You are on page 1of 10

Proceedings of Bridge Engineering 2 Conference 2009

April 2009, University of Bath, Bath, UK

A CRITICAL ANALYSIS OF BANDRA-WORLI CABLE STAYED


BRIDGE, MUMBAI
C.S.W. DAVIES1
1 Undergraduate Student - University Of Bath

Abstract: This paper provides an analysis of the aesthetic and structural properties of the cable stayed section
of the Bandra Worli Sea Link. Both theoretical and visual interpretations of the bridge have been included.
Supplementary information helps to interpret the critical analysis such as the construction process and the use
of the bridge. Giving context to the paper.

Keywords: Bandra-Worli Sea-Link, Cable-Stayed, Dar Al-Handasah, Mumbai.

1 Introduction 2 Form

The construction of the Bandra-Worli Bridge is part The main cable stayed section of the bridge spans
of the Bandra-Worli Sea Link project necessitated by the 600m in length, consisting of two 250m cable supported
exceptionally large amounts of traffic which currently spans and two 50m conventional approach spans. The
use the Mahim Causeway travel from the western smaller cable stayed section is 350m in length and
suburbs of Mumbai to the commercial hub of the island comprises of 2 smaller cable stayed sections with a 150m
City. This affects the efficiency and links to the central span and 2 50m approach spans on either side Fig
economic metropolis and the internationally used 2. The design is described as follows by the designer.
harbour. As an upshot of Mumbai’s rapid growth in “The overall tower configuration is an inverted "Y"
economy and population since its independence, traffic shape with the inclined legs oriented along the axis of the
has stalled in the city centre. It is thought that 120,000 bridge” [1] Fig. 3. In total there are 264 cables attached
PCU’s use the Mahim causeway every day [1]. to the towers, they form a semi-fan arrangement.
Therefore for the sea link to make a substantial difference The bridge deck is constructed of pre cast box girder
to the level of traffic on the mainland it is required to be sections which are identical those used for the
able to accommodate large amounts of traffic. 8 lanes approaches “the bridge is proposed to be built utilizing
will be provided. It is the first bridge of its kind to be the concept of precast, post - tensioned, twin segmented
built in open sea, which has brought up a number of concrete box girder sections”.[2]
engineering issues.
The infrastructure within the city is completely
saturated and there is little room for expansion on the
mainland, there was no other alternative than to construct
over the bay. With this solution come a number of other
benefits, such as reduced pollution within the city,
reduced vehicle operation costs and journey times as well
as the city obtaining a coastal landmark.
This paper will be mainly concerned with the larger
two twinned tower cable stayed sections of the bridge
which were designed by consultants Dar Al-Handasah.
The bridge is expected to be opened to traffic on the 1st Figure 2: Layout
of May 2009.

