CELLAR FLOOR

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

Earth work excavation for


foundation and depositing
on bank with initial lead, lift
1) in B.C. Soil as per 20B for
foundations on digging
bores 0.30m & .38 dia with
D.U.R. Piles 4.57m depth.
Piles
12" dia 18 4.57
15" dia 543 4.57
Sqmt -

Dust filling the foundation


in layers with local sand
2)
including consolidation
upto basement level
1 50.88 42.37 0.76 CUM -

PCC (1:4:8) using 40mm


HBG metal including cost of
all material and labour
charges including cost of
3)
mixing, placing, centring,
labour,curing etc.,
complete for finished item
of work.
1) Pile Caps
a) 3-15"dia 3 2.82 1.29 0.15
3 1.93 1.29 0.15
b) 4-15" dia 9 2.41 3.09 0.15
9 1.8 3.09 0.15
c) 6-15" dia 21 4.34 2.82 0.15
d) 8-15" dia 9 5.86 7.86 0.15
e) 9-15" dia 5 4.34 4.34 0.15
f) 12-15" dia 1 6.13 4.34 0.15

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

g) 8-15" dia 7 5.86 2.82 0.15


h) 10-15" dia 3 7.39 2.82 0.15
i) 12-15" dia 4 5.86 4.34 0.15
j) 12-15" dia 2 5.86 4.19 0.15
k) 12-15" dia 2 8.91 2.82 0.15
l) 15-15" dia 1 4.34 7.39 0.15
m) 15-15" dia 1 7.08 4.34 0.15
n) 20-15" dia 1 7.39 6.11 0.15
o) 18-12" dia 1 3.65 7.31 0.15
2) Bed Concrete 1 32.93 50.88 0.15
CUM -

R.C.C. 1:1 1/2:3 Mix using


20 mm H.B.G. Metal
including Cost &
4) Conveyances of All
Materials , Labour
chargesfor centering rob
bending etc. Complete
1) Piles
12" dia 18 (∏/4(0.30)²) 4.57
15" dia 543 (∏/4(0.38)²) 4.57
2) Pile Caps
a) 3-15"dia 3 2.21 0.68 0.76
3 1.32 0.68 0.76
b) 4-15" dia 9 1.8 2.48 0.76
9 1.19 2.48 0.76
c) 6-15" dia 21 3.73 2.21 0.76
d) 8-15" dia 9 5.25 7.25 0.76
e) 9-15" dia 5 3.73 3.73 0.83
f) 12-15" dia 1 5.52 3.73 0.91
g) 8-15" dia 7 5.25 2.21 0.76
h) 10-15" dia 3 6.78 2.21 1.06
i) 12-15" dia 4 5.25 3.73 1.06
j) 12-15" dia 2 5.25 3.58 1.06
k) 12-15" dia 2 8.3 2.21 1.06
l) 15-15" dia 1 3.73 6.78 0.99
m) 15-15" dia 1 6.47 3.73 1.21
n) 20-15" dia 1 6.78 5.5 1.14
o) 18-12" dia 1 3.04 6.7 0.83
3) Plinth Beam
Cross Beams 8 32.93 0.23 0.38
Long Beams 12 50.88 0.23 0.38
4) Columns Up to Roof Level
(a) 9"X18" 2 0.23 0.45 2.25
(b) 9"X24" 38 0.23 0.60 2.25
(C ) 12"X24" 50 0.30 0.60 2.25
(d) 12"X30" 10 0.30 0.76 2.25

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

5) Roof Beams
Cross Beams 8 32.93 0.23 0.38
Long Beams 12 50.88 0.23 0.38
6) Roof Slab 1 32.93 50.88 0.12
CUM -

Supply and delivery of


various sizes of steel
reinforcement for R.C.C
Works including
straightening, cutting,
5)
bending, placing in
position, binding and labour
charges, cost conveyance
of all material and labour
etc, complete. @ 1.0%
1 0.01 7850 0.00 KG -

Laying in Floor matt


Parking Tiles laid on
20mm thick in C.M (1:6)
including grouting the
6) joints with matching
pigment, including Cost &
conveyance of all materials
and labour charges etc,
complete. 1 32.93 50.88 - SQMT -

Brick masonry in C.M.(1:6 )


mix for Stilt floor,
basement and
7) superstructure using 2nd
class Bricks including Cost
& conveyance of all labour
etc, complete.
Lift 1 2 3.13 0.23 2.25
2 2.01 0.10 2.25
Lift 2 2 2.51 0.23 2.25
2 2.21 0.10 2.25
CUM -

Plastering with sponge


finishing C.M. (1:5) mix
20mm thick internal and
8) external of the building
including cost and
conveyance of all material
and labour etc, complete.

