Total Price
Item Description Quantity including Taxes &
Duties (INR)
Head Works
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 1- Page 1 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
1.2.22 Others LS
Disc Filters
1.2.31 Others LS
1.2.39 Others LS
1.2.42 Others LS
Miscellaneous
1.2.43 Roads LS
1.2.44 Drains LS
1.2.45 Landscaping LS
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 1- Page 2 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 1- Page 3 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 1- Page 4 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
LS
LS
LS
LS
LS
Signature of Bidder
Company
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 1- Page 5 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
Head Works
SBR Tank
2.1.21 Return Activated Sludge Pumps & Surplus Activated Sludge Pumps LS
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 6 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
2.1.34 Others LS
2.1.42 Others LS
2.1.45 Others LS
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 7 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
Miscellaneous
2.1.47 Roads LS
2.1.48 Drains LS
2.1.49 Landscaping LS
The bidder shall list here details of any additional items (all area of the works)
LS
required for a complete installation
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 8 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 9 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
2.2.5.5 Decanter, sludge sump and Pumps, valves and Piping and accessories LS
Ventilation system for Blower House & Mixed Liquor Internal Recycle
2.2.7.7 LS
Pumping Station
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 10 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
The bidder shall list here details of any additional items (all areas of the works)
required for a complete installation
2.2.13 LS
2.2.14 LS
2.2.15 LS
2.2.16 LS
2.3.1.1 11kV Outdoor cable termination at Tariff Metering Unit / BESCOM VCB LS
11kV indoor cable terminations at incomer and outgoings of 11kV Metal
2.3.1.2 LS
Enclosed Switchboard of Sewage Treatment plant
11kV outdoor cable terminations at primary side of 11kV / 0.433 kV
2.3.1.3 LS
Transformers I & II
11kV XLPE Cable from Tariff Metering Unit to incomer of 11kV Metal
2.3.1.4 LS
Enclosed Switchboard of Sewage Treatment Plant
11kV XLPE Cables from Outgoing Switchgears of 11kV Metal Enclosed
2.3.1.5 Switchboard of Sewage Treatment Plant to Primary cable end boxes of LS
11kV/0.433kV Transformers
2.3.1.6 11kV Straight through joints as required LS
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 11 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
2.3.2.5 Non Segregated Aluminium Bus ducts with necessary supporting structure LS
2.3.2.6 415V Switchgear and other accessories PCCs, PMCCs as per Scope LS
2.3.2.7 415V Capacitor banks with Automatic Power Factor Correction Relay LS
2.3.2.8 110V D.C Battery, Battery Charger with D.C Distribution Board LS
Installation, testing and Commissioning of Motor Control Centres,
Distribution boards etc at various locations in Sewage Pump station &
2.3.3
Treatment plant with following major equipment, items as per scope,
specification and drawings.
2.3.3.1 Raw Sewage Pump Station MCC LS
2.3.3.2 STP PMCC LS
2.3.3.3 Decantering MCC LS
2.3.3.4 Chlorinator MCC LS
2.3.3.5 Sludge Thickner LS
2.3.3.6 Centrifuge Unit LS
2.3.3.7 Filterate Supernatant Sump Cum Pump House LS
Point wiring with conduits, wires, supports etc for Lighting fixtures,
2.3.4.4 LS
Receptacles, Ceiling fans etc
2.3.4.5 Street Lighting and Area Lighting poles with Junction boxes and Over hang LS
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 12 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
2.3.11 LS
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 13 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 14 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
LS
LS
Installation, testing & commissioning of the following Online
2.4.2
Analytical Instruments as per Technical Specification.
