Professional Documents
Culture Documents
A 14 20
B 10 16
C 7 15
D 6 17
Shortest processing time : - D-C-B-A, it is sequenced based on time with least one first
Earlier due date : - C-B-D-A, it is sequenced based on the least due date asfirst one.
Critical ratio : - A-C-D-B, In order to sequence by this we need to perform ratio analysis. For that we need
to assume 0
A 14 20 (20-0)/14 = 1.43
B 10 16 (16-0)/10 = 1.6
C 7 15 (15-0)/7 = 2.14
D 6 17 (17-0)/6 = 2.83
B 10 16 (16-14)/10 = 0.2
C 7 15 (15-14)/7 = 0.143
D 6 17 (17-14)/6 = 0.5
B 10 16 (16-21)/10 = -0.5
D 6 17 (17-21)/6 = -0.67
Job Time Due date Flow time Tardiness (flow time - due date)
A 14 20 14 14-20 = -6 = 0
B 10 16 24 24-16 = 8
C 7 15 31 31-15 = 16
D 6 17 37 37-17 = 20
Total 37 106 44
Average job flow time = Total flow time / no.of jobs = 106/4 = 26.50
Average number of jobs = Total flow time / Total time = 106/37 = 2.86 Jobs
Job Time Due date Flow time Tardiness (flow time - due date)
D 6 17 6 6-17 = 0
C 7 15 13 13-15 = 0
B 10 16 23 23-16 = 7
A 14 20 37 37-20 = 17
Total 37 79 24
Average job flow time = Total flow time / no.of jobs = 79/4 = 19.75
Average number of jobs = Total flow time / Total time = 79/37 = 2.14 Jobs
Earliest due date
Job Time Due date Flow time Tardiness (flow time - due date)
C 7 15 7 7-15 = 0
B 10 16 17 17-16 = 1
D 6 17 23 23-17 = 6
A 14 20 37 37-20 = 17
Total 37 84 24
Average job flow time = Total flow time / no.of jobs = 84/4 = 21
Average number of jobs = Total flow time / Total time = 84/37 = 2.27 Jobs
Critical ratio
Job Time Due date Flow time Tardiness (flow time - due date)
A 14 20 14 14-20 = -6 = 0
C 7 15 21 21-15 = 6
D 6 17 27 27-17 = 10
B 10 16 37 37-16 = 21
Total 37 99 37
Average job flow time = Total flow time / no.of jobs = 99/4 = 24.75
Average number of jobs = Total flow time / Total time = 99/37 = 2.68 Jobs
c) From the above analysis we can conclude that Shortest processing time is the best order to sequence
the job because average flow time, tardiness and jobs is low when compared to other sequence orders.