1) Lift 1
Internal & external 2 10.26 - 2.25
Lift 2
Internal & external 2 9.44 2.25
2) Columns Up to Roof Level
(a) 9"X18" 2 1.36 2.25
(b) 9"X24" 38 1.66 2.25
(C ) 12"X24" 50 1.8 2.25

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

(d) 12"X30" 10 2.12 2.25


3) Roof Beams
Cross Beams 16 32.93 - 0.38
Long Beams 24 50.88 - 0.38
4) Roof Slab 1 32.93 50.88 -
SQMT -

White cement Painting with


two cots over one coat of
primary coat to the
external and internal of the
9)
building including cost &
conveyance of all material
and labour charges etc,
complete.
Same asa Item No: 8 SQMT -

Cost of Staircase providing


quality Handrails, including
10) 2
material and labour
charges
-
Provision for Electrification
11) -
works @

Provision for Water supply


12) -
& Sanitary works @

Cellar Floor Total -

STILT FLOOR

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

R.C.C. 1:1 1/2:3 Mix using


20 mm H.B.G. Metal
including Cost &
1) Conveyances of All
Materials , Labour
chargesfor centering rob
bending etc. Complete
1) Columns Up to Roof Level
(a) 9"X18" 2 0.23 0.45 2.57
(b) 9"X24" 38 0.23 0.60 2.57
(C ) 12"X24" 50 0.30 0.60 2.57
(d) 12"X30" 10 0.30 0.76 2.57
2) Roof Beams
Cross Beams 8 32.93 0.23 0.38
Long Beams 12 50.88 0.23 0.38
3) Roof Slab 1 32.93 50.88 0.12
Deductions ( - )
Tot-Lot - 1 1 3.13 15.11 0.12

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

Tot-Lot - 2 1 3.13 12.85 0.12


Tot-Lot - 3,4 2 3.13 14.98 0.12
Ramp Slab Cutting 1 5.4 1.2 0.12
CUM -

Supply and delivery of


various sizes of steel
reinforcement for R.C.C
Works including
straightening, cutting,
2)
bending, placing in
position, binding and labour
charges, cost conveyance
of all material and labour
etc, complete. @ 1.0%
1 0.01 7850 0.00 KG -

Laying in Floor matt


Parking Tiles laid on
20mm thick in C.M (1:6)
including grouting the
3) joints with matching
pigment, including Cost &
conveyance of all materials
and labour charges etc,
complete.
Area 1 32.93 50.88 -
Deductions
Tot Lots 1 3.13 15.11 -
1 3.13 12.85 -
2 3.13 14.98 -
Ramp Slab Cutting 1 5.4 1.2 -
SQMT -

Brick masonry in C.M.(1:6 )


mix for Stilt floor,
basement and
4) superstructure using 2nd
class Bricks including Cost
& conveyance of all labour
etc, complete.
Lift 1 2 3.13 0.23 2.57
2 2.01 0.10 2.57
Lift 2 2 2.51 0.23 2.57
2 2.21 0.10 2.57
CUM -
Plastering with sponge
finishing C.M. (1:5) mix
20mm thick internal and
5) external of the building
including cost and
conveyance of all material
and labour etc, complete.

