B 
 
The story cards developed during release planning help the team with iteration 
planning. 
 
 
 
 
 
 
Process Improvement 
   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /29 

 
1.  Correct Response: False 
 
2.  Correct Response: D 

Value stream mapping is a Lean tool that includes creating models of the process 
streams and using those models to find waste. 
 
3.  Correct Response: A 

Partially done work is a story that is not finished according to the “Definition of Done”. 
 
 
Product Quality 
 
1.  Correct Response: False 
 
2.  Correct Response: D 

The entire team is responsible for avoiding buggy code and improving the process. 
 
3.  Correct Response: True 
 
 
Risk Management 
 
1.  Correct Response: A 
 
The Expected Value calculation is numerical probability times the impact in days – in this 
case 40% x 5 days. 
 
2.  Correct Response: C 
 
Only those risks which are unique to that project are included in the risk census.   
 
3.  Correct Response: A 

Try to defer low‐value, high‐risk items right out of the project. 
 
 
Value‐based Prioritization 
 
1.  Correct Response: A 
   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
30/PMI‐ACP Examination Boot Camp 

Retained revenue considers the revenue a project will generate from customers who 
might have otherwise gone to a competitive product. 
 
2.  Correct Response: B 

Internal Rate of Return (IRR) is a measure of how quickly the money invested in a 
project/theme will increase in value. 
 
3.  Correct Response: C 

Threshold features are those that must be present in the product for it to be successful ‐ 
often referred to as must‐have features. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /31 

Knowledge and Skills


Student Guide Index
 

 
 
  Knowledge and Skills Content  Page 
1  Agile values and principles   262 
33 knowledge and skills 
have been identified by PMI  2  Agile frameworks and terminology   266 
as being key to passing the 
PMI‐ACP examination. 
3  Agile methods and approaches   278 
4  Assessing and incorporating community and  282 
stakeholder values  
5  Stakeholder management   290 
6  Communication management   296 
7  Facilitation methods   305 
8  Knowledge sharing/written communication   311 
9  Leadership   319 
10  Building agile teams   328 
11  Team motivation   336 
12  Physical and virtual co‐location   346 
13  Global, cultural, and team diversity   352 
14  Training, coaching, and mentoring   358 
15  Developmental mastery models (for example,  364 
Tuckman, Dreyfus, Shu Ha Ri)  
16  Self‐assessment tools and techniques   377 
17  Participatory decision models (for example,  384 
convergent, shared collaboration)  
18  Principles of systems thinking (for example,  390 
complex adaptive, chaos) 
19  Problem solving   401 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
32/PMI‐ACP Examination Boot Camp 

20  Prioritization   409 


21  Incremental delivery   419 
22  Agile discovery   423 
23  Agile sizing and estimation   429 
24  Value based analysis and decomposition   436 
25  Process analysis   455 
26  Continuous improvement   460 
27  Agile hybrid models   465 
28  Managing with agile KPIs  470 
29  Agile project chartering   475 
30  Agile contracting   481 
31  Agile project accounting principles   489 
32  Regulatory compliance   496 
33  PMI's Code of Ethics and Professional  501 
Conduct  
 
Not every form of the exam will contain each knowledge 
and skill.  
The page numbers above refer to the student manual 
page numbers.  Use these to find the first slide in the 
student manual corresponding to the topic listed in the 
table. 
 
  

   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /33 

Knowledge and Skills (Q&A)


 
Agile Manifesto Values and Principles 
 
1.  Correct Response: D 

Individuals and interactions over processes and tools is the only value worded correctly; 
the other three are phrased backwards. 
 
2.  Correct Response: A 

Welcoming changing requirements, even late in development is the only principle 
phrased correctly according to the Agile Manifesto. 
 
3.  Correct Response: B 

Agile principles state that individuals are motivated and can be trusted to get the job 
done when they have the environment and support they need. 
 
 
Agile Frameworks and Terminology 
 
1.  Correct Response: C 

The Sprint retrospective meeting is conducted to encourage the Scrum Team to revise, 
within the Scrum process framework and practices, its development process to make it 
more effective and enjoyable for the next Sprint. 
 
2.  Correct Response: D 

The output of the Sprint Planning Meeting is called the Sprint Backlog composed of 
tasks, task estimates and assignments the Scrum Team will work on developing. 
 
3.  Correct Response: A 

One of the benefits of timeboxed iterations is it is a time period the team can control. 
 
 
 
 
 
 
   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
34/PMI‐ACP Examination Boot Camp 

 
Agile Methods and Approaches 
 
1.  Correct Response: B  
 
Paired programming involves two developers working together to improve code quality. 
 
2.  Correct Response: C 

The Product Backlog, Sprint Backlog, and Increment are three major artifacts of Scrum 
another is Burndown Charts. 
 
3.  Correct Response: D 

Lean principles include Seeing/Avoiding Waste, Create Knowledge, Build Quality In, Fast 
Delivery, Respect, and Improve. 
 
 
Assessing and Incorporating Community and Stakeholder Values 
 
1.  Correct Response: True 
 
2.  Correct Response: D 

There are three levels of participants.  Critical participants can prevent your project 
from achieving success before or after implementation. 
 
3.  Correct Response: A 

A persona is an imaginary representation of a user role. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /35 

Stakeholder Management 
 
1.  Correct Response: True 
 
2.  Correct Response: B 

A Sprint review meeting is used by the Team to present what was developed during the 
Sprint. 
 
3.  Correct Response: D 

The Product Owner, ScrumMaster, and Scrum Team are all management roles, other 
stakeholders in an organization are chickens who have a vested interest in the project, 
but have to work through the pigs. 
 
 
Communications Management 
 
1.  Correct Response: A 

Having programming pairs sit at the same workstation will result in less delays, 
diminished lost opportunity costs, and increased communication. 
 
2.  Correct Response: D 

Drafts are used to describe hearing unwanted information. 
 
3.  Correct Response: B 

Information radiators are marvelous for passing along information quietly, with little 
effort, and without disturbing the people whose status is being reported. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
36/PMI‐ACP Examination Boot Camp 

Facilitation Methods 
 
1.  Correct Response: B 

The ScrumMaster helps facilitate the Scrum Team's search for better ways for the Scrum 
process to work. 
 
2.  Correct Response: True 
 
3.  Correct Response: A 

Delegating is not an important facilitation skill for an Agile leader to possess. 
 
Knowledge Sharing/Written Communication 
 
1.  Correct Response: C 

Relearning is not tapping into the knowledge readily available within the Agile team or 
sharing that knowledge within the team. 
 
2.  Correct Response: D 

An exponential increase in productivity for a team continues until the team reaches 
seven people, give or take two. 
 
3.  Correct Response: A 

Paper documentation is the least richest form of the communications channel. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /37 

Leadership 
 
1.  Correct Response: B 

Agile leaders are "light" in terms of top‐down decision making and are "heavy" in the 
other characteristics. 
 
2.  Correct Response: D 

Given the circumstances, this is the most appropriate response when a team member or 
anyone starts yelling during a daily stand‐up meeting. 
 
3.  Correct Response: False 
 
 
Building Agile Teams 
 
1.  Correct Response: B 

True self‐organization involves giving the whole team the task and asking the team to 
complete the task without specifying who should do what. 
 
2.  Correct Response: A 

The Scrum Team owns the Daily Scrum and conducts the meeting. 
 
3.  Correct Response: A 

In high‐performance teams, the leaders manage the principles, and the principles 
manage the team. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
38/PMI‐ACP Examination Boot Camp 

Team Motivation 
 
1.  Correct Response: B 

Rewarding the team with financial bonuses for increased velocity is an extrinsic 
motivator not an intrinsic motivator. 
 
2.  Correct Response: C 

Working agreements belong to the team and are monitored during the retrospective. 
 
3.  Correct Response: A 

Teams experience loss as the first phase, followed by chaos, transforming idea, then 
practice and integration. 
 
 
Physical and Virtual Co‐location  
 
1.  Correct Response: D 

The Cone of Silence strategy is where one or more people are sequestered away from 
everyone else for the sole purpose of avoiding communication. 
 
2.  Correct Response: C 

Erg‐seconds captures the cost in both labor and time to get a question answered. 
 
3.  Correct Response: A 

In the absence of face‐to‐face osmotic communication, using microphones and web 
cams would be the best choice. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /39 

Global, Cultural, and Team Diversity 
 
1.  Correct Response: B 

Diversity in backgrounds helps to generate innovation in a project. 
 
2.  Correct Response: A 

Technology increases effectiveness when it lets people express their thoughts more 
easily. 
 
3.  Correct Response: D 

Trust, respect, and communication are most important when teams are comprised of 
different cultures and locations. 
 
 
 
 
Training, Coaching and Mentoring 
 
1.  Correct Response: C 

A ScrumMaster following Agile practices does not use command and control tactics. 
 
2.  Correct Response: A 

Effective project leaders focus on people, product, and process ‐ in that order. 
 
3.  Correct Response: C 

The ScrumMaster is ultimately responsible for teaching others how to use the Scrum 
process. 
 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
40/PMI‐ACP Examination Boot Camp 

Development Mastery Models (e.g., Tuckman, Dreyfus, Shu Ha Ri) 
 
1.  Correct Response: C 

The five stages of Tuckman’s team development are forming, storming, norming, 
performing, and adjourning 

2.  Correct Response: A 

3.  Correct Response: A 

 
Self Assessment Tools and Techniques 
 
1.  Correct Response: D 

Servant leadership characteristics to self‐assess include listening, empathizing, accepting 
others, and developing others. 
 
2.  Correct Response: True 
 
3.  Correct Response: A 

Emotional wake is the impact ‐ whether harm was intended and whether you think the 
other person should feel hurt or not. 
 
 
Participatory Decision Models (e.g., Convergent, Shared Collaboration) 
 
1.  Correct Response: C 

Participatory decision making is a process of reconceiving a solution to a problem based 
on information from all team members. 
 
2.  Correct Response: B 

Convergence means that not everyone is in complete agreement, but that everyone has 
participated and will support the final decision. 
 
3.  Correct Response: D 

Consensus does not imply unanimous agreement, but it does mean that people 
understand the decision rationale. 
 
   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /41 

 
Principles of Systems Thinking (e.g., Complex Adaptive, Chaos) 
 
1.  Correct Response: A 

The three steps of systems thinking lead naturally to a fourth step ‐ formulating an 
answer to the question, what can we do about this?  (Answer) 
 
2.  Correct Response: C 

Begin with the evidence. What are some of the facts and why are they an issue? (Events) 
 
3.  Correct Response: B 

Systems thinking studies systems as a whole being composed of subsystems with 
repeating patterns of behavior between the subsystems. 
 
 
Problem Solving 
 
1.  Correct Response: C 
 
The purpose of the Ishikawa (Fishbone) diagram is to perform root cause analysis. 
 
2.  Correct Response: B 

Complex problem solving requires frequent inspection and adaption because these are 
the only known control mechanisms. 
 
3.  Correct Response: D 

Let the team tell diagnose the problem, identify the root cause, and implement a 
solution. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
42/PMI‐ACP Examination Boot Camp 

Prioritization 
 
1.  Correct Response: B 

The Product Owner frequently prioritizes the Product Backlog to queue up the most 
valuable requirements for the next iteration. 
 
2.  Correct Response: B 

When stakeholders identify any new functionality during the Sprint Review they need to 
request the functionality is added to the Product Backlog for prioritization. 
 
3.  Correct Response: C 

MoSCoW analysis uses won't haves for prioritization purposes. 
 
 
 
Incremental Delivery 
 
1.  Correct Response: D 

Incremental delivery helps the team made orderly progress toward completing the 
release since each increment is tested as it is coded.  The team performs frequent 
inspection and adaptation which empowers them to find their own way through 
complex situations and have a sense of accomplishment. 
 
2.  Correct Response: C 
 
The results of the Iteration does not have to reflect the early understanding of the 
product, it needs to reflect the current understanding of the product. 
 
3.  Correct Response: A 

An increment of product functionality needs to be well‐structured, well‐written, and 
thoroughly tested. 
 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /43 

Agile Discovery 
 
1.  Correct Response: D 
   
Questions need to be asked and answers need to be given, but it is not really discovery 
unless there is understanding. 
 
2.  Correct Response: A 
   
  Project Scope Descriptions are an artifact of Predictive (Waterfall) project management. 
 
3.  Correct Response: False 
 
  Establishing KPIs should begin with discovery. 
 
 
Agile Sizing and Estimation 
 
1.  Correct Response: B 

Estimates are not created by a single individual on the team; estimates are best derived 
collaboratively by the team. 
 
2.  Correct Response: B 

From the estimate of size ‐ 200 points, and known velocity value ‐ 20 points every 4 
weeks, we can derive there will be 10 iterations lasting 40 weeks. 
 
3.  Correct Response: D 

Teams should re‐estimate when their opinion of the relative size of one or more stories 
has changed. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
44/PMI‐ACP Examination Boot Camp 

Value‐based Analysis and Decomposition 
 
1.  Correct Response: B 

A Minimal Marketable Feature (MMF) is the smallest amount of functionality that 
makes sense to market; it adds value to the user. 
 
2.  Correct Answer: B 

The Vision describes why the project is being undertaken and what the desired end 
state is. 
 
3.  Correct Response: D 

Time‐bound is not part of the INVEST model; testable is part of the model. 
 
 
Process Analysis 
 
1.  Correct Response: B 

Teams should usually wait to modify practices until after they've tried them for an 
iteration or two. 
 
2.  Correct Response: False 
 
3.  Correct Response: B 

The PDCA cycle stands for Plan‐Do‐Check‐Act. 
 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /45 

Continuous Improvement  
 
1.  Correct Response: C 

Effective Agile teams cover the team ‐ as in how well the processes and practices being 
used by the team are working, not how individuals are performing. 
 
2.  Correct Response: D 

Every team member has a responsibility to improve teamwork. 
 
3.  Correct Response: False 
 
 
Agile Hybrid Models 
 
1.  Correct Response: False 
 
2.  Correct Response: C 
 
  TDD is Test Driven Development, a development methodology used in XP. 
 
3.  Correct Response: B 
 
  XP uses TDD and Pair Programming (among others) development methodologies. 
 
 
Managing with Agile KPIs 
 
1.  Correct Response: A 
 
2.  Correct Response: B 
 
  For a project, KPIs are for software and the development process. 
 
3.  Correct Response: True 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
46/PMI‐ACP Examination Boot Camp 

Agile Project Chartering 
 
1.  Correct Response: A 

The Vision on the Project Charter reminds everyone of the main business goals during 
the project. 
 
2.  Correct Response: C 

The creation of the Project Charter is the responsibility of the Product Owner, with input 
from the team. 
 

3.  Correct Response: B 

The content of a Project Charter usually fits onto one page, sometimes two so it can be 
quickly reviewed. 
 
 
Agile Contracting 
 
1.  Correct Response: True 
 
2.  Correct Response: A 

Fixed cost contracts assume that all requirements can be established and documented 
prior to the beginning of work, which works well for Waterfall types of projects but not 
Agile projects with evolving requirements. 
 
3.  Correct Response: A 
 
Technical competence is more important than experience with the Agile methodology. 
 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /47 

Agile Project Accounting Principles 
 
1.  Correct Response: D 

Agile EVM is a valuable technique when cost performance must be measured. 
 
2.  Correct Response: False 
 
3.  Correct Response: A 

Budgeting is easier because of fixed time and resources, the costs become more 
controllable because of flexible scope. 
 
 
Regulatory Compliance 
 
1.  Correct Response: B 

The most common way of handling imposed regulations is to consider them to be 
additional User Stories. 
 
2.  Correct Response: False 
 
3.  Correct Response: D 

Additional User Stories created to address imposed government regulations should be 
added to the Product Backlog and prioritized by the Product Owner (customer). 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
48/PMI‐ACP Examination Boot Camp 

PMI’s Code of Ethics and Professional Conduct 
 
1.  Correct Response: C 

Responsibility, Respect, Fairness, and Honesty are the four key areas of ethical behavior. 
 
2.  Correct Response: A 

Programmers can detect mismatches in pay and organizational values and this type of 
mismatch will lead to programmers behaving in ways that will hurt the organization. 
 
3.  Correct Response: B 

If the Scrum Team feels itself unable to complete all of the Sprint Backlog during the Sprint, 
they can consult with the Product Owner on which items to remove from the current Sprint.  
 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp/49 

Final Practice Exam 1


 

 
Domain  Percentage of Items on 
the Test 

Domain I.  Agile Principles and  16% 
The exam is 3 hours long  Mindset 
with 120 questions.  You 
will be scored on 100 of  Domain II.  Value‐Driven  20% 
those questions.    Delivery 

Domain III.  Stakeholder  17% 
Engagement 

Domain IV.  Team  16% 
Performance  

Domain V.  Adaptive Planning  12% 

Domain VI.  Problem  10% 
Detection and Resolution 

Domain VII.  Continuous  9% 
Improvement 
 
The PMI‐ACPSM exam will have 120 questions; 20 of 
those questions will not count toward your pass/fail 
grade.  The other 100 questions will be scored and do 
count toward your pass/fail grade.  You will not be 
able to tell which questions count and which ones do 
not. 
 
You will have 3 hours to take the real exam.  Since the 
passing score is not made public, we encourage your 
goal score should be 82% or better.   
 
Use the following practice exam as a way to simulate 
the day of the exam. 
 

 
PMI‐ACP Study Guide 
©2019 ASPE, Inc. 
 
50/PMI‐ACP Examination Boot Camp 

Final Practice Exam 1


 
1.  Which of the following is used to describe the cadence of work that can be 
maintained indefinitely? 
 
a) Sustainable Pace 
b) Project Schedule 
c) Resource Allocation 
d) Continuous Integration 
 
2.  Which of the following audiences was the Declaration of Interdependence created 
for? 
 
a) Software Development 
b) Project Team Members 
c) Project Leaders 
d) Project Stakeholders 
 
3.  Which of the following Agile business objectives focuses on lowering technical debt? 
 
a) Continuous Innovation 
b) Reliable Results 
c) People and Process Adaptability 
d) Product Adaptability 
 
4.  An Agile team member is incorporating multiple team member view points and 
insights in order to resolve a conflict.  Which approach are they using? 
 
a) Smooth / Accommodate 
b) Compromise / Reconcile 
c) Collaborate / Problem Solve 
d) Force / Direct 
 
5.  An Agile team is working on a project to improve the way orders are processed for 
their customers by eliminating almost all of the manual intervention currently being 
used.  What dominant source of return is this project seeking? 
 
a) Retained Revenue 
b) Operational Efficiencies 
c) New Revenue 
d) Incremental Revenue 
 
 
   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /51 

6.  Which of the following factors is NOT taken into account when determining the 
length of a retrospective? 
 
a) Number of stories 
b) Complexity 
c) Team size 
d) Level of conflict or controversy 
 
7.  Which Scrum role is responsible for initial and ongoing funding for the project? 
 
a) Product Owner 
b) Sponsor 
c) ScrumMaster 
d) Project Manager 
 
8.  Which type of decision making approach is the most damaging to the team's ability 
to self‐organize? 
 
a) Unilateral decision making 
b) Compromising decision making 
c) Participatory decision making 
d) Collaborative decision making 
 
9.  An Agile Coach is meeting with a team member and after listening begins to interpret 
what was said through their own view.  Based on the Levels of Listening from the 
school of coactive coaching, at what level is the Agile Coach listening? 
 
a) Level II ‐ Focused Listening 
b) Level III ‐ Global Listening 
c) Level IV ‐ Super Listening 
d) Level I ‐ Internal Listening 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
52/PMI‐ACP Examination Boot Camp 

10.  One of the senior managers at your organization has asked you (the ScrumMaster) 
to complete an end‐of‐iteration summary at the conclusion of each sprint.  Should 
this type of report and documentation even be considered on an Agile project? 
 
a) No, this senior manager does not understand Agile practices.  You as the 
ScrumMaster need to let him know the rules of Agile. 
b) Yes, this request is acceptable on an Agile project and as the ScrumMaster 
you should delegate this responsibility to one of the team members. 
c) Yes, because the end‐of‐iteration summary can be helpful for communicating 
current information and can be used as a historical document for future use.  
As the ScrumMaster you should communicate what the senior manager has 
requested. 
d) No, this senior manager has been a problem throughout the entire project.  
Escalate this issue to your Product Owner and let him/her communicate to 
the senior manager that the summary will not be completed. 
 
11.  What information is depicted on the vertical axis of a release burndown chart? 
 
a) Number of activities and tasks completed 
b) Number of story points or ideal days remaining 
c) Number of major milestones completed 
d) Number of activities and tasks remaining 
 
12.  Which of the following is the best team strategy to create early and regular delivery 
on a project? 
 
a) Hardest‐last strategy 
b) Worst‐things‐first strategy 
c) Simplest first, worst second strategy 
d) Most difficult first, easy second strategy 
 
13.  Which of the following techniques is NOT useful in helping multiple Agile teams 
work on the same project? 
 
a) Agile teams should establish a common basis for their estimates. 
b) On highly complex projects with many interteam dependencies, it can be 
helpful to incorporate feeding buffers into the plan. 
c) Multiple teams benefit from incorporating a rolling lookahead plan into their 
Release Planning. 
d) When multiple teams need to work together, it is useful to wait to add detail 
to user stories until later in the project planning. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /53 

14.  During the Daily Scrum, two of the Scrum Team members get into a side 
conversation about what they are going to do this weekend.  What should happen in 
this instance? 
 
a) Scrum Team members are self‐organized and should correct the unabiding 
Scrum Team members. 
b) The ScrumMaster needs to remind the Scrum Team of the rule that only one 
person talks at a time during the Daily Scrum. 
c) The ScrumMaster should wait to speak with the Scrum Team members until 
the Daily Scrum is over. 
d) The ScrumMaster should escalate this issue to the Product Owner. 
 
15.  Which of the following is used to document the economic feasibility study as a basis 
for authorization of additional project management activities? 
 
a) Project Charter 
b) Business Case 
c) Cost‐Benefit Analysis 
d) Vision Document 
 
16.  Which of the following are NOT aspects of empirical process control? 
 
a) Adaptation 
b) Development 
c) Visibility 
d) Inspection 
 
17.  An Agile team is surveying users to determine which features to include in their 
project.  They receive feedback about a feature the customers expect to have and 
they want more and more of these types of features in the product.  According to 
the Kano Model of Customer Satisfaction, which category have the customers 
described? 
 
a) Exciters and delighters 
b) Linear features 
c) Threshold features 
d) Dissatisfiers 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
54/PMI‐ACP Examination Boot Camp 

18.   A project retrospective is scheduled to last an entire day.  One of the stakeholders 
asks if they can drop‐in and dropout throughout the day.  What should the 
retrospective leader tell this stakeholder? 
 
a) Tell the stakeholder full‐time attendance is necessary because each part of 
the retrospective structure builds on the preceding portion. 
b) Tell the stakeholder it's okay to drop‐in and dropout since their feedback is 
important. 
c) Ask the stakeholder to still attend the retrospective and bring their other 
work with them to do in private. 
d) Reschedule the retrospective until every participant's schedule allows for 
full‐day attendance. 
 
19.   Which of the following is used to measure the amount of time that passes? 
 
a) Elapsed time 
b) Bottom‐up Estimates 
c) Top‐down Estimates 
d) Ideal time 
 
20.   Which of the following testing is NOT performed in Agile projects? 
 
a) Automated regression testing 
b) Unit testing 
c) End‐to‐end testing 
d) Manual regression testing 
 
21.   Which of the following plans is the most precise? 
 
a) Release Plan 
b) Daily Plan   
c) Iteration Plan 
d) Project Plan 
 
22.   Which Scrum artifact evolves as the product, the requirements, and the 
environment in which it will be used evolves? 
 
a) Sprint Backlog 
b) Gantt Chart 
c) Burndown Chart 
d) Product Backlog 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /55 

23.    Which of the following is NOT a key value for an Agile Leader? 
 
a) Leading the team over managing tasks. 
b) Delivering value over meeting constraints. 
c) Managing tasks over leading the team. 
d) Adapting to change over following a plan. 
 
