LAPORAN MINGGUAN PROYEK

- NAMA PROYEK -
PERUM PERURI - KARAWANG

Rencana (Ra) Realisasi (Ri) Deviasi MINGGU KE- RENCANA REALISASI DEVIASI
Minggu
Tanggal Periode Bulan Minggu Kum Minggu Kum (Ra - Ri) Keterangan
ke -
% % % % % 3 1.289 1.806 0.517

1 25-Jun-18 - 1-Jul-18 1 0.367 0.367 0.154 0.154 -0.213


2 2-Jul-18 - 8-Jul-18 0.367 0.734 0.628 0.782 0.048
3 9-Jul-18 - 15-Jul-18 0.555 1.289 1.024 1.806 0.517 21 159
4 16-Jul-18 - 22-Jul-18 2 0.555 1.844
5 23-Jul-18 - 29-Jul-18 0.555 2.399
HARI
6 30-Jul-18 - 5-Aug-18 2.313 4.712 TERPAKAI HARI TERSISA
7 6-Aug-18 - 12-Aug-18 2.313 7.025
8 13-Aug-18 - 19-Aug-18 0.021 7.046
3
9 20-Aug-18 - 26-Aug-18 2.726 9.772
10 27-Aug-18 - 2-Sep-18 4.419 14.191 GRAFIK PROGRESS MINGGUAN
11 3-Sep-18 - 9-Sep-18 4.477 18.668 9

12 10-Sep-18 - 16-Sep-18 4.766 23.434


4
13 17-Sep-18 - 23-Sep-18 7.561 30.995 8

14 24-Sep-18 - 30-Sep-18 7.314 38.309


15 1-Oct-18 - 7-Oct-18 8.402 46.711 7

16 8-Oct-18 - 14-Oct-18 5.804 52.515


17 15-Oct-18 - 21-Oct-18 5 7.444 59.959 6

18 22-Oct-18 - 28-Oct-18 8.081 68.040


5
19 29-Oct-18 - 4-Nov-18 4.521 72.561
20 5-Nov-18 - 11-Nov-18 5.16 77.721
4
21 12-Nov-18 - 18-Nov-18 4.731 82.452
6
22 19-Nov-18 - 25-Nov-18 5.235 87.687
3
23 26-Nov-18 - 2-Dec-18 2.609 90.296
24 3-Dec-18 - 9-Dec-18 4.839 95.135
2
25 10-Dec-18 - 16-Dec-18 7 2.245 97.380
26 17-Dec-18 - 21-Dec-18 2.622 100.000
1

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Renca na Real i sa si

Time Schedule Vs Realisasi


100.000

95.000

90.000

85.000

80.000

75.000

70.000

65.000

60.000

55.000

50.000

45.000

40.000

35.000

30.000

25.000

20.000

15.000

10.000

5.000

0.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Re ncana Rea li s as i