Professional Documents
Culture Documents
SCIENCE AND
TECHNOLOGY
Mining Science and Technology 19 (2009) 0736–0739
www.elsevier.com/locate/jcumt
Abstract: Drilling and blasting play vital roles in opencast mining. These operations not only affect the cost of production directly
but as well and significantly, the overall operational costs. This research was carried out to find a possible way of optimizing the
drilling and blasting operations in an open pit mine of Somair (Société des Mines de l’Air), in the Niger Republic. In order to opti-
mize the drilling operation, the time taken by two drilling machines to accomplish the same task was analyzed statistically. The
result indicates that the Down the Hole Hammer Drilling Rig (DMNo406) is more efficient than the Drill Master (DM405). The
relative unit consumption of two explosives (Explus and Nitram 9), when used under the same operating conditions, were also con-
sidered and the results indicate Explus to be more economical per unit consumption with a range of 0.15 g/t–0.183 g/t, when com-
pared with Nitram 9 with a unit consumption range of 0.19 g/t–0.24 g/t in the study area.
Keywords: drilling; blasting; cumulative time; unit consumption explosive
expenditures depend to a great extend on the organi- These sophisticated crawler rigs come with an
zation and quality of blasting[8]. air-conditioned operator cabin with fully automated
However, the amount of a particular explosive re- rod handling. At the start of the drilling operation,
quired to blast a certain volume of rock is difficult to stop watches were switched on and switched off after
estimate, since it depends on parameters which in- the drilling operation, when the required level of
clude but are not limited to, the following: the drilling had been reached. A steel tape was used to
strength, toughness and incidence of discontinuities measure the depth/length of each of the holes drilled.
within the rock formation[9]. It can therefore be said A minimum of seven holes were drilled per day by
that an explosive with the greatest energy and con- each machine and the times taken to accomplish each
centration is required for removing very hard and hole were recorded. These observations continued for
medium hard rock, where high-velocity detonation three months: from June to August 2003. Sample re-
produces a shattering effect. A medium to high explo- sults of the timing of drilling operations for the two
sive can be used in medium to hard laminated rocks. machines are presented in Tables 1 and 2. The result
The greatest efficiency is obtained with fairly bulky of analysis of the drilling operations is presented in
explosives in soft to medium rock[10]. Table 3, while the cumulative result of the drilling
In the last twenty years, a number of investigators operation is presented in Table 4. In order to obtain a
have studied the possible ways of optimizing drilling comparison of the two drill rigs with respect to cu-
and blasting operations and arrive at different results. mulative time taken to accomplish a hole, the follow-
Most of them suggested that the entire process should ing equations were used:
be modelled[11–14]. Nevertheless, some of them are n
xi
still of the opinion that better understanding of the
site matter most in modeling and design of drilling
Arithmetic mean x = ¦n
i =1
(1)
¦ (x − x )
the performance of two drilling machines with a view n 2
to optimize the drilling time and to optimize the unit i
consumption of explosives for cost effective blasting. Variance s2= i =1
(3)
n −1
2 Study area
¦ (x − x )
n 2
i
This study was carried out at SOMAIR (Société 2
des Mines de l’Air), one of the important industrial Standard deviation ı= s = i =1
(4)
n −1
units in the Niger Republic, located in the northern
part of the country (district of ARLIT), at coordinates
Utilization coefficient K=
(5)
¦ time
19°3'45" and 8°25'12". The company invested in the T
exploitation of uranium ore by open pit mining. The where x is variable (shift); n number of holes drilled
average depth of occurrence of the ore ranges from per shift; ¦ time useful time of the machine per
40 m to 80 m. The sediments resulted from a
weathering process of crystalline rocks, combined shift; T duration of the shift; and Y cumulative time.
with some organic matter at the level of the Air The efficiency of a particular machine is given by
massif. The most important rocks housing the the coefficient K, when K<0.40 it means the machine
radioactive minerals (uranium-carnotite, pitchblende, is efficient; when K>0.40 the machine is not efficient.
autunite, broggerite and thorianite) are sand stone and Table 1 Timing of drilling operation on 27/06/03
shale. Length of Machine
Cumulative
Level Hole
Date time taken
drilling used (m) No.
(min)
3 Materials and method 27/06/03 21 DMNo406 25 19/38 1
27/06/03 21 DMNo406 17 19/38 2
In carrying out this study, two operations (i.e.,
27/06/03 21 DMNo406 17 19/38 3
drilling and blasting operations) were monitored.
27/06/03 21 DMNo406 17 19/38 4
3.1 Drilling operation 27/06/03 21 DMNo406 17 19/38 5
27/06/03 21 DMNo406 18 19/38 6
Data relating to the drilling operation were ob-
tained from two different machines: a Down the Hole 27/06/03 21 DMNo406 19 19/38 7
Hammer Drilling Rig (DMNo406) and a Drill Master 27/06/03 21 DMNo406 18 19/38 8
(DM405). A stop watch was connected to each of the 27/06/03 20 DMNo406 17 19/38 9
machine in order to determine its drilling time. The 27/06/03 20 DMNo406 17 19/38 10
two drilling machines were powered by a compressor. 27/06/03 20 DMNo406 16 19/38 11
They were equipped with down the hole air hammers. Note: Source: Field survey Somair, Niger Republic, 2003.