1) Lift 1
Internal & external 2 10.06 - 2.95
Lift 2

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

Internal & external 2 8.2 2.95


2) Columns Up to Roof Level
(a) 9"X18" 2 1.36 2.57
(b) 9"X24" 38 1.66 2.57
(C ) 12"X24" 50 1.8 2.57
(d) 12"X30" 10 2.12 2.57
3) Roof Beams
Cross Beams 16 32.93 - 0.38
Long Beams 24 50.88 - 0.38
4) Roof Slab 1 32.93 50.88 -
Dedcutions
Tot-Lot - 1 1 3.13 15.11 0.12
Tot-Lot - 2 1 3.13 12.85 0.12
Tot-Lot - 3,4 2 3.13 14.98 0.12
Ramp Slab Cutting 1 5.4 1.2 0.12
SQMT -

White cement Painting with


two cots over one coat of
primary coat to the
external and internal of the
5)
building including cost &
conveyance of all material
and labour charges etc,
complete.
Same asa Item No: 8 SQMT -

Cost of Staircase providing


quality Handrails, including
5)
material and labour
charges
-
Provision for Electrification
6) -
works @

Provision for Water supply


7) -
& Sanitary works @

Stilt Floor Total -


TYPICAL FLOOR
Measurment (m) QUANTITY
SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

R.C.C. 1:1 1/2:3 Mix using


20 mm H.B.G. Metal
including Cost &
1) Conveyances of All
Materials , Labour
chargesfor centering rob
bending etc. Complete
1) Columns Up to Roof Level
(a) 9"X18" 2 0.23 0.45 2.4 0.50

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

(b) 9"X24" 38 0.23 0.60 2.4


(C ) 12"X24" 50 0.30 0.60 2.4
(d) 12"X30" 10 0.30 0.76 2.4
2) Roof Beams
Cross Beams 8 32.93 0.23 0.38
Long Beams 12 50.88 0.23 0.38
3) Roof Slab 1 32.93 50.88 0.12
CUM -

Supply and delivery of


various sizes of steel
reinforcement for R.C.C
Works including
straightening, cutting,
2)
bending, placing in
position, binding and labour
charges, cost conveyance
of all material and labour
etc, complete. @ 1.0%
1 0.01 7850 0.00 KG -

Brick masonry in C.M.(1:6 )


mix for Stilt floor,
basement and
3) superstructure using 2nd
class Bricks including Cost
& conveyance of all labour
etc, complete.
Flat No-1
Cross Walls 2 17.34 0.23 2.4
3 17.34 0.115 2.4
Long Walls 2 15.09 0.23 2.4
5 15.09 0.115 2.4
Flat No-2
Cross Walls 2 13.64 0.23 2.4
3 13.64 0.115 2.4
Long Walls 2 15.09 0.23 2.4
2 15.09 0.115 2.4
1 4.7 0.115 2.4
Flat No-3
Cross Walls 2 13.64 0.23 2.4
3 13.64 0.115 2.4
Long Walls 2 15.09 0.23 2.4
2 15.09 0.115 2.4
1 4.7 0.115 2.4
Flat No-4
Cross Walls 1 13.64 0.23 2.4
3 13.64 0.115 2.4
1 2.06 0.115 2.4
1 11.58 0.115 2.4
Long Walls 2 15.11 0.23 2.4

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

3 15.11 0.115 2.4


Flat No-5
Cross Walls 1 13.64 0.23 2.4
3 13.64 0.115 2.4
1 2.06 0.115 2.4
1 11.58 0.115 2.4
Long Walls 2 15.11 0.23 2.4
3 15.11 0.115 2.4
Flat No-6
Cross Walls 2 17.34 0.23 2.4
3 17.34 0.115 2.4
Long Walls 2 15.11 0.23 2.4
4 15.11 0.115 2.4
Dedcutions
D 6 1.06 0.23 2.1
D1 18 0.99 0.115 2.1
D2 16 0.91 0.115 2.1
D3 38 0.83 0.115 2.1
W' 1 2.44 0.23 2.44
W1 2 2.2 0.23 2.00
W2 43 2.00 0.115 2.00
W3 2 1.91 0.115 2.00
W4 10 1.52 0.115 1.68
V 25 1.00 0.23 1.00
CUM -