24.    Which of the following approaches is NOT used to estimate velocity? 
 
a) Run an iteration 
b) Use historical values 
c) Make a forecast 
d) Compare to other Agile teams 
 
25.    What type of meeting does the Scrum Team use to synchronize the work of all 
Team members and to schedule any meetings the Team needs to forward its 
progress? 
 
a) Sprint Review 
b) Sprint Retrospective 
c) Sprint Planning Meeting 
d) Daily Scrum 
 
26.    Which of the following is a common root cause analysis technique used by Agile 
teams? 
 
a) Value Stream Mapping 
b) The Five Whys 
c) Monte Carlo Simulation 
d) Six Sigma 
 
27.    Which Scrum role is responsible for being self‐managed and self‐organized? 
 
a) Scrum Team 
b) ScrumMaster 
c) Project Manager 
d) Product Owner 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
56/PMI‐ACP Examination Boot Camp 

28.    When the person paying for a project requests a written report of the project 
retrospective, which role is responsible for creating the report? 
 
a) The ScrumMaster or Agile Project Manager 
b) The Product Owner 
c) The Team Lead 
d) The Team 
 
29.    An Agile team working on their estimates decides to use a new technique where 
they compare a user story against a couple of other stories that have been 
estimated.  What technique is the team using? 
 
a) Triangulation 
b) Expert opinion 
c) Disaggregation 
d) PERT 
 
30.    What should the Agile team do if the executive sponsor is not attending the 
iteration demos? 
 
a) Ask the Product Owner to fill‐in for the Executive Sponsor. 
b) Keep the iteration demos short and have the Product Owner conduct a 
private demo at least once a month whenever the Executive Sponsor cannot 
attend. 
c) Request a new Executive Sponsor. 
d) Nothing, the customer's feedback is the most important feedback needed for 
the demo. 
 
31.    Once an Agile team has completed an iteration, when is the ideal time to hold an 
iteration retrospective?? 
 
a) Right after a release 
b) Right before iteration planning 
c) Right after iteration planning 
d) Right before a release 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /57 

32.    An Agile team is using an estimating technique that involves the Product Owner 
reading the description of the user story and answering questions from the team.  
The team members then privately select a card representing their estimate and 
reveal them simultaneously.  What estimating technique is the team using? 
 
a) Triangulation 
b) Planning Poker 
c) Storyboarding 
d) PERT 
 
33.    During a Sprint the Scrum Team completed all of the tasks early.  What should be 
done in this instance? 
 
a) Nothing should be done; the Scrum Team has accomplished their velocity for 
this Sprint. 
b) The Scrum Team should consult with each other as to which additional 
Product Backlog items can be added to this Sprint. 
c) The Scrum Team should consult with the ScrumMaster as to which additional 
Product Backlog items can be added to this Sprint. 
d) The Scrum Team should consult with the Product Owner as to which 
additional Product Backlog items can be added to this Sprint. 
 
34.    Which of the following conflict resolution techniques is used to describe 
emphasizing areas of agreement rather than areas of difference? 
 
a) Collaborate / Problem Solve 
b) Compromise / Reconcile 
c) Force / Direct 
d) Smooth / Accommodate 
 
35.    Why is it oftentimes dangerous to estimate in ideal days? 
 
a) Because it's easier to get started with estimating in story points than ideal 
days. 
b) Because ideal days are equal among team members. 
c) Because there is pressure to make an actual day closer to an ideal day. 
d) Because ideal day estimates do not decay. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
58/PMI‐ACP Examination Boot Camp 

36.    A project manager is presented with a different strategy for managing projects 
than the waterfall strategy he/she has been using for years.  The project manager 
decides not to try the new strategy.  Which failure mode has the project manager 
fallen into? 
 
a) Making mistakes 
b) Preferring to fail conservatively 
c) Inventing rather than researching 
d) Being creatures of habit 
 
37.    What is the correct order for the Agile Project Management Delivery Framework? 
 
a) Explore‐Envision‐Speculate‐Close‐Adapt 
b) Envision‐Speculate‐Explore‐Adapt‐Close 
c) Initiate‐Plan‐Execute‐Control‐Close 
d) Explore‐Initiate‐Plan‐Adapt‐Close 
 
38.    Which of the following is NOT part of The Declaration of Interdependence? 
 
a) We increase return on investment by making process our focus. 
b) We boost performance through group accountability for results and shared 
responsibility for team effectiveness. 
c) We deliver reliable results by engaging customers in frequent interactions 
and shared ownership. 
d) We expect uncertainty and manage for it through iterations, anticipation, 
and adaptation. 
 
39.    Which of the following is used to describe a single‐page summary of key business 
and quality objectives, product capabilities, and project management information 
for the Envision phase? 
 
a) Project Management Plan 
b) Vision Document 
c) Scope Definition Document 
d) Project Data Sheet 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /59 

40.    An Agile team estimated story points for the following user stories: 

User Story A  5 story points 
User Story B  3 story points 
User Story C  2 story points 
User Story D  1 story point 
 

The team's velocity in the prior sprint was 11.  Due to unforeseen risks in this 
sprint, the team was only able to finish User Stories A and B.  What is their velocity 
for this sprint? 
 
a) 3 
b) 8 
c) 11 
d) 0 
 
41.    Which of the following is the correct order of phases used during a retrospective? 
 
a) Set the stage, Gather data, Generate insights, Decide what to do, and Close 
the retrospective 
b) Gather data, Set the stage, Generate insights, Decide what to do, and Close 
the retrospective 
c) Gather data, Set the stage, Generate insights, Decide what not to do, and 
Close the retrospective 
d) Generate insights, Gather data, Set the stage, Decide what not to do, Close 
the retrospective 
 
42.    An Agile team is working on a project to encourage customers to purchase more 
licenses.  What dominant source of return is this project seeking? 
 
a) Retained Revenue 
b) Operational Efficiencies 
c) New Revenue 
d) Incremental Revenue 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
60/PMI‐ACP Examination Boot Camp 

43.    During the second week of a sprint the Product Owner asks the team to include a 
change to the functionality they are working on.  Is this considered good practice 
in Agile? 
 
a) Yes, this is acceptable in Agile practice. 
b) Yes, as long as the Product Owner okays this decision with the ScrumMaster. 
c) Yes, because the Product Owner determines the priorities based on 
customer and business needs. 
d) No, the Product Owner should document the change in the Product Backlog. 
 
44.    Who is responsible for driving Agile development? 
 
a) Customers and Product Managers 
b) Product Owner 
c) Scrum Team 
d) ScrumMaster 
 
45.    The Product Owner on an Agile team has asked the ScrumMaster to begin tracking 
individual velocity for the team.  Should this practice be implemented by the 
ScrumMaster? 
 
a) Yes, this is acceptable in Agile practice because it will help individuals 
become better at estimating and the Product Owner should be supported by 
the ScrumMaster in this practice. 
b) No, individuals should be given every incentive possible to work 
collaboratively as a team and the ScrumMaster should explain this rule to the 
Product Owner. 
c) Yes, because the Product Owner is responsible for the rules the Agile team 
follows and the ScrumMaster answers to the Product Owner. 
d) No, the Product Owner should not be changing the rules for the Agile team in 
the middle of a project.  It's okay to change the rules after the project ends. 
 
46.    Which of the following roles is responsible for eliminating waste in an Agile 
project? 
 
a) The Agile Leader 
b) The Product Owner 
c) The Team 
d) The Product Manager 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /61 

47.    During which meeting does the Scrum Team consider changing any of the rules of 
Scrum? 
 
a) Sprint Retrospective 
b) Sprint Planning   
c) Daily Scrum 
d) Sprint Review 
 
48.    An Agile team and ScrumMaster are working together on the Release Plan.  Which 
of the following should be done during this planning process? 
 
a) Creating a plan that shows which team members will work on which user 
stories. 
b) Creating a plan that shows which team members will work on specific tasks. 
c) Selecting an iteration length. 
d) Creating a plan that shows how much the user stories will cost. 
 
49.    Which of the following is the correct scope to consider for Agile projects? 
 
a) Articulated Product Vision 
b) Defined Requirements 
c) Project Scope Statement 
d) BHAGs ‐ Big Hairy Audacious Goals 
 
50.    Recently during the Daily Scrum meetings, there have been several chickens 
attending the meeting that have caused the meetings to exceed the 15‐minute 
limit.  What should be done in this instance? 
 
a) The ScrumMaster should escalate this issue to the Product Owner. 
b) The ScrumMaster needs to change the time of the Daily Scrum meeting so 
the chickens miss it. 
c) The ScrumMaster should ask the chickens to immediately leave the meeting. 
d) The ScrumMaster needs to limit the attendance so the meeting is orderly and 
focused. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
62/PMI‐ACP Examination Boot Camp 

51.    A template written in this form ‐ "As a <type of user>, I want <capability> so that 
<business value>" is used to create which of the following? 
 
a) Activities 
b) Epics 
c) Themes 
d) User Stories 
 
52.    Which Scrum role creates the initial overall requirements, ROI objectives, and 
release plans? 
 
a) Scrum Team 
b) ScrumMaster 
c) Sponsor 
d) Product Owner 
 
53.    During an iteration retrospective one of the team members, Kim is continuously 
talking about every point and is not allowing other team members to provide 
input/feedback.  What should the retrospective leader do first? 
 
a) Be direct by asking Kim to immediately leave the retrospective. 
b) Be indirect by showing Kim through your body language to tone it down. 
c) Be direct by asking Kim privately to talk less and listen more. 
d) Let the team members correct Kim since they are self‐organized. 
 
54.    Once the Release Plan is done, how often should it be revisited and updated? 
 
a) Once the Release Plan is complete it doesn't need to be revisited unless a 
change control request is issued. 
b) The Release Plan should be revisited and updated with regular frequency ‐ 
after each iteration or as long as every 4‐6 weeks. 
c) The Release Plan should be revisited and updated every week. 
d) The Release Plan should be revisited and updated every day. 
 
55.    Which of the following Scrum roles have the option to attend the Sprint 
Retrospective meeting? 
 
a) ScrumMaster 
b) Scrum Team 
c) Product Champion 
d) Product Owner 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /63 

56.    Company XYZ has just begun using Scrum practices.  They recently had a meeting 
where customers and other key stakeholders were involved in functionality 
demonstrations.  Which type of meeting was being conducted? 
 
a) Sprint Retrospective 
b) Sprint Planning Meeting 
c) Sprint Review 
d) Daily Scrum 
 
57.    Which of the following is NOT performed during Iteration Planning? 
 
a) Individual task assignments are made. 
b) User stories are organized. 
c) User stories are decomposed into tasks. 
d) Tasks are estimated in ideal hours. 
 
58.    Which of the following is the most important aspect of self‐organized teams? 
 
a) Self‐discipline 
b) Accountability 
c) Collaboration 
d) Respect 
 
59.    Which of the following roles is NOT considered a "pig"? 
 
a) ScrumMaster 
b) Project Stakeholders 
c) Product Owner 
d) Scrum Team 
 
60.    Which types of features should be developed first in an Agile project? 
 
a) Low‐value, high‐risk 
b) High‐value, low‐risk 
c) Low‐value, low‐risk 
d) High‐value, high‐risk 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
64/PMI‐ACP Examination Boot Camp 

61.    Which of the following audiences was the Manifesto for Agile Software 
Development created for? 
 
a) Project Team Members 
b) Project Leaders 
c) Project Stakeholders 
d) Software Development 
 
62.    What time of day is best to hold the Daily Scrum meeting? 
 
a) First thing in the day 
b) Last thing in the day 
c) Before lunch 
d) After lunch 
 
63.    The Product Owner is trying to determine which themes to select and fund for 
cash flow streams and decided to measure the amount of time required to earn 
back the initial investment by taking into account the time value of money.  Which 
way did the Product Owner evaluate the cash flow streams? 
 
a) Payback Period 
b) Internal Rate of Return (IRR) 
c) Net Present Value (NPV) 
d) Discounted Payback Period 
 
64.    An Agile team has created a chart that includes a rectangular box for each theme 
depicting the name of the theme, the number of stories in the theme, the number 
of story points, and percentage of story points completed.  What is the name of 
this chart? 
 
a) Burndown Chart 
b) Burnup Chart 
c) Burndown Bar Chart 
d) Parking‐Lot Chart 
 
65.    Which of the following information radiators works best for an Agile team that has 
12 people? 
 
a) Paper 
b) Digital cameras 
c) Printing whiteboards 
d) Wall charts 
 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /65 

66.    When using Commitment‐Driven Iteration Planning, how long does is it typically 
take for a team to get a feel for how many hours they should plan for an iteration? 
 
a) Approximately 7 iterations 
b) Approximately 10 iterations 
c) Approximately 2 iterations 
d) 1 iteration 
 
67.    What is happening to an Agile project when the top of the bar is lowered on the 
burndown chart? 
 
a) Work has been added 
b) Work has been completed 
c) Work has been removed   
d) No work has been added to or removed from the release 
 
68.    Which of the following is NOT a valid reason for terminating a Sprint? 
 
a) When business conditions change and the Sprint holds no value for the 
business. 
b) When the Scrum Team is interfered with during the Sprint by anyone outside 
the Scrum Team. 
c) When the ScrumMaster is controlling and directing the work of the Scrum 
Team. 
d) When the technology proves unworkable. 
 
69.    Which of the following practices is considered to use line‐of‐sight‐and‐hearing 
learning? 
 
a) Scrum 
b) Lean Software Development 
c) Dynamic Systems Development Method (DSDM) 
d) eXtreme Programming (XP) 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
66/PMI‐ACP Examination Boot Camp 

70.    An Agile team has created a list of the product's requirements, prioritized them 
and determined that not every feature will be delivered.  In fact, the team 
recommends that 30 percent of the effort of the project be considered optional.  
What is the Agile team doing? 
 
a) Creating a feeding buffer 
b) Creating a feature buffer 
c) Creating a schedule buffer 
d) Putting together a scope management plan 
 
71.    Which Scrum role is responsible for prioritizing the order in which to discuss 
potential Scrum improvements during the Sprint Retrospective? 
 
a) ScrumMaster 
b) Product Owner 
c) Scrum Team 
d) Product Champion 
 
72.    Which of the following techniques is used to split a story or feature into smaller, 
easier‐to‐estimate pieces? 
 
a) Triangulation 
b) Expert opinion 
c) Disaggregation 
d) Analogy 
 
73.    The Product Owner is trying to determine which themes to select and fund for 
cash flow streams and decided to measure the amount of time required to earn 
back the initial investment.  Which way did the Product Owner evaluate the cash 
flow streams? 
 
a) Payback Period 
b) Internal Rate of Return (IRR) 
c) Net Present Value (NPV) 
d) Expected Monetary Value (EMV) 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /67 

74.    Which of the following concepts refers to the creation of two zones in the room 
set‐up: one zone to maximize osmotic communication/information transfer and 
the second zone to provide a private place for team members to make phone calls, 
check email, and have a separate space? 
 
a) Osmotic Zone and Quiet Zone 
b) Osmotic Communication and The Cone of Silence 
c) Drafts and Hot Air 
d) Caves and Common 
 
75.    An Agile team has determined they want to use Gantt charts for communicating 
the Agile plan.  Which of the following approaches do they need to avoid? 
 
a) Stopping at the feature level and not decomposing each user story into its 
constituent tasks. 
b) Showing each feature as taking the full length of the iteration in which it's 
scheduled. 
c) Not allocating resources to the identified features. 
d) Allocating resources to each of the identified features. 
 
76.    Which of the following terms is used to describe a period of time that cannot be 
exceeded and within which an event or meeting occurs? 
 
a) Timebox 
b) Time limit 
c) Duration 
d) Sprint / Iteration 
 
77.    Which of the following numbers is assigned to tiny features? 
 
a) 1 
b) 0.5 
c) 0 
d) 0.25 
 
78.    Which of the following is NOT a benefit of moving QA closer to the front of the 
value stream? 
 
a) To reduce or eliminate delay 
b) To reduce or eliminate the need for testing 
c) To reduce or eliminate redundancy 
d) To reduce or eliminate miscommunication 
 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
68/PMI‐ACP Examination Boot Camp 

79.    How long does a Sprint review meeting last? 
 
a) 1 hour 
b) 8 hours 
c) 4 hours 
d) It depends on the length of the Sprint and whether the Demo is included 
 
80.    When a team is using planning poker for estimating user stories, how many rounds 
does it usually take for the estimates to converge? 
 
a) As many rounds as it takes 
b) 7 rounds 
c) 5 rounds 
d) 2 rounds 
 
81.    Which of the following concepts is NOT part of simplicity? 
 
a) Delivery versus Compliance 
b) Generative Rules 
c) Barely Sufficient Methodology 
d) Prescriptive Principles 
 
82.    Which of the following is used to describe the time from when the team begins 
work on a feature until that feature delivers value to users? 
 
a) Duration 
b) Schedule 
c) Project Plan 
d) Cycle Time 
 
83.    Company XYZ has just implemented Scrum practices.  The development team 
members on an Agile project are assigned tasks by the ScrumMaster according to 
their role, including analysis, design, coding, testing, and documentation, with a 
different team member fulfilling each role.  What approach is the team using? 
 
a) Scrum 
b) XP 
c) Test Driven Development 
d) Waterfall 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /69 

84.    In Lean, at what point does the team form, assign roles, determine logistics for 
meetings, and decide how to work together? 
 
a) During Iteration 1 
b) During Release Planning 
c) After the Project Charter has been approved 
d) During Iteration 0 
 
85.    The Product Owner is trying to determine which themes to select and fund for 
cash flow streams and decided to measure how much money each theme is 
expected to return in today's present value.  Which way did the Product Owner 
evaluate the cash flow streams? 
 
a) Payback Period 
b) Internal Rate of Return (IRR) 
c) Net Present Value (NPV) 
d) Discounted Payback Period 
 
86.    Which of the following constraints are NOT considered when using a tradeoff 
matrix? 
 
a) Risk 
b) Scope 
c) Schedule 
d) Cost 
 
87.    Which role owns the learnings from a retrospective? 
 
a) The Agile Leader 
b) The Product Owner 
c) The Product Manager 
d) The Team 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
70/PMI‐ACP Examination Boot Camp 

88.    An Agile team is surveying users to determine which features to include in their 
project.  They receive feedback about a feature the customers would love to have 
in your product to differentiate your company from other companies and they are 
willing to pay extra for this feature.  According to the Kano Model of Customer 
Satisfaction, which category have the customers described? 
 
a) Exciters and delighters 
b) Linear features 
c) Threshold features 
d) Dissatisfiers 
 
89.    During an iteration a developer runs into a problem and begins performing a rapid 
experiment to investigate.  What is the developer working on? 
 
a) Spike 
b) Feature 
c) Task 
d) Minimal Marketable Feature 
 
90.    How long should an iteration demo last? 
 
a) 1 hour 
b) 1/2 day 
c) 10‐30 minutes 
d) It depends on the length of the iteration. 
 
91.    An Agile team is working on an enhancement project and adds new features to 
attract different customers.  What dominant source of return is this project 
seeking? 
 
a) Retained Revenue 
b) Operational Efficiencies 
c) New Revenue 
d) Incremental Revenue 
 
92.    When an Agile team is tailoring their documentation practices, which of the 
following should they be careful with? 
 
a) Level of ceremony 
b) Permanent documentation 
c) Working papers 
d) Zero or burdensome documentation 
 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /71 

93.    At what point on an Agile project are stakeholders allowed to provide criticism, 
comments, or observations. 
 
a) During the Sprint 
b) During the Daily Scrum 
c) During the Sprint Review 
d) During the Sprint Retrospective 
 
94.    Which of the following is used to describe technical debt? 
 
a) Partially done work 
b) Writing poor quality code that makes future changes difficult or not using 
learning to improve design 
c) Work‐in‐process (WIP) 
d) Extra features 
 
95.    In the second iteration of a project, the Agile team planned to do 20 story points of 
work.  During this iteration the Product Owner identified another 20 points of 
work that is needed in the release.  How would the additional 20 points of work 
appear in the burndown chart? 
 
a) As a change request 
b) As a burndown 
c) As scope creep 
d) As a burnup 
 
96.    During an iteration the Agile project team forgot about an impending risk.  What 
should the Agile project team do next? 
 
a) Get the product team and development team together to create a risk 
register. 
b) Stop the iteration and include risk response strategies for the next iteration. 
c) Determine if this is a significant need that requires adding a supplementary 
practice. 
d) Ask the ScrumMaster what he/she recommends the team should do. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
72/PMI‐ACP Examination Boot Camp 

97.    An Agile team has created a margin of safety to their project schedule by adding to 
the sum of their estimates and removing local safety.  What is the Agile team 
doing? 
 
a) Padding their estimates 
b) Estimating using story points or ideal days 
c) Creating a schedule buffer 
d) Creating a feature buffer 
 
98.    During a project retrospective several managers were in attendance and before 
team members had an opportunity to contribute regarding improvements, the 
managers began dominating and hijacking the agenda.  What is the best approach 
the retrospective leader can take to correct this situation? 
 
a) Let the managers contribute so the project gets back in control. 
b) Meet with managers before the next retrospective; coach them on 
appropriate participation, including signals to communicate when managers 
are being too assertive. 
c) Prompt the Product Owner to take control of the managers and their 
behavior. 
d) Ask the managers to listen since they are supposed to be observers during 
the retrospective and not participants of the retrospective. 
 
99.    An Agile project team is starting to identify and discuss their strengths and 
weaknesses and determine roles that best suit their abilities and needs.  Which of the 
following stages is the team encountering? 
 
a) Storming 
b) Performing 
c) Norming 
d) Forming 
 
100.  During a sprint one of the key stakeholders keeps providing instructions to one of 
the Scrum Team members.  What should be done in this instance? 
 
a) The ScrumMaster needs to remind the stakeholder of the Scrum rules and 
ask them to refrain from interrupting the Scrum Team member. 
b) The ScrumMaster should escalate this issue to the Product Owner. 
c) The ScrumMaster should allow the interruptions to continue because this 
shows collaboration. 
d) Scrum Team members are self‐organized and should correct the unabiding 
stakeholder. 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /73 

101.  Which of the following approaches is usually the best option to select when 
estimating velocity? 
 
  a)  Run an iteration 
  b)  Use historical values 
  c)  Make a forecast 
  d)  Compare to other Agile teams 
 
102.  Which of the following is FALSE regarding the core beliefs of Agile? 
 
a)   Working code is the most accurate way of seeing the progress of the 
development effort. 
b)   Groups working together minimizes delays as well as the loss of information 
between people. 
c)   You cannot know everything required to build a software product at the start 
of the project. 
d)  You can test at the end of a project and achieve the required quality. 
 
103.  When an organization is moving toward Agile practices, which type of meeting 
tends to be challenged the most? 
 
a)   Daily Standup Meetings 
b)   Release Planning Meetings 
c)   Iteration Planning Meetings 
d)   Retrospective Meetings 
 
104.  Which of the following conflict response modes is assertive and not cooperative? 
 
a)   Avoiding / Withdrawing 
b)   Forcing / Directing 
c)   Collaborating / Problem Solving 
d)   Compromising / Reconciling 
 
105.   Which of the following practices does NOT use strict iteration lengths for the 
completion of stories? 
 
a)   Scrum 
b)   Kanban 
c)   eXtreme Programming 
d)   Lean‐Agile 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
74/PMI‐ACP Examination Boot Camp 

106.   Which of the following feedback forms is NOT valuable when using eXtreme 
Programming (XP)? 
 
a)   Feedback from automated tests. 
b)   Feedback from the continuous integration process. 
c)   Feedback during paired programming. 
d)   Feedback that is delayed. 
 
107.   Which of the following is the best description of servant leadership? 
 
a)   Having the team serve and work for the project leader. 
b)   Ensuring the team serves each other by becoming self‐organized. 
c)   Having the project leader ensure that everyone has the resources to do his or 
her work and providing services to the team. 
d)   Ensuring the team serves and works for the customer. 
 
108.    An Agile team is working on improving the product's design without changing 
externally visible functionality to make the product more reliable and adaptable.  
What is the Agile team doing? 
 
a)   Refactoring 
b)   Continuous Integration 
c)   Reducing Technical Debt 
d)   Team Code Ownership 
 
109.   Which of the following best describes the planning process in Agile projects? 
 
a)   Following a rolling wave approach using top‐down planning. 
b)   Specifying requirements upfront. 
c)   Identifying tasks upfront and estimating those tasks. 
d)   Preparing a project scope document. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /75 

110.   The Product Owner on an Agile project has been attempting to micromanage the 
team by getting into the details of how team members are performing their work.  
What is the best thing the Agile Project Manager can do in this instance? 
 
a)   Explain to the Agile team the Product Owner has every right to micromanage 
the team. 
b)   Report the Product Owner's behavior to the Sponsor. 
c)   Coach the Product Owner to focus on how much work he/she asks the team 
to do, not on how they are doing it. 
d)   Ask the Product Owner to take Agile training. 
 
111.   Which of the following is the most powerful way of reporting the team's progress? 
 
a)   Demos of working software 
b)   Progress reports 
c)   Status meetings 
d)   Iteration retrospectives 
 
112.   Which of the following is used to describe a fixed start date and a fixed end date 
for Agile teams to complete their work? 
 
a)   Duration 
b)   Timebox 
c)   Network Diagram 
d)   Gantt Chart   
 
113.   Which of the following is NOT used as part of the empirical inspection and 
adaptation practices of Scrum? 
 
a)   Sprint Review 
b)   Daily Planning Meeting 
c)   Daily Scrum 
d)   Sprint Retrospective 
 
114.    An Agile team is experiencing different opinions, misunderstandings, and 
conflicting values.  According to the five levels of conflict, what level of conflict is 
this team experiencing? 
 
a)   Level 3 
b)   Level 1 
c)   Level 4 
d)   Level 5 
 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
76/PMI‐ACP Examination Boot Camp 

115.    An Agile team is facing crunch time during a release and the Agile Project 
Manager made the decision to hold two‐a‐day standup meetings.  Is this 
considered good practice? 
 
a)   No, this process would need to be created and supported by the team, not 
because the Agile Project Manager is creating the process out of fear. 
b)   Yes, the Agile Project Manager knows and reinforces Agile principles. 
c)   No, the Agile Project Manager needs to conduct fewer daily standups during 
crunch time. 
d)   Yes, the Agile Project Manager is leading the Agile team to be successful 
during a stressful part of the release. 
 
