You are on page 1of 2

Beneath the wire reinforcing mesh,

53,000 feet of 11⁄4-inch 4-D wrought


iron pipe is laid on 4-inch centers in
the Chicago Stadium. Once the wire
mesh was tied down, the concrete
placing operation began.

ARTIFICIAL ICE SKATE RINKS


BY JOSEPH SMITH tance of durable brine lines and the best concrete con-
A. M. BYERS COMPANY struction.
The new floor, a permanent-type rink, measures 85 by
190 feet. Approximately 53 thousand feet of 11⁄4-inch 4-D
wrought iron pipe was laid in a hair-pin coil pattern with

P ermanent ice skating rinks are becoming more and


more popular with sports-minded Americans and
are being ordered by park districts to provide year-
each coil measuring 175 feet. The pipe runs were spaced
on 4-inch centers and placed over the original cork
board which was not removed during the razing.
round skating facilities for urban areas, as well as by There are two general types of rink floors—the open
public stadiums where ice skating shows and ice hock- and the closed or permanent type. The size depends on
ey provide amusement for thousands of people who how the rink will be used. Regulation hockey rinks must
never skate themselves. Properly managed, a perma- be a minimum of 80 by 185 feet—most rinks are 85 feet
nent ice rink can be a profitable investment, for the ice wide and 185 to 200 feet long. Ice rink floors in civic or
surface can be quickly melted and arrangements made sports arenas vary in size but are generally large enough
for roller skating, dancing, meetings and other activi- to accommodate ice shows and hockey games.
ties. OPEN TYPE This type of rink is simply constructed
Probably the most important item that must be con- and much less expensive to build than the permanent
sidered in constructing an ice rink is the brine piping. floor. It is usually built outdoors, and can be used only
Rink designers realize that once the pipe runs are buried for ice skating.
in concrete, it is costly to rip up the concrete floor and In constructing the open floor rink the refrigerant pip-
replace corroded, leaking sections. ing is usually supported on creosoted wooden sleepers,
A good example of this was the remodeling of the steel saddles, or precast concrete blocks. A bed of sand,
Chicago Stadium rink. Steel pipe failure after only 7 gravel, or other fill is provided beneath the brine piping.
years led to the first reconstruction of this rink in 1935, It should be pointed out that neither cinders, slag, or
when a wrought iron pipe system was installed. Con- similar sulphur- or chloride-bearing materials be used
crete and structural failures necessitated the second raz- as fill. Sulphur and chloride compounds in the presence
ing of the floor in 1959. However, the wrought iron brine of moisture are highly corrosive, especially to metal pipe.
lines embedded in the concrete 24 years earlier were in The ice surface is formed on a layer of clean sand which
excellent condition and probably would have served is filled in and around the piping and made level on the
many more years. top of the piping.
The cost of renovating the stadium floor was CLOSED FLOORS A permanent or closed floor may
$175,000—a figure which surely emphasizes the impor- be constructed on either an existing sub-floor or, as in
the case of many outdoor rinks, on a bed of sand or grav- proving heat transfer. In addition to reinforcement, pro-
el topped with a waterproof membrane. Where a visions must also be made for expansion and contrac-
drainage problem exists, the floor may also be installed tion of the rink floor and headers.
on concrete piers which raise it above grade level. The need for insulation is dependent upon the loca-
The piping in a permanent floor is completely embed- tion of the floor and whether or not the ice surface is to
ded in concrete, with approximately 11⁄2 inches of con- be constantly maintained. Where the floor is on grade
crete both above and below the piping. The brine head- and where a bed can be prepared which will not have a
ers are located in a trench outside of the rink floor. The tendency to settle or collect water, insulation is not nec-
floor is usually surfaced with either a cement trowel fin- essary if the ice surface is to be maintained throughout
ish, 1⁄4 inch to 3⁄8 inch thick, or with a terrazzo topping ap- the skating season. However, if the ice is to be removed
proximately 3⁄4 inch thick. A bituminous topping has and restored at frequent intervals or is to be maintained
been used in a few cases, but has not proved particular- during the summer months, the use of insulation is ad-
ly desirable as it has a tendency to absorb heat. More- visable and a level sub-floor upon which it can be laid
over, its rate of thermal conductivity is lower than that should be constructed.
of concrete or terrazzo. Insulation is always required if there are rooms, tun-
In order to obtain a satisfactory ice surface, it is es- nels, or other spaces beneath the rink floor. An insulat-
sential that the piping be adequately supported and ing material should be selected which is water-resistant
maintained in a level position. Herring bone supports, and resistant to decay, and which has a low thermal con-
creosoted sleepers, or metal T bars are generally used for ductivity. The thickness required is dependent upon pre-
pipe supports. While the pipe supports are instrumen- vailing conditions.
tal in reinforcing the slab, additional longitudinal rein- More people with more leisure will create a greater de-
forcing should also be used to resist the stresses imposed mand for structures like skating rinks and swimming
upon the floor. In a few installations, heavy gauge wire pools. It is important to have at hand the information
mesh has been wired to the top of the pipes, serving you will need if you are asked to build one.
both as a partial reinforcement and as a means of im-

OPEN FLOOR

CLOSED FLOOR

PUBLICATION #C620333, Copyright © 1962, The Aberdeen Group, All rights reserved

You might also like