2.4.2.1 Dissolved Oxygen Analyzer+ Accessories + fittings LS
Instrumentation (Analog) & Control Cables and Power Cables, OFC, Trays,
2.4.3.1 LS
Glands & Lugs, cable conduits
2.4.3.2 Cable Trays LS
Installation, testing & commissioning of the following Process
2.4.4
systems with Control System Equipments
2.4.4.1 Liquid processes LS
2.4.4.3 Chlorination LS
LS
LS
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 15 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
Master (Redundant Hot Stand by) & Slaves PLC Configuration Plant floor
2.4.5.1 LS
terminal
2.4.5.2 Power supply module for PLC CPU LS
2.4.5.8 Control Panels with Internal Wiring & Local Control Panels LS
2.4.5.17 Laptop LS
2.4.5.21 Printers LS
LS
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 16 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Quantity including Taxes &
Duties (INR)
Building Services including domestic water systems The bidder shall list here
2.5.1
details of any additional items required for a complete installation
LS
LS
Total of Schedule 2 (Sub Total 2.1+Sub Total 2.2+Sub Total 2.3+Sub Total
LS 0.00
2.4+Sub Total 2.5+Sub Total 2.6) Carried to Schedule 7 - Grand Summary
Signature of Bidder
Company
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 2- Page 17 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 18 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 19 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 20 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
The bidder shall list here details of any additional items (all
areas of the works) required for a complete installation
LS 0.00
LS 0.00
LS 0.00
LS 0.00
LS 0.00
Sub Total 3.1 LS 0.00
3.2 Electrical Systems
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 21 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
3.2.3.8 110V D.C Battery, Battery Charger with D.C Distribution Board LS 0.00
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 22 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 23 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 24 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 25 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 26 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 27 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
LS 0.00
LS 0.00
LS 0.00
Sub Total 3.3 LS 0.00
3.4 General Mechanical Systems
Building Services including domestic water systems The bidder
3.4.1 shall list here details of any additional items required for a LS 0.00
complete installation.
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 28 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Signature of Bidder
Company
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 3- Page 29 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Unit including Taxes & Duties
(INR)
Chlorine++
6.1.2.1 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Poly Electrolyte++
6.1.2.2 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
(i) Network Operating charges for Wireless communication System (GPRS gateway)
Chlorine++
6.2.2.1 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Poly Electrolyte++
6.2.2.2 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
(i) Network Operating charges for Wireless communication System (GPRS gateway)
(ii)
Including all other software updates, consumables & Stationeries.
6.2.3 (iii) Instrumentation(Analog) & Control Cables and Power Cables, Per year
OFC, etc.
(iv) Refer clause no 16.5 in part-16 of volume 2 in Tender Documents
of the O&M for complete IC&A.
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 6- Page 31 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Unit including Taxes & Duties
(INR)
Chlorine++
6.3.2.1 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Poly Electrolyte++
6.3.2.2 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
(i) Network Operating charges for Wireless communication System (GPRS gateway)
(ii)
Including all other software updates, consumables, stationeries
(iii) Instrumentation(Analog) & Control Cables and Power Cables, OFC,
6.3.3 etc. Per year
(iv) Troubleshooting for ICA Equipments, painting for field Instrument enclosures.
(v) Refer
clause no 16.5 in part-16 of volume 2 in Tender Documents of the O&M for complete
IC&A.
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 6- Page 32 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Unit including Taxes & Duties
(INR)
Chlorine++
6.4.2.1 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Poly Electrolyte++
6.4.2.2 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
(i) Network Operating charges for Wireless communication System (GPRS gateway)
(ii) Including all other software updates, consumables, stationeries
(iii) Instrumentation (Analog) & Control Cables and Power Cables,
OFC, etc.
6.4.3 (iv) Troubleshooting for ICA Equipments, painting for field Instrument enclosures. Per year
(v) Refer clause no 16.5 in part-16 of volume 2 in Tender Documents of the O&M for
complete IC&A.
Chlorine++
6.5.2.1 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Poly Electrolyte++
6.5.2.2 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
(i) Network Operating charges for Wireless communication System (GPRS gateway)
(v) Refer clause no 16.5 in part-16 of volume 2 in Tender Documents of the O&M for
complete IC&A.
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 6- Page 33 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Unit including Taxes & Duties
(INR)
Chlorine++
6.6.2.1 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Poly Electrolyte++
6.6.2.2 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
(i) Network Operating charges for Wireless communication System (GPRS gateway)
(v) Refer clause no 16.5 in part-16 of volume 2 in Tender Documents of the O&M for
complete IC&A.
Training of BWSSB personnel and all other inspection, Testing, Repair, and
6.7 Per year
Handing over activities required.