116.    The customer is having difficulty prioritizing a story.  Which of the following is the 
best choice in this situation? 
 
a)    Tell the customer you will determine the priorities. 
b)    Re‐estimate the story. 
c)    Consider splitting the story. 
d)    Ask the customer to flip a coin between the stories. 
 
117.    During a sprint retrospective a team member states, "We need more people on 
our side; they're wrong, plain and simple".  According to the five levels of conflict, 
what level of conflict is this Agile team experiencing? 
 
a)    Level 4 
b)    Level 1 
c)    Level 5 
d)    Level 3 
 
118.    An Agile team is using a signaling system in their scheduling process where a limit 
is set on WIP and new work is "pulled" through the system.  What practice is the 
Agile team using? 
 
a) Scrum 
b) Dynamic Systems Development Method 
c) Feature Driven Development 
d) Kanban 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /77 

119.    Which of the following is true about Agile projects? 
 
a) The triple constraints can be traded off for one another to correct for 
unknowns. 
b) A plan gets more accurate over time because it is constantly revised and 
trued up to the team's actual performance. 
c) Scope can be locked down with later discoveries being handled as change 
requests against the scheduled end date. 
d) A plan gets more accurate over time as the team fleshes out the project 
through phases of activity: requirements, design, development, testing, etc. 
 
120.    An Agile Project Manager suspects the Product Owner has prioritized the product 
backlog based on who they promised a particular feature to instead of prioritizing 
on value, cost, risk, and knowledge gained.  What is the best thing for the Agile 
Project Manager to do in this instance? 
 
a) Demand the Product Owner prioritize User Stories based on value, cost, risk, 
and knowledge gained. 
b) Ask the Product Owner open‐ended questions about what's behind the 
ranking of one User Story vs. another. 
c) Tell the project Sponsor that the Product Owner does not know how to 
prioritize User Stories correctly. 
d) Accept the Product Owner's prioritized backlog because he/she represents 
the customer's needs. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
78/PMI‐ACP Examination Boot Camp 

This page intentionally left blank.   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /79 

Correct Responses
Final Practice Exam 1
 
 

 
 
This section includes the correct responses to the 
questions, the rationale behind the correct 
responses, and book/chapter references where 
The practice exam correct  the question was obtained. 
responses include 
 
explanations and references 
to help you learn.    Make sure you read through the rationale on 
questions you get correct as well as questions you 
miss to solidify your learning.   
 
 

Final Practice Exam 1 Correct Responses


 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
80/PMI‐ACP Examination Boot Camp 

1.  Which of the following is used to describe the cadence of work that can be 
maintained indefinitely? 
a) Sustainable Pace 
b) Project Schedule 
c) Resource Allocation 
d) Continuous Integration 
 
Correct Response: A 
Sustainable pace is the cadence of work that can be maintained indefinitely by 
the Agile team. 
 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 8 
 
 
2.  Which of the following audiences was the Declaration of Interdependence created 
for? 
a) Software Development 
b) Project Team Members 
c) Project Leaders 
d) Project Stakeholders 
 
Correct Response: C 
The Declaration of Interdependence was developed with project leaders in mind. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 1 
 
3.  Which of the following Agile business objectives focuses on lowering technical debt? 
a) Continuous Innovation 
b) Reliable Results 
c) People and Process Adaptability 
d) Product Adaptability 
 
Correct Response: D 
Agile technical practices focus on lowering technical debt (improving the ability 
to adapt) as an integral part of the development process. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 1 
 
 
 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /81 

4.  An Agile team member is incorporating multiple team member view points and 
insights in order to resolve a conflict.  Which approach are they using? 
a) Smooth / Accommodate 
b) Compromise / Reconcile 
c) Collaborate / Problem Solve 
d) Force / Direct 
 
Correct Response: C 
Collaborate/Problem Solve is incorporating multiple view points and insights 
from differing perspectives; requires a cooperative attitude and open dialogue 
that typically leads to consensus and commitment. 
 
  ‐ PMBOK Guide, Chapter 9 
 
5.  An Agile team is working on a project to improve the way orders are processed for 
their customers by eliminating almost all of the manual intervention currently being 
used.  What dominant source of return is this project seeking? 
a) Retained Revenue 
b) Operational Efficiencies 
c) New Revenue 
d) Incremental Revenue 
 
Correct Response: B 
Operational efficiency considers the revenue a project will generate through 
process improvement. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 10 
 
6.  Which of the following factors is NOT taken into account when determining the 
length of a retrospective? 
a) Number of stories 
b) Complexity 
c) Team size 
d) Level of conflict or controversy 
 
Correct Response: A 
The number of user stories is not taken into account to determine length of a 
retrospective.  Length of the iteration, complexity, size of the team, and level of 
conflict or controversy are all considered. 
 
‐ Esther Derby & Diana Larsen, Agile Retrospectives, Chapter 1 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
82/PMI‐ACP Examination Boot Camp 

7.  Which Scrum role is responsible for initial and ongoing funding for the project? 
a) Product Owner 
b) Sponsor 
c) ScrumMaster 
d) Project Manager 
 
Correct Response: A 
The Product Owner achieves initial and ongoing funding for the project. 
 
 
8.  Which type of decision making approach is the most damaging to the team's ability 
to self‐organize? 
a) Unilateral decision making 
b) Compromising decision making 
c) Participatory decision making 
d) Collaborative decision making 
 
Correct Response: A 
Leaders at any level who are making more than three or four unilateral decisions 
a month are adversely impacting their team's ability to self‐organize. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products 
2nd Edition, Chapter 9 
 
9.  An Agile Coach is meeting with a team member and after listening begins to interpret 
what was said through their own view.  Based on the Levels of Listening from the 
school of coactive coaching, at what level is the Agile Coach listening? 
a) Level II ‐ Focused Listening 
b) Level III ‐ Global Listening 
c) Level IV ‐ Super Listening 
d) Level I ‐ Internal Listening 
 
Correct Response: D 
The Agile Coach who hears the speaker's words and only interprets them 
through their own lens is listening at Level I ‐ Internal Listening 
 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 3 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /83 

10.  One of the senior managers at your organization has asked you (the ScrumMaster) 
to complete an end‐of‐iteration summary at the conclusion of each sprint.  Should 
this type of report and documentation even be considered on an Agile project? 
a) No, this senior manager does not understand Agile practices.  You as the 
ScrumMaster need to let him know the rules of Agile. 
b) Yes, this request is acceptable on an Agile project and as the ScrumMaster 
you should delegate this responsibility to one of the team members. 
c) Yes, because the end‐of‐iteration summary can be helpful for communicating 
current information and can be used as a historical document for future use.  
As the ScrumMaster you should communicate what the senior manager has 
requested. 
d) No, this senior manager has been a problem throughout the entire project.  
Escalate this issue to your Product Owner and let him/her communicate to 
the senior manager that the summary will not be completed. 
 
Correct Response: C 
On some projects an end‐of‐iteration summary can be useful, both in 
disseminating information and as a historical document for use in the future. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 21 
 
 
11.  What information is depicted on the vertical axis of a release burndown chart? 
a) Number of activities and tasks completed 
b) Number of story points or ideal days remaining 
c) Number of major milestones completed 
d) Number of activities and tasks remaining 
 
Correct Response: B 
The vertical axis of a release burndown chart shows the number of story points 
(or the number of ideal days) remaining. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 19 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
84/PMI‐ACP Examination Boot Camp 

12.  Which of the following is the best team strategy to create early and regular delivery 
on a project? 
a) Hardest‐last strategy 
b) Worst‐things‐first strategy 
c) Simplest first, worst second strategy 
d) Most difficult first, easy second strategy 
 
Correct Response: C 
The repaired strategy is simplest first, worst second.  With one victory under its 
collective belt, the team is in a stronger position to attack the worst problem. 
 
‐ Alistair Cockburn, Agile Software Development, 2nd edition, Chapter 2 
 
13.  Which of the following techniques is NOT useful in helping multiple Agile teams 
work on the same project? 
a) Agile teams should establish a common basis for their estimates. 
b) On highly complex projects with many interteam dependencies, it can be 
helpful to incorporate feeding buffers into the plan. 
c) Multiple teams benefit from incorporating a rolling lookahead plan into their 
Release Planning. 
d) When multiple teams need to work together, it is useful to wait to add detail 
to user stories until later in the project planning. 
 
Correct Response: D 
When multiple teams need to work together, it is often useful to add detail to 
their user stories sooner. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 18 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /85 

14. During the Daily Scrum, two of the Scrum Team members get into a side 
conversation about what they are going to do this weekend.  What should happen in 
this instance? 
a) Scrum Team members are self‐organized and should correct the unabiding 
Scrum Team members. 
b) The ScrumMaster needs to remind the Scrum Team of the rule that only one 
person talks at a time during the Daily Scrum. 
c) The ScrumMaster should wait to speak with the Scrum Team members until 
the Daily Scrum is over. 
d) The ScrumMaster should escalate this issue to the Product Owner. 
 
Correct Response: B 
During the Daily Scrum, only one person talks at a time and there are no side 
conversations.  The ScrumMaster is responsible for ensuring the Scrum Team 
follows the rules. 
 
 
 
15.  Which of the following is used to document the economic feasibility study as a basis 
for authorization of additional project management activities? 
a) Project Charter 
b) Business Case 
c) Cost‐Benefit Analysis 
d) Vision Document 
 
Correct Response: B 
The business case is a documented economic feasibility study used to establish 
validity of the benefits of a selected component lacking sufficient definition and 
is used as a basis for the authorization of further project management activities. 
 
‐ Project Management Body of Knowledge, Glossary 
 
16.  Which of the following are NOT aspects of empirical process control? 
a) Adaptation 
b) Development 
c) Visibility 
d) Inspection 
 
Correct Response: B 
The three aspects of empirical process control are visibility, inspection, and 
adaptation. 
 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
86/PMI‐ACP Examination Boot Camp 

17.  An Agile team is surveying users to determine which features to include in their 
project.  They receive feedback about a feature the customers expect to have and 
they want more and more of these types of features in the product.  According to 
the Kano Model of Customer Satisfaction, which category have the customers 
described? 
a) Exciters and delighters 
b) Linear features 
c) Threshold features 
d) Dissatisfiers 
 
Correct Response: B 
Linear features are ones the customer will generally expect and are often known 
as satisfiers.  The more satisfiers the better. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 11 
 
18.   A project retrospective is scheduled to last an entire day.  One of the stakeholders 
asks if they can drop‐in and dropout throughout the day.  What should the 
retrospective leader tell this stakeholder? 
a) Tell the stakeholder full‐time attendance is necessary because each part of 
the retrospective structure builds on the preceding portion. 
b) Tell the stakeholder it's okay to drop‐in and dropout since their feedback is 
important. 
c) Ask the stakeholder to still attend the retrospective and bring their other 
work with them to do in private. 
d) Reschedule the retrospective until every participant's schedule allows for 
full‐day attendance. 
 
Correct Response: D 
Drop‐ins slow down the retrospective process; dropouts send a different, often 
puzzling message.  Set the expectation for full‐time attendance as recommended 
in this answer choice.  A key word in the question is project.  If this was Iteration 
retrospective then the answer would be different.  In that case rescheduling 
might not be a good option.  Remember to read the questions carefully. 
 
‐ Esther Derby & Diana Larsen, Agile Retrospectives, Chapter 9 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /87 

19.   Which of the following is used to measure the amount of time that passes? 
a) Elapsed time 
b) Bottom‐up Estimates 
c) Top‐down Estimates 
d) Ideal time 
 
Correct Response: A 
Elapsed time is the amount of time that passes on a clock or on a calendar. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 5 
 
20.   Which of the following testing is NOT performed in Agile projects? 
a) Automated regression testing 
b) Unit testing 
c) End‐to‐end testing 
d) Manual regression testing 
 
Correct Response: D 
The Agile team doesn't perform any manual regression testing. 
 
 
21.   Which of the following plans is the most precise? 
a) Release Plan 
b) Daily Plan   
c) Iteration Plan 
d) Project Plan 
 
Correct Response: B 
The daily plan, as committed to by each participant in a team's daily meeting is 
fairly precise. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 22 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
88/PMI‐ACP Examination Boot Camp 

22.   Which Scrum artifact evolves as the product, the requirements, and the 
environment in which it will be used evolves? 
a) Sprint Backlog 
b) Gantt Chart 
c) Burndown Chart 
d) Product Backlog 
 
Correct Response: D 
The Product Backlog evolves as the product and the environment in which it will 
be used evolves. 
 
 
23.    Which of the following is NOT a key value for an Agile Leader? 
a) Leading the team over managing tasks. 
b) Delivering value over meeting constraints. 
c) Managing tasks over leading the team. 
d) Adapting to change over following a plan. 
 
Correct Response: C 
Managing tasks is not a key value for Agile Leaders, while leading the team is a 
key value. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 1 
 
24.    Which of the following approaches is NOT used to estimate velocity? 
a) Run an iteration 
b) Use historical values 
c) Make a forecast 
d) Compare to other Agile teams 
 
Correct Response: D 
Comparing velocities between Agile teams is not a good indicator of estimating 
velocity and should be avoided. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 16 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /89 

25.    What type of meeting does the Scrum Team use to synchronize the work of all 
Team members and to schedule any meetings the Team needs to forward its 
progress? 
a) Sprint Review 
b) Sprint Retrospective 
c) Sprint Planning Meeting 
d) Daily Scrum 
 
Correct Response: D 
The Daily Scrum synchronizes the work of all Team members daily and is used to 
schedule any meetings the Team needs to forward its progress. 
 
 
26.    Which of the following is a common root cause analysis technique used by Agile 
teams? 
a) Value Stream Mapping 
b) The Five Whys 
c) Monte Carlo Simulation 
d) Six Sigma 
 
Correct Response: B 
The “Five Whys” is a common root cause analysis technique used on Agile 
projects. 
 
‐ Alan Shalloway, Guy Beaver, & James Trott, Lean‐Agile Software 
Development, Chapter 1 
 
27.    Which Scrum role is responsible for being self‐managed and self‐organized? 
a) Scrum Team 
b) ScrumMaster 
c) Project Manager 
d) Product Owner 
 
Correct Response: A 
Scrum Teams are self‐managing, self‐organizing, and cross functional. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
90/PMI‐ACP Examination Boot Camp 

28.    When the person paying for a project requests a written report of the project 
retrospective, which role is responsible for creating the report? 
a) The ScrumMaster or Agile Project Manager 
b) The Product Owner 
c) The Team Lead 
d) The Team 
 
Correct Response: D 
The person paying for a large retrospective may want a written report. The 
report should come from the team, not the retrospective leader. As part of the 
closing, decide who will create the report. When a retrospective leader writes 
the report, it reduces team ownership.  (key word in the question is project) 
 
‐ Esther Derby & Diana Larsen, Agile Retrospectives, Chapter 9 
 
29.    An Agile team working on their estimates decides to use a new technique where 
they compare a user story against a couple of other stories that have been 
estimated.  What technique is the team using? 
a) Triangulation 
b) Expert opinion 
c) Disaggregation 
d) PERT 
 
Correct Response: A 
Triangulation involves comparing the story being estimated against a couple of 
other stories that have already been estimated. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 6 
 
30.    What should the Agile team do if the executive sponsor is not attending the 
iteration demos? 
a) Ask the Product Owner to fill‐in for the Executive Sponsor. 
b) Keep the iteration demos short and have the Product Owner conduct a 
private demo at least once a month whenever the Executive Sponsor cannot 
attend. 
c) Request a new Executive Sponsor. 
d) Nothing, the customer's feedback is the most important feedback needed for 
the demo. 
 
Correct Response: B 
You can increase the likelihood of the Executive Sponsor attending by keeping 
the demo short.  If the Executive Sponsor doesn't come, conduct a private demo 
at least once a month. 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /91 

31.    Once an Agile team has completed an iteration, when is the ideal time to hold an 
iteration retrospective? 
a) Right after a release 
b) Right before iteration planning 
c) Right after iteration planning 
d) Right before a release 
 
Correct Response: B 
Holding your iteration retrospective right before iteration planning is ideal. 
‐ Esther Derby & Diana Larsen, Agile Retrospectives, Chapter 1 
 
32.    An Agile team is using an estimating technique that involves the Product Owner 
reading the description of the user story and answering questions from the team.  
The team members then privately select a card representing their estimate and 
reveal them simultaneously.  What estimating technique is the team using? 
a) Triangulation 
b) Planning Poker 
c) Storyboarding 
d) PERT 
 
Correct Response: B 
The team is playing planning poker that combines expert opinion, analogy, and 
disaggregation into one estimating approach. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 6 
 
33.    During a Sprint the Scrum Team completed all of the tasks early.  What should be 
done in this instance? 
a) Nothing should be done; the Scrum Team has accomplished their velocity for 
this Sprint. 
b) The Scrum Team should consult with each other as to which additional 
Product Backlog items can be added to this Sprint. 
c) The Scrum Team should consult with the ScrumMaster as to which additional 
Product Backlog items can be added to this Sprint. 
d) The Scrum Team should consult with the Product Owner as to which 
additional Product Backlog items can be added to this Sprint. 
 
Correct Response: D 
When the Scrum Team determine they can address more Product Backlog during 
the Sprint than it selected during the Sprint Planning meeting, it can consult with 
the Product Owner on which additional Product Backlog items can be added to 
the Sprint. 
 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
92/PMI‐ACP Examination Boot Camp 

34.    Which of the following conflict resolution techniques is used to describe 
emphasizing areas of agreement rather than areas of difference? 
a) Collaborate / Problem Solve 
b) Compromise / Reconcile 
c) Force / Direct 
d) Smooth / Accommodate 
 
Correct Response: D 
The Smooth/Accommodate conflict resolution technique emphasizes areas of 
agreement rather than areas of difference; conceding one's position to the 
needs of others to maintain harmony and relationships? 
 
‐ Project Management Body of Knowledge Guide, Chapter 9 
 
35.    Why is it oftentimes dangerous to estimate in ideal days? 
a) Because it's easier to get started with estimating in story points than ideal 
days. 
b) Because ideal days are equal among team members. 
c) Because there is pressure to make an actual day closer to an ideal day. 
d) Because ideal day estimates do not decay. 
 
Correct Response: C 
Because ideal days are so easily understandable in some organizations there will 
be pressure to make an actual day closer to an ideal day. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 8 
 
36.    A project manager is presented with a different strategy for managing projects 
than the waterfall strategy he/she has been using for years.  The project manager 
decides not to try the new strategy.  Which failure mode has the project manager 
fallen into? 
a) Making mistakes 
b) Preferring to fail conservatively 
c) Inventing rather than researching 
d) Being creatures of habit 
 
Correct Response: B 
The project manager is afraid to try the risky new strategy and selected the 
normal conservative strategy, a guaranteed standard outcome which is the 
failure mode of preferring to fail conservatively rather than to risk succeeding 
differently. 
‐ Alistair Cockburn, Agile Software Development, 2nd edition, Chapter 2 
 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /93 

37.    What is the correct order for the Agile Project Management Delivery Framework? 
a) Explore‐Envision‐Speculate‐Close‐Adapt 
b) Envision‐Speculate‐Explore‐Adapt‐Close 
c) Initiate‐Plan‐Execute‐Control‐Close 
d) Explore‐Initiate‐Plan‐Adapt‐Close 
 
Correct Response: B 
The Agile Project Management Delivery Framework consists of Envision‐
Speculate‐Explore‐Adapt‐Close. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 5 
 
38.    Which of the following is NOT part of The Declaration of Interdependence? 
a) We increase return on investment by making process our focus. 
b) We boost performance through group accountability for results and shared 
responsibility for team effectiveness. 
c) We deliver reliable results by engaging customers in frequent interactions 
and shared ownership. 
d) We expect uncertainty and manage for it through iterations, anticipation, 
and adaptation. 
 
Correct Response: A 
We increase return on investment by making continuous flow of value our focus. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 1 
 
39.    Which of the following is used to describe a single‐page summary of key business 
and quality objectives, product capabilities, and project management information 
for the Envision phase? 
a) Project Management Plan 
b) Vision Document 
c) Scope Definition Document 
d) Project Data Sheet 
 
Correct Response: D 
The Project Data Sheet (PDS) is a single‐page summary of key business and 
quality objectives, product capabilities, and project management information 
from the Envision Phase. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 6 
 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
94/PMI‐ACP Examination Boot Camp 

40.    An Agile team estimated story points for the following user stories: 

User Story A  5 story points 
User Story B  3 story points 
User Story C  2 story points 
User Story D  1 story point 
 

The team's velocity in the prior sprint was 11.  Due to unforeseen risks in this 
sprint, the team was only able to finish User Stories A and B.  What is their velocity 
for this sprint? 
a) 3 
b) 8 
c) 11 
d) 0 
 
Correct Response: B 
If a story is done (coded, tested, and accepted by the Product Owner), the 
team earns all the points, but if anything on the story isn't done, they earn 
nothing. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 7 
 
41.    Which of the following is the correct order of phases used during a retrospective? 
a) Set the stage, Gather data, Generate insights, Decide what to do, and Close 
the retrospective 
b) Gather data, Set the stage, Generate insights, Decide what to do, and Close 
the retrospective 
c) Gather data, Set the stage, Generate insights, Decide what not to do, and 
Close the retrospective 
d) Generate insights, Gather data, Set the stage, Decide what not to do, Close 
the retrospective 
 
Correct Response: A 
The correct sequence of retrospective phases is: Set the stage, Gather data, 
Generate insights, Decide what to do, and Close the retrospective. 
 
‐ Esther Derby & Diana Larsen, Agile Retrospectives, Chapter 1 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /95 

42.    An Agile team is working on a project to encourage customers to purchase more 
licenses.  What dominant source of return is this project seeking? 
a) Retained Revenue 
b) Operational Efficiencies 
c) New Revenue 
d) Incremental Revenue 
 
Correct Response: D 
Incremental revenue considers the revenue a project will generate from current 
customers buying more copies or additional services. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 10 
 
43.    During the second week of a sprint the Product Owner asks the team to include a 
change to the functionality they are working on.  Is this considered good practice 
in Agile? 
a) Yes, this is acceptable in Agile practice. 
b) Yes, as long as the Product Owner okays this decision with the ScrumMaster. 
c) Yes, because the Product Owner determines the priorities based on 
customer and business needs. 
d) No, the Product Owner should document the change in the Product Backlog. 
 
Correct Response: D 
Changes and interruptions during a Sprint keep the adaptations from turning 
meaningful progress into floundering, as overadaptation overwhelms the 
project. 
 
 
44.    Who is responsible for driving Agile development? 
a) Customers and Product Managers 
b) Product Owner 
c) Scrum Team 
d) ScrumMaster 
 
Correct Response: A 
Customers and Product Managers drive Agile development. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 2 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
96/PMI‐ACP Examination Boot Camp 

45.    The Product Owner on an Agile team has asked the ScrumMaster to begin tracking 
individual velocity for the team.  Should this practice be implemented by the 
ScrumMaster? 
a) Yes, this is acceptable in Agile practice because it will help individuals 
become better at estimating and the Product Owner should be supported by 
the ScrumMaster in this practice. 
b) No, individuals should be given every incentive possible to work 
collaboratively as a team and the ScrumMaster should explain this rule to the 
Product Owner. 
c) Yes, because the Product Owner is responsible for the rules the Agile team 
follows and the ScrumMaster answers to the Product Owner. 
d) No, the Product Owner should not be changing the rules for the Agile team in 
the middle of a project.  It's okay to change the rules after the project ends. 
 
Correct Response: B 
Teams should not calculate or track individual velocity because this discourages 
collaboration and working together as a team.  The ScrumMaster is responsible 
for ensuring everyone follows Agile rules. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 20 
 
46.    Which of the following roles is responsible for eliminating waste in an Agile 
project? 
a) The Agile Leader 
b) The Product Owner 
c) The Team 
d) The Product Manager 
 
Correct Response: C 
The responsibility for eliminating waste lies with the team. 
 
‐ Alan Shalloway, Guy Beaver, & James Trott, Lean‐Agile Software 
Development, Chapter 9 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /97 

47.    During which meeting does the Scrum Team consider changing any of the rules of 
Scrum? 
a) Sprint Retrospective 
b) Sprint Planning   
c) Daily Scrum 
d) Sprint Review 
 
Correct Response: A 
If someone wants to change the rules of Scrum, use the Sprint retrospective 
meeting as a forum for discussion. 
 