Figure 1: General View Figure 3: Inverted Y Piers


Craig S W Davies – cswd20@bath.ac.uk
3 Aesthetics are different, efforts have been made to mirror structural
elements to create order. The cable stayed sections are of
It was the intention of the designers to create a the same proportions, the greater span of the Bandra end
striking landmark in the design of this structure. bridge is created by merely increasing the number of
Although large span cable stayed bridge design is fairly cables, the tower height and cable spacing is similar for
restrictive due to designs of this size being fairly standard both cable stayed sections. The spacing of the piers for
and there being a finite number of cable layout options. the approach section is concurrent however it could be
There are a number of subtle design choices used for this argued that the spans could be made larger as from some
bridge that have helped to achieve an impressive design. angles there appears to be a forest of piers Fig. 4 due to
I will analyse the aesthetics of the bridge bearing in the bridge curving on plan. As already mentioned the
mind the 10 areas of importance in bridge aesthetics order of the cables seems to work well, the semi-fan
suggested by Fritz Leonhardt. These are: layout compliments the structural form of the towers
because the density of cables connected in one plane
 Fulfilment of function. increases as the 4 columns become one. This is an
 Proportions improvement of a precedent to this design in the Rion
 Order within the structure Antirion Bridge in Greece, where in my opinion the four
 Refinement of design columns which join appear too slender in comparison to
 Integration with the environment the larger pier beneath the deck.
 Surface Texture There are a number of refinements that have been
 Colour of components used to assist and improve the elegance of this structure.
Most of these refinements tend to promote the simplicity
 Character
of the bridge rather than adding to its complexity. The
 Complexity in variety most worthwhile mentioning is the connection between
 Incorporation of nature. the stays and the deck.
As with most cable stayed bridges its structural
function is clear and the structure seems to be fulfilling
its function well and efficiently. It is clear without
performing calculations, when looking at the spans
involved compared to those in the approach section the
purpose of the cables in taking the load of the bridge
deck. Due to the structural form of cable stayed bridges
the interaction between separate functional parts is very
pronounced which creates clarity and simplicity in
design. Although there are a lot of cables, the colour and
semi-fan layout blurs them when looking from a
distance, giving, in my opinion the look of a translucent Figure 4: Forest of Piers
surface.
The bridge is well proportioned. Although the The connection is hidden beneath the deck which offers a
towers are massive they do not appear to be very neat interaction between the stays and the top side
disproportional when looking at the span that they have of the deck. This solution is both graceful and practical
to cater for and again from a visual point of view there as the connections are still accessible for inspection. The
appears to be little redundancy in design. The deck is piers supporting the approach deck are widened at their
very slender; the aerodynamic shape of the box girder juncture with the deck so that there is dimensional
sections allows the edges to be thin. The final design coherence between the two elements. There is a gentle
shows that the edges will be finished in a light colour, taper to the columns in the towers which is continued
drawing attention to the deck. The width of the deck is through the deck, this is pleasing to the eye without being
so great it would have been easy to end up with very overly apparent.
large towers. A graceful solution has been found As a rule of thumb cable stayed bridges look fitting
whereby the 4 columns supporting the deck meet to form over a large expanse of water, in that sense I think that it
one column above the deck and 2 piers below. was a good design choice for its natural environment but
Disguising the fact that there is such an expansive deck. the more important factor with this bridge is its sympathy
The deck appears sufficient in completing the triangle to its urban environment. It is in a very prominent
created by the towers and the deck. position and needs to look appropriate for its stage. The
There is order in the repetitive nature of this bridge designers had the tricky task of designing something that
and although the two cable stayed sections of the bridge would befit a business district and a harbour town.
Whether this had been achieved is a matter of opinion. I created by the closed triangle. The stiff pylon in
think that the designers have achieved in making conjunction with the slender deck and numerous cables
something that from a distance is stylish and intricately means that the pylon will be subjected to high
simple in appearance but for the commuters who will use longitudinal moments due to the live loads on the deck
the road it will feel as though it is part of the city and and pylon itself.
merely an extension to the road network.
The primary observation about texture is that the 4.2 Cables
concrete in the towers is notched making it appear much
darker than the concrete used in the deck. Whether this The arrangement of the cables is 4 planes of a semi-
was a detail based more on practicality than aesthetics I fan arrangement. “The Cable Stay system comprises
am not sure but it does serve to emphasise the much 2,250 km of high strength galvanized steel wires which
lighter cables and deck which is a virtuous property in support the Cable Stay Bridge weighing 20,000 tons”[3].
bridge design. The piers also appear to be darker, this Each deck section has 2 planes of inclined cables which
may be due to them being shaded by the deck, this helps are attached to the top of the tower in one plane. This
in making the piers merge with the sea. It is difficult to layout of cables is suitable for the large spans as the
analyse how colours will look on completion. inclined arrangement provides the lateral stiffness
It is also difficult to define the character of this required. The advantage of this layout is that the deck
bridge because of the nature of the large span cable can be slender as it does not have to account for the
structure and the similarities to many other bridges of torsional inadequacies of a single plane of cables whilst
this type. My opinion is that the character of this bridge taking advantage of the preferred aesthetics of a single
is defined by its use and the fact that the function of this plane attachment to the pylon. The cables are inclined
bridge says a lot about the surrounding area and the due to A-frame pylons. “The deck and the two planes of
congestion in Mumbai, the fact that the solution to inclined stays behave like a rigid closed section in
connecting two areas which are not separated themselves bending”[4] Having this apparent closed section made
by water, using a bridge over the sea is testament to the by the deck, the inclined stays and pylon causes the
level of traffic in Mumbai and the desperate need to rigidities of the deck and pylons to work together to
relieve this with such an ambitious solution. make a rigid structure which acts against rotation in the
It is important to give a separate consideration to the deck. The inclination of the cables is such that clearance
pylons and cables which appear to have been subject to is not an issue for the passage of vehicles across the deck
much thought in terms of design. The pylons tend to due to the spans involved and the height of the pylon, it
have a governing influence over the overall architectural means that the level of inclination is slight. The method
layout. However the design appears to make structural of lateral suspension used in this case causes transverse
sense and you can see that it is proportioned well when bending moments with a maximum in the centre of the
considering the loads that it is carried. Although it is an deck. There are points of maximum shear at the edges of
architectural statement it does not clash with the the deck. It was therefore important that the design took
structural behaviour and therefore does not interrupt the into consideration the possibility that the transverse pre-
clarity of structural form which is so often one of the stress in the deck and the anchorage for the cables may
most attractive features of cable stayed structures. clash.
Cable spacing is 6.0 meters along the bridge deck.
4 Structure Fig 5