Plastering with sponge


finishing C.M. (1:5) mix
20mm thick internal and
4) external of the building
including cost and
conveyance of all material
and labour etc, complete.
1) Lift 1
Internal & external 2 10.26 - 2.8
Lift 2
Internal & external 2 9.44 2.8
2) Roof Slab 1 32.93 50.88 -
SQMT -
External Plastering
Flat no - 1 1 65.1 - 2.8
Dedcutions
D 1 1.06 0.23 2.1
W' 6 2.44 0.23 2.44
W2 1 2.00 0.115 2.00
V 6 1.00 0.23 1.00

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

Flat no - 2 1 49.16 - 2.8


Dedcutions
D 1 1.06 0.23 2.1
W' 8 2.44 0.23 2.44
V 4 1.00 0.23 1.00

Flat no - 3 1 49.16 - 2.8


Dedcutions
D 1 1.06 0.23 2.1
W' 8 2.44 0.23 2.44
V 4 1.00 0.23 1.00

Flat no - 4 1 54.06 - 2.8


Dedcutions
D 1 1.06 0.23 2.1
W' 4 2.44 0.23 2.44
W2 2 2.00 0.115 2.00
V 3 1.00 0.23 1.00

Flat no - 5 1 54.06 - 2.8


Dedcutions
D 1 1.06 0.23 2.1
W' 4 2.44 0.23 2.44
W2 2 2.00 0.115 2.00
V 3 1.00 0.23 1.00

Flat no - 6 1 61.44 - 2.8


Dedcutions
D 1 1.06 0.23 2.1
W' 6 2.44 0.23 2.44
W2 2 2.00 0.115 2.00
V 4 1.00 0.23 1.00

Internal Plastering
Flat No - 1
Living 1 24.28 - 2.68
Dining 1 17.92 - 2.68
Kitchen 1 16.56 - 2.68
Bed Room - 01 1 23.14 - 2.68
Dress Room 1 7.1 2.68
Toilet 1 9.42 - 2.68
Bed Room - 02 1 20.58 - 2.68
Dress Room 1 6.02 2.68
Toilet 1 8.34 - 2.68
Bed Room - 03 1 19.4 - 2.68

Measurment (m)
SI.NO DESCRIPTION OF ITEM NO'S PER AMOUNT
L B D/H

Dress Room 1 6.24 2.68


Toilet 1 9.3 - 2.68
Bed Room - 04 1 18.9 - 2.68
Dress Room 1 7.68 - 2.68
Toilet 1 7.68 - 2.68
Puja 1 7.7 - 2.68
Store 1 7.46 - 2.68
Passage-1 1 6.68 - 2.68
Passage-2 1 7.54 - 2.68
Balcony 2 13.74 - 2.68
Utility 1 5.11 - 2.68
Flat No - 2
Living 1 22.84 - 2.68
Dining & Kitchen 1 31.7 - 2.68
Bed Room - 01 1 16.34 - 2.68
Dress Room 1 6.08 - 2.68
Toilet 1 8.06 - 2.68
Bed Room - 02 1 20.16 - 2.68
Dress Room 1 6.7 - 2.68
Toilet 1 10.02 - 2.68
Bed Room - 03 1 15.56 - 2.68
Toilet 1 7.56 - 2.68
Bed Room - 04 1 17.18 - 2.68
Toilet 1 8.12 - 2.68
Balcony 2 11.36 - 2.68
Flat No - 3
Living 1 22.84 - 2.68
Dining & Kitchen 1 31.7 - 2.68
Bed Room - 01 1 16.34 - 2.68
Dress Room 1 6.08 - 2.68
Toilet 1 8.06 - 2.68
Bed Room - 02 1 20.16 - 2.68
Dress Room 1 6.7 - 2.68
Toilet 1 10.02 - 2.68
Bed Room - 03 1 15.56 - 2.68
Toilet 1 7.56 - 2.68
Bed Room - 04 1 17.18 - 2.68
Toilet 1 8.12 - 2.68
Balcony 2 11.36 - 2.68
Flat No - 4
Living 1 21.64 - 2.68
Dining 1 24.04 - 2.68
Kitchen 1 17.3 - 2.68
Bed Room - 01 1 20 - 2.68
Dress Room 1 7.92 - 2.68