 
48.    An Agile team and ScrumMaster are working together on the Release Plan.  Which 
of the following should be done during this planning process? 
a) Creating a plan that shows which team members will work on which user 
stories. 
b) Creating a plan that shows which team members will work on specific tasks. 
c) Selecting an iteration length. 
d) Creating a plan that shows how much the user stories will cost. 
 
Correct Response: C 
The other three responses are too detailed for Release Planning.   
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 13 
 
49.    Which of the following is the correct scope to consider for Agile projects? 
a) Articulated Product Vision 
b) Defined Requirements 
c) Project Scope Statement 
d) BHAGs ‐ Big Hairy Audacious Goals 
 
Correct Response: A 
The correct scope to consider for Agile projects is the articulated product vision ‐ 
a releasable product. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 4 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
98/PMI‐ACP Examination Boot Camp 

50.    Recently during the Daily Scrum meetings, there have been several chickens 
attending the meeting that have caused the meetings to exceed the 15‐minute 
limit.  What should be done in this instance? 
a) The ScrumMaster should escalate this issue to the Product Owner. 
b) The ScrumMaster needs to change the time of the Daily Scrum meeting so 
the chickens miss it. 
c) The ScrumMaster should ask the chickens to immediately leave the meeting. 
d) The ScrumMaster needs to limit the attendance so the meeting is orderly and 
focused. 
 
Correct Response: D 
If too many chickens attend the meeting, the ScrumMaster can limit attendance 
so the meeting can remain orderly and focused. 
 
 
51.    A template written in this form ‐ "As a <type of user>, I want <capability> so that 
<business value>" is used to create which of the following? 
a) Activities 
b) Epics 
c) Themes 
d) User Stories 
 
Correct Response: D 
It can be useful to think of a story generally fitting this form: "As a <type of 
user>, I want <capability> so that <business value>." 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 3 
 
52.    Which Scrum role creates the initial overall requirements, ROI objectives, and 
release plans? 
a) Scrum Team 
b) ScrumMaster 
c) Sponsor 
d) Product Owner 
 
Correct Response: D 
The Product Owner creates the project's initial overall requirements, return on 
investment (ROI) objectives, and release plans. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /99 

53.    During an iteration retrospective one of the team members, Kim is continuously 
talking about every point and is not allowing other team members to provide 
input/feedback.  What should the retrospective leader do first? 
a) Be direct by asking Kim to immediately leave the retrospective. 
b) Be indirect by showing Kim through your body language to tone it down. 
c) Be direct by asking Kim privately to talk less and listen more. 
d) Let the team members correct Kim since they are self‐organized. 
 
Correct Response: C 
The first response to Kim's behavior should be done in private since Kim may not 
be aware of the problem.   
 
‐ Esther Derby & Diana Larsen, Agile Retrospectives, Chapter 3 
 
54.    Once the Release Plan is done, how often should it be revisited and updated? 
a) Once the Release Plan is complete it doesn't need to be revisited unless a 
change control request is issued. 
b) The Release Plan should be revisited and updated with regular frequency ‐ 
after each iteration or as long as every 4‐6 weeks. 
c) The Release Plan should be revisited and updated every week. 
d) The Release Plan should be revisited and updated every day. 
 
Correct Response: B 
The Release Plan should be revisited and updated with some regular frequency ‐ 
this could be after each iteration or could go as long as 4‐6 weeks. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 13 
 
55.    Which of the following Scrum roles have the option to attend the Sprint 
Retrospective meeting? 
a) ScrumMaster 
b) Scrum Team 
c) Product Champion 
d) Product Owner 
 
Correct Response: D 
The Sprint Retrospective meeting is only attended by the Scrum Team, 
ScrumMaster, and the Product Owner.  The Product Owner is optional. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
100/PMI‐ACP Examination Boot Camp 

56.    Company XYZ has just begun using Scrum practices.  They recently had a meeting 
where customers and other key stakeholders were involved in functionality 
demonstrations.  Which type of meeting was being conducted? 
a) Sprint Retrospective 
b) Sprint Planning Meeting 
c) Sprint Review 
d) Daily Scrum 
 
Correct Answer: C 
A Sprint Review meeting sometimes includes demonstrations of functionality 
completed during that Sprint.  This is the best answer even though the Demo is 
frequently held as a separate meeting. 
 
 
57.    Which of the following is NOT performed during Iteration Planning? 
a) Individual task assignments are made. 
b) User stories are organized. 
c) User stories are decomposed into tasks. 
d) Tasks are estimated in ideal hours. 
 
Correct Response: A 
While planning an iteration, tasks are not allocated to specific individuals. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 14 
 
58.    Which of the following is the most important aspect of self‐organized teams? 
a) Self‐discipline 
b) Accountability 
c) Collaboration 
d) Respect 
 
Correct Response: C 
Growing and maturing effective Agile teams takes time and dedication to 
building relationships and encouraging collaboration.  This is the most important 
task of the project leader and team members. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 3 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /101 

59.    Which of the following roles is NOT considered a "pig"? 
a) ScrumMaster 
b) Project Stakeholders 
c) Product Owner 
d) Scrum Team 
 
Correct Response: B 
The Product Owner, ScrumMaster, and Team are considered to be pigs because 
they are committed to a project and have "skin in the game". 
 
 
60.    Which types of features should be developed first in an Agile project? 
a) Low‐value, high‐risk 
b) High‐value, low‐risk 
c) Low‐value, low‐risk 
d) High‐value, high‐risk 
 
Correct Response: D 
High‐value, high‐risk features should be developed first because they deliver the 
most value and working on them eliminates significant risks. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 9 
 
61.    Which of the following audiences was the Manifesto for Agile Software 
Development created for? 
a) Project Team Members 
b) Project Leaders 
c) Project Stakeholders 
d) Software Development 
 
Correct Response: D 
The Manifesto for Agile Software Development (Agile Manifesto) was developed 
with software development in mind. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 1 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
102/PMI‐ACP Examination Boot Camp 

62.    What time of day is best to hold the Daily Scrum meeting? 
a) First thing in the day 
b) Last thing in the day 
c) Before lunch 
d) After lunch 
 
Correct Response: A 
The Daily Scrum is best held first thing in the day so Scrum Team members are 
focused for the day. 
 
 
63.    The Product Owner is trying to determine which themes to select and fund for 
cash flow streams and decided to measure the amount of time required to earn 
back the initial investment by taking into account the time value of money.  Which 
way did the Product Owner evaluate the cash flow streams? 
a) Payback Period 
b) Internal Rate of Return (IRR) 
c) Net Present Value (NPV) 
d) Discounted Payback Period 
 
Correct Response: D 
Discounted payback period is the amount of time required to earn back the 
initial investment by taking into account the time value of money and applying 
the appropriate discount factor to each item in the cash flow stream. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 10 
 
64.    An Agile team has created a chart that includes a rectangular box for each theme 
depicting the name of the theme, the number of stories in the theme, the number 
of story points, and percentage of story points completed.  What is the name of 
this chart? 
a) Burndown Chart 
b) Burnup Chart 
c) Burndown Bar Chart 
d) Parking‐Lot Chart 
 
Correct Response: D 
A parking‐lot chart compresses a great deal of information into a small space by 
summarizing information about a release's themes in large boxes. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 19 
 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /103 

65.    Which of the following information radiators works best for an Agile team that has 
12 people? 
a) Paper 
b) Digital cameras 
c) Printing whiteboards 
d) Wall charts 
 
Correct Response: C 
Printing whiteboards work best for 12 people when it comes to communicating 
information. 
 
‐ Alistair Cockburn, Agile Software Development, 2nd edition, Chapter 3 
 
66.    When using Commitment‐Driven Iteration Planning, how long does is it typically 
take for a team to get a feel for how many hours they should plan for an iteration? 
a) Approximately 7 iterations 
b) Approximately 10 iterations 
c) Approximately 2 iterations 
d) 1 iteration 
 
Correct Response: C 
After as few as a couple of iterations, most teams begin to get a feel for 
approximately how many hours they should plan for an iteration. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 14 
 
67.    What is happening to an Agile project when the top of the bar is lowered on the 
burndown chart? 
a) Work has been added 
b) Work has been completed 
c) Work has been removed   
d) No work has been added to or removed from the release 
 
Correct Response: B 
Any time work is completed the top of the bar on a burndown chart is lowered. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 19 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
104/PMI‐ACP Examination Boot Camp 

68.    Which of the following is NOT a valid reason for terminating a Sprint? 
a) When business conditions change and the Sprint holds no value for the 
business. 
b) When the Scrum Team is interfered with during the Sprint by anyone outside 
the Scrum Team. 
c) When the ScrumMaster is controlling and directing the work of the Scrum 
Team. 
d) When the technology proves unworkable. 
 
Correct Response: C 
All of these are valid reasons except for when the ScrumMaster is controlling and 
directing the Sprint.  This instance requires coaching of the ScrumMaster, not 
termination of the Sprint. 
 
 
69.    Which of the following practices is considered to use line‐of‐sight‐and‐hearing 
learning? 
a) Scrum 
b) Lean Software Development 
c) Dynamic Systems Development Method (DSDM) 
d) eXtreme Programming (XP) 
 
Correct Response: D 
Pair programming has been repopularized through eXtreme Programming (XP) 
that provides line‐of‐sight‐and‐hearing learning. 
 
‐ Alistair Cockburn, Agile Software Development, 2nd edition, Chapter 2 
 
70.    An Agile team has created a list of the product's requirements, prioritized them 
and determined that not every feature will be delivered.  In fact, the team 
recommends that 30 percent of the effort of the project be considered optional.  
What is the Agile team doing? 
a) Creating a feeding buffer 
b) Creating a feature buffer 
c) Creating a schedule buffer 
d) Putting together a scope management plan 
 
Correct Response: B 
A feature buffer is created when a product's requirements are prioritized and it 
is acknowledged that not every feature may be delivered.  If time runs short, the 
schedule can still be met by dropping items in the feature buffer. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 17 
 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /105 

71.    Which Scrum role is responsible for prioritizing the order in which to discuss 
potential Scrum improvements during the Sprint Retrospective? 
a) ScrumMaster 
b) Product Owner 
c) Scrum Team 
d) Product Champion 
 
Correct Response: C 
The Scrum Team prioritizes in which order it wants to talk about the potential 
improvements during the Sprint Retrospective. 
 
 
72.    Which of the following techniques is used to split a story or feature into smaller, 
easier‐to‐estimate pieces? 
a) Triangulation 
b) Expert opinion 
c) Disaggregation 
d) Analogy 
 
Correct Response: C 
Disaggregation splits a story or feature into smaller, easier‐to‐estimate pieces by 
breaking the large story or feature down. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 6 
 
73.    The Product Owner is trying to determine which themes to select and fund for 
cash flow streams and decided to measure the amount of time required to earn 
back the initial investment.  Which way did the Product Owner evaluate the cash 
flow streams? 
a) Payback Period 
b) Internal Rate of Return (IRR) 
c) Net Present Value (NPV) 
d) Expected Monetary Value (EMV) 
 
Correct Response: A 
Payback period is the amount of time required to earn back the initial 
investment. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 10 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
106/PMI‐ACP Examination Boot Camp 

74.    Which of the following concepts refers to the creation of two zones in the room 
set‐up: one zone to maximize osmotic communication/information transfer and 
the second zone to provide a private place for team members to make phone calls, 
check email, and have a separate space? 
a) Osmotic Zone and Quiet Zone 
b) Osmotic Communication and The Cone of Silence 
c) Drafts and Hot Air 
d) Caves and Common 
 
Correct Response: D 
Caves and common refers to the creation of two zones in the room ‐ the 
common area is organized to maximize osmotic communication and information 
transfer.  The caves portion of the room is organized to give people a private 
place to do email, make phone calls, and take care of their need for separation. 
 
‐ Alistair Cockburn, Agile Software Development, 2nd edition, Chapter 3 
 
75.    An Agile team has determined they want to use Gantt charts for communicating 
the Agile plan.  Which of the following approaches do they need to avoid? 
a) Stopping at the feature level and not decomposing each user story into its 
constituent tasks. 
b) Showing each feature as taking the full length of the iteration in which it's 
scheduled. 
c) Not allocating resources to the identified features. 
d) Allocating resources to each of the identified features. 
 
Correct Response: D 
No resource allocations should be communicated on the Agile Gantt chart 
because the whole team is responsible for delivery of all features. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 21 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /107 

76.    Which of the following terms is used to describe a period of time that cannot be 
exceeded and within which an event or meeting occurs? 
a) Timebox 
b) Time limit 
c) Duration 
d) Sprint / Iteration 
 
Correct Response: A 
A timebox is a period of time that cannot be exceeded and within which an even 
or meeting occurs.  For example, a Daily Scrum is time‐boxed to 15 minutes and 
terminates at the end of those 15 minutes. 
 
 
77.    Which of the following numbers is assigned to tiny features? 
a) 1 
b) 0.5 
c) 0 
d) 0.25 
 
Correct Response: C 
Assigning zero values to tiny features helps teams size features appropriately 
and avoid having completion of the feature contribute toward its velocity 
calculations. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 6 
 
78.    Which of the following is NOT a benefit of moving QA closer to the front of the 
value stream? 
a) To reduce or eliminate delay 
b) To reduce or eliminate the need for testing 
c) To reduce or eliminate redundancy 
d) To reduce or eliminate miscommunication 
 
Correct Response: B 
Moving QA closer to the front of the value stream can reduce or eliminate 
redundancy, miscommunication, and delay. 
 
‐ Alan Shalloway, Guy Beaver, & James Trott, Lean‐Agile Software 
Development, Chapter 9 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
108/PMI‐ACP Examination Boot Camp 

79.    How long does a Sprint review meeting last? 
a) 1 hour 
b) 8 hours 
c) 4 hours 
d) It depends on the length of the Sprint and whether the Demo is included 
 
Correct Response: D 
At the end of the Sprint, a Sprint review meeting is held that sometimes includes 
the Demo of completed stories.  The Demo is sometimes held as a separate 
meeting. 
 
 
80.    When a team is using planning poker for estimating user stories, how many rounds 
does it usually take for the estimates to converge? 
a) As many rounds as it takes 
b) 7 rounds 
c) 5 rounds 
d) 2 rounds 
 
Correct Response: D 
In many cases, the estimates will converge by the second round; it rarely takes 
more than three rounds. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 6 
 
81.    Which of the following concepts is NOT part of simplicity? 
a) Delivery versus Compliance 
b) Generative Rules 
c) Barely Sufficient Methodology 
d) Prescriptive Principles 
 
Correct Response: D 
Practices when driven by guiding principles are generative, not prescriptive. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 2 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /109 

82.    Which of the following is used to describe the time from when the team begins 
work on a feature until that feature delivers value to users? 
a) Duration 
b) Schedule 
c) Project Plan 
d) Cycle Time 
 
Correct Response: D 
Cycle time is the time from when the team begins work on a feature (the start of 
a process) until that feature delivers value to users (the end of that process). 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 22 
 
83.    Company XYZ has just implemented Scrum practices.  The development team 
members on an Agile project are assigned tasks by the ScrumMaster according to 
their role, including analysis, design, coding, testing, and documentation, with a 
different team member fulfilling each role.  What approach is the team using? 
a) Scrum 
b) XP 
c) Test Driven Development 
d) Waterfall 
 
Correct Response: D 
The development team is using a waterfall way of thinking about their work 
instead of Agile practices. 
 
 
84.    In Lean, at what point does the team form, assign roles, determine logistics for 
meetings, and decide how to work together? 
a) During Iteration 1 
b) During Release Planning 
c) After the Project Charter has been approved 
d) During Iteration 0 
 
Correct Response: D 
Iteration 0 is the time to form and locate the team(s), assign roles, determine 
logistics, and decide how to work together. 
 
‐ Alan Shalloway, Buy Beaver, James Trott, Lean‐Agile Software 
Development, Chapter 6 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
110/PMI‐ACP Examination Boot Camp 

85.    The Product Owner is trying to determine which themes to select and fund for 
cash flow streams and decided to measure how much money each theme is 
expected to return in today's present value.  Which way did the Product Owner 
evaluate the cash flow streams? 
a) Payback Period 
b) Internal Rate of Return (IRR) 
c) Net Present Value (NPV) 
d) Discounted Payback Period 
 
Correct Response: C 
Net Present Value (NPV) is a measure of how much money a project/theme can 
be expected to return in today's present value. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 10 
 
86.    Which of the following constraints are NOT considered when using a tradeoff 
matrix? 
a) Risk 
b) Scope 
c) Schedule 
d) Cost 
 
Correct Response: A 
The tradeoff matrix indicates relative importance of the three constraints (scope, 
schedule, and cost) identified on the Agile triangle (value, quality, constraints). 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 6 
 
87.    Which role owns the learnings from a retrospective? 
a) The Agile Leader 
b) The Product Owner 
c) The Product Manager 
d) The Team 
 
Correct Response: D 
Retrospective learnings belong to the team, and team members.  The team needs 
to own them. 
 
‐ Esther Derby & Diana Larsen, Agile Retrospectives, Chapter 1 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /111 

88.    An Agile team is surveying users to determine which features to include in their 
project.  They receive feedback about a feature the customers would love to have 
in your product to differentiate your company from other companies and they are 
willing to pay extra for this feature.  According to the Kano Model of Customer 
Satisfaction, which category have the customers described? 
a) Exciters and delighters 
b) Linear features 
c) Threshold features 
d) Dissatisfiers 
 
Correct Response: A 
Exciters and delighters are features that provide great satisfaction, often adding 
a price premium to the product. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 11 
 
89.    During an iteration a developer runs into a problem and begins performing a rapid 
experiment to investigate.  What is the developer working on? 
a) Spike 
b) Feature 
c) Task 
d) Minimal Marketable Feature 
 
Correct Response: A 
A spike is a short exploration into some aspect of the system.  A developer 
typically writes code that will be discarded just to help understand the problem 
at hand. 
 
‐ Alan Shalloway, Buy Beaver, James Trott, Lean‐Agile Software 
Development, Chapter 8 
 
90.    How long should an iteration demo last? 
a) 1 hour 
b) 1/2 day 
c) 10‐30 minutes 
d) It depends on the length of the iteration. 
 
Correct Response: D 
The entire iteration demo might be 30 to 60 minutes per week of iteration.  It’s 
not a one‐size‐fits‐all length.  If its hard to get stakeholders to attend then a 
shorter demo may resolve this. 
 
 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
112/PMI‐ACP Examination Boot Camp 

91.    An Agile team is working on an enhancement project and adds new features to 
attract different customers.  What dominant source of return is this project 
seeking? 
a) Retained Revenue 
b) Operational Efficiencies 
c) New Revenue 
d) Incremental Revenue 
 
Correct Response: C 
New revenue considers the revenue the project will generate from new 
customers. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 10 
 
92.    When an Agile team is tailoring their documentation practices, which of the 
following should they be careful with? 
a) Level of ceremony 
b) Permanent documentation 
c) Working papers 
d) Zero or burdensome documentation 
 
Correct Response: D 
The issue isn't zero or burdensome documentation, it's what documentation 
contributes to delivery and what documentation is required for external 
compliance. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 6 
 
93.    At what point on an Agile project are stakeholders allowed to provide criticism, 
comments, or observations. 
a) During the Sprint 
b) During the Daily Scrum 
c) During the Sprint Review 
d) During the Sprint Retrospective 
 
Correct Response: C 
Stakeholders are free to voice any comments, observations, or criticisms 
regarding product functionality between presentations during the Sprint Review 
or Sprint Demo.  These two are sometimes held as one meeting called the Sprint 
Review. 
 
 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /113 

94.    Which of the following is used to describe technical debt? 
a) Partially done work 
b) Writing poor quality code that makes future changes difficult or not using 
learning to improve design 
c) Work‐in‐process (WIP) 
d) Extra features 
 
Correct Response: B 
Technical debt is writing poor quality code that makes future changes more 
difficult and not taking advantage of what you've recently learned about the 
system to improve the design. 
 
‐ Alan Shalloway, Buy Beaver, James Trott, Lean‐Agile Software 
Development, Chapter 6 
 
95.    In the second iteration of a project, the Agile team planned to do 20 story points of 
work.  During this iteration the Product Owner identified another 20 points of 
work that is needed in the release.  How would the additional 20 points of work 
appear in the burndown chart? 
a) As a change request 
b) As a burndown 
c) As scope creep 
d) As a burnup 
 
Correct Response: D 
The burndown chart may show a burnup because work has been added to the 
release. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 19 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
114/PMI‐ACP Examination Boot Camp 

96.    During an iteration the Agile project team forgot about an impending risk.  What 
should the Agile project team do next? 
a) Get the product team and development team together to create a risk 
register. 
b) Stop the iteration and include risk response strategies for the next iteration. 
c) Determine if this is a significant need that requires adding a supplementary 
practice. 
d) Ask the ScrumMaster what he/she recommends the team should do. 
 
Correct Response: C 
Team members and project leaders need to fight the tendency to add 
supplementary practices early ‐ they need to wait until a specific and significant 
need arises. 
 
‐ Jim Highsmith, Agile Project Management: Creating Innovative 
Products, 2nd edition, Chapter 6 
 
97.    An Agile team has created a margin of safety to their project schedule by adding to 
the sum of their estimates and removing local safety.  What is the Agile team 
doing? 
a) Padding their estimates 
b) Estimating using story points or ideal days 
c) Creating a schedule buffer 
d) Creating a feature buffer 
 
Correct Response: C 
A schedule buffer is a necessary margin of safety added to the sum of estimates 
from which local safety has been removed. 
 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 17 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /115 

98.    During a project retrospective several managers were in attendance and before 
team members had an opportunity to contribute regarding improvements, the 
managers began dominating and hijacking the agenda.  What is the best approach 
the retrospective leader can take to correct this situation? 
 
a) Let the managers contribute so the project gets back in control. 
b) Meet with managers before the next retrospective; coach them on 
appropriate participation, including signals to communicate when managers 
are being too assertive. 
c) Prompt the Product Owner to take control of the managers and their 
behavior. 
d) Ask the managers to listen since they are supposed to be observers during 
the retrospective and not participants of the retrospective. 
 
Correct Response: B 
The best approach is to be proactive.  Agile leaders coach others on the 
principles and rules of Agile.   
 
‐ Esther Derby & Diana Larsen, Agile Retrospectives, Chapter 3 
More often managers are not invited to the Iteration Retrospective. 
 
99.    An Agile project team is starting to identify and discuss their strengths and 
weaknesses and determine roles that best suit their abilities and needs.  Which of 
the following stages is the team encountering? 
a) Storming 
b) Performing 
c) Norming 
d) Forming 
 
Correct Response: C 
In the Norming stage, group members begin to identify their individual strengths 
and weaknesses, and seek roles that best fit their abilities and desires. 
 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 13 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
116/PMI‐ACP Examination Boot Camp 

100.  During a sprint one of the key stakeholders keeps providing instructions to one of 
the Scrum Team members.  What should be done in this instance? 
a) The ScrumMaster needs to remind the stakeholder of the Scrum rules and 
ask them to refrain from interrupting the Scrum Team member. 
b) The ScrumMaster should escalate this issue to the Product Owner. 
c) The ScrumMaster should allow the interruptions to continue because this 
shows collaboration. 
d) Scrum Team members are self‐organized and should correct the unabiding 
stakeholder. 
 
Correct Response: A 
The ScrumMaster needs to remove impediments for the Scrum Team and ensure 
Scrum rules are being followed. 
 
 
101.  Which of the following approaches is usually the best option to select when 
estimating velocity? 
  a)  Run an iteration 
  b)  Use historical values 
  c)  Make a forecast 
  d)  Compare to other Agile teams 
 
  Correct Response: A 
An ideal way to forecast velocity is to run an iteration (or two or three) and then 
estimate velocity from the observed velocity during the one to three iterations.  
This is the best way to predict velocity. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 16  
 
102.  Which of the following is FALSE regarding the core beliefs of Agile? 
a)   Working code is the most accurate way of seeing the progress of the 
development effort. 
b)   Groups working together minimizes delays as well as the loss of information 
between people. 
c)   You cannot know everything required to build a software product at the start 
of the project. 
d)  You can test at the end of a project and achieve the required quality. 
 