4.1 Pylons

Pylons are arguably the most important components


of a cable stayed bridge. The main span bridge has 2
pylons, each with 4 legs, each tower is inclined towards
the other by 10°, eventually merging at 98m above deck
to become a single tower. Transverse and longitudinal
post - tensioning is provided in the tower head to resist
local cable forces[4]. The single tower is tapered
towards the very top. Beneath the superstructure of the
bridge the 4 legs merge to 2 points which are carried into
the ground through the pile caps.
As with most cable stayed bridges the pylons are
very stiff. An A-frame adds torsional stiffness to the Figure 5: Cable Spacing
bridge, this is due to the natural resistance to twisting
4.3 Deck

The deck of the Bandra Worli Sea Link consists of a


hollow concrete box section with 3 cores, the dimensions
of the deck varies throughout the length of the bridge.
The pre-cast segments vary in length from 1.5m to 3.1m.
Each section of bridge deck will be post tensioned
following installation. The idea behind having a very
slender and lightweight deck is to reduce the longitudinal
stiffness, it is therefore advantageous to provide a very
flexible deck. Because this bridge utilises a lateral Figure 7. Pile Caps
suspension, bending within the deck is reduced and
torsion in the deck is not normally a critical case. For 5 Construction Methods
flexible decks the dimensions of the deck are determined
by the transverse moments and the size of the point loads The precast concrete sections of the deck were
at the anchorages, this is therefore governed by the launched incrementally between the pillars using a truss
separation of those cables. [4] For the type of box section system, known as the balanced cantilever method [6].
used at Bandra Worli Sea link the top slab is continuous The bespoke girder Fig. 8 spans between two piers with
over the webs and props. The use of webs and props the girder being supported on the outside pier by a
creates a multi-box section allows the large width which temporary support. This allows the central carriage to
is required for each direction of traffic. move between the two piers to install the precast deck
sections by picking them up and winching them into the
appropriate position. The precast sections were then
epoxied together and given a certain degree of pre-stress
to hold them in place[6]. Once each span had completed
and geometrical adjustments made the primary
continuous tendons were stressed to the required level.
Once the deck section was in its requisite position cable
connection can begin, using the following method. The
cables are delivered to site and uncoiled using a winch,
fixed to their anchor at the upper tower, winched towards
the deck connection and guided into the anchorage then
stressed to the required level using hydraulic jacks.
One major obstacle which had to be overcome
during the construction process was how to move the
large truss from the Bandra end of the bridge to the Worli
Figure 6: Deck Construction end without having to dismantle the truss which would
be too time consuming on such a high profile structure
4.4 Foundations with a strict timescale. A decision was made to use a
large sea crane to lift the truss into its new position,
The foundations were designed by Lachel Felice. however the depth of the water at low tide meant that the
The drilled shaft method of construction was used to for
the shafts. The shafts vary considerably in size,
depending on the bedrock “Rock encountered at the site
included highly weathered, fractured and oxidized
volcanic material with RQD’s of less than 25 percent and
unconfined compressive strengths of 1 MPa”[5].
Foundations for the towers comprised of 52 2m diameter
Fig. 7 piles arranged in a H shape to capably support the
legs of the pylon, they are up to 34m in length. The
loads on different parts of the structure vary considerably
and this was reflected in the variability of the shaft sizes
to accommodate loads from 2-25MN.