Measurment (m)
SI.NO DESCRIPTION OF ITEM NO'S PER AMOUNT
L B D/H

Toilet 1 9.9 - 2.68


Bed Room - 02 1 16.72 - 2.68
Dress Room 1 7.92 - 2.68
Toilet 1 9.3 - 2.68
Bed Room - 03 1 15.76 - 2.68
Toilet 1 11.14 - 2.68
Puja 1 7.1 - 2.68
Balcony 2 15.66 - 2.68

Flat No - 5
Living 1 21.64 - 2.68
Dining 1 24.04 - 2.68
Kitchen 1 17.3 - 2.68
Bed Room - 01 1 20 - 2.68
Dress Room 1 7.92 - 2.68
Toilet 1 9.9 - 2.68
Bed Room - 02 1 16.72 - 2.68
Dress Room 1 7.92 - 2.68
Toilet 1 9.3 - 2.68
Bed Room - 03 1 15.76 - 2.68
Toilet 1 11.14 - 2.68
Puja 1 7.1 - 2.68
Balcony 2 15.66 - 2.68
Flat No - 6
Living 1 30.26 2.68
Dining 1 11.1 2.68
Kitchen 1 16.46 2.68
Bed Room - 01 1 21.92 2.68
Dress Room 1 7.1 2.68
Toilet 1 9.42 2.68
Bed Room - 02 1 18.42 2.68
Dress Room 1 6.48 2.68
Toilet 1 9.08 2.68
Bed Room - 03 1 17.3 2.68
Dress Room 1 7.22 2.68
Toilet 1 7.86 2.68
Bed Room - 04 1 19.62 2.68
Dress Room 1 7.71 2.68
Toilet 1 9.02 2.68
Puja 1 7.06 2.68
Passage-1 1 6.86 2.68
Balcony 2 13.26 2.68
Utility 1 9.54 2.68

Dedcutions
D 6 1.06 0.23 2.1

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

D1 18 0.99 0.115 2.1


D2 16 0.91 0.115 2.1
D3 38 0.83 0.115 2.1
W' 1 2.44 0.23 2.44
W1 2 2.2 0.23 2.00
W2 43 2.00 0.115 2.00
W3 2 1.91 0.115 2.00
W4 10 1.52 0.115 1.68
V 25 1.00 0.23 1.00
SQMT -

5) Provision for doors


1) Main Doors With teak
wood frame and teakwood
shutter including hardware.
Polishing and all other
making charges etc.
D 6 1.06 2.1 -

2) All internal doors with


teak wood frame with
vineered shuitter finish
including haedware and
making and fixing charges
D1 18 0.99 2.1 -
D2 16 0.91 2.1 -
D3 38 0.83 2.1 -
SQMT -
Upvc windows and
ventilators with grillsmoke
6) glass and mosquito mash
including fixing charges
etc.
w' 1 2.44 2.44 -
w1 2 2.2 2.00 -
w2 43 2.00 2.00 -
w3 2 1.91 2.00 -
w4 10 1.52 1.68 -
v 25 1.00 1.00 -
SQMT -

Enamel Painting with two


coats with best primer coat
of white lead on new wood
7)
work including cost and
conveyance of all material
and labour etc, complete.
Same as Item No: 5 1 SQMT -

Provision for Tiles including


cost and convenyance of all
8)
materials and labour
charges etc.