738 Mining Science and Technology Vol.19 No.6
Table 2 Timing of drilling operation on 12/07/03 spective holes during charging operations. Electric
Cumulative detonators were used with each respective charge.
Length of Machine Level Hole
Date
drilling used
time taken
(m) No. The tonnages of blasted materials produced were re-
(min)
corded. The weights of explosives consumed were
12/07/03 23 DM405 35 0/19 1
also recorded. The summary of the results is pre-
12/07/03 23 DM405 33 0/19 2
sented in Table 5.
12/07/03 23 DM405 36 0/19 3
12/07/03 23 DM405 35 0/19 4
4 Results and discussion
12/07/03 23 DM405 37 0/19 5
12/07/03 23 DM405 37 0/19 6
The study is limited to only two level of operation
12/07/03 23 DM405 35 0/19 7
i.e., levels 0/19 m and 19/38 m, where laborious
Note: Source: Field survey Somair, Niger Republic, 2003. blasting work was needed to fragment the overburden
material. Therefore, the two drilling machines were
Table 3 Result of analysis of drilling operation used under the same operating conditions in order to
Arithmetic Standard Utilization evaluate their performance. Tables 1 and 2 present a
Variance
Shift means x s2
deviation coefficient Machine day sample field records for drilling operations car-
ı K
(min) ried out using machines DMNo406 and DM405,
1 18.0 0.625 0.625 0.41 DMNo406 clearly showing that it takes machine DM405 more
2 18.9 0.400 0.400 0.39 DMNo406 time to drill and accomplish the same depth of hole,
3 21.1 0.150 0.150 0.39 DMNo406
compared with machine DMNo406. The result of the
analysis of the drilling operations when the statistical
4 24.1 0.900 0.900 0.35 DMNo406
equations were used as shown in Table 3, indicate
Mean 0.385 that machine DMNo406 is more efficient, given its
<0.40 average utilization coefficient K<0.40, while the av-
1 35.4 0.450 0.450 0.52 DM405 erage utilization coefficient of machine DM405 is
2 36.6 0.450 0.150 0.61 DM405 K>0.40. The cumulative result of the drilling opera-
tion in Table 4 and its graph in Fig. 1 shows clearly
3 38.0 0.200 0.200 0.63 DM405
that the cumulative time spent by Drill Master
4 37.2 0.500 0.500 0.56 DM405
DM405 is within 260 min and 413 min while the
Mean 0.58 cumulative time spent by the Down the Hole Hammer
>0.40 Drilling Rig, DMNo406 is between 169 min and 198
Note: Source: Field survey Somair, Niger Republic, 2003. min.
1XPEHURIEODVW
Fig. 2 Unit consumption of explosive as a Fig. 3 Unit consumption of ANFO by the two
function of the number of blast explosives as a function of the number of blast
5 Conclusions 38–44.
[3] Steve F. A solid drilling program yield more benefits
than simply cost savings. Engineering and Mining
Drilling and blasting are important steps in the Journal, 2000.
chain of mining processes and their results, such as [4] Brahma K C, Pal B K, Das C. A study on application of
fragmentation, muckpile shape and looseness, dilu- Markovian decision process in drilling and blasting op-
tion, damage and rock softening, affect the efficiency eration of opencast mines. Journal of Mines, Metals and
of downstream processes. However, the application Fuels, 2007(55): 24–29.
[5] McGregor K. The Drilling of Rock. London: C.R. Books
of the operation of blasting must conform to site con-
Ltd, 1967.
ditions and should not be borrowed from somewhere [6] Kahraman S, Bilgin N, Feridunoglu C. Dominant rock
else where improvement have been made based on properties affecting the penetration rate of percussive
safety, economy and selectivity requirements. This drills. International Journal of Rock Mechanics and
study has been able to show that after monitoring Mining Sciences, 2003(40): 711–723.
drilling and blasting operations in a particular open [7] Beste U, Jacobson S, Hogmark S. Rock penetration into
cemented carbide drill buttons during rock drilling.
pit mine one can use statistical methods to optimize
Journal of Wear, 2007(264): 1142–1151.
the entire operations for the smooth running of a [8] Rzhevsky V V. Open Cast Mining Unit Operation.
mine. Moscow: Mir Publishers, 1985.
[9] Franklin J A, Dusseault M B. Rock Engineering. New
York: McGraw-Hill Publishing Company, 1989.
Acknowledgements [10] Bell F G. Engineering in Rock Masses. London: Butter-
worth Heinemann, 1992.
The author acknowledges the contribution of Mr. [11] Neiman I B. Mathematical model of the explosive action
Idrissa Abass for providing field data of the study of a fracturing charge in a ledge rock mass. Soviet Min-
area. ing Science, 1984(19): 494–499.
[12] Favreau R F, Lilly D. Optimizing blasts through charac-
terization and on-site computer modeling during blast
References preparation. In: Proceedings, Annual Meeting Society of
Mining Engineers AIME. Minnesota, 1986.
[1] Khochman L, Hadjadj A E. New methodology selection [13] Smith M L, Hautala R L. Coupling numeric and sym-
of drilling machines. Asian Journal of Information bolic modeling in blast design. In: Proceedings of the
Technology, 2006(5): 1310–1312. Conference on Explosives and Blasting Technique. Las
[2] Piche A, Liu Q, Tran H, Van H L. Drilling and blasting at Vegas, 1991.
the Noranda Technology Centre. CIM Bulletin, 2000(93):