TIME SCHEDULE

PROYEK DBU
PEKERJA Jalan DBU
LOKASI Muara enim-Lahat

Sept-18
NO URAIAN PEKERJAAN Start End BOBOT 7
% Bulan ke-1

1 Persiapan

1.1 Mobilisasi Alat 7-Sep-18 12-Sep-18 1.25 1.25


A.Eksavator 7-Sep-18 12-Sep-18
B.Dozer 7-Sep-18 12-Sep-18
C.Vibro 7-Sep-18 12-Sep-18
D.Grader 7-Sep-18 12-Sep-18
E.Dumptruck 7-Sep-18 12-Sep-18

1.2 Survey Dan Soft Drawing


A.Stakeout 7-Sep-18 20-Sep-18
B.Pemasangan Patok Sta 7-Sep-18 20-Sep-18
C.Soft Drawing 18-Sep-18 22-Sep-18

2 Pekerjaan Tanah

2.1 Land Clearing 6.20 2.07


A. 1 - 2 KM 8-Sep-18 9-Sep-18
B. 2 - 3 KM 10-Sep-18 11-Sep-18
C. 3 - 4 KM 12-Sep-18 13-Sep-18
D. 4 - 5 KM 14-Sep-18 15-Sep-18
E. 5 - 6 KM 16-Sep-18 17-Sep-18
F. 6 - 7 KM 18-Sep-18 19-Sep-18
G. 7 - 8 KM 20-Sep-18 21-Sep-18

2.2 Cut & Fill 25.80 2.87


A. 1 - 2 KM 10-Sep-18 17-Sep-18
B. 2 - 3 KM 18-Sep-18 25-Sep-18
C. 3 - 4 KM 26-Sep-18 1-Oct-18
D. 4 - 5 KM 2-Oct-18 9-Oct-18
E. 5 - 6 KM 10-Oct-18 17-Oct-18
F. 6 - 7 KM 18-Oct-18 25-Oct-18
G. 7 - 8 KM 26-Oct-18 2-Nov-18

2.3 Galian Drainase ( termasuk cut n fill) 3.03


A. 1 - 2 KM 4-Oct-18 8-Oct-18
B. 2 - 3 KM 9-Oct-18 13-Oct-18
C. 3 - 4 KM 14-Oct-18 18-Oct-18
D. 4 - 5 KM 19-Oct-18 23-Oct-18
E. 5 - 6 KM 24-Oct-18 28-Oct-18
F. 6 - 7 KM 29-Oct-18 2-Nov-18
G. 7 - 8 KM 3-Nov-18 7-Nov-18

2.4 Galian BandWall


A. 1 - 2 KM 15-Oct-18 18-Oct-18
B. 2 - 3 KM 19-Oct-18 22-Oct-18
C. 3 - 4 KM 23-Oct-18 26-Oct-18
D. 4 - 5 KM 27-Oct-18 30-Oct-18
E. 5 - 6 KM 31-Oct-18 3-Nov-18
F. 6 - 7 KM 4-Nov-18 7-Nov-18
G. 7 - 8 KM 8-Nov-18 11-Nov-18

2.5 Test CBR Subgrade


A. 1 - 2 KM 9-Sep-18 10-Sep-18
B. 2 - 3 KM 13-Sep-18 14-Sep-18
C. 3 - 4 KM 17-Sep-18 20-Sep-18
D. 4 - 5 KM 23-Sep-18 24-Sep-18
E. 5 - 6 KM 27-Sep-18 28-Sep-18
F. 6 - 7 KM 1-Oct-18 2-Oct-18
G. 7 - 8 KM 5-Oct-18 6-Oct-18

3 Finishing

3.1 Penghamparan Agregat Kelas C 63.72


A. 1 - 2 KM 26-Oct-18 29-Oct-18
B. 2 - 3 KM 30-Oct-18 2-Nov-18
C. 3 - 4 KM 3-Nov-18 6-Nov-18
D. 4 - 5 KM 7-Nov-18 10-Nov-18
E. 5 - 6 KM 11-Nov-18 14-Nov-18
F. 6 - 7 KM 15-Nov-18 18-Nov-18
G. 7 - 8 KM 19-Nov-18 22-Nov-18

3.2 Test CBR Subgrade


A. 1 - 2 KM 30-Oct-18 31-Oct-18
B. 2 - 3 KM 3-Nov-18 4-Nov-18
C. 3 - 4 KM 7-Nov-18 8-Nov-18
D. 4 - 5 KM 11-Nov-18 12-Nov-18
E. 5 - 6 KM 15-Nov-18 16-Nov-18
F. 6 - 7 KM 19-Nov-18 20-Nov-18
G. 7 - 8 KM 23-Nov-18 24-Nov-18

3.3 Perapian 23-Nov-18 30-Nov-18

3.4 Report 30-Nov-18 30-Nov-18

Total Bobot Komulatif 100.00

Plan Progress 100 6.18


Plan Progress Komulatif 100 6.18
Aktual Progress
Aktual Progress Komulatif
Deviasi
Sept-18 Oct-18 Nov - 18
14 21 28 5 12 19 26 2 9 16
Bulan ke-1 Bulan ke-2 Bulan ke-3

2.07 2.07

2.87 2.87 2.87 2.87 2.87 2.87 2.87 2.87

0.51 0.51 0.51 0.51 0.51 0.51


15.93 15.93 15.93 15.93

4.93 4.93 3.37 3.37 3.37 3.37 19.30 19.30 15.93 15.93
11.12 16.05 19.42 22.79 26.17 29.54 48.84 68.14 84.07 100.00
Nov - 18 Description
23 30
Bulan ke-3
- -
100.00 100.00