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

1.vitrieed Marble in the plith of flats


Flat No - 1
Living 1 4.7 7.44 -
Dining 1 5.78 3.18 -
Kitchen 1 4.14 4.14 -
Bed Room - 01 1 6.09 5.48 -
Dress Room 1 1.72 1.83
Toilet 1 2.88 1.83 -
Bed Room - 02 1 4.93 5.36 -
Dress Room 1 1.29 1.72
Toilet 1 1.29 2.88 -
Bed Room - 03 1 4.45 5.25 -
Dress Room 1 1.4 1.72
Toilet 1 2.93 1.72 -
Bed Room - 04 1 4.45 5 -
Dress Room 1 1.4 2.44 -
Toilet 1 1.4 2.44 -
Puja 1 1.41 2.44 -
Store 1 1.4 2.83 -
Passage-1 1 1.52 1.82 -
Passage-2 1 1.29 2.48 -
Balcony 2 4.39 1.94 -
Utility 1 3.28 1.83 -
Flat No - 2
Living 1 5.86 5.56 -
Dining & Kitchen 1 5.8 10.05 -
Bed Room - 01 1 4.14 4.03 -
Dress Room 1 1.52 1.52
Toilet 1 2.51 1.52 -
Bed Room - 02 1 5.26 4.82 -
Dress Room 1 1.83 1.52
Toilet 1 1.83 3.18 -
Bed Room - 03 1 4.18 3.6 -
Toilet 1 1.57 2.21 -
Bed Room - 04 1 4.45 4.14 -
Toilet 1 1.57 2.49 -
Balcony 2 4.18 1.5
Flat No - 3
Living 1 5.86 5.56 -
Dining & Kitchen 1 5.8 10.05 -
Bed Room - 01 1 4.14 4.03 -
Dress Room 1 1.52 1.52
Toilet 1 2.51 1.52 -
Bed Room - 02 1 5.26 4.82 -
Dress Room 1 1.83 1.52
Toilet 1 1.83 3.18 -

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

Bed Room - 03 1 4.18 3.6 - 15.05


Toilet 1 1.57 2.21 - 3.47
Bed Room - 04 1 4.45 4.14 - 18.42
Toilet 1 1.57 2.49 - 3.91
Balcony 2 4.18 1.5 12.54
Flat No - 4
Living 1 4.96 5.86 - 29.07
Dining 1 4.96 7.06 - 35.02
Kitchen 1 4.14 4.51 - 18.67
Bed Room - 01 1 4.14 5.86 - 24.26
Dress Room 1 1.52 2.44 3.71
Toilet 1 2.51 2.44 - 6.12
Bed Room - 02 1 3.85 4.51 - 17.36
Dress Room 1 1.52 2.44 3.71
Toilet 1 2.21 2.44 - 5.39
Bed Room - 03 1 3.85 4.03 - 15.52
Toilet 1 3.85 1.72 - 6.62
Puja 1 1.83 1.72 - 3.15
Balcony 2 6.00 1.83 21.96
Flat No - 5
Living 1 4.96 5.86 - 29.07
Dining 1 4.96 7.06 - 35.02
Kitchen 1 4.14 4.51 - 18.67
Bed Room - 01 1 4.14 5.86 - 24.26
Dress Room 1 1.52 2.44 3.71
Toilet 1 2.51 2.44 - 6.12
Bed Room - 02 1 3.85 4.51 - 17.36
Dress Room 1 1.52 2.44 3.71
Toilet 1 2.21 2.44 - 5.39
Bed Room - 03 1 3.85 4.03 - 15.52
Toilet 1 3.85 1.72 - 6.62
Puja 1 1.83 1.72 - 3.15
Balcony 2 6.00 1.83 21.96
Flat No - 6
Living 1 6.22 8.91 - 55.42
Dining 1 4.03 1.52 - 6.13
Kitchen 1 4.03 4.2 - 16.93
Bed Room - 01 1 6.09 4.87 - 29.66
Dress Room 1 1.72 1.83 3.15
Toilet 1 2.88 1.83 - 5.27
Bed Room - 02 1 4.45 4.76 - 21.18
Dress Room 1 1.52 1.72 2.61
Toilet 1 2.82 1.72 - 4.85
Bed Room - 03 1 4.45 4.2 - 18.69
Dress Room 1 1.4 2.21 3.09

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

Toilet 1 1.72 2.21 - 3.80


Bed Room - 04 1 4.09 5.72 - 23.39
Dress Room 1 2.13 1.72 3.66
Toilet 1 2.13 2.38 - 5.07
Puja 1 2.13 1.4 2.98
Passage-1 1 1.22 2.21 2.70
Balcony 2 5 1.63 16.30
Utility 1 2.94 1.83 - 5.38
664.77
Skirting 10% of the Total Quantity 66.48
731.25 800 SQMT 584,999.62

