AIRFILED PAVEMENT REMEDIATION WORKS AT HIA

CONCRETE BATCHING PLANT PRODUCTIVITY TRACKER (4-WEEKS)

Cum. Planned Cum. Planned Qty.


Planned (m3) Actual Qty. (m3) Variance
(m3) (m3)
Date

CTB Mix PCC CTB Mix PCC CTB Mix PCC CTB Mix PCC CTB Mix PCC

5-Apr-19 871 0 871 1303 0 1303 0 432


6-Apr-19 350 871 350 1742 50 676 50 1979 -300 237
7-Apr-19 350 871 700 2613 140 1523 190 3502 -510 889
8-Apr-19 350 871 1050 3484 240 1296 430 4798 -620 1314
9-Apr-19 350 871 1400 4355 80 1165 510 5963 -890 1608
10-Apr-19 350 871 1750 5226 120 830 630 6793 -1120 1567
11-Apr-19 350 2100 5226 270 150 900 6943 -1200 1717
12-Apr-19 1187 2100 6413 460 900 7403 -1200 990
13-Apr-19 361 1187 2461 7600 404 900 7807 -1561 207
14-Apr-19 361 1187 2822 8787 150 1029 1050 8836 -1772 49
15-Apr-19 361 1187 3183 9974 150 452 1200 9288 -1983 -686
16-Apr-19 361 1187 3544 11161 420 680 1620 9968 -1924 -1193
17-Apr-19 361 1187 3905 12348 475 904 2095 10872 -1810 -1476
18-Apr-19 361 4266 12348 300 90 2395 10962 -1871 -1386
19-Apr-19 1285 4266 13633 1000 2395 11962 -1871 -1671
20-Apr-19 368 1285 4634 14918 100 1212 2495 13174 -2139 -1744
21-Apr-19 368 1285 5002 16203 50 880 2545 14054 -2457 -2149
22-Apr-19 368 1285 5370 17488 675 3220 14054 -2150 -3434
23-Apr-19 368 1285 5738 18773 450 3670 14054 -2068 -4719
24-Apr-19 368 1285 6106 20058 240 740 3910 14794 -2196 -5264
25-Apr-19 368 6474 20058 310 44 4220 14838 -2254 -5220
26-Apr-19 1285 6474 21343 1218 4220 16056 -2254 -5287
27-Apr-19 368 1285 6842 22628 330 893 4550 16949 -2292 -5679
28-Apr-19 368 1285 7210 23913 450 904 5000 17853 -2210 -6060
29-Apr-19 368 1285 7578 25198 390 1060 5390 18913 -2188 -6285
30-Apr-19 368 1285 7946 26483 620 1220 6010 20133 -1936 -6350
1-May-19 368 1285 8314 27768 375 1246 6385 21379 -1929 -6389
2-May-19 368 8682 27768 660 60 7045 21439 -1637 -6329