Professional Documents
Culture Documents
Executive Summary
1
EXECUTIVE SUMMARY
INTRODUCTION
Even before the passage of RA 9184, the government was already addressing
the issue on transparency in government procurement and inefficiency due to
manual and paper-driven procurement processes. Thus, in November 2000, the
internet-based Electronic Procurement System (EPS) was established. This is at
present required to be used by all government agencies.
AUDIT OBJECTIVE
The audit was conducted to assess whether the procurement system of the
DSWD KALAHI-CIDSS Project was effectively undertaken to ensure quality
projects at reasonable costs through provision of adequate capability building
assistance to community beneficiaries.
3
EXECUTIVE SUMMARY
To achieve the audit objective, the team adopted the following audit techniques,
among others:
The audit was conducted from August 15, 2005 to June 30, 2006, in compliance
with MS/TS Office Order No. 2005-034 and 034C dated July 1, 2005 and
January 10, 2006.
AUDIT CONCLUSION
The audit concluded that the procurement system for the KALAHI-CIDSS:
KKB Project was not effectively undertaken due to inadequate capability
building assistance and technical support provided by the DSWD to the
community beneficiaries.
• The required review of the detailed estimates and Program of Works (POW)
in a number of projects was not adequately undertaken resulting in the excess
grant of funds, over procurement of goods and varied cost estimates for
similar projects. In several projects, unit costs of a number of items reflected
in the detailed estimates were higher by 15% to as high as 291% of the actual
costs. The excess grants/savings were then used to procure additional
materials not included in the detailed estimates and not needed to complete the
project as designed.
4
EXECUTIVE SUMMARY
A well reviewed detailed estimates and POW would facilitate the procurement
activities of the community. Apparently, the multiple assignments of the
Deputy Area Coordinator (DAC) limited his capability to provide adequate
assistance. The need for a thorough review of each plans and estimates is
crucial due to the absence of standard designs and estimates even for
commonly implemented infrastructure projects. The absence of standards
further resulted in significant variances in unit costs per square meter of
similar projects implemented within the same municipality.
• The project procurement plans were likewise not adequately reviewed and
compliance thereof not monitored. The procurement plans of two (2) projects
were not consistent with the POW and detailed estimates while some other
procurement plans were not strictly observed. Even materials not included
therein were procured and construction changes implemented without
approved change order. The necessity of changes undertaken was therefore
not evaluated.
5
EXECUTIVE SUMMARY
MANAGEMENT’S REACTION
The results of the audit were discussed with concerned DSWD KALAHI-
CIDSS officials in an exit conference conducted on November 7, 2006.
Overall, they acknowledged the existence of deficiencies with some
reservations and are taking measures to address the concerns raised in the
report. In particular, they claimed that the DACs continuously review plans and
cost estimates, LGUs’ participation is intensified, and that standards of other
government agencies for commonly implemented projects were adopted as the
standards. Their comments were incorporated in the report, where appropriate.
TEAM’S REJOINDER
As discussed in the report, a number of plans and estimates did not pass through
the required review, apparently due to multiple assignments of DACs.
Likewise, despite the alleged LGUs intensified participation, results of audit
would show that the reviews and assistance of DACs are still necessary.
It is also apparent that the DSWD’s policy of adopting the standards of other
government agencies for commonly implemented projects were not strictly
observed in Region IV-A. The audit disclosed that similar projects implemented
even within the same municipality were of different designs and costs.