Correct Response: D 
Testing at the end of a project to achieve the required quality is a core belief of 
Waterfall. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Introduction 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /117 

103.  When an organization is moving toward Agile practices, which type of meeting 
tends to be challenged the most? 
a)   Daily Standup Meetings 
b)   Release Planning Meetings 
c)   Iteration Planning Meetings 
d)   Retrospective Meetings 
 
Correct Response: A 
The most contested meeting in an Agile setting is the daily standup.  Teams often 
complain that they feel as if this is a mechanism only in place so managers can 
micromanage. 
‐  Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 16 
 
104.  Which of the following conflict response modes is assertive and not cooperative? 
a)   Avoiding / Withdrawing 
b)   Forcing / Directing 
c)   Collaborating / Problem Solving 
d)   Compromising / Reconciling 
 
Correct Response: B 
The forcing / directing conflict response mode is assertive and not cooperative. 
‐ PMBOK Guide, Chapter 9 
 
105.   Which of the following practices does NOT use strict iteration lengths for the 
completion of stories? 
a)   Scrum 
b)   Kanban 
c)   eXtreme Programming 
d)   Lean‐Agile 
 
Correct Response: B 
Kanban systems do have periodic releasable timeframes, but don't use strict 
iteration lengths in which all stories are completed. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 8 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
118/PMI‐ACP Examination Boot Camp 

106.   Which of the following feedback forms is NOT valuable when using eXtreme 
Programming (XP)? 
a)   Feedback from automated tests. 
b)   Feedback from the continuous integration process. 
c)   Feedback during paired programming. 
d)   Feedback that is delayed. 
 
Correct Response: D 
XP teams value feedback, and the more immediate the feedback the better. 
‐ Mike Cohn, User Stories Applied, Appendix A 
 
107.   Which of the following is the best description of servant leadership? 
 
a)   Having the team serve and work for the project leader. 
b)   Ensuring the team serves each other by becoming self‐organized. 
c)   Having the project leader ensure that everyone has the resources to do his or 
her work and providing services to the team. 
d)   Ensuring the team serves and works for the customer. 
 
Correct Response: C 
Servant leadership is a style of project management where the leader provides 
services to the team and ensures that everyone has the resources to do his or 
her work. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 9 
 
108.    An Agile team is working on improving the product's design without changing 
externally visible functionality to make the product more reliable and adaptable.  
What is the Agile team doing? 
a)   Refactoring 
b)   Continuous Integration 
c)   Reducing Technical Debt 
d)   Team Code Ownership 
 
Correct Response: A 
Refactoring involves updating a product's internal components (improving the 
design), without changing externally visible functionality to make the product 
more reliable and adaptable. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 9 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /119 

109.   Which of the following best describes the planning process in Agile projects? 
a)   Following a rolling wave approach using top‐down planning. 
b)   Specifying requirements upfront. 
c)   Identifying tasks upfront and estimating those tasks. 
d)   Preparing a project scope document. 
 
Correct Response: A 
Agile plans follow more of a rolling wave approach using to‐down planning. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 1 
 
110.   The Product Owner on an Agile project has been attempting to micromanage the 
team by getting into the details of how team members are performing their work.  
What is the best thing the Agile Project Manager can do in this instance? 
 
a)   Explain to the Agile team the Product Owner has every right to micromanage 
the team. 
b)   Report the Product Owner's behavior to the Sponsor. 
c)   Coach the Product Owner to focus on how much work he/she asks the team 
to do, not on how they are doing it. 
d)   Ask the Product Owner to take Agile training. 
 
Correct Response: C 
When the Product Owner thinks he/she needs to get into the details of how 
team members are performing the work, coach him/her that their best control 
comes from how much he/she asks the team to do, not how they are doing it. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 5 
 
111.   Which of the following is the most powerful way of reporting the team's progress? 
a)   Demos of working software 
b)   Progress reports 
c)   Status meetings 
d)   Iteration retrospectives 
 
Correct Response: A 
Nothing is as powerful at demonstrating progress as working software.  Invite 
stakeholders to the demos. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
120/PMI‐ACP Examination Boot Camp 

112.   Which of the following is used to describe a fixed start date and a fixed end date 
for Agile teams to complete their work? 
a)   Duration 
b)   Timebox 
c)   Network Diagram 
d)   Gantt Chart   
 
Correct Response: B 
A timebox is a length of time with a fixed start date and a fixed end date in which 
Agile teams complete their work. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 3 
 
113.   Which of the following is NOT used as part of the empirical inspection and 
adaptation practices of Scrum? 
a)   Sprint Review 
b)   Daily Planning Meeting 
c)   Daily Scrum 
d)   Sprint Retrospective 
 
Correct Response: B 
The Sprint planning meeting, the Daily Scrum, the Sprint review, and the Sprint 
retrospective constitute the empirical inspection and adaptation practices of 
Scrum.  The Daily Scrum might be considered a Daily Planning Meeting but this is 
not standard terminology and Daily Scrum is a better term or Daily Standup. 
 
114.    An Agile team is experiencing different opinions, misunderstandings, and 
conflicting values.  According to the five levels of conflict, what level of conflict is 
this team experiencing? 
a)   Level 3 
b)   Level 1 
c)   Level 4 
d)   Level 5 
 
Correct Response: B 
At level 1 ‐ Problem to Solve, people have different opinions, misunderstanding 
may have happened, conflicting goals or values may exist, and team members 
likely feel anxious about the conflict in the air. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 9 
The team should get comfortable with this level of conflict as it leads to synergy.  
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /121 

115.    An Agile team is facing crunch time during a release and the Agile Project 
Manager made the decision to hold two‐a‐day standup meetings.  Is this 
considered good practice? 
a)   No, this process would need to be created and supported by the team, not 
because the Agile Project Manager is creating the process out of fear. 
b)   Yes, the Agile Project Manager knows and reinforces Agile principles. 
c)   No, the Agile Project Manager needs to conduct fewer daily standups during 
crunch time. 
d)   Yes, the Agile Project Manager is leading the Agile team to be successful 
during a stressful part of the release. 
 
Correct Response: A 
At release time, the team goes into crunch mode, so the manager assumes that 
because one daily standup is good, then two much be better.  It's fine if this is a 
process that the team creates and supports, but it's different if these two‐a‐days 
are created by the manager out of fear. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 13 
 
116.    The customer is having difficulty prioritizing a story.  Which of the following is the 
best choice in this situation? 
a)    Tell the customer you will determine the priorities. 
b)    Re‐estimate the story. 
c)    Consider splitting the story. 
d)    Ask the customer to flip a coin between the stories. 
 
Correct Response: C 
If a customer is having trouble prioritizing a story, the story may need to be split. 
‐ Mike Cohn, User Stories Applied, Chapter 9 
 
117.    During a sprint retrospective a team member states, "We need more people on 
our side; they're wrong, plain and simple".  According to the five levels of conflict, 
what level of conflict is this Agile team experiencing? 
a) Level 4 
b) Level 1 
c) Level 5 
d) Level 3 
 
Correct Response: A 
At level 4 ‐ Crusade, resolving the situation isn't good enough.  Team members 
believe the people on the "other side" of the issues will not change. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 9 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
122/PMI‐ACP Examination Boot Camp 

118.    An Agile team is using a signaling system in their scheduling process where a limit 
is set on WIP and new work is "pulled" through the system.  What practice is the 
Agile team using? 
a) Scrum 
b) Dynamic Systems Development Method 
c) Feature Driven Development 
d) Kanban 
 
Correct Response: D 
Kanban introduces a signaling system into the scheduling process in which a limit 
is set on WIP (depending on resources), and new work (stories or other work 
items) is introduced as in‐process work completes.  Work is "pulled" through the 
system (as an item is completed it pulls the next item off the backlog). 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 8 
 
119.    Which of the following is true about Agile projects? 
a) The triple constraints can be traded off for one another to correct for 
unknowns. 
b) A plan gets more accurate over time because it is constantly revised and 
trued up to the team's actual performance. 
c) Scope can be locked down with later discoveries being handled as change 
requests against the scheduled end date. 
d) A plan gets more accurate over time as the team fleshes out the project 
through phases of activity: requirements, design, development, testing, etc. 
 
Correct Response: B 
A plan gets more accurate over time because it is constantly revised and trued 
up to the team's actual performance. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 1 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /123 

120.    An Agile Project Manager suspects the Product Owner has prioritized the product 
backlog based on who they promised a particular feature to instead of prioritizing 
on value, cost, risk, and knowledge gained.  What is the best thing for the Agile 
Project Manager to do in this instance? 
a) Demand the Product Owner prioritize User Stories based on value, cost, risk, 
and knowledge gained. 
b) Ask the Product Owner open‐ended questions about what's behind the 
ranking of one User Story vs. another. 
c) Tell the project Sponsor that the Product Owner does not know how to 
prioritize User Stories correctly. 
d) Accept the Product Owner's prioritized backlog because he/she represents 
the customer's needs. 
 
Correct Response: B 
If you suspect something is amiss regarding the priorities of User Stories in the 
backlog, ask open (and powerful) questions about what's behind the ranking of 
one vs. another. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 5 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
124/PMI‐ACP Examination Boot Camp 

This page intentionally left blank.   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /125 

Final Practice Exam 2


 

 
 
Domain  Percentage of Items on 
the Test 

The exam is 3 hours long  Domain I.  Agile Principles and  16% 


with 120 questions.  You  Mindset 
will be scored on 100 of 
those questions.    Domain II.  Value‐Driven  20% 
Delivery 

Domain III.  Stakeholder  17% 
Engagement 

Domain IV.  Team  16% 
Performance  

Domain V.  Adaptive Planning  12% 

Domain VI.  Problem  10% 
Detection and Resolution 

Domain VII.  Continuous  9% 
Improvement 
 
The PMI‐ACPSM exam will have 120 questions; 20 of 
those questions will not count toward your pass/fail 
grade.  The other 100 questions will be scored and do 
count toward your pass/fail grade.  You will not be 
able to tell which questions count and which ones do 
not. 
 
You will have 3 hours to take the real exam.  Since the 
passing score is not made public, we encourage your 
goal score should be 82% or better.   
 
Use the following practice exam as a way to simulate 
the day of the exam. 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
126/PMI‐ACP Examination Boot Camp 

Final Practice Exam 2


 
1.   A team working in an Agile environment is assigned to a project where the customer 
is demanding some requirements documentation prior to signing a contract.  In 
which iteration should the team place this card? 
 
a) Iteration 1   
b) Iteration 0 
c) Any Iteration that fits the customer's needs 
d) It isn't necessary to complete a card for this work 
 
2.  Which of the following is considered to be FALSE regarding servant leaders? 
 
a) Educating others who interact with the team or affect the team's 
performance. 
b) Assigning roles, responsibilities, and tasks to the team. 
c) Removing impediments to the team's progress. 
d) Protecting the team from outside distractions. 
 
3.  Who is responsible for monitoring the eXtreme Programming (XP) team for burnout? 
 
a) The XP Team 
b) The XP Tracker 
c) The XP Customer   
d) The XP Coach 
 
4.  How long does a Sprint typically last? 
 
a) Maximum of 4 weeks 
b) As long as it takes 
c) 2‐4 months 
d) 1 week 
 
5.  Which of the following factors are typically considered first when prioritizing the 
development of new capabilities? 
 
a) Value and risk 
b) Value and cost 
c) Cost and risk 
d) Value and learning 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /127 

6.  Which of the following is used to describe the philosophy of preventing doing more 
than is absolutely necessary for documentation that must be submitted prior to 
obtaining project approval? 
 
a) Use Barely Sufficient 
b) Employ Just Enough 
c) Create a Functional Requirements Specification 
d) Prepare a Project Scope Document 
 
7.  Which of the following plans is subject to review and revision at the end of each 
iteration? 
 
a) Iteration Plan 
b) Product Plan 
c) Daily Plan   
d) Release Plan   
 
8.  The following chart was put together to estimate the number of hours left in the 
iteration.  What is the name of this chart?   
 
350

300

250
Hours Remaining

200

150
Hours Remaining
100

50

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Days
 
 
a) Daily Burnup Chart 
b) Iteration Burnup Chart 
c) Release Burndown Chart 
d) Daily Burndown Chart 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
128/PMI‐ACP Examination Boot Camp 

9.  Which of the following is NOT an example of an impediment that gets in the way of 
companies making the transition to Lean‐Agile?  
 
a) Teams are not well formed  
b) Integration is done at project's end  
c) Large batches of unprioritized requirements are pushed through the 
organization  
d) Teams are co‐located  
 
10.  The Product Owner on an Agile project does not know how to frame up releases or 
how to find out the real need of the customer.  What is the best thing for the Agile 
Project Manager to do in this instance? 
 
a) Fill‐in for the Product Owner until he/she can get up‐to‐speed. 
b) Sugarcoat the Product Owner's shortcomings to the Agile team and key 
stakeholders. 
c) Get help from the Product Owner's manager and the project Sponsor. 
d) Coach the Product Owner on how to fulfill their role. 
 
11.  What type of tool does an Agile team use to organize and visualize their work? 
 
a) Task Board 
b) Burnup Chart 
c) Burndown Chart 
d) WBS & Activity List 
 
12.  What are the primary benefits of retrospectives? 
 
a) Performing root cause analysis in order to fix issues. 
b) Affixing ownership and accountability. 
c) Allowing the team to go back to older more comfortable habits. 
d) Inspecting and adapting. 
 
13.  Which of the following is the best way to increase throughput? 
 
a) Minimizing the team size to concentrate efforts. 
b) Increasing the amount of projects each team member works on to ensure 
they are busy. 
c) Minimizing multitasking and reducing the number of projects for each team 
member. 
d) Increasing the amount of work‐in‐process. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /129 

14.  During a sprint retrospective a team member states, "Cody always forgets to check 
in his code".  According to the five levels of conflict, what level of conflict is this 
Agile team experiencing? 
 
a) Level 5 
b) Level 2 
c) Level 4 
d) Level 3 
 
15.  Which of the following is NOT an effective example of a closed story? 
 
a) A recruiter can manage job listings.   
b) A recruiter can review resumes from applicants to one of her ads. 
c) A recruiter can change the expiration date of an ad. 
d) A recruiter can delete an application that is not a good match for a job. 
 
16.  Which Scrum role is responsible for developing functionality? 
 
a) ScrumMaster 
b) Product Owner 
c) Project Manager 
d) Scrum Team 
 
17.  Which of the following Scrum values is used to describe committing, acting, being 
open, and expecting respect? 
 
a) Commitment 
b) Respect 
c) Courage 
d) Openness 
 
18.  Which of the following is NOT correct when favoring estimating in story points over 
estimating in ideal days? 
 
a) Story point estimates decay. 
b) My ideal days are not your ideal days. 
c) Story points help drive cross‐functional behavior. 
d) Estimating in story points typically is faster. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
130/PMI‐ACP Examination Boot Camp 

19.  In an iteration backlog visual control, how are the stories prioritized? 
 
a) Right to left 
b) Top to bottom 
c) Left to right 
d) Bottom to top 
 
20.  During a retrospective the team is discussing whether to change their standup time 
to 10 a.m.  Throughout the conversation, you notice most of the team has spoken 
and no one has been talked over or ignored.  The general energy of the group feels 
upbeat, and it seems they are in sync with one another.  As the Agile Project 
Manager, which approach is best in this situation? 
 
a) Implement the change 
b) Get approval from upper management before making the change 
c) Tell the team they cannot change the time until the next project 
d) Do a consent check 
 
21.  According to the PMBOK® Guide, which of the following is used to describe keeping 
the delivery team together from iteration to iteration, with each delivered 
increment, an enhancement and/or evolution of the previous increment? 
 
a) Incremental Delivery 
b) Project Life Cycle Development 
c) Evolutionary Delivery 
d) Progressive Elaboration 
 
22.  How long does a Sprint planning meeting last? 
 
a) 1‐2 days 
b) 4 hours 
c) It depends on the length of the Sprint but not longer than 8 hours 
d) As long as it takes 
 
23.  Which of the following defines one or more iterations that build upon one another 
to complete a set of related functionality? 
 
a) Sprint 
b) Sprint Backlog 
c) Release 
d) Product Backlog 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /131 

24.  How frequently are iteration/sprint retrospectives conducted? 
 
a) At the end of the project. 
b) At the end of each release. 
c) At the end of each project phase. 
d) At the end of every iteration/sprint. 
 
25.  In eXtreme Programming (XP), how do the developers perform pair programming? 
 
a) Both developers code. 
b) One developer codes ‐ the driver, and the other developer thinks ‐ the 
navigator. 
c) Both developers code and then hand off their code to another pair to 
evaluate. 
d) Both developers think about strategic issues as they review code. 
 
26.  Who has to understand every User Story? 
 
a) Every team member 
b) The team member performing the work 
c) The ScrumMaster 
d) The Product Owner 
 
27.  A project team is using a business analyst to interact with the customers and create 
documents that are passed on to the development team.  The development team 
has little contact with the customers or business analyst.  Which environment is the 
team working in? 
 
a) Scrum 
b) eXtreme Programming 
c) Waterfall 
d) Lean‐Agile 
 
28.  Which of the following statements is FALSE regarding the twelve practices of 
eXtreme Programming (XP)? 
 
a) The "Planning Game" is used for release and iteration planning to 
collaboratively predict the future. 
b) XP teams support the quest for simple design by finding a metaphor that can 
be used for the whole system. 
c) The customer writes the stories, writes acceptance tests, and is on hand to 
answer questions as soon as they arise. 
d) A team is allowed to deliver half of a feature. 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
132/PMI‐ACP Examination Boot Camp 

29.  Which of the following contract types is best suited to an Agile project? 
 
a) Fixed‐Price Contracts 
b) Cost‐Reimbursable Contracts 
c) Incentive‐Fee Contracts 
d) Time and Material Contracts 
 
30.  Which of the following is used to describe a task in the Iteration Plan done 
specifically to gain knowledge or answer a question? 
 
a) Activity 
b) Feature 
c) Minimum Marketable Feature 
d) Spike 
 
31.  Which of the following is NOT part of the three distinct horizons Agile teams use to 
plan? 
 
a) Product Planning 
b) Iteration Planning 
c) Daily Planning 
d) Release Planning 
 
32.  A new Agile team has encountered team members doing email during their daily 
standup.  How should the ScrumMaster handle this situation? 
 
a) Leave the situation alone, it will more than likely resolve itself as the team 
gets used to daily standups. 
b) Intervene to model positive standup behavior and nip negative standup 
behavior. 
c) Individually pull aside the team members doing emails after the daily 
standup and coach them on correct behaviors. 
d) Report the team member's behavior to their manager and ask that manager 
to discuss the improper behavior with the team member. 
 
33.  For Agile software development projects, where is the acceptance criteria 
captured? 
 
a) On the back of the User Story card. 
b) In the UAT Test Plan. 
c) In the UAT Test Cases. 
d) In the UAT Defect Log. 
 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /133 

34.  Which of the following is FALSE regarding factors that work against the Scrum‐of‐
Scrums? 
 
a) Human nature 
b) Common goals 
c) Team motivation 
d) Team perspective 
 
35.  Which of the following acronyms is used to describe the four qualities of a well‐
groomed product backlog? 
 
a) INVEST 
b) SMART 
c) CRUD 
d) DEEP 
 
36.  Which of the following is NOT a common technique for Agile estimating? 
 
a) Disaggregation 
b) Expert opinion 
c) Analogy 
d) PERT 
 
37.  An Agile team has been taking two days to plan each two‐week iteration.  Is this 
considered good practice? 
 
a) No, typically 1‐2 hours per week of iteration is enough time to plan the 
iteration. 
b) Yes, the team should take as long as it needs to plan for the iteration. 
c) No, the Agile Project Manager should be planning the iteration, not the 
entire team. 
d) Yes, the team is ensuring they perform their due diligence in the planning 
process. 
 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
134/PMI‐ACP Examination Boot Camp 

38.  The following table lists all of the stories for an Agile project sorted in descending 
priority order: 
 
Story  Story Points 
A  6 
B  10 
C  10 
D  6 
E  2 
F  16 
G  10 
H  10 
I  10 
J  4 
 
The Agile team has a velocity of 26.  Assuming no iteration can be planned to have more 
than 26 story points in it, how would you allocate these stories to iterations? 
 
a) Iteration 1; Stories A, B, C; Story Points 26 
Iteration 2; Stories F, G; Story Points 26 
Iteration 3; Stories E, H, I, J; Story Points 26 
b) Iteration 1; Stories J, I, H; Story Points 24 
Iteration 2; Stories G, F; Story Points 26 
Iteration 3; Stories E, D, C; Story Points 18 
Iteration 4; Stories B, A; Story Points 16 
c) Iteration 1; Stories A, B, C; Story Points 26 
Iteration 2; Stories D, E, F; Story Points 24 
Iteration 3; Stories G, H, J; Story Points 24 
Iteration 4; Stories I; Story Points 10 
d) Iteration 1; Stories A, B, C; Story Points 26 
Iteration 2; Stories D, E, F, G (2 of the points); Story Points 26 
Iteration 3; Stories G (8 of the points), H, I (8 of the points) Story Points 26 
Iteration 4; Stories I (2 of the points), J; Story Points 6 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /135 

39.  A Product Owner that has received education on how to fulfill the role and declines 
the ScrumMaster's help on the thinking needed to prioritize the backlog shows up 
to the next sprint with the backlog unprepared.  What should the ScrumMaster do 
in this instance? 
 
a) Report the Product Owner to the project Sponsor. 
b) Cover for the Product Owner in this instance so the project can continue to 
progress. 
c) Ask management to replace the Product Owner. 
d) Let the consequences be what they will be; let the Product Owner fail. 
 
40.  Which of the following is NOT a valid reason for why planning poker works? 
 
a) Planning poker allows one expert to share their opinion. 
b) Planning poker is fun. 
c) Planning poker creates lively discussions which ensures estimators justify 
their estimates. 
d) Planning poker leads to better results because of averaging individual 
estimates. 
 
41.  Which of the following strategies is most effective in reducing technical debt?  
 
a) Perform just‐in‐time fixes to technical debt problems.  
b) Focus on technical debt early in the product development cycle and then 
avoid changes.  
c) Work faster on the project so the amount of technical debt incurred is less.  
d) Be dedicated to reduce technical debt early and often while the costs are 
low.  
 
42.  According to the Agile Manifesto, how frequently should working software be 
delivered? 
 
a) After every iteration 
b) From a couple of weeks to a couple of months 
c) Every two‐four weeks 
d) Once a month 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
136/PMI‐ACP Examination Boot Camp 

43.  When is the best time for a ScrumMaster to coach the Sponsor? 
 
a) Prior to the Sprint Review 
b) After the Sprint Review 
c) At the beginning of the project 
d) At the end of the project 
 
44.  Which of the following is NOT a key term for the definition of Agile? 
 
a) Time‐boxed 
b) Tasks 
c) Incremental 
d) Iterative 
 
45.  The customer and developers have gathered together to create estimates.  They 
brought the story cards, as well as additional blank note cards.  The customer 
selects a story at random from the stack and reads it to the developers.  The 
developers ask questions and write an estimate on a card, not yet revealing the 
estimate to the others.  When everyone is finished estimating, the estimators turn 
over their cards for all to see.  When the estimates differ, the high and low 
estimators explain their estimates and repeat the process until the estimates 
converge on a single estimate.  What estimating approach is the Agile team using? 
 
a) Planning Poker   
b) Wideband Delphi 
c) Triangulate 
d) Expert Judgment 
 
46.  Which of the following is the primary benefit of information radiators? 
 
a) It gives passersby's the opportunity to identify all of their questions before 
the next meeting. 
b) It allows for effective two‐way communication. 
c) It increases management's interruptions of the team. 
d) Passersby's don't need to ask questions because the information simply hits 
them as they pass. 
 
47.  Which of these tasks should NOT be included in the Iteration Plan? 
 
a) Tasks associated with testing. 
b) Tasks associated with documenting the product. 
c) Email tasks associated with the iteration. 
d) Meetings related to the story. 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /137 

 
48.  During an iteration, which of the following is the primary role of an Agile Project 
Manager? 
 
a) Educating others about Agile 
b) Assigning roles, responsibilities, and tasks to the team 
c) Preventing distractions 
d) Removing impediments 
 
49.  Which of the following conflict response modes is neither assertive nor 
cooperative? 
 
a) Competing 
b) Accommodating 
c) Compromising 
d) Avoiding 
 
50.  Which of the following is FALSE regarding the four levels of completion that code 
must go through in XP practice? 
 
a) Ready to demo to stakeholders. 
b) Builds and passes most tests. 
c) Ready to release to real users and customers. 
d) Broken. 
 
51.  Which of the following is a FALSE "bad smell" indicator that something is amiss in 
the project's application of user stories? 
 
a) Stories that don’t have a full description of details 
b) Goldplating 
c) Including user interface details too soon 
d) Splitting too many stories 
 
52.  Who is responsible for ensuring the most valuable functionality is produced first and 
built upon? 
 
a) Scrum Team 
b) ScrumMaster 
c) Product Owner 
d) Project Manager 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
138/PMI‐ACP Examination Boot Camp 

53.  In order to prevent an Agile team from reverting back to Waterfall and spend the 
entire first iteration doing nothing but analysis, which of the following would be 
most beneficial? 
 
a) Have the team create a Work Breakdown Structure (WBS). 
b) Coach the team to decompose the first iteration's User Stories into tasks. 
c) Deliver at least one feature in parallel with the required project approval 
documentation. 
d) Use Iteration 0 to perform the analysis work. 
 