Figure 8: Truss Girder


crane could only be used at instances of high tide, this combination of the effects of a UDL over a notional lane
meant that the operation took a number of days. and a knife-edge load place at the most critical point
The span by span method was used for the within this lane. HB loading takes account of a
construction of the approach sections of the bridge. particularly large truck placed at the most critical point
along the bridge.
Where each span was constructed up to its nearest point
of contraflexure to the pier, the formwork is then shifted 6.1 Dead Loads
to the next span and the cycle is repeated.
All of the rebar and formwork for the pylon, the Dead loads are taken to be just the weight of the
diaphragm and the pier table were constructed off site precast deck sections, any reinforcing steel is assumed to
and the pouring was carried out in stages. Due to the be accounted for by the increased density of the concrete.
inclination and height of the main tower temporary Where dimensional information is not available
longitudinal and transverse compression struts were conservative values have been assumed.
required during construction. Geometric control is The 2 separate decks for traffic in opposite directions
required to ensure as-built accuracy, for this reason can be considered in isolation as the structural systems
reference points are taken at the base of towers, anchor for each deck are independent. The deck sections
point and completed structure, these point are used to set considered are 3m in length along most of the bridge,
formwork. there are some variations in the dimensions of the
A programme of works for the cable stayed section approach sections but these account for small differences
of the bridge as suggested by the contractor can be seen and will be neglected for the purpose of analysis.
below [1]:
Density of reinforced concrete = 2400kg/m3=23.5kN/m3
 Construction of Foundation
 Construction of Tower /Pylon below the deck The web thickness and the top and soffit thickness
 Construction of Tower / Pylon above the deck vary slightly over the sectional profile of the deck. The
 Construction of Pier Table thickness of top and soffit can be approximated as
 Construction of Diaphragm 150mm and 200mm for the web.
 Construction of Tower/ Pylon above the deck Erection of
Deck and Stay Cables Cross-sectional deck area = 7.2𝑚2
 Stressing of Stay Cables
23.5 × 7.2 = 169.5𝑘𝑁/𝑚
 Wet Joint Construction
(1)
 Continuity PT and Grouting of Cables
6.2 Super-imposed Dead Load
 Force adjustment and fine tuning.
The super-imposed dead load will be taken as merely
the components of the road surface. In reality there will
be loads incident from the services for the bridge, such as
lighting and prestressing. It is likely that these loads will
be neglible in comparison to those from the road surface.
It is likely that the deck covering will consist of a
waterproof layer, a sand asphalt mix and an asphalt
Figure 9. Dimensions For Cable Stayed Deck Section surface. I have assumed that this layer can be modelled
as 200mm of asphalt with a density of 2300kg/m 3, for
6 Loading analysis.
The following analysis of some of the primary 22.6𝑘𝑁
structural considerations for this bridge will be carried 2300 × 9.81 ÷ 1000 =
𝑚
out for Ultimate Limit State (ULS) and Serviceability 22.6 × 22.7 × 0.2 = 102𝑘𝑁/𝑚
Limit State (SLS). Dead loads for serviceability should
be taken as the actual loads whereas the loads for 6.3 Live Traffic Loading
ultimate limit state will be subject to factors for particular
materials and varying load cases such as favourable and HA is the combination of the effects of a UDL over
unfavourable effects, these are to be found in BS5400 – a notional lane and a knife-edge load place at the most
Table 1. Live loads must also be taken into account. . critical point within this lane. The primary issue which
The nominal vales for traffic loads will be given using needs to be considered at this point is the number of
the HA and HB loading convention where. HA is the
notional lanes for the deck, BS5400 3.2.9.3; this defines
how much loading there will be on the deck.