Providing and laying


Dadoing Towards with
ceramic non-skid tiles of
First Quality tiles of Size
Not Less Than 200X300mm
laid over IN cm (1:1) 12mm
9)
thick. Over cc Bed already
laid and pointed with white
white cement mixed with
pigment of matching shade
including cost &
conveyance of all materials
Internal Plastering
Flat No - 1
Kitchen 1 16.56 - 1.21 20.04
Toilet 1 9.42 - 2.13 20.06
Toilet 1 8.34 - 2.13 17.76
Toilet 1 9.3 - 2.13 19.81
Toilet 1 7.68 - 2.13 16.36
Utility 1 5.11 - 1.21 6.18
Dedcutions
D2 2 0.91 2.1 -3.82
D3 4 0.83 2.1 -6.97
Flat No - 2
Dining & Kitchen 1 31.7 - 1.21 38.36
Toilet 1 8.06 - 2.13 17.17
Toilet 1 10.02 - 2.13 21.34
Toilet 1 7.56 - 2.13 16.10
Toilet 1 8.12 - 2.13 17.30
Balcony 2 11.36 - 2.68 60.89
Dedcutions
D2 2 0.91 2.1 -3.82
D3 4 0.83 2.1 -6.97
Flat No - 3
Dining & Kitchen 1 31.7 - 2.68 84.96
Toilet 1 8.06 - 2.13 17.17
Toilet 1 10.02 - 2.13 21.34
Toilet 1 7.56 - 2.13 16.10

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

Toilet 1 8.12 - 2.13 17.30


Balcony 2 11.36 - 1.21 27.49
Dedcutions
D2 2 0.91 2.1 -3.82
D3 4 0.83 2.1 -6.97
Flat No - 4
Kitchen 1 17.3 - 1.21 20.93
Toilet 1 9.9 - 2.13 21.09
Toilet 1 9.3 - 2.13 19.81
Toilet 1 11.14 - 2.13 23.73
Balcony 2 15.66 - 1.21 37.90
Dedcutions
D2 2 0.91 2.1 -3.82
D3 3 0.83 2.1 -5.23
Flat No - 5
Kitchen 1 17.3 - 1.21 20.93
Toilet 1 9.9 - 2.13 21.09
Toilet 1 9.3 - 2.13 19.81
Toilet 1 11.14 - 2.13 23.73
Balcony 2 15.66 - 1.21 37.90
Dedcutions
D2 2 0.91 2.1 -3.82
D3 3 0.83 2.1 -5.23
Flat No - 6
Kitchen 1 16.46 1.21 19.92
Toilet 1 9.42 2.13 20.06
Toilet 1 9.08 2.13 19.34
Toilet 1 7.86 2.13 16.74
Toilet 1 9.02 2.13 19.21
Utility 1 9.54 1.21 11.54
Dedcutions
D2 2 0.91 2.1 -3.82
D3 4 0.83 2.1 -6.97
748.18 600 SQMT 448,907.10

Internal and external


painting and polishing
including cost and
10)
conveyance of materials
and labour chargesetc.,
complete
Same as Item No: 4 0.00 300 SQMT -

Provisions for POP Celing


11) ceiling in Hall, Dinning and
bed Room
Flat No - 1
Living 1 4.7 7.44 - 34.97
Dining 1 5.78 3.18 - 18.38
Bed Room - 01 1 6.09 5.48 - 33.37