54.  Which of the following is NOT a good example of a User Story? 
 
a) The user can undo up to fifty commands. 
b) The software will be released by November 30. 
c) The user will be prompted to save her work if she hasn't saved it for 10 
minutes. 
d) The user can export data to XML. 
 
55.  What output do stakeholders see at the end of every Sprint? 
 
a) New functionality 
b) Requirements 
c) Models 
d) Gantt charts 
 
56.  Which of the following is NOT correct when defining Agile planning? 
 
a) Encourages change. 
b) Is spread throughout the project. 
c) Is focused more on the planning than on the plan. 
d) Results in plans that are difficult to change. 
 
57.  Which of the following is one of the core beliefs of Agile? 
 
a) Working on one project at a time improves the productivity of the team. 
b) You can effectively have separate groups do analysis, design, code, and test. 
c) Customers can accurately tell you what they want at the start of the project. 
d) You don't need to get feedback from the customer until the end of the 
project. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /139 

58.  At level 3 of the five levels of conflict, which of the following is the best successful 
response option? 
 
a) Collaboration 
b) Compromising 
c) Accommodating 
d) Avoiding 
 
59.  Once a sprint begins, which role is allowed to add work to the sprint? 
 
a) The Customer 
b) The Team 
c) The Customer and the Team 
d) The ScrumMaster   
 
60.  Which Scrum artifact is used to define the work and tasks planned during the 
Sprint? 
 
a) Sprint Backlog 
b) Network Diagram 
c) Activity List 
d) Product Backlog 
 
61.  Which of the following factors should be considered when determining iteration 
length? 
 
a) The overhead of iterating 
b) The amount of certainty 
c) How soon a feeling of urgency is established 
d) How long priorities can remain unchanged 
 
62.  An Agile team of 8 members has been experiencing tremendous conflict and seems 
to have resolved the conflict, but not to the level you would have done as the Agile 
Project Manager.  What should you do in this instance? 
 
a) Intervene by walking the team through the conflict resolution tactics for 
Agile. 
b) Report the behavior to each of the team member's managers to have them 
resolve the situation. 
c) Discuss the situation with all 8 team members to get their perspective. 
d) Leave the team members alone, even though it wasn't done perfectly. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
140/PMI‐ACP Examination Boot Camp 

63.  In eXtreme Programming (XP), which of the following is a FALSE statement 
regarding the customer role? 
 
a) The XP customer role is responsible for prioritizing stories. 
b) The XP customer role is responsible for writing stories. 
c) The XP customer role is responsible for monitoring the team's use of XP 
practices. 
d) The XP customer role is responsible for writing and executing tests that 
demonstrate the stories were developed as expected. 
 
64.  How long does a Daily Scrum meeting last? 
 
a) 30 minutes 
b) 15 minutes 
c) 1 hour 
d) 2‐4 hours 
 
65.  Which of the following roles is responsible for keeping work‐in‐process (WIP) to a 
minimum? 
 
a) The Agile Project Manager 
b) The Team 
c) The Product Owner 
d) The Team Lead 
 
66.  When is the best time for a ScrumMaster to coach individual team members? 
 
a) Midsprint 
b) Beginning of the sprint 
c) End of the sprint 
d) Before each sprint begins 
 
67.  Which of the following strategies is the best way to handle a complex story? 
 
a) Disaggregate the story into a set of constituent stories. 
b) Triangulate the story. 
c) Turn this story into an epic. 
d) Split the story into two stories: one investigative and one developing the new 
feature. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /141 

68.  Which of the following is NOT one of the five failure modes to take into account 
when working with people on Agile projects? 
 
a) People make mistakes 
b) People are creatures of habit 
c) People tend to be consistent 
d) People prefer to fail conservatively 
 
69.  What is happening to an Agile project when the bottom of the bar is moved up on a 
burndown chart? 
 
a) Work has been added to the iteration 
b) This is normal on a burndown chart and shows the team is making progress 
c) Work has been removed from the iteration 
d) No work has been added to or removed from the iteration 
 
70.  Which of the following roles is critical for helping teams avoid waste? 
 
a) Each Team Member 
b) The Product Owner 
c) The Agile Project Manager 
d) The Team Lead 
 
71.  An Agile team member is underperforming on a project.  Who is responsible for 
confronting this team member about their performance? 
 
a) Any team member 
b) The ScrumMaster or Agile Project Manager 
c) The Product Owner 
d) The Team Lead 
 
72.  Which of the following is FALSE regarding the use of story points? 
 
a) Estimating story points is done by the customer to ensure proper 
prioritization. 
b) When a story (possibly an epic) is disaggregated into its constituent stories, 
the sum of the estimates for the individual stories does not need to equal the 
estimate of the initial story or epic. 
c) Your team's story points are not equivalent to my team's story points. 
d) A story may be disaggregated into constituent tasks.  The sum of the 
estimates for the tasks does not need to equal the estimate of the initial 
story. 
 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
142/PMI‐ACP Examination Boot Camp 

73.  During the sprint review, which role is insignificant (or, at least appears so from an 
outsider's point of view)? 
 
a) The Team Members 
b) The Stakeholders 
c) The ScrumMaster 
d) The Customers 
 
74.  An organization is planning on implementing Agile principles for their software 
development projects.  They have decided to adopt daily standup meetings and still 
keep their weekly status meetings.  Is this considered good practice? 
 
a) Yes, a daily standup meeting is for the team, and the status meeting is for the 
Agile Project Manager to determine status and progress. 
b) No, this practice would be redundant. 
c) No, the Agile meetings should replace existing ones because people are not 
supposed to attend Agile meetings and non‐agile meetings. 
d) Yes, a daily standup meeting is for the team to assess their progress, and the 
weekly status meeting is for the Agile Project Manager to discover 
impediments preventing team progress. 
 
75.  In Agile software development, who is best suited to write User Stories? 
 
a) The Team 
b) The Developer 
c) The Customer 
d) The ScrumMaster or Agile Project Manager 
 
76.  Which of these questions is NOT used by the Scrum Team during the Daily Scrum 
meeting? 
 
a) What did you get done yesterday that the ScrumMaster told you to do? 
b) What do you plan on doing on this project between now and the next Daily 
Scrum meeting? 
c) What impediments stand in the way of you meeting your commitments to 
this Sprint and this project? 
d) What have you done on this project since the last Daily Scrum meeting? 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /143 

77.  Which of the following is used to describe Scrum? 
 
a) An iterative development process for teams centered around several 
engineering practices, including test‐driven development, paired 
programming, and continuous integration. 
b) A lightweight Agile approach that focuses on eliminating waste, creating 
knowledge, building quality in, deferring commitment, optimizing the whole, 
delivering fast, and respecting people. 
c) A lightweight Agile process characterized by iterative and incremental 
approaches that are largely based on the Rapid Application Development 
(RAD) methodology. 
d) An Agile process characterized by self‐organizing, cross‐functional teams 
doing iterative development in what are called sprints. 
 
78.  An Agile team is working on a replacement product project that will take over 18 
months to complete.  They have put together a wave plan spanning several 
iterations.  Typically, how long should each wave last? 
 
a) 3 months 
b) 1‐2 weeks 
c) 1 month 
d) 2‐4 weeks 
 
79.  The Product Owner gets top billing for being the vision keeper on an Agile project.  
What other role is critical for articulating the vision from their point of view as to 
why the product is important to the company? 
 
a) Team Lead 
b) Agile Project Manager or ScrumMaster 
c) Product Manager 
d) Sponsor 
 
80.  In Agile software development, when are acceptance tests written? 
 
a) After the programmer has completed coding. 
b) At the end of each release. 
c) Prior to the end of each release. 
d) Before the programmer begins coding. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
144/PMI‐ACP Examination Boot Camp 

81.  Which Scrum role is responsible for ensuring everyone follows Scrum rules and 
practices? 
 
a) Product Owner 
b) ScrumMaster 
c) Scrum Team 
d) Project Sponsor 
 
82.  In which of the stages of team formation does real communication occur? 
 
a) Norming 
b) Performing  
c) Storming 
d) Forming 
 
83.  Which of the following statements does NOT support why task estimating on an 
Agile project should be done by a team? 
 
a) Because tasks are allocated to specific individuals during Iteration Planning. 
b) Hearing how long something is expected to take can help the team identify 
misunderstandings about a User Story or task. 
c) When the person who will do the work provides the estimate, the person's 
pride and ego may make him/her reluctant to admit later that an estimate 
was incorrect. 
d) Even though a specific individual will be the one to do a task, and even 
though he/she may know the most about that task, it does not mean that 
others have nothing to contribute. 
 
84.  Which type of decision making process works best for Agile teams? 
 
a) Compromising decision making 
b) Participatory decision making 
c) Unilateral decision making 
d) Top‐down decision making 
 
85.  Who is allowed to attend the Sprint Review meeting? 
 
a) Scrum Team 
b) ScrumMaster 
c) Scrum Team and Product Owner 
d) Scrum Team, Product Owner, and other stakeholders who want to attend 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /145 

86.  Which of the following is FALSE regarding Agile projects? 
 
a) Clients getting the business value they need is the only measure of success. 
b) Scope remains flexible, and changes of any kind are welcomed even late in 
the project. 
c) Only delivered end products indicate progress and value delivered. 
d) Controlling through the project plan is the responsibility of the Agile Project 
Manager. 
 
87.  An Agile team estimated a story to be eight points.  After working on the story the 
team discovered it was much larger than they originally thought and that it should 
have been estimated at twelve points.   How many points does this story contribute 
toward the team's velocity? 
 
a) 12 points 
b) 8 points 
c) 4 points 
d) 20 points 
 
88.  An Agile team has been varying their iteration lengths based upon their planning 
and estimating at the beginning of each iteration.  Is this considered good practice? 
 
a) Yes, it is okay to have two‐weeks for one iteration and three‐weeks for the 
next iteration. 
b) No, iteration lengths should be constant. 
c) Yes, because the team is learning their cadence. 
d) No, because the Agile Project Manager should tell the team how long their 
iterations will last. 
 
89.  Which of the following signals should the Agile Project Manager watch for during 
the last iteration before a release? 
 
a) Using the last iteration to capture final screenshots for marketing and 
training materials. 
b) Using the last iteration as a bug‐fixing opportunity. 
c) Using the last iteration to finalize release notes. 
d) Using the last iteration to do performance and load testing. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
146/PMI‐ACP Examination Boot Camp 

90.  Which of the following is NOT a role for eXtreme Programming (XP)? 
 
a) XP Tracker 
b) XP ScrumMaster 
c) XP Customer 
d) XP Programmer 
 
91.  Which of the following is used to coordinate interrelated teams working on 
different products? 
 
a) Daily Scrum Meetings 
b) Scrum‐of‐Scrums 
c) Project Portfolio Management 
d) Program Management Office (PMO) 
 
92.  The Agile team has discovered several bugs they determined can be fixed fairly 
quickly.  Which approach is the best way for the team to handle these bugs? 
 
a) Combine the bugs into one or more stories. 
b) Write a separate User Story for each bug. 
c) Ask the customer to write User Stories for these bugs so they can be 
prioritized. 
d) Don't worry about User Stories for the bugs and just complete the work. 
 
93.  An Agile team's daily standup meetings have been lasting close to 30 minutes and 
some of the team members have gradually stopped coming.  What is the best 
approach to take in this instance? 
 
a) The Agile Project Manager needs to lead all of the meetings from now on. 
b) Nothing should be done, as the team needs to work through any problems 
and issues in order to continue making progress. 
c) The Product Owner needs to tell the team they are discussing the wrong 
things during the daily standup meetings. 
d) The meeting facilitator needs to nudge the team to take further discussions 
offline from the daily standup meeting. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /147 

94.  At level 5 of the five levels of conflict, what is the one option that exists? 
 
a) Discuss how to peacefully resolve the situation. 
b) Separate the combatants so they don't hurt one another. 
c) Align with one side of the conflict or the other side. 
d) Conduct constructive disagreement discussions. 
 
95.  In Lean‐Agile, which of the following are the two biggest wastes in software 
development? 
 
a) Delays and building what is not needed. 
b) Bugs and interruptions. 
c) Smells and defects. 
d) Handoffs and partially done work. 
 
96.  How does an Agile team measure its rate of progress? 
 
a) Velocity 
b) Gantt Charts 
c) Activities completed 
d) Milestones 
 
97.  Which of the following is used to describe eXtreme Programming (XP)? 
 
a) An iterative development process for teams centered around several 
engineering practices, including test‐driven development, paired 
programming, and continuous integration. 
b) A lightweight Agile approach that focuses on eliminating waste, creating 
knowledge, building quality in, deferring commitment, optimizing the whole, 
delivering fast, and respecting people. 
c) A lightweight Agile process characterized by iterative and incremental 
approaches that are largely based on the Rapid Application Development 
(RAD) methodology. 
d) An Agile process characterized by self‐organizing, cross‐functional teams 
doing iterative development in what are called sprints. 
 
98.  Which of the following statements is FALSE regarding the benefits of story cards? 
 
a) Story cards are a formal medium for recording detailed requirements. 
b) Story cards act as agreements between customers and team members to 
discuss requirements during an iteration. 
c) Story cards are used for developing work estimates. 
d) Story cards are used to define acceptance tests. 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
148/PMI‐ACP Examination Boot Camp 

 
99.  An organization is considering using Agile principles in their workplace and is a 
global company.  It will be cost‐prohibitive to have their teams co‐located.  Which 
of the following statements needs to be shared with management to ensure they 
understand how the team will communicate? 
 
a) Technology and tools are adequate replacements for face‐to‐face 
communication. 
b) Tell management that Agile teams cannot work together without having 
face‐to‐face communication. 
c) Tools can help support communication, but cannot replace their 
conversations. 
d) Inform management that Agile teams can use written communication to 
replace oral communication. 
 
100.  What is the difference between a traditional Project Manager and an Agile Coach? 
 
a) A Project Manager's success equals the success of the project.  An Agile 
Coach's success equals the team's continual improvement and their pursuit 
of high performance. 
b) An Agile Coach plans and controls, supervising throughout.  A Project 
Manager guides the team. 
c) A Project Manager focuses on getting clients the business value they need.  
An Agile Coach is concerned with delivering on time, within budget, and on 
scope. 
d) An Agile Coach's success equals the success of the project.  A Project 
Manager's success equals the team's continual improvement and their 
pursuit of high performance. 
 
101.  Which of the following approaches works best when transitioning into Lean‐Agile? 
 
a) Top‐down leadership, Bottom‐up implementation 
b) Bottom‐up leadership, Top‐down implementation 
c) Bottom‐up leadership, Bottom‐up implementation 
d) Top‐down leadership, Top‐down implementation 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /149 

102.  In eXtreme Programming (XP), which of the following roles is allowed to change 
code? 
 
a) Any pair of developers can change the code. 
b) Only the developer who wrote the code can change the code. 
c) The code must be outsourced to a contractor in order to change the code. 
d) A User Story must be created to change the code so the developer who 
wrote the code can change it. 
 
103.  Which of the following techniques defines a highly structured brainstorming 
session used to generate ideas for an alternative work method to solve a particular 
challenge on Lean‐Agile projects? 
 
a) Problem Solving 
b) Kaizen 
c) Value Stream Mapping 
d) Visual Controls 
 
104.  Which Scrum role is allowed to change the Sprint Backlog? 
 
a) ScrumMaster 
b) Product Owner 
c) Scrum Team 
d) Any stakeholder 
 
105.  Which of the following is the ultimate goal of a story‐writing workshop? 
 
a) Write as many User Stories in as short a time as possible. 
b) Write the User Stories and elaborate on them. 
c) Write the User Stories and begin estimating the User Stories using story 
points. 
d) Write the User Stories, estimate story points, identify tasks to complete the 
User Story, and determine who is responsible. 
 
106.  In which type of project approach are stakeholders expected to be actively 
involved throughout the duration of the project? 
 
a) Agile 
b) Waterfall 
c) RUP 
d) System Development Life Cycle 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
150/PMI‐ACP Examination Boot Camp 

107.  Which of the following eXtreme Programming (XP) practices involves writing tests 
before code? 
 
a) Acceptance Test Driven Development 
b) Continuous Integration 
c) Test Driven Development 
d) Refactoring 
 
108.  Which of the following is FALSE regarding Lean visual controls? 
 
a) Can only be viewed by people involved with the project. 
b) Mirrors (at least some part of) the process the team is using. 
c) Controls the work‐in‐process. 
d) Describes the state of the work‐in‐process. 
 
109.  An organization is frequently pushing their Agile teams through crunch mode by 
requiring the team members to work overtime during every iteration.  Which Agile 
principle is this organization violating? 
 
a) Maximizing the amount of work not done. 
b) Working at a sustainable pace. 
c) Building projects around motivated individuals. 
d) Welcome changing requirements, even late in development. 
 
110.  When trying to predict the number of iterations remaining for an Agile team, 
which of the following should NOT be considered? 
 
a) The average (mean) velocity of the three fastest iterations 
b) The average (mean) velocity of the three slowest iterations 
c) The average (mean) velocity 
d) The velocity of the most recent iteration 
 
111.  Which of the five levels of conflict is the most constructive and is where an Agile 
team thrives? 
 
a) Level 5 
b) Level 1 
c) Level 3 
d) Level 2 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /151 

112.  In Lean‐Agile, which of the following is used to pull the work to be done based on 
what delivers the most value to the business? 
 
a) The Product Backlog 
b) The Iteration Backlog 
c) The Value Stream 
d) The Story Board 
 
113.  Which of the following is NOT a value of eXtreme Programming (XP)? 
 
a) Communication 
b) Continuous Integration 
c) Courage 
d) Feedback 
 
114.  Which Scrum role is responsible for planning the work? 
 
a) Product Owner 
b) ScrumMaster 
c) Scrum Team 
d) Team Lead 
 
115.  Which of the following Agile principles helps to decrease goldplating? 
 
a) The best architectures, requirements, and designs emerge from self‐
organizing teams. 
b) Working software is the primary measure of progress. 
c) Simplicity ‐ the art of maximizing the amount of work not done ‐ is essential. 
d) Business people and developers must work together daily throughout the 
project. 
 
116.  On Agile projects which of the following constraints is flexible? 
 
a) Time 
b) Cost 
c) Scope  
d) Resources 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
152/PMI‐ACP Examination Boot Camp 

117.  While working on an Agile project, a developer finds a challenging bug that she 
can't debug normally.  What is the best approach in this situation? 
 
a) Tag or Label 
b) Roll Back 
c) Time Travel 
d) Revert 
 
118.  When using eXtreme Programming (XP), when does the team integrate the work 
of multiple developers? 
 
a) At the end of the iteration. 
b) At the end of each release. 
c) At least daily. 
d) Once a week. 
 
119.  An Agile Project Manager mistakenly delegated tasks to the Agile team members 
during the daily standup meeting and midway through the day realized what 
happened.  What is the best option for the Agile Project Manager to use in this 
situation? 
 
a) Do nothing, Agile team members are used to changes and adaptations. 
b) Wait and see if the Agile team members notice.  If they don't, the Agile 
Project Manager should act as if nothing is wrong. 
c) Let the Product Owner know about the mistake in case team members 
complain to him/her. 
d) Own up to the impact of the mistake and apologize for it by telling the team 
which Agile principle was mistakenly undermined. 
 
120.  Chris, an Agile Project Manager, has been working on creating a tool to synch up 
project plans with status reports in order to manage the overwhelming work‐in‐
process (WIP).  Is using this tool considered good practice in Lean‐Agile? 
 
a) Yes, Chris is working on improving the process, which will then reduce WIP. 
b) No, this approach is not part of Lean principles. 
c) Yes, this tool will fix the problem and keep management satisfied. 
d) No, a better approach is to use the Five Whys to determine the root cause as 
to why there is so much WIP. 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /153 

Correct Responses
Final Practice Exam 2

 
 
This section includes the correct responses to the 
questions, the rationale behind the correct 
responses, and book/chapter references where 
The practice exam correct  the question was obtained. 
responses include 
 
explanations and references 
to help you learn.    Make sure you read through the rationale on 
questions you get correct as well as questions you 
miss to solidify your learning.   
 
 

   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
154/PMI‐ACP Examination Boot Camp 

Final Practice Exam 2 Correct Responses


 
1.   A team working in an Agile environment is assigned to a project where the customer 
is demanding some requirements documentation prior to signing a contract.  In 
which iteration should the team place this card? 
a) Iteration 1   
b) Iteration 0 
c) Any Iteration that fits the customer's needs 
d) It isn't necessary to complete a card for this work 
 
Correct Response: B 
In Iteration 0, a card should be created for preliminary work and placed in 
Iteration 0. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 7 
 
2.  Which of the following is considered to be FALSE regarding servant leaders? 
a) Educating others who interact with the team or affect the team's 
performance. 
b) Assigning roles, responsibilities, and tasks to the team. 
c) Removing impediments to the team's progress. 
d) Protecting the team from outside distractions. 
 
Correct Response: B 
Protecting the team from outside distractions, educating others who interact 
with the team or affect the team's performance, and removing impediments to 
the team's progress are all responsibilities of a servant leader. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 13 
 
3.  Who is responsible for monitoring the eXtreme Programming (XP) team for burnout? 
a) The XP Team 
b) The XP Tracker 
c) The XP Customer   
d) The XP Coach 
 
Correct Response: D 
An XP Coach is responsible for monitoring the team for burnout.  If the coach 
senses a team is burning out he/she will help the team shift back to working at a 
sustainable pace. 
‐ Mike Cohn, User Stories Applied, Appendix A 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /155 

4.  How long does a Sprint typically last? 
a) Maximum of 4 weeks 
b) As long as it takes 
c) 2‐4 months 
d) 1 week 
 
Correct Response: A 
Each Sprint is an iteration of 30 consecutive calendar days.  This is the Scrum 
Guide guidance.  Typically Sprints run from 2 to 4 weeks. 
 
5.  Which of the following factors are typically considered first when prioritizing the 
development of new capabilities? 
a) Value and risk 
b) Value and cost 
c) Cost and risk 
d) Value and learning 
 
Correct Response: B 
Because most projects are undertaken either to save or to make money, value 
and cost often dominate prioritization discussions, however, learning and risk on 
the project is critical if we are to prioritize optimally. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 9 
 
6.  Which of the following is used to describe the philosophy of preventing doing more 
than is absolutely necessary for documentation that must be submitted prior to 
obtaining project approval? 
a) Use Barely Sufficient 
b) Employ Just Enough 
c) Create a Functional Requirements Specification 
d) Prepare a Project Scope Document 
 
Correct Response: A 
If the documentation must all be submitted prior to obtaining project approval, 
use Alistair Cockburn's "barely sufficient" philosophy in order to prevent doing 
more than is absolutely necessary. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 14 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
156/PMI‐ACP Examination Boot Camp 

7.  Which of the following plans is subject to review and revision at the end of each 
iteration? 
a) Iteration Plan 
b) Product Plan 
c) Daily Plan   
d) Release Plan   
 
Correct Response: D 
The release plan is subject to review and revision at the end of each iteration. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 7 
 
8.  The following chart was put together to estimate the number of hours left in the 
iteration.  What is the name of this chart?   
 
350

300

250
Hours Remaining

200

150
Hours Remaining
100

50

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Days
 
 
a) Daily Burnup Chart 
b) Iteration Burnup Chart 
c) Release Burndown Chart 
d) Daily Burndown Chart  
 
Correct Response: D 
The daily burndown chart shows the estimated number of hours left in the 
iteration.  
‐ Mike Cohn, User Stories Applied, Chapter 11  
This could also be called the Iteration Burndown chart. 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /157 

9.  Which of the following is NOT an example of an impediment that gets in the way of 
companies making the transition to Lean‐Agile?  
a) Teams are not well formed  
b) Integration is done at project's end  
c) Large batches of unprioritized requirements are pushed through the 
organization  
d) Teams are co‐located  
 
Correct Response: D 
Teams that are not co‐located is one of the common impediments for companies 
making the transition to Lean‐Agile. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 10 
 
10.  The Product Owner on an Agile project does not know how to frame up releases or 
how to find out the real need of the customer.  What is the best thing for the Agile 
Project Manager to do in this instance? 
a) Fill‐in for the Product Owner until he/she can get up‐to‐speed. 
b) Sugarcoat the Product Owner's shortcomings to the Agile team and key 
stakeholders. 
c) Get help from the Product Owner's manager and the project Sponsor. 
d) Coach the Product Owner on how to fulfill their role. 
 
Correct Response: C 
When you encounter such a Product Owner, get help from the Product Owner's 
manager and the Sponsor.  Rely on these people to plug the holes in the Product 
Owner's business acumen or replace the Product Owner if the holes are too big 
to plug. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 5 
 
11.  What type of tool does an Agile team use to organize and visualize their work? 
a) Task Board 
b) Burnup Chart 
c) Burndown Chart 
d) WBS & Activity List 
 
Correct Response: A 
A task board ‐ which is usually a whiteboard or corkboard on a wall ‐ helps a 
team organize and visualize their work. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 20 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
158/PMI‐ACP Examination Boot Camp 

12.  What are the primary benefits of retrospectives? 
a) Performing root cause analysis in order to fix issues. 
b) Affixing ownership and accountability. 
c) Allowing the team to go back to older more comfortable habits. 
d) Inspecting and adapting. 
 