Carriageway width:

>19.0m and 22.8< Figure 11: Maximum Sag Loading Plan

Therefore there will be 6 notional lanes. A possible case of maximum hogging is shown
below. The largest vehicle has been chosen for HB
The two types of live loads which need to be applied loading to concentrate as much load as possible towards
to the bridge separately in their most adverse form are the centre of the spans adjacent to the hogging pier. An
HA and HB loading. iterative process may be required in order to place the
HA is a UDL action over 2 notional lanes where all KEL in the most critical position but for simplicity I have
other notional lanes are loaded with 1/3 HA. In addition assumed that it is in the centre of the span to the right of
a KEL of 120kN per notional lane. These loads must be the pier.
factored for limit state analysis. Because the loaded
length is over 380m a load of 9kN/m will be used. This
needs converted into a UDL: 9 3.3 = 2.7kN/m2. 3.3m is
the notional width of the loaded lanes.
HB loading represents an abnormally large truck.
Due to the size and funtion of this bridge I believe that it Figure 12: Maximum Hog Loading Elevation
is reaosnable to suggest full HB loading for the bridge.
This is 45 units, where each wheel carries 112.5kN. The
critical load cases for maximum hogging and sagging are
shown in Figs 10-13.

6.4 Combination Loading

There are a number of load combinations to consider in Figure 13: Maximum Hog Loading Plan
finding the worst case.
For this example I will look at load case 1 which An assumption has been made for the bending and
includes all permanent loads and primary live loads (all compression calculations based on this load case that
traffic loads). These loads have been calculated there is no lengthening of the cables during normal
previously and are shown below. loading conditions.

Table 1: Loading For Load Case 1


6.5 Wind Loading
Loads Factors (γf) Value
Dead 1.05 177.9kN/m From BS5400 5.3.2.1, the maximum gust that could
strike the bridge is:
Super-imposed Dead 1.75 178.5kN/m
HA 1.5 13.5kN/m 𝑉𝑐 = 𝑣𝐾1𝑆1𝑆2
HB 1.3 45 units, nominally (3)
The height of the deck is 74m from sea level
146.3kN per wheel The loaded length is 500m
The loads needs to be applied to spans in a critical S1=1
manner for both hogging and sagging in order to find the S2=1.66
bending moments in the deck. In order to display this K2=1.42
clearly I have shown the calculations for the 50m The average wind speed was found to be 4.5m/s
approach span sections of the bridge.
For maximum sag the smallest, distance between the Therefore, 𝑉𝑐 = 4.5 × 1.42 × 1 × 1.66 = 10.6𝑚/𝑠
wheel axels will cause the critical situation for HB
loading, therefore 6m separation, 9.6m in total. The horizontal wind load acting on the deck =
qA1Cd. Where q is the dynamic pressure head, 0.613Vc
And A1 is the solid horizontal projected area

Figure 10: Maximum Sag Loading Elevation


Cd is a function of b/d. In the case of the Bandra worli and lateral stability. There are a number of other minor
sea link, the depth of the deck with a 1m parapet is features which contribute to the bridges seismic design
greater than the height of the largest vehicle. For a such as using DISKTRON bearings which allow
conservsative assumtion I have said that the bridge has a complete rotation in both longitudinal and transverse
solid parapet. directions.

