Professional Documents
Culture Documents
Brick Work Calculation: Please Put All Dimenssion in Metre
Brick Work Calculation: Please Put All Dimenssion in Metre
mix of cement-sand, the volume of dry mix is reduced. It happens due to the presence of air voids in sand particles.
ontain air voids. So, when water is added to the dry sand, the volume of sand is reduced. It is happened due to the presence of air voids in
centage of air void compressibility of sand when converting the wet volume into the dry volume. That is 27%.
ement, the air void compressibility of it is ignored.
ctually 27% increased in dry condition. But, the sand isn’t used at a time for preparing mortar. mortar is normally mixed in various places in
percentage of air void compressibility of sand, it will be 30% (27% + 3%).
ume of mortar, we just multiply the wet volume by 1.30.
e presence of air voids in sand particles. The percentage of air void compressibility of sand is somehow 20% to 27%.
mixed in various places in the building. So, some portion of sand is wasted which isn’t normally happened in mixing concrete. that is the re
ng concrete. that is the reason we normally calculate 3% wastage of sand for mortar which isn’t taken for calculating sand for concrete.
ting sand for concrete.
1m=3.28084f
1m3=35.31cf
Ratio
Cement Sand Sum of Mix
1 6 7
Cement
Bags CUM KG
3.9990857 0.1388571 199.95428571
Sand
CUM CFT
0.8331429 29.418274
1m=3.28084f
1m3=35.31cf
Dry volume to consider 20% bulking of the sand and 15% Wastage of the sand at the site.
BBS of Stirrups
Column Size
Cover Dia of 90° 135° Length
Dia half Hooks 45° Bend Bend
B W bar Bend of Bar
400 750 25 8 4 2 0 3 2 2164
2.164
10d or 75mm
Hook
Length
45° Bend 1d
90° Bend 2d
135° Bend 3d
m
Insert table with heade
Formula define withou
Steel % by volume Data validate name of
of Concrete
Analysis for Beam Slab 1.00%
Wet vol., m3 2 Beam 2.00%
Column 2.50%
Road 0.60%
Steel, Kg 314
Binding wire = 10 grams per kg of
reinforcement. 3.14
Minimum reinforcement is 0.12% for HYSD bars and 0.15% for mild steel bars.
The maximum diameter of bar used in slab should not exceed 1/8 of the total thickness of slab.
Slab
Maximum spacing of main bar is restricted to 3 times effective depth or 300 mm whichever is less.
For distribution bars the maximum spacing is specified as 5 times the effective depth or 450 mm whichever is le
hever is less.
or 450 mm whichever is less.
Beam
D2 8
10
S2 X
Y
192
300
V(m3) Proportion Aggregate Dry Cement Sand Course Agg.
(Wet) Factor (Bag) (Cft) (Cft)
Case:
If N=1 Cl.15.2.2 Acceptance 29
Cube test results (N/mm2) Av
Shif 19 26 16 20.3
Rejected due to
1. Min strength of 29 is not achieved Rebound hammer / drilled cores
2. 26 and 16 are out of range
If Vol.<=30m3 and N<4
In 3 shifs 27m3 foundation concreting was done
Shif Cube test results (N/mm2) Av
1 33 29 32 31.3
2 24 32 28 28.0
3 25 29 32 28.7
Accepted
1. All cubes strength are within range
2. From shits 1,2 and 3 all cube strengths are >= 23
3. Average cubes strength of shifs 1, 2 and 3 is 29.3 which is > 29
If N>=4
Shif Cube test results (N/mm2) Av
1 22 28 26 25.3
2 26 24 28 26.0
3 31 35 33 33.0
4 32 31 33 32.0
5 31 32 33 32.0
6 26 25 24 25.0
Accepted
1. All cubes strength are within range
2. From shits 1,2,3,4,5 and 6 all cube strengths are >= 22
3. Average cubes strength of shifs 1, 2,3 and 4 is 29.1 which is > 28
4. Average cubes strength of shifs 2, 3,4 and 5 is 30.8 which is > 28
5. Average cubes strength of shifs 3, 4,5 and 6 is 30.5 which is > 28
Vol. of work
(m3)
No. of sample (N)
1 to 5 1
6 to 15 2
16 to 30 3
31 to 50 4
>50 4+1 per additional 50
min. Mean
0.85Av 1.15Av
17.28 23.38
range +/-15 of Av
0.85Av 1.15Av Acceptance 28 min. Mean of average of 4 non overlaping test results
21.5 29.1 22 min. Individual
22.1 29.9
28.1 38.0
27.2 36.8
27.2 36.8
21.3 28.8
range +/-15 of Av
non overlaping test results
Crushing Average Square Of
Sample Number Strength Strength Deviation Deviation
1.00 43.00 -1.45 2.10
1.98