Correct Response: D 
Inspecting and adapting every iteration is key to the continued success of the 
Agile team. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 17 
 
13.  Which of the following is the best way to increase throughput? 
a) Minimizing the team size to concentrate efforts. 
b) Increasing the amount of projects each team member works on to ensure 
they are busy. 
c) Minimizing multitasking and reducing the number of projects for each team 
member. 
d) Increasing the amount of work‐in‐process. 
 
Correct Response: C 
Throughput can be greatly increased by minimizing multitasking. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 8 
 
14.  During a sprint retrospective a team member states, "Cody always forgets to check 
in his code".  According to the five levels of conflict, what level of conflict is this 
Agile team experiencing? 
a) Level 5 
b) Level 2 
c) Level 4 
d) Level 3 
 
Correct Response: D 
At level 3 ‐ Contest, team members pay attention to building their cases and they 
make overgeneralizations.  Discussion becomes either/or and blaming flourishes. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 9 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /159 

15.  Which of the following is NOT an effective example of a closed story? 
a) A recruiter can manage job listings.   
b) A recruiter can review resumes from applicants to one of her ads. 
c) A recruiter can change the expiration date of an ad. 
d) A recruiter can delete an application that is not a good match for a job. 
 
Correct Response: A 
A closed story is one that finishes with the achievement of a meaningful goal and 
that allows the user to feel she has accomplished something.  This story is not 
closed.  The word manage is very open ended. 
‐ Mike Cohn, User Stories Applied, Chapter 7 
 
16.  Which Scrum role is responsible for developing functionality? 
a) ScrumMaster 
b) Product Owner 
c) Project Manager 
d) Scrum Team 
 
Correct Response: D 
The Team is responsible for developing functionality. 
 
17.  Which of the following Scrum values is used to describe committing, acting, being 
open, and expecting respect? 
 
a) Commitment 
b) Respect 
c) Courage 
d) Openness 
 
Correct Response: C 
The Scrum value of courage includes having the courage to commit, to act, to be 
open, and to expect respect. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 2 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
160/PMI‐ACP Examination Boot Camp 

18.  Which of the following is NOT correct when favoring estimating in story points over 
estimating in ideal days? 
a) Story point estimates decay. 
b) My ideal days are not your ideal days. 
c) Story points help drive cross‐functional behavior. 
d) Estimating in story points typically is faster. 
 
Correct Response: A 
An estimate expressed in story points has a longer shelf life than an estimate in 
ideal days; therefore, story point estimates do not decay. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 8 
 
19.  In an iteration backlog visual control, how are the stories prioritized? 
a) Right to left 
b) Top to bottom 
c) Left to right 
d) Bottom to top 
 
Correct Response: C 
The stories in an iteration backlog visual control are prioritized from left to right. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 8 
 
20.  During a retrospective the team is discussing whether to change their standup time 
to 10 a.m.  Throughout the conversation, you notice most of the team has spoken 
and no one has been talked over or ignored.  The general energy of the group feels 
upbeat, and it seems they are in sync with one another.  As the Agile Project 
Manager, which approach is best in this situation? 
a) Implement the change 
b) Get approval from upper management before making the change 
c) Tell the team they cannot change the time until the next project 
d) Do a consent check 
 
Correct Response: D 
Use a consent check when it sounds like all voices that want to be heard have 
been heard and the group is generally moving forward toward a shared 
conclusion. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 9 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /161 

21.  According to the PMBOK Guide®, which of the following is used to describe keeping 
the delivery team together from iteration to iteration, with each delivered 
increment, an enhancement and/or evolution of the previous increment? 
a) Incremental Delivery 
b) Project Life Cycle Development 
c) Evolutionary Delivery 
d) Progressive Elaboration 
 
Correct Response: D 
The PMBOK® Guide refers to keeping the delivery team together from iteration 
to iteration, with each delivered increment an enhancement and/or evolution of 
the previous increment. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 2 
 
22.  How long does a Sprint planning meeting last? 
a) 1‐2 days 
b) 4 hours 
c) It depends on the Sprint cadence but not longer than 8 hours 
d) As long as it takes 
 
Correct Response: C 
Sprint planning meetings cannot last longer than 8 hours ‐ they are timeboxed to 
avoid too much hand‐wringing. 
 
 
23.  Which of the following defines one or more iterations that build upon one another 
to complete a set of related functionality? 
a) Sprint 
b) Sprint Backlog 
c) Release 
d) Product Backlog 
 
Correct Response: C 
A release comprises one or more (usually more) iterations that build upon one 
another to complete a set of related functionality. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 3 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
162/PMI‐ACP Examination Boot Camp 

24.  How frequently are iteration/sprint retrospectives conducted? 
a) At the end of the project. 
b) At the end of each release. 
c) At the end of each project phase. 
d) At the end of every iteration/sprint. 
 
Correct Response: D 
Unlike a project postmortem, or lessons learned, which is held once at the end of 
the entire project, iteration retrospectives are conducted at the end of every 
iteration. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 3 
 
25.  In eXtreme Programming (XP), how do the developers perform pair programming? 
a) Both developers code. 
b) One developer codes ‐ the driver, and the other developer thinks ‐ the 
navigator. 
c) Both developers code and then hand off their code to another pair to 
evaluate. 
d) Both developers think about strategic issues as they review code. 
 
Correct Response: B 
In pair programming, one person codes ‐ the driver, and the other person is the 
navigator, whose job is to think. 
 
 
 
26.  Who has to understand every User Story? 
a) Every team member 
b) The team member performing the work 
c) The ScrumMaster 
d) The Product Owner 
 
Correct Response: A 
Since the whole team commits to all the work in the sprint, each team member 
must understand every story. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 6 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /163 

27.  A project team is using a business analyst to interact with the customers and create 
documents that are passed on to the development team.  The development team 
has little contact with the customers or business analyst.  Which environment is the 
team working in? 
a) Scrum 
b) eXtreme Programming 
c) Waterfall 
d) Lean‐Agile 
 
Correct Response: C 
In a Waterfall environment, business analysts interact with the customers and 
create documents that are passed on to the development teams.  The 
development team has little contact with the customers or analysts.  
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 7 
 
28.  Which of the following statements is FALSE regarding the twelve practices of 
eXtreme Programming (XP)? 
a) The "Planning Game" is used for release and iteration planning to 
collaboratively predict the future. 
b) XP teams support the quest for simple design by finding a metaphor that can 
be used for the whole system. 
c) The customer writes the stories, writes acceptance tests, and is on hand to 
answer questions as soon as they arise. 
d) A team is allowed to deliver half of a feature. 
 
Correct Response: D 
One of the twelve principles is small releases; however a team is not allowed to 
deliver half of a feature. 
‐ Mike Cohn, User Stories Applied, Appendix A 
 
 
29.  Which of the following contract types is best suited to an Agile project? 
a) Fixed‐Price Contracts 
b) Cost‐Reimbursable Contracts 
c) Incentive‐Fee Contracts 
d) Time and Material Contracts 
 
Correct Response: D 
Although a time and materials contract (or "pay‐as‐you‐go") is better suited to 
an Agile project, it is not always possible to negotiate. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 14 

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
164/PMI‐ACP Examination Boot Camp 

30.  Which of the following is used to describe a task in the Iteration Plan done 
specifically to gain knowledge or answer a question? 
a) Activity 
b) Feature 
c) Minimum Marketable Feature 
d) Spike 
 
Correct Response: D 
A spike is a task [or a story] included in an Iteration Plan that is being undertaken 
specifically to gain knowledge or answer a question.  It is timeboxed. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 14 
 
31.  Which of the following is NOT part of the three distinct horizons Agile teams use to 
plan? 
a) Product Planning 
b) Iteration Planning 
c) Daily Planning 
d) Release Planning 
 
Correct Response: A 
The three distinct horizons Agile teams plan for are release planning, iteration 
planning, and daily planning. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 3 
 
 
32.  A new Agile team has encountered team members doing email during their daily 
standup.  How should the ScrumMaster handle this situation? 
a) Leave the situation alone, it will more than likely resolve itself as the team 
gets used to daily standups. 
b) Intervene to model positive standup behavior and nip negative standup 
behavior. 
c) Individually pull aside the team members doing emails after the daily 
standup and coach them on correct behaviors. 
d) Report the team member's behavior to their manager and ask that manager 
to discuss the improper behavior with the team member. 
 
Correct Response: B 
On a new team, when you teach them how standups work, err on the side of 
fixing it.  Intervene to model positive standup behavior, and nip negative 
standup behavior. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 6 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /165 

33.  For Agile software development projects, where is the acceptance criteria 
captured? 
a) On the back of the User Story card. 
b) In the UAT Test Plan. 
c) In the UAT Test Cases. 
d) In the UAT Defect Log. 
 
Correct Response: A 
The expectations of the project's users are best captured in the form of 
acceptance tests on the back of the User Story cards. 
‐ Mike Cohn, User Stories Applied, Chapter 1 
 
34.  Which of the following is FALSE regarding factors that work against the Scrum‐of‐
Scrums? 
a) Human nature 
b) Common goals 
c) Team motivation 
d) Team perspective 
 
Correct Response: B 
If you have a large project team with a common goal, Scrum‐of‐Scrums may 
work well. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 12 
 
 
35.  Which of the following acronyms is used to describe the four qualities of a well‐
groomed product backlog? 
a) INVEST 
b) SMART 
c) CRUD 
d) DEEP 
 
Correct Response: D 
The acronym DEEP acts as a memory‐jogger that a well‐groomed product 
backlog has four qualities: detailed appropriately, estimated, emergent, and 
prioritized. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 6 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
166/PMI‐ACP Examination Boot Camp 

36.  Which of the following is NOT a common technique for Agile estimating? 
a) Disaggregation 
b) Expert opinion 
c) Analogy 
d) PERT 
 
Correct Response: D 
The three most common techniques for Agile estimating are expert opinion, 
analogy, and disaggregation. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 6 
 
37.  An Agile team has been taking two days to plan each two‐week iteration.  Is this 
considered good practice? 
a) No, typically 1‐2 hours per week of iteration is enough time to plan the 
iteration. 
b) Yes, the team should take as long as it needs to plan for the iteration. 
c) No, the Agile Project Manager should be planning the iteration, not the 
entire team. 
d) Yes, the team is ensuring they perform their due diligence in the planning 
process. 
 
Correct Response: A 
Iteration planning sessions will vary in time required, depending on the type of 
project and length of the iteration, but 1‐2 hours per week of iteration would be a 
reasonable guide. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 2nd 
edition, Chapter 9 
 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /167 

38.  The following table lists all of the stories for an Agile project sorted in descending 
priority order: 
 
Story  Story Points 
A  6 
B  10 
C  10 
D  6 
E  2 
F  16 
G  10 
H  10 
I  10 
J  4 
 
The Agile team has a velocity of 26.  Assuming no iteration can be planned to have more 
than 26 story points in it, how would you allocate these stories to iterations? 
a) Iteration 1; Stories A, B, C; Story Points 26 
Iteration 2; Stories F, G; Story Points 26 
Iteration 3; Stories E, H, I, J; Story Points 26 
b) Iteration 1; Stories J, I, H; Story Points 24 
Iteration 2; Stories G, F; Story Points 26 
Iteration 3; Stories E, D, C; Story Points 18 
Iteration 4; Stories B, A; Story Points 16 
c) Iteration 1; Stories A, B, C; Story Points 26 
Iteration 2; Stories D, E, F; Story Points 24 
Iteration 3; Stories G, H, J; Story Points 24 
Iteration 4; Stories I; Story Points 10 
d) Iteration 1; Stories A, B, C; Story Points 26 
Iteration 2; Stories D, E, F, G (2 of the points); Story Points 26 
Iteration 3; Stories G (8 of the points), H, I (8 of the points) Story Points 26 
Iteration 4; Stories I (2 of the points), J; Story Points 6 
 
Correct Response: C 
Because the team expects a velocity of 26, no iteration can be planned to have 
more than 26 story points in it.  This means the second and third iterations are 
planned to have only 24 story points.  In the third iteration the team chose to 
include Story J over the higher priority Story I because Story I is too large to 
include in the third iteration. 
‐ Mike Cohn, User Stories Applied, Chapter 1 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
168/PMI‐ACP Examination Boot Camp 

39.  A Product Owner that has received education on how to fulfill the role and declines 
the ScrumMaster's help on the thinking needed to prioritize the backlog shows up 
to the next sprint with the backlog unprepared.  What should the ScrumMaster do 
in this instance? 
a) Report the Product Owner to the project Sponsor. 
b) Cover for the Product Owner in this instance so the project can continue to 
progress. 
c) Ask management to replace the Product Owner. 
d) Let the consequences be what they will be; let the Product Owner fail. 
 
Correct Response: D 
Once the Product Owner has received education on the role and been coached 
as appropriate, if he/she declines coaching and shows up to sprint planning with 
the backlog unprepared, then let the consequence be what they will be.  In other 
words, let the Product Owner fail. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 5 
 
40.  Which of the following is NOT a valid reason for why planning poker works? 
a) Planning poker allows one expert to share their opinion. 
b) Planning poker is fun. 
c) Planning poker creates lively discussions which ensures estimators justify 
their estimates. 
d) Planning poker leads to better results because of averaging individual 
estimates. 
 
Correct Response: A 
Planning poker brings together multiple expert opinions to do the estimating, 
not just one expert sharing their opinion. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 6 
 
41.  Which of the following strategies is most effective in reducing technical debt?  
a) Perform just‐in‐time fixes to technical debt problems.  
b) Focus on technical debt early in the product development cycle and then 
avoid changes.  
c) Work faster on the project so the amount of technical debt incurred is less.  
d) Be dedicated to reduce technical debt early and often while the costs are 
low.  
 
Correct Response: D 
The secret to long‐term technical debt reduction lies in doing it early and often 
while the cost is low. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 9 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /169 

42.  According to the Agile Manifesto, how frequently should working software be 
delivered? 
a) After every iteration 
b) From a couple of weeks to a couple of months 
c) Every two‐four weeks 
d) Once a month 
 
Correct Response: B 
Deliver working software frequently, from a couple weeks to a couple of months, 
with a preference to the shorter timescale. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 1 
 
 
43.  When is the best time for a ScrumMaster to coach the Sponsor? 
a) Prior to the Sprint Review 
b) After the Sprint Review 
c) At the beginning of the project 
d) At the end of the project 
 
Correct Response: A 
The best time to coach Sponsors occurs just prior to a sprint review. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 5 
 
44.  Which of the following is NOT a key term for the definition of Agile? 
a) Time‐boxed 
b) Tasks 
c) Incremental 
d) Iterative 
 
Correct Response: B 
Tasks are not a key term for the definition of Agile; feature‐based is a key term. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 2 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
170/PMI‐ACP Examination Boot Camp 

45.  The customer and developers have gathered together to create estimates.  They 
brought the story cards, as well as additional blank note cards.  The customer 
selects a story at random from the stack and reads it to the developers.  The 
developers ask questions and write an estimate on a card, not yet revealing the 
estimate to the others.  When everyone is finished estimating, the estimators turn 
over their cards for all to see.  When the estimates differ, the high and low 
estimators explain their estimates and repeat the process until the estimates 
converge on a single estimate.  What estimating approach is the Agile team using? 
a) Planning Poker   
b) Wideband Delphi 
c) Triangulate 
d) Expert Judgment 
 
Correct Response: B 
The Agile team is using the Wideband Delphi approach which uses an iterative 
approach to develop estimates. 
‐ Mike Cohn, User Stories Applied, Chapter 8 
 
46.  Which of the following is the primary benefit of information radiators? 
a) It gives passersby's the opportunity to identify all of their questions before 
the next meeting. 
b) It allows for effective two‐way communication. 
c) It increases management's interruptions of the team. 
d) Passersby's don't need to ask questions because the information simply hits 
them as they pass. 
 
Correct Response: D 
An information radiator displays information in a place where passersby can see 
it; they don't need to ask questions, the information simply hits them as they 
pass. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 8 
 
47.  Which of these tasks should NOT be included in the Iteration Plan? 
a) Tasks associated with testing. 
b) Tasks associated with documenting the product. 
c) Email tasks associated with the iteration. 
d) Meetings related to the story. 
 
Correct Response: C 
The iteration plan should identify only those tasks that add immediate value to 
the current project.  Emails are not directly related to developing the product. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 14 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /171 

48.  During an iteration, which of the following is the primary role of an Agile Project 
Manager? 
a) Educating others about Agile 
b) Assigning roles, responsibilities, and tasks to the team 
c) Preventing distractions 
d) Removing impediments 
 
Correct Response: D 
The Agile Project Manager's primary role within the iteration is to remove 
impediments that affect the team's progress. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 13 
 
49.  Which of the following conflict response modes is neither assertive nor 
cooperative? 
a) Competing 
b) Accommodating 
c) Compromising 
d) Avoiding 
 
Correct Response: D 
The avoiding conflict response mode is neither assertive nor cooperative. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 3 
 
 
50.  Which of the following is FALSE regarding the four levels of completion that code 
must go through in XP practice? 
a) Ready to demo to stakeholders. 
b) Builds and passes most tests. 
c) Ready to release to real users and customers. 
d) Broken. 
 
Correct Response: B 
Codes goes through these four levels: 1) broken; 2) builds and passes all tests; 3) 
ready to demo to stakeholders; and 4) ready to release to real users and 
customers. 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
172/PMI‐ACP Examination Boot Camp 

51.  Which of the following is a FALSE "bad smell" indicator that something is amiss in 
the project's application of user stories? 
a) Stories that don’t have a full description of details 
b) Goldplating 
c) Including user interface details too soon 
d) Splitting too many stories 
 
Correct Response: A 
Stories are not expected to have all the details defined until the story is being 
implemented. 
 
52.  Who is responsible for ensuring the most valuable functionality is produced first and 
built upon? 
a) Scrum Team 
b) ScrumMaster 
c) Product Owner 
d) Project Manager  
 
Correct Response: C 
The Product Owner is responsible for using the Product Backlog to ensure that 
the most valuable functionality is produced first and built upon. 
 
53.  In order to prevent an Agile team from reverting back to Waterfall and spend the 
entire first iteration doing nothing but analysis, which of the following would be 
most beneficial? 
a) Have the team create a Work Breakdown Structure (WBS). 
b) Coach the team to decompose the first iteration's User Stories into tasks. 
c) Deliver at least one feature in parallel with the required project approval 
documentation. 
d) Use Iteration 0 to perform the analysis work. 
 
Correct Response: C 
To prevent the team from reverting back to a Waterfall‐like approach where it 
spends the entire first iteration doing nothing but analysis, it is important to 
deliver at least one feature in parallel with the required project approval 
documentation. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 14 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /173 

54.  Which of the following is NOT a good example of a User Story? 
a) The user can undo up to fifty commands. 
b) The software will be released by November 30. 
c) The user will be prompted to save her work if she hasn't saved it for 10 
minutes. 
d) The user can export data to XML. 
 
Correct Response: B 
This is not a good story; it is a constraint that will need to be considered during 
release planning. 
‐ Mike Cohn, User Stories Applied, Chapter 1 
 
 
55.  What output do stakeholders see at the end of every Sprint? 
a) New functionality 
b) Requirements 
c) Models 
d) Gantt charts 
 
Correct Answer: A 
At the end of every Sprint, stakeholders see new functionality.  Models, 
requirements, and internal artifacts might be of use to developers, but they are 
never shown to stakeholders. 
 
56.  Which of the following is NOT correct when defining Agile planning? 
a) Encourages change. 
b) Is spread throughout the project. 
c) Is focused more on the planning than on the plan. 
d) Results in plans that are difficult to change. 
 
Correct Response: D 
Agile planning results in plans that are easily changed. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 1 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
174/PMI‐ACP Examination Boot Camp 

57.  Which of the following is one of the core beliefs of Agile? 
a) Working on one project at a time improves the productivity of the team. 
b) You can effectively have separate groups do analysis, design, code, and test. 
c) Customers can accurately tell you what they want at the start of the project. 
d) You don't need to get feedback from the customer until the end of the 
project. 
 
Correct Response: A 
Working on one project at a time in order to improve the productivity of the 
team is a core belief of Agile. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Introduction 
 
58.  At level 3 of the five levels of conflict, which of the following is the best successful 
response option? 
a) Collaboration 
b) Compromising 
c) Accommodating 
d) Avoiding 
 
Correct Response: C 
At level 3 ‐ Contest, accommodating is the best successful response option.  
Yielding to the other's view when the relationship is more important than the 
issue. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 9 
 
 
59.  Once a sprint begins, which role is allowed to add work to the sprint? 
a) The Customer 
b) The Team 
c) The Customer and the Team 
d) The ScrumMaster   
 
Correct Response: B 
Once the sprint starts, only the team may add work to the sprint. 
‐ Mike Cohn, User Stories Applied, Chapter 15 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /175 

60.  Which Scrum artifact is used to define the work and tasks planned during the 
Sprint? 
a) Sprint Backlog 
b) Network Diagram 
c) Activity List 
d) Product Backlog 
 
Correct Response: A 
The Sprint Backlog defines the work, or tasks, that a Scrum Team defines for 
turning the Product Backlog it selected for the Sprint into the work the Scrum 
Team plans to accomplish during the Sprint. 
 
61.  Which of the following factors should NOT be considered when determining 
iteration length? 
a) The overhead of iterating 
b) The amount of certainty 
c) How soon a feeling of urgency is established 
d) How long priorities can remain unchanged 
 
Correct Response: B 
The amount of uncertainty needs to be considered. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 15 
 
 
62.  An Agile team of 8 members has been experiencing tremendous conflict and seems 
to have resolved the conflict, but not to the level you would have done as the Agile 
Project Manager.  What should you do in this instance? 
a) Intervene by walking the team through the conflict resolution tactics for 
Agile. 
b) Report the behavior to each of the team member's managers to have them 
resolve the situation. 
c) Discuss the situation with all 8 team members to get their perspective. 
d) Leave the team members alone, even though it wasn't done perfectly. 
 
Correct Response: D 
Agile teams ‐ even new ones and broken ones ‐ can often navigate conflict by 
themselves, if team members navigate the conflict well enough, leave them 
alone. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 9 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
176/PMI‐ACP Examination Boot Camp 

63.  In eXtreme Programming (XP), which of the following is a FALSE statement 
regarding the customer role? 
a) The XP customer role is responsible for prioritizing stories. 
b) The XP customer role is responsible for writing stories. 
c) The XP customer role is responsible for monitoring the team's use of XP 
practices. 
d) The XP customer role is responsible for writing and executing tests that 
demonstrate the stories were developed as expected. 
 
Correct Response: C 
The XP coach is responsible for monitoring the team's use of the XP practices and 
gently nudging them back on track when they stray; the XP customer is not 
responsible to perform this work. 
‐ Mike Cohn, User Stories Applied, Appendix A 
 
64.  How long does a Daily Scrum meeting last? 
a) 30 minutes 
b) 15 minutes 
c) 1 hour 
d) 2‐4 hours 
 
Correct Response: B 
Every day, the team gets together for a 15‐minute meeting called a Daily Scrum. 
 
65.  Which of the following roles is responsible for keeping work‐in‐process (WIP) to a 
minimum? 
a) The Agile Project Manager 
b) The Team 
c) The Product Owner 
d) The Team Lead 
 
Correct Response: B 
The team must monitor how many stories are open and try to minimize that 
number (i.e., keep WIP to a minimum). 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 8 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /177 

66.  When is the best time for a ScrumMaster to coach individual team members? 
a) Midsprint 
b) Beginning of the sprint 
c) End of the sprint 
d) Before each sprint begins 
 
Correct Response: A 
Since Agile coaches protect the team's ability to focus by leaving them alone to 
work, midsprint is the perfect time for individual coaching. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 5 
 
67.  Which of the following strategies is the best way to handle a complex story? 
a) Disaggregate the story into a set of constituent stories. 
b) Triangulate the story. 
c) Turn this story into an epic. 
d) Split the story into two stories: one investigative and one developing the new 
feature. 
 
