Professional Documents
Culture Documents
Davies PDF
Davies PDF
Abstract: This paper provides an analysis of the aesthetic and structural properties of the cable stayed section
of the Bandra Worli Sea Link. Both theoretical and visual interpretations of the bridge have been included.
Supplementary information helps to interpret the critical analysis such as the construction process and the use
of the bridge. Giving context to the paper.
1 Introduction 2 Form
The construction of the Bandra-Worli Bridge is part The main cable stayed section of the bridge spans
of the Bandra-Worli Sea Link project necessitated by the 600m in length, consisting of two 250m cable supported
exceptionally large amounts of traffic which currently spans and two 50m conventional approach spans. The
use the Mahim Causeway travel from the western smaller cable stayed section is 350m in length and
suburbs of Mumbai to the commercial hub of the island comprises of 2 smaller cable stayed sections with a 150m
City. This affects the efficiency and links to the central span and 2 50m approach spans on either side Fig
economic metropolis and the internationally used 2. The design is described as follows by the designer.
harbour. As an upshot of Mumbai’s rapid growth in “The overall tower configuration is an inverted "Y"
economy and population since its independence, traffic shape with the inclined legs oriented along the axis of the
has stalled in the city centre. It is thought that 120,000 bridge” [1] Fig. 3. In total there are 264 cables attached
PCU’s use the Mahim causeway every day [1]. to the towers, they form a semi-fan arrangement.
Therefore for the sea link to make a substantial difference The bridge deck is constructed of pre cast box girder
to the level of traffic on the mainland it is required to be sections which are identical those used for the
able to accommodate large amounts of traffic. 8 lanes approaches “the bridge is proposed to be built utilizing
will be provided. It is the first bridge of its kind to be the concept of precast, post - tensioned, twin segmented
built in open sea, which has brought up a number of concrete box girder sections”.[2]
engineering issues.
The infrastructure within the city is completely
saturated and there is little room for expansion on the
mainland, there was no other alternative than to construct
over the bay. With this solution come a number of other
benefits, such as reduced pollution within the city,
reduced vehicle operation costs and journey times as well
as the city obtaining a coastal landmark.
This paper will be mainly concerned with the larger
two twinned tower cable stayed sections of the bridge
which were designed by consultants Dar Al-Handasah.
The bridge is expected to be opened to traffic on the 1st Figure 2: Layout
of May 2009.
4.1 Pylons
Carriageway width:
Therefore there will be 6 notional lanes. A possible case of maximum hogging is shown
below. The largest vehicle has been chosen for HB
The two types of live loads which need to be applied loading to concentrate as much load as possible towards
to the bridge separately in their most adverse form are the centre of the spans adjacent to the hogging pier. An
HA and HB loading. iterative process may be required in order to place the
HA is a UDL action over 2 notional lanes where all KEL in the most critical position but for simplicity I have
other notional lanes are loaded with 1/3 HA. In addition assumed that it is in the centre of the span to the right of
a KEL of 120kN per notional lane. These loads must be the pier.
factored for limit state analysis. Because the loaded
length is over 380m a load of 9kN/m will be used. This
needs converted into a UDL: 9 3.3 = 2.7kN/m2. 3.3m is
the notional width of the loaded lanes.
HB loading represents an abnormally large truck.
Due to the size and funtion of this bridge I believe that it Figure 12: Maximum Hog Loading Elevation
is reaosnable to suggest full HB loading for the bridge.
This is 45 units, where each wheel carries 112.5kN. The
critical load cases for maximum hogging and sagging are
shown in Figs 10-13.
There are a number of load combinations to consider in Figure 13: Maximum Hog Loading Plan
finding the worst case.
For this example I will look at load case 1 which An assumption has been made for the bending and
includes all permanent loads and primary live loads (all compression calculations based on this load case that
traffic loads). These loads have been calculated there is no lengthening of the cables during normal
previously and are shown below. loading conditions.