Therefore b/d=22700/4000=5.675 and Cd= 1.3 7 Natural Frequency

The effects of vibration on the structure of a bridge


2
𝑃𝑡 = 0.613 × 10.6 × 4 × 1.3 = 358𝑁/𝑚 can be great. Examples of where natural frequency
(4) issues of a bridge have caused problems are the Tacoma
This is not a large force; this is largely due to the Narrows bridge and the Millennium Bridge crossing the
relatively low maximum gust. These calculations do not Thames. These two examples highlight how the
take into account the aerodynamic shape of the deck. frequency of live loads, apart from wind have to be
This force is taken to act at the centroid. This force will considered. It demonstrates that the bridge should be
have been taken into account for stability of the parapet. analysed bearing in mind not only collapse but the
comfort of the users. Therefore a range of frequencies
Vertical wind can also be considered for live loading should be considered to confirm that the bridge will not
and may be part of the critical load situation, both suffer excessive movement due to having a natural
upwards and downwards wind need to be considered. frequency which matches the frequency of any
oscillatory loads applied to the bridge. “Without
A similar equation for horizontal loading is used: damaging the structure, the vibrations due to wind and
traffic can inconvenience users. These physiological
𝑃𝑡 = 𝑞𝐴3𝐶𝑙 effects are generally very subjective experiences”[4].
These physiological effects are acceptable when the
68.9 × 22.7 × 0.4 = 625.6𝑁/𝑚 natural frequency of the bridge is:
(5)
As the depth of the deck and parapet is greater than 𝟓𝑯𝒛 < 𝑓𝑜 < 75𝑯𝒛
the largest expected vehicle the depth of 4m will be used Using:
again. For uplift the depth without vehicles is always
𝐶 2 𝐸𝐼𝑔
considered as the critical case would always occur when 𝑓𝑜 =
the bridge had no vehicle loading. 2𝜋𝑙 𝑀
(6)
6.6 Seismic Loading
The value of C is π because the 2 spans on opposite sides
Mumbai is in a geographically sensitive area for of the piers are equal.
earthquakes. In general cable stayed structures are
extremely effective at coping with ground displacements L = 250m – the longest span occurs at Worli end
due to them “resting on a limited number of point suspension section.
supports” [walther]. However differential movement of E = 30GPa
the supports can cause damage to the structure, this is I = 17m4
fairly common with a bridge of this size due to the
separation and therefore geological variation between the So:
ground beneath them. Particularly affecting the junctions
between piers and the deck. For this reason horizontal
affects are much more hazardous than vertical 𝜋 30 × 106 × 9.81 × 17
𝑓𝑜 = × = 26.9
movements. 2 × 250 272.5
The Bandra-Worli Sea link design fulfils the criteria
laid out in the Indian standard for earthquake design in This is within acceptable bounds
bridges IS 1893 (1984). In the introduction to the codes
it is stated that all earthquake resistant structures should 8 Cable Sizing
have good structural configuration, good lateral stability,
stiffness and ductility. The structural form of a cable The spacing of the cables at the deck is every 6
stayed structure delivers adequate ductility and the A- metres. There is a cable connection at every other
frame shape of the piers along with the generous sizing precast section of deck. The load carried by each cable
of the foundations provides a certain degree of stiffness will include the live loads and the dead loads of the
bridge. The worst case will be when there is full HA If I now consider the section between the cables as
loading on two lanes and a third HA loading on the other 𝑤 𝑙2 505000 ×6 2
simply supported, 𝑀𝑚𝑎𝑥 = 12
= 12
=
4 notional lanes. There will also be a KEL of 120kN per
notional lane. There are 2 inclined planes per deck; for 1515kNm
the purpose of this analysis the cables will feel the entire
load. These calculations therefore conservatively neglect To check in tension, minimum compression in the deck
any support from the piers in the cable section. of the suspended bridge section will occur for a in the
I will just display calculations for the worst case deck section furthest away from the pier, it has a stress
cable. This is assumed to be where the angle of the cable of:
to the plane of the bridge is least. It should be born in
6.2
mind when looking at these calculations using 𝜎𝑏 = = 0.86𝑁/𝑚𝑚2
operational loads that the worst loading case for the 7.2
cables may be during construction. The critical angle is (10)
26°. The compression due to bending moments is shown
below:
120
tan 𝜃 = 1515 × 106 × 2000
250 𝜎𝑏 = = 0.176𝑁/𝑚𝑚2
17 × 1012
𝜃 = 26° (11)
(7) This level of stress seems fairly low for the size of
The total load over 6 metres of the bridge with the load we are looking at. This seems to be due to the
aforementioned vertical loading loading is 3.03MN. This particularly high second moment of area value for the
is split evenly between 2 planes, therefore 1.515MN. deck. These calculations show that the whole section of
the deck will be in compression due to the force
This will be the vertical load in the cable, the tension in transferred by the cables and tensile considerations can
the cable is therefore: be ignored.

1.514 9.2 Compression in the Tower


𝑇 = sin 26 = 3.46𝑀𝑁 (8)
The vertical force in each cable will be equal to the
Using technical information from cable contractors, weight of the section of deck that the cable carries and
Shanghai Pujyang Cable Company, I have found that the any live loads that this section of the deck may be
strength of the steel used is 1860N/mm2. This is 64mm subjected to. This has been calculated to be 3.03MN.
diameter of solid steel or 19 cables with a diameter of For all of the cables, the total compressive force carried
15.7mm diameter. into the tower is around 242.4MN. Due to the changing
cross section of the tower it is difficult to easily see
9 Compression and Bending where the maximum stress will occur without more in
depth analysis. For this purpose, as I do not have
9.1 Deck Compression dimensional information for the tower, I