Correct Response: D 
The complex story is a User Story that is inherently large and cannot easily be 
disaggregated into a set of constituent stories; instead split the story into two 
stories: one investigative and one developing the new feature. 
‐ Mike Cohn, User Stories Applied, Chapter 2 
 
68.  Which of the following is NOT one of the five failure modes to take into account 
when working with people on Agile projects? 
a) People make mistakes 
b) People are creatures of habit 
c) People tend to be consistent 
d) People prefer to fail conservatively 
 
Correct Response: C 
The five failure modes take into account people being inconsistent. 
‐ Alistair Cockburn, Agile Software Development, 2nd edition, Chapter 2 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
178/PMI‐ACP Examination Boot Camp 

69.  What is happening to an Agile project when the bottom of the bar is moved up on a 
burndown chart? 
a) Work has been added to the iteration 
b) This is normal on a burndown chart and shows the team is making progress 
c) Work has been removed from the iteration 
d) No work has been added to or removed from the iteration 
 
Correct Response: C 
The bottom of the bar on a burndown bar chart is raised whenever work is 
removed from an iteration. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 19 
 
 
70.  Which of the following roles is critical for helping teams avoid waste? 
a) Each Team Member 
b) The Product Owner 
c) The Agile Project Manager 
d) The Team Lead 
 
Correct Response: C 
In Lean‐Agile, the Agile Project Manager is essential in helping teams avoid waste 
because teams often can't recognize waste in their own processes. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 11 
 
71.  An Agile team member is underperforming on a project.  Who is responsible for 
confronting this team member about their performance? 
a) Any team member 
b) The ScrumMaster or Agile Project Manager 
c) The Product Owner 
d) The Team Lead 
 
Correct Response: A 
Each and every member must take the initiative to confront others when they 
are not performing, or behaving, according to team rules. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 9 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /179 

72.  Which of the following is FALSE regarding the use of story points? 
a) Estimating story points is done by the customer to ensure proper 
prioritization. 
b) When a story (possibly an epic) is disaggregated into its constituent stories, 
the sum of the estimates for the individual stories does not need to equal the 
estimate of the initial story or epic. 
c) Your team's story points are not equivalent to my team's story points. 
d) A story may be disaggregated into constituent tasks.  The sum of the 
estimates for the tasks does not need to equal the estimate of the initial 
story. 
 
Correct Response: A 
Estimating stories needs to be done by the team, and the estimates are owned 
by the team rather than individuals. 
‐ Mike Cohn, User Stories Applied, Chapter 8 
 
73.  During the sprint review, which role is insignificant (or, at least appears so from an 
outsider's point of view)? 
a) The Team Members 
b) The Stakeholders 
c) The ScrumMaster 
d) The Customers 
 
Correct Response: C 
During the sprint review, the ScrumMaster is insignificant (or, at least, seems so 
from an outsider's point of view).  He/she sits in the back, away from the main 
action, observes and takes notes. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 6 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
180/PMI‐ACP Examination Boot Camp 

74.  An organization is planning on implementing Agile principles for their software 
development projects.  They have decided to adopt daily standup meetings and still 
keep their weekly status meetings.  Is this considered good practice? 
a) Yes, a daily standup meeting is for the team, and the status meeting is for the 
Agile Project Manager to determine status and progress. 
b) No, this practice would be redundant. 
c) No, the Agile meetings should replace existing ones because people are not 
supposed to attend Agile meetings and non‐agile meetings. 
d) Yes, a daily standup meeting is for the team to assess their progress, and the 
weekly status meeting is for the Agile Project Manager to discover 
impediments preventing team progress. 
 
Correct Response: C 
Asking the team to follow two different processes isn't efficient at all ‐ the Agile 
meetings should replace existing ones.   
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 16 
 
75.  In Agile software development, who is best suited to write User Stories? 
a) The Team 
b) The Developer 
c) The Customer 
d) The ScrumMaster or Agile Project Manager 
 
Correct Response: C 
Responsibility for writing stories resides with the customer and cannot be passed 
to the developers. 
‐ Mike Cohn, User Stories Applied, Chapter 7 
 
76.  Which of these questions is NOT used by the Scrum Team during the Daily Scrum 
meeting? 
a) What did you get done yesterday that the ScrumMaster told you to do? 
b) What do you plan on doing on this project between now and the next Daily 
Scrum meeting? 
c) What impediments stand in the way of you meeting your commitments to 
this Sprint and this project? 
d) What have you done on this project since the last Daily Scrum meeting? 
 
Correct Response: A 
This type of question is not used for Daily Scrum meetings using Agile processes. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /181 

77.  Which of the following is used to describe Scrum? 
a) An iterative development process for teams centered around several 
engineering practices, including test‐driven development, paired 
programming, and continuous integration. 
b) A lightweight Agile approach that focuses on eliminating waste, creating 
knowledge, building quality in, deferring commitment, optimizing the whole, 
delivering fast, and respecting people. 
c) A lightweight Agile process characterized by iterative and incremental 
approaches that are largely based on the Rapid Application Development 
(RAD) methodology. 
d) An Agile process characterized by self‐organizing, cross‐functional teams 
doing iterative development in what are called sprints. 
 
Correct Response: D 
Scrum is a popular Agile process used at the team level and is characterized by 
self‐organizing, cross‐functional teams doing iterative development in what are 
called sprints. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Introduction 
 
78.  An Agile team is working on a replacement product project that will take over 18 
months to complete.  They have put together a wave plan spanning several 
iterations.  Typically, how long should each wave last? 
a) 3 months 
b) 1‐2 weeks 
c) 1 month 
d) 2‐4 weeks 
 
Correct Response: A 
A wave (or milestone) plan spans several iterations and for software projects a 
typical length is three months, unless synchronization requirements dictate 
another length. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 8 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
182/PMI‐ACP Examination Boot Camp 

79.  The Product Owner gets top billing for being the vision keeper on an Agile project.  
What other role is critical for articulating the vision from their point of view as to 
why the product is important to the company? 
a) Team Lead 
b) Agile Project Manager or ScrumMaster 
c) Product Manager 
d) Sponsor 
 
Correct Response: D 
Although the Product Owner gets top billing for being the vision keeper, 
something magical happens when a Sponsor articulates that same vision to the 
team, including why the product is important to the company and to the team 
personally. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 5 
 
80.  In Agile software development, when are acceptance tests written? 
a) After the programmer has completed coding. 
b) At the end of each release. 
c) Prior to the end of each release. 
d) Before the programmer begins coding. 
 
Correct Response: D 
Acceptance tests are written before the programmer begins coding as part of the 
development process, not something that happens "after coding is done." 
‐ Mike Cohn, User Stories Applied, Chapter 6 
 
81.  Which Scrum role is responsible for ensuring everyone follows Scrum rules and 
practices? 
a) Product Owner 
b) ScrumMaster 
c) Scrum Team 
d) Project Sponsor 
 
Correct Response: B 
The ScrumMaster is responsible for ensuring that everyone follows Scrum rules 
and practices. 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /183 

82.  In which of the stages of team formation does real communication occur? 
a) Norming 
b) Performing  
c) Storming 
d) Forming 
 
Correct Response: C 
Storming is characterized by conflict and open, sometimes harsh dialogue and 
can be viewed as a sign that real communication is occurring. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 13 
 
83.  Which of the following statements does NOT support why task estimating on an 
Agile project should be done by a team? 
a) Because tasks are allocated to specific individuals during Iteration Planning. 
b) Hearing how long something is expected to take can help the team identify 
misunderstandings about a User Story or task. 
c) When the person who will do the work provides the estimate, the person's 
pride and ego may make him/her reluctant to admit later that an estimate 
was incorrect. 
d) Even though a specific individual will be the one to do a task, and even 
though he/she may know the most about that task, it does not mean that 
others have nothing to contribute. 
 
Correct Response: A 
Because tasks are not allocated to specific individuals during Iteration Planning, 
it is impossible to ask the specific person who will do the work. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 14 
 
84.  Which type of decision making process works best for Agile teams? 
a) Compromising decision making 
b) Participatory decision making 
c) Unilateral decision making 
d) Top‐down decision making 
 
Correct Response: B 
If we want to build adaptive teams and products, we need a participatory 
decision making process. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 9 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
184/PMI‐ACP Examination Boot Camp 

85.  Who is allowed to attend the Sprint Review meeting? 
a) Scrum Team 
b) ScrumMaster 
c) Scrum Team and Product Owner 
d) Scrum Team, Product Owner, and other stakeholders who want to attend 
 
Correct Response: D 
The Scrum Team, Product Owner, and any other stakeholders can attend the 
Sprint Review meeting.  
 
86.  Which of the following is FALSE regarding Agile projects? 
a) Clients getting the business value they need is the only measure of success. 
b) Scope remains flexible, and changes of any kind are welcomed even late in 
the project. 
c) Only delivered end products indicate progress and value delivered. 
d) Controlling through the project plan is the responsibility of the Agile Project 
Manager. 
 
Correct Response: D 
Controlling through the project plan is a traditional project management core 
underpinning. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 1 
 
87.  An Agile team estimated a story to be eight points.  After working on the story the 
team discovered it was much larger than they originally thought and that it should 
have been estimated at twelve points.   How many points does this story contribute 
toward the team's velocity? 
a) 12 points 
b) 8 points 
c) 4 points 
d) 20 points 
 
Correct Response: B 
This story contributes eight points to the velocity calculation, not twelve. 
‐ Mike Cohn, User Stories Applied, Chapter 11 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /185 

88.  An Agile team has been varying their iteration lengths based upon their planning 
and estimating at the beginning of each iteration.  Is this considered good practice? 
a) Yes, it is okay to have two‐weeks for one iteration and three‐weeks for the 
next iteration. 
b) No, iteration lengths should be constant. 
c) Yes, because the team is learning their cadence. 
d) No, because the Agile Project Manager should tell the team how long their 
iterations will last. 
 
Correct Response: B 
Iteration lengths should be constant; with different‐length iterations, team can't 
get into a good rhythm and velocity estimating becomes very difficult. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 9 
 
89.  Which of the following signals should the Agile Project Manager watch for during 
the last iteration before a release? 
a) Using the last iteration to capture final screenshots for marketing and 
training materials. 
b) Using the last iteration as a bug‐fixing opportunity. 
c) Using the last iteration to finalize release notes. 
d) Using the last iteration to do performance and load testing. 
 
Correct Response: B 
Just be sure that your team isn't using this last iteration solely as a bug‐fixing 
opportunity ‐ that's a signal that the team is committing to more features in each 
iteration than it has time to test. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 14 
 
90.  Which of the following is NOT a role for eXtreme Programming (XP)? 
a) XP Tracker 
b) XP ScrumMaster 
c) XP Customer 
d) XP Programmer 
 
Correct Response: B 
XP teams benefit from the use of an XP coach and possibly a project manager. 
‐ Mike Cohn, User Stories Applied, Appendix A 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
186/PMI‐ACP Examination Boot Camp 

91.  Which of the following is used to coordinate interrelated teams working on 
different products? 
a) Daily Scrum Meetings 
b) Scrum‐of‐Scrums 
c) Project Portfolio Management 
d) Program Management Office (PMO) 
 
Correct Response: B 
A Scrum‐of‐Scrums is used to coordinate interrelated teams working on different 
products. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 5 
 
92.  The Agile team has discovered several bugs they determined can be fixed fairly 
quickly.  Which approach is the best way for the team to handle these bugs? 
a) Combine the bugs into one or more stories. 
b) Write a separate User Story for each bug. 
c) Ask the customer to write User Stories for these bugs so they can be 
prioritized. 
d) Don't worry about User Stories for the bugs and just complete the work. 
 
Correct Response: A 
For bugs that the team expects to be able to fix quickly, they should combine the 
bugs into one or more stories. 
‐ Mike Cohn, User Stories Applied, Chapter 16 
 
93.  An Agile team's daily standup meetings have been lasting close to 30 minutes and 
some of the team members have gradually stopped coming.  What is the best 
approach to take in this instance? 
a) The Agile Project Manager needs to lead all of the meetings from now on. 
b) Nothing should be done, as the team needs to work through any problems 
and issues in order to continue making progress. 
c) The Product Owner needs to tell the team they are discussing the wrong 
things during the daily standup meetings. 
d) The meeting facilitator needs to nudge the team to take further discussions 
offline from the daily standup meeting. 
 
Correct Response: D 
The meeting facilitator's role in the daily stand up, which can be rotated from 
day to day, is to smooth the progress of the meeting itself.  The facilitator might 
nudge the team to take further discussions offline from this meeting. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 9 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /187 

94.  At level 5 of the five levels of conflict, what is the one option that exists? 
a) Discuss how to peacefully resolve the situation. 
b) Separate the combatants so they don't hurt one another. 
c) Align with one side of the conflict or the other side. 
d) Conduct constructive disagreement discussions. 
 
Correct Response: B 
Only one option at level 5 (World War) exists: to separate the combatants (aka 
team members) so that they don't hurt one another.  No constructive outcome 
can be had. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 9 
 
95.  In Lean‐Agile, which of the following are the two biggest wastes in software 
development? 
a) Delays and building what is not needed. 
b) Bugs and interruptions. 
c) Smells and defects. 
d) Handoffs and partially done work. 
 
Correct Response: A 
The two biggest wastes in software development are delays and building what is 
not needed. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 11 
 
96.  How does an Agile team measure its rate of progress? 
a) Velocity 
b) Gantt Charts 
c) Activities completed 
d) Milestones 
 
Correct Response: A 
An Agile team measures its rate of progress with velocity, expressed as the 
number of story points (or ideal days) completed per iteration. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 19 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
188/PMI‐ACP Examination Boot Camp 

97.  Which of the following is used to describe eXtreme Programming (XP)? 
a) An iterative development process for teams centered around several 
engineering practices, including test‐driven development, paired 
programming, and continuous integration. 
b) A lightweight Agile approach that focuses on eliminating waste, creating 
knowledge, building quality in, deferring commitment, optimizing the whole, 
delivering fast, and respecting people. 
c) A lightweight Agile process characterized by iterative and incremental 
approaches that are largely based on the Rapid Application Development 
(RAD) methodology. 
d) An Agile process characterized by self‐organizing, cross‐functional teams 
doing iterative development in what are called sprints. 
 
Correct Response: A 
eXtreme Programming is an iterative development process for teams centered 
around several engineering practices; the most common is test‐driven 
development, paired programming, and continuous integration. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Introduction 
 
98.  Which of the following statements is FALSE regarding the benefits of story cards? 
a) Story cards are a formal medium for recording detailed requirements. 
b) Story cards act as agreements between customers and team members to 
discuss requirements during an iteration. 
c) Story cards are used for developing work estimates. 
d) Story cards are used to define acceptance tests. 
 
Correct Response: A 
Story cards are a simple medium for gathering basic information about stories 
and recording high‐level requirements. 
‐ Jim Highsmith, Agile Project Management: Creating Innovative Products, 
2nd edition, Chapter 7 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /189 

99.  An organization is considering using Agile principles in their workplace and is a 
global company.  It will be cost‐prohibitive to have their teams co‐located.  Which 
of the following statements needs to be shared with management to ensure they 
understand how the team will communicate? 
a) Technology and tools are adequate replacements for face‐to‐face 
communication. 
b) Tell management that Agile teams cannot work together without having 
face‐to‐face communication. 
c) Tools can help support communication, but cannot replace their 
conversations. 
d) Inform management that Agile teams can use written communication to 
replace oral communication. 
 
Correct Response: C 
When team members aren't face‐to‐face (this is indeed a global market), tools 
can help support ‐ not replace ‐ those conversations.  Never underestimate the 
value of a simple phone call. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 1 
 
100.  What is the difference between a traditional Project Manager and an Agile Coach? 
a) A Project Manager's success equals the success of the project.  An Agile 
Coach's success equals the team's continual improvement and their pursuit 
of high performance. 
b) An Agile Coach plans and controls, supervising throughout.  A Project 
Manager guides the team. 
c) A Project Manager focuses on getting clients the business value they need.  
An Agile Coach is concerned with delivering on time, within budget, and on 
scope. 
d) An Agile Coach's success equals the success of the project.  A Project 
Manager's success equals the team's continual improvement and their 
pursuit of high performance. 
 
Correct Response: A 
A Project Manager's success equal the success of the project.  An Agile Coach's 
success equals the team's continual improvement and their pursuit of high 
performance. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 1 
 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
190/PMI‐ACP Examination Boot Camp 

101.  Which of the following approaches works best when transitioning into Lean‐Agile? 
a) Top‐down leadership, Bottom‐up implementation 
b) Bottom‐up leadership, Top‐down implementation 
c) Bottom‐up leadership, Bottom‐up implementation 
d) Top‐down leadership, Top‐down implementation 
 
Correct Response: A 
The only viable Lean‐Agile transition strategy is one with top‐down leadership 
and bottom‐up implementation. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 11 
 
102.  In eXtreme Programming (XP), which of the following roles is allowed to change 
code? 
a) Any pair of developers can change the code. 
b) Only the developer who wrote the code can change the code. 
c) The code must be outsourced to a contractor in order to change the code. 
d) A User Story must be created to change the code so the developer who 
wrote the code can change it. 
 
Correct Response: A 
With the XP Team Code Ownership practice, any pair of developers can change 
the code. 
‐ Mike Cohn, User Stories Applied, Appendix A 
 
103.  Which of the following techniques defines a highly structured brainstorming 
session used to generate ideas for an alternative work method to solve a particular 
challenge on Lean‐Agile projects? 
a) Problem Solving 
b) Kaizen 
c) Value Stream Mapping 
d) Visual Controls 
 
Correct Response: B 
A kaizen is a highly structured brainstorming session used to generate ideas for 
an alternative work method to solve a particular challenge. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 11 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /191 

104.  Which Scrum role is allowed to change the Sprint Backlog? 
a) ScrumMaster 
b) Product Owner 
c) Scrum Team 
d) Any stakeholder 
 
Correct Response: C 
Only the Scrum Team can change the Sprint Backlog. 
 
105.  Which of the following is the ultimate goal of a story‐writing workshop? 
a) Write as many User Stories in as short a time as possible. 
b) Write the User Stories and elaborate on them. 
c) Write the User Stories and begin estimating the User Stories using story 
points. 
d) Write the User Stories, estimate story points, identify tasks to complete the 
User Story, and determine who is responsible. 
 
Correct Response: A 
The goal of a story‐writing workshop is to write as many User Stories in as short 
a time as possible by remaining at a very high level. 
‐ Mike Cohn, User Stories Applied, Chapter 4 
 
106.  In which type of project approach are stakeholders expected to be actively 
involved throughout the duration of the project? 
a) Agile 
b) Waterfall 
c) RUP 
d) System Development Life Cycle 
 
Correct Response: A 
In Agile, there is an expectation of the active involvement of a customer or 
customer representative throughout the duration of the project. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 2 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
192/PMI‐ACP Examination Boot Camp 

107.  Which of the following eXtreme Programming (XP) practices involves writing tests 
before code? 
a) Acceptance Test Driven Development 
b) Continuous Integration 
c) Test Driven Development 
d) Refactoring 
 
Correct Response: C 
In Test Driven Development, tests are written before the code. 
‐ Mike Cohn, User Stories Applied, Appendix A 
 
108.  Which of the following is FALSE regarding Lean visual controls? 
a) Can only be viewed by people involved with the project. 
b) Mirrors (at least some part of) the process the team is using. 
c) Controls the work‐in‐process. 
d) Describes the state of the work‐in‐process. 
 
Correct Response: A 
Lean visual controls can be viewed by anyone. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 8 
 
109.  An organization is frequently pushing their Agile teams through crunch mode by 
requiring the team members to work overtime during every iteration.  Which Agile 
principle is this organization violating? 
a) Maximizing the amount of work not done. 
b) Working at a sustainable pace. 
c) Building projects around motivated individuals. 
d) Welcome changing requirements, even late in development. 
 
Correct Response: B 
We recommend working at a sustainable pace in every iteration in order to avoid 
burnout, instability of the product, delaying the release, or losing staff. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 17 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /193 

110.  When trying to predict the number of iterations remaining for an Agile team, 
which of the following should NOT be considered? 
a) The average (mean) velocity of the three fastest iterations 
b) The average (mean) velocity of the three slowest iterations 
c) The average (mean) velocity 
d) The velocity of the most recent iteration 
 
Correct Response: A 
The average (mean) velocity of the three fastest iterations value does not 
present a good picture of what just happened. 
‐ Mike Cohn, Agile Estimating and Planning, Chapter 21 
 
111.  Which of the five levels of conflict is the most constructive and is where an Agile 
team thrives? 
a) Level 5 
b) Level 1 
c) Level 3 
d) Level 2 
 
Correct Response: B 
Teams that actively navigate conflict and de‐escalate regularly can learn to thrive 
in level 1 conflict.  Here, they live in a world of constructive disagreement. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 9 
 
112.  In Lean‐Agile, which of the following is used to pull the work to be done based on 
what delivers the most value to the business? 
a) The Product Backlog 
b) The Iteration Backlog 
c) The Value Stream 
d) The Story Board 
 
Correct Response: C 
In Lean‐Agile, the work to be done is pulled through the value stream based on 
what delivers the most value to the business. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 8 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
194/PMI‐ACP Examination Boot Camp 

113.  Which of the following is NOT a value of eXtreme Programming (XP)? 
a) Communication 
b) Continuous Integration 
c) Courage 
d) Feedback 
 
Correct Response: B 
Continuous Integration is a practice of XP.  The four values of XP include: 
communication, simplicity, feedback, and courage. 
‐ Mike Cohn, User Stories Applied, Appendix A 
 
114.  Which Scrum role is responsible for planning the work? 
a) Product Owner 
b) ScrumMaster 
c) Scrum Team 
d) Team Lead 
 
Correct Response: C 
The Scrum Team figures out how to maximize its productivity itself; the job of 
planning and executing the work belongs solely to the Scrum Team. 
 
115.  Which of the following Agile principles helps to decrease goldplating? 
a) The best architectures, requirements, and designs emerge from self‐
organizing teams. 
b) Working software is the primary measure of progress. 
c) Simplicity ‐ the art of maximizing the amount of work not done ‐ is essential. 
d) Business people and developers must work together daily throughout the 
project. 
 
Correct Response: C 
Simplicity is the anti‐goldplating mechanism of Agile.  Agile teams only build 
what the customer wants, and no more. 
‐ Michele Sliger and Stacia Broderick, The Software Project Manager's 
Bridge to Agility, Chapter 1 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 
PMI‐ACP Examination Boot Camp /195 

116.  On Agile projects which of the following constraints is flexible? 
a) Time 
b) Cost 
c) Scope  
d) Resources 
 
Correct Response: C 
Time and budget (people) are held constant.  Only scope flexes. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 1 
 
117.  While working on an Agile project, a developer finds a challenging bug that she 
can't debug normally.  What is the best approach in this situation? 
a) Tag or Label 
b) Roll Back 
c) Time Travel 
d) Revert 
 
Correct Response: C 
When you find a challenging bug that you can't debug normally, go back in time 
(time travel) to an old version of the code when the bug didn't exist. 
 
 
118.  When using eXtreme Programming (XP), when does the team integrate the work 
of multiple developers? 
a) At the end of the iteration. 
b) At the end of each release. 
c) At least daily. 
d) Once a week. 
 
Correct Response: C 
With the XP Continuous Integration practice, XP teams integrate at least daily so 
that integration problems are fixed one at a time in extremely small batches as 
soon as they occur. 
‐ Mike Cohn, User Stories Applied, Appendix A 
 
   

   
PMI‐ACP Study Reference and Practice Exams 
©2019 ASPE, Inc. 
 
 
196/PMI‐ACP Examination Boot Camp 

119.  An Agile Project Manager mistakenly delegated tasks to the Agile team members 
during the daily standup meeting and midway through the day realized what 
happened.  What is the best option for the Agile Project Manager to use in this 
situation? 
a) Do nothing, Agile team members are used to changes and adaptations. 
b) Wait and see if the Agile team members notice.  If they don't, the Agile 
Project Manager should act as if nothing is wrong. 
c) Let the Product Owner know about the mistake in case team members 
complain to him/her. 
d) Own up to the impact of the mistake and apologize for it by telling the team 
which Agile principle was mistakenly undermined. 
 
Correct Response: D 
The most important thing an Agile Project Manager can do is to own up to the 
impact of the mistake and apologize for it.  Tell the team which Agile value or 
principle was mistakenly undermined so the team can learn from this example. 
‐ Lyssa Adkins, Coaching Agile Teams, Chapter 1 
 
120.  Chris, an Agile Project Manager, has been working on creating a tool to synch up 
project plans with status reports in order to manage the overwhelming work‐in‐
process (WIP).  Is using this tool considered good practice in Lean‐Agile? 
a) Yes, Chris is working on improving the process, which will then reduce WIP. 
b) No, this approach is not part of Lean principles. 
c) Yes, this tool will fix the problem and keep management satisfied. 
d) No, a better approach is to use the Five Whys to determine the root cause as 
to why there is so much WIP. 
 
Correct Response: D 
An Agile Project Manager gets at the root cause of the problem first, to ensure 
that the tool is adding value, and not merely bandaging over a more 
fundamental issue. 
‐ Alan Shalloway, Guy Beaver, James R. Trott, Lean‐Agile Software 
Development, Chapter 11 
 
 
 
 

   
PMI‐ACP Study Reference and Practice Exams 
  ©2019 ASPE, Inc. 
 

You might also like