Location: Entrance
Hazard: Electricity
RCD or Circuit Breaker not used Enclose the main supplier board Immediate
in power connection. Also the within wooden box.
main board located outside
without any protection from rain. Provide Safety devices 5 days
Consequence: This creates the ELCB/RCD in distribution boxes
risk of electrical spark in case of to control earth leakage and to
high voltage and in adverse avoid electric sparks on the
weather condition which may workplace.
result in electrical shock and/or
damage to electrical equipment.
Location: Workplace
Hazard: First aid Allocate resources for the Immediate
For minor cuts and injuries the provision of first aid treatment.
bandages are available but in
case of serious injury proper first Arrangements for the provision of Two week.
aid treatment does not exist in first aid facilities.
the premises.
Consequence: In serious injury,
the blood will be lost in amount
to react to hospital and resulting
death can also occur.
Location: Workplace
Hazard: Stress
High rate of workload imposed Reduce the workload by giving Immediate
on the workers in order to them sufficient time on
comply with the orders in a short completion of the order.
time.
Consequence: psychologically Consult with workers on regular Timely
worker suffers allot and worker basis on work and shift pattern.
motivation and attitude to the
work change.