𝜀𝑐 = 𝛼∆𝑇
𝜀𝑐 = (12 × 10−6 ) × 25
𝜀𝑐 = 300𝜇𝜀
𝛿 = 𝜀𝑐 𝑙
𝛿 = 300 × 10−6 × 500000 = 150𝑚𝑚
(14)
The apparent stress in the deck can then be found:
𝑎𝑝𝑝𝑎𝑟𝑒𝑛𝑡
𝜎𝑐 = 𝐸𝜀𝑐
Figure 14: Bending Moment and Shear Force Diagram
𝑎𝑝𝑝𝑎𝑟𝑒𝑛𝑡
for Cable Section 𝜎𝑐 = 210000 × 300 × 106 = 63𝑁/𝑚𝑚2
(15)
Fig. 14 shows the bridge under combination 1
loading. The deck is continuous and is supported by
cables which are assumed to take all of the loads, any
support from piers has been neglected. There are
movements at each end of the cable stayed section of the
bridge and there is no moment carried. The bending and
shear diagram above shows just a small section but due
to the symmetrical and orthotropic nature of the cable
stayed section of this bridge the values will be concurrent
for the whole length of the cable stayed section. The
maximum sagging moment is 2.27MNm and the Figure15: Temperature Gradient and Associated Strains
maximum hogging is 9.09NMm.
This produces a stress of: Using Fig. 9 in BS5400 to obtain the expected
temperature gradient over the depth of the bridge.
𝑀𝑦 9.09 × 109 × 1500 Clearly these values will have to be adapted somewhat to
𝜎= = = 0.8𝑁/𝑚𝑚2 < 1 allow for the different temperatures in India. The
𝐼 17 × 1012
(13) corresponding values for strain are also shown. Stress in
10 Temperature Effects the deck can also be found and used to confirm the
capacity of the deck.
Effective temperature fluctuations and a severe
temperature gradient over the profile of a bridge can The maximum stress due to temperature effects will
cause deformations in the members. These deformations occur when the strain is 240µε. In this instance the
must be accommodated in design to avoid high levels of associated stress, assuming E of concrete is 30GPa is
stress being induced in the structure. For example, the 7.2N/mm2.
designer needs to provide bearings with adequate
displacement and rotation capacities. [7] For cable 11 Creep Effects
stayed bridges it is extremely important that temperature
changes will not cause the cables to slacken thus One of the most critical factors in the assessment of
reducing their tension and load carrying capacity a bridge is how the structure will perform and change
resulting in the large span section acting more as a beam with time. There are a number of parameters which can
affect the loading on the bridge such as, stress relaxation,
settlement and earth pressure. Possible shrinkage and must also allow inspection of the cables passage into the
creep effects are two of the most important and need to socket using an endoscope. Other methods of inspection
be incorporated into the design. are available such as electromagnetic and x-ray
The effects of creep are inevitable in concrete inspection which allow for examination of internal steel.
structures, to a certain degree. “Due to the effect of The sockets for the cables are located on the soffit of the
creep, a structure tend to amplify its deformation under a deck to aid inspection [9].
given load condition over time” [8]. These changes can Mitigation is a more effective solution but is not
substantially effect the stresses and strains calculated wholly reliable in all cases and does not remove the need
throughout this paper, which have neglected the effects for inspection. A number of measures have been taken in
of creep. The interaction between deformations of this case to improve durability and reduce the amount of
different portions of the structural system can cause required maintenance such as having glavanised strands
difficulties in design, for example “increase in the with a protective coating and covering the whole cable
deformations of the deck and pylons over time leads to with a polyethylene sheath. Microsillica and other
an increase in the initial tension in the stays” [8]. admixtures have been added to the concrete creating a
It is therefore important to counter these effects by denser, stronger and less permeable material which is
putting some initial prestress into the cables to reduce the less likely to require maintenance during construction.
effect that the creep in the concrete has on the cables. The bridge has been designed with contingency for
The amount of creep must be known in order to be able increase in traffic anticipated in Mumbai and no changes
to adjust the level of prestress accordingly. At the are anticipated in the near future.
Bandra Worli Sea Link O-Cells are used which are able
to output data about creep behaviour at various points 13 Conclusion
along the bridge, these can remain in-situ post
construction. “The bridge will be tested for reference Having studied the Bandra Worli Sea Link in depth I
geometry after 200 days in service stage which requires a can appreciate that it is a worthy representation of current
detailed analysis of the time dependant factors.” bridge engineering technology and a good example of
what is possible in the current climate. The optimised
execution of the inverted Y design of the pylon is a
solution that is both aesthetically and technically
successful. The use of tensioning mechanisms has
provided an efficient compromise between deck sizing
and costly strengthening methods.
References