Chlorine++
6.8.2.1 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Poly Electrolyte++
6.8.2.2 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 6- Page 34 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Unit including Taxes & Duties
(INR)
(i) Network Operating charges for Wireless communication System (GPRS gateway)
(v) Refer clause no 16.5 in part-16 of volume 2 in Tender Documents of the O&M for
complete IC&A.
Chlorine++
6.9.2.1 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Poly Electrolyte++
6.9.2.2 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
(i) Network Operating charges for Wireless communication System (GPRS gateway)
(v) Refer clause no 16.5 in part-16 of volume 2 in Tender Documents of the O&M for
complete IC&A.
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 6- Page 35 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Unit including Taxes & Duties
(INR)
Chlorine++
6.10.2.1 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Poly Electrolyte++
6.10.2.2 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
(i) Network Operating charges for Wireless communication System (GPRS gateway)
(v) Refer clause no 16.5 in part-16 of volume 2 in Tender Documents of the O&M for
complete IC&A.
Chlorine++
6.11.2.1 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
Poly Electrolyte++
6.11.2.2 Tonne Per year
Total quantity ----------- Tonne per year. ( Bidder to mention the quantity )
(i) Network Operating charges for Wireless communication System (GPRS gateway)
(v) Refer clause no 16.5 in part-16 of volume 2 in Tender Documents of the O&M for
complete IC&A.
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 6- Page 36 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Total Price
Item Description Unit including Taxes & Duties
(INR)
Total of Schedule 6 (Sub Total 6.1+Sub Total 6.2+Sub Total 6.3+Sub Total 6.4+Sub Total
6.5+Sub Total6.6+Sub Total 6.7+ Sub Total 6.8+ Sub Total 6.9+ Sub Total 6.10+ Sub Total 0.00
6.11) Carried to Schedule 7 - Grand Summary
Note:
+ The bidder shall quote the cost for manpower which includes manmonth rate including accommodation, transportation allowance, etc. complete
+ + The payment for The chemicals will be made to The Contractor as per actual consumption during the O&M period.
Cost of Electrical energy Consumption shall not be added in above O&M cost. Payment for Electrical energy consumption will be made directly to
BESCOM by Employer up to the amount corresponding to the energy usage guaranteed by the contractor in the Technical schedule XI.
Tenderer quoted rate for operation and maintenance (Schedule -6) cost per year shall be minimum 3.0% of the tenderer capital cost
Signature of Bidder
Company
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 6- Page 37 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Sub Total -1
Signature of Bidder
Company
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 7- Page 38 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
8.1 Mechanical
8.1.1 Pumps
8.1.1.1
8.1.1.2
8.1.1.3
8.1.1.4
8.1.1.5
8.1.2.1
8.1.2.2
8.1.2.3
8.1.2.4
8.1.2.5
8.1.3.1
8.1.3.2
8.1.3.3
8.1.3.4
8.1.3.5
8.1.4.1
8.1.4.2
8.1.4.3
8.1.4.4
8.1.5.1
8.1.5.2
8.1.5.3
8.1.5.4
8.1.5.5
8.1.6.1
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 8- Page 39 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
8.1.6.2
8.1.6.3
8.1.6.4
8.1.6.5
8.1.7.1
8.1.7.2
8.1.7.3
8.1.7.4
8.1.7.5
8.1.8.1
8.1.8.2
8.1.8.3
8.1.8.4
8.1.8.5
8.1.9 Chlorinators
8.1.9.1
8.1.9.2
8.1.9.3
8.1.9.4
8.1.9.5
8.1.10.1
8.1.10.2
8.1.10.3
8.1.10.4
8.1.10.5
8.1.11.1
8.1.11.2
8.1.11.3
8.1.11.4
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 8- Page 40 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
8.1.11.5
8.1.12.1
8.1.12.2
8.1.12.3
8.1.12.4
8.1.12.5
8.1.13.1
8.1.13.2
8.1.13.3
8.1.13.4
8.1.13.5
8.1.14.1
8.1.14.2
8.1.14.3
8.1.14.4
8.1.14.5
8.1.15.1
8.1.15.2
8.1.15.3
8.1.15.4
8.1.15.5
8.1.16.1
8.1.16.2
8.1.16.3
8.1.16.4
8.1.16.5
8.1.17.1
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 8- Page 41 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
8.1.17.2
8.1.17.3
8.1.17.4
8.1.17.5
8.1.18.1
8.1.18.2
8.1.18.3
8.1.18.4
8.1.18.5
8.1.19.1
8.1.19.2
8.1.19.3