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

Dress Room 1 1.72 1.83 3.15


Bed Room - 02 1 4.93 5.36 - 26.42
Dress Room 1 1.29 1.72 2.22
Bed Room - 03 1 4.45 5.25 - 23.36
Dress Room 1 1.4 1.72 2.41
Bed Room - 04 1 4.45 5 - 22.25
Dress Room 1 1.4 2.44 - 3.42
Puja 1 1.41 2.44 - 3.44
Store 1 1.4 2.83 - 3.96
Passage-1 1 1.52 1.82 - 2.77
Passage-2 1 1.29 2.48 - 3.20
Flat No - 2
Living 1 5.86 5.56 - 32.58
Dining & Kitchen 1 5.8 10.05 - 58.29
Bed Room - 01 1 4.14 4.03 - 16.68
Dress Room 1 1.52 1.52 2.31
Bed Room - 02 1 5.26 4.82 - 25.35
Dress Room 1 1.83 1.52 2.78
Bed Room - 03 1 4.18 3.6 - 15.05
Bed Room - 04 1 4.45 4.14 - 18.42
Flat No - 3
Living 1 5.86 5.56 - 32.58
Dining & Kitchen 1 5.8 10.05 - 58.29
Bed Room - 01 1 4.14 4.03 - 16.68
Dress Room 1 1.52 1.52 2.31
Bed Room - 02 1 5.26 4.82 - 25.35
Dress Room 1 1.83 1.52 2.78
Bed Room - 03 1 4.18 3.6 - 15.05
Bed Room - 04 1 4.45 4.14 - 18.42
Flat No - 4
Living 1 4.96 5.86 - 29.07
Dining 1 4.96 7.06 - 35.02
Bed Room - 01 1 4.14 5.86 - 24.26
Dress Room 1 1.52 2.44 3.71
Bed Room - 02 1 3.85 4.51 - 17.36
Dress Room 1 1.52 2.44 3.71
Bed Room - 03 1 3.85 4.03 - 15.52
Puja 1 1.83 1.72 - 3.15
Flat No - 5
Living 1 4.96 5.86 - 29.07
Dining 1 4.96 7.06 - 35.02
Bed Room - 01 1 4.14 5.86 - 24.26
Dress Room 1 1.52 2.44 3.71
Bed Room - 02 1 3.85 4.51 - 17.36
Dress Room 1 1.52 2.44 3.71
Bed Room - 03 1 3.85 4.03 - 15.52

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

Puja 1 1.83 1.72 - 3.15


Flat No - 6
Living 1 6.22 8.91 - 55.42
Dining 1 4.03 1.52 - 6.13
Bed Room - 01 1 6.09 4.87 - 29.66
Dress Room 1 1.72 1.83 3.15
Bed Room - 02 1 4.45 4.76 - 21.18
Dress Room 1 1.52 1.72 2.61
Bed Room - 03 1 4.45 4.2 - 18.69
Dress Room 1 1.4 2.21 3.09
Bed Room - 04 1 4.09 5.72 - 23.39
Dress Room 1 2.13 1.72 3.66
Puja 1 2.13 1.4 2.98
Passage-1 1 1.22 2.21 2.70
962.51 600 SQMT 577,503.36
Providing, making and
fixing Modular Kitchen
with under-counter and
over head cup-boards with
19mm thick. Commercial
12)
water proof boad of
laminate finish as external
as well as on internal faces
with ss baskets, channels
etc.
No:of Flats - 6 6 ### 7,200,000.00

Cost of Staircase
providing quality Handrails, 2
13) L.S 100,000.00
including material and
labour charges

Provision for cement


planks & cupboard s with
Teak wood frames and
Vineer Laminated Ply wood
14) shutters in Rose wood
polish finish including cost
and conveyance of
materials and labour
chargers etc.,
No:of Flats 6 500,000 3,000,000.00

11,911,410.08
Electrification including
15) fixtures and labours 10% 1,191,141.01
chargesetc.

Plumbing and sanitary


including cost and
16) conveyance materials and 10% 1,191,141.01
labour charges
etc.,complete

TYPICAL FLOOR TOTAL 14,293,692.10

Measurment (m) QUANTITY


SI.NO DESCRIPTION OF ITEM NO'S IN RATE PER AMOUNT
L B D/H CUM

External Devlopment & Additional Works Building

Provisions for compound


1) L.S 600,000.00
wall and parapet wall

Bore well including


2) L.S 250,000.00
submerged motar

3) Lift (6 Pasangers) 2 L.S 2,800,000.00

4) Over Head Tank L.S 400,000.00

5) Elevation L.S 1,500,000.00


6) Generator L.S 800,000.00

7) Transformer L.S 500,000.00

8) Solar Paneels L.s 600,000.00

9) Ro Water Plant L.S 500,000.00

7,950,000.00

ABSTRACT

1) Cellar Floor Total -

1) Stilt Floor Total -

2) Typical floor 5 71,468,460.50

External Development &


3) Additional Work of the 7,950,000.00
Building
19,77,61,411.27
79,418,460.50

Total Amount
(or
say)

19,77,62,000.00