8.1.19.4
8.1.19.5
8.1.20.1
8.1.20.2
8.1.20.3
8.1.20.4
8.1.20.5
8.1.21.1
8.1.21.2
8.1.21.3
8.1.21.4
8.1.21.5
8.1.22.1
8.1.22.2
8.1.22.3
8.1.22.4
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 8- Page 42 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
8.1.22.5
8.2.1 11 kV Switchgear*
8.2.1.1
8.2.1.2
8.2.1.3
8.2.1.4
8.2.1.5
8.2.2.1
8.2.2.2
8.2.2.3
8.2.2.4
8.2.2.5
8.2.3.1
8.2.3.2
8.2.3.3
8.2.3.4
8.2.3.5
8.2.4.1
8.2.4.2
8.2.4.3
8.2.4.4
8.2.4.5
8.2.5.1
8.2.5.2
8.2.5.3
8.2.5.4
8.2.5.5
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 8- Page 43 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
8.2.6.1
8.2.6.2
8.2.6.3
8.2.6.4
8.2.6.5
8.2.7.1
8.2.7.2
8.2.7.3
8.2.7.4
8.2.7.5
8.2.8.1
8.2.8.2
8.2.8.3
8.2.8.4
8.2.8.5
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 8- Page 44 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Note:
2. Bidder may modify the Unit and Equipment details as per his proposed process and treatment scheme.
Signature of Bidder
Company
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 8- Page 45 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Schedule 9: Dayworks
Total Price
Item Description Unit Quantity Unit Price (INR) including Taxes &
Duties (INR)
A All Labour
B Design Staff
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 9- Page 46 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Schedule 9: Dayworks
Total Price
Item Description Unit Quantity Unit Price (INR) including Taxes &
Duties (INR)
C All Equipment
Standing/Idle Equipment
Standing/idle equipment to be paid at 30% of the rate of
working equipment
Sum (C2) =30%*
0.00
Sum (C1)
Rates for equipment categories outside the above are to
be agreed by reference to the above rates.
Section C Total {Sum (C1) +Sum (C2)} 0.00
D Materials
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 9- Page 47 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
Schedule 9: Dayworks
Total Price
Item Description Unit Quantity Unit Price (INR) including Taxes &
Duties (INR)
E Fee
Sum (E)=%*Sum
(Total of Section 0.00
% A+B+C+D)
Signature of Bidder
Name & Designation
Company
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 9- Page 48 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
(The Bidder shall complete his estimated payment schedule along with his Price Proposal, based on payments being made on a periodic (monthly) basis
according to the pre-estimated construction progress. The total amount of payments to be made shall not exceed the quoted Price. The Employer and
Contractor shall make necessary adjustments to the payment schedule as the work proceeds based on the actual progress of the Works.)
Milestone
Payment Month Estimated Percent Estimated Amount Cumulative %
(Wherever Applicable)
1st Payment
2nd Payment
3rd Payment
4th Payment
5th Payment
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 10- Page 49 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
(The Bidder shall complete his estimated payment schedule along with his Price Proposal, based on payments being made on a periodic (monthly) basis
according to the pre-estimated construction progress. The total amount of payments to be made shall not exceed the quoted Price. The Employer and
Contractor shall make necessary adjustments to the payment schedule as the work proceeds based on the actual progress of the Works.)
Milestone
Payment Month Estimated Percent Estimated Amount Cumulative %
(Wherever Applicable)
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 10- Page 50 of 51
Bangalore Water Supply and Sewerage Board Volume-4- Price Proposal
(The Bidder shall complete his estimated payment schedule along with his Price Proposal, based on payments being made on a periodic (monthly) basis
according to the pre-estimated construction progress. The total amount of payments to be made shall not exceed the quoted Price. The Employer and
Contractor shall make necessary adjustments to the payment schedule as the work proceeds based on the actual progress of the Works.)
Milestone
Payment Month Estimated Percent Estimated Amount Cumulative %
(Wherever Applicable)
Section 9B: Price Schedule Contract : KR Puram STP Price Schedule 10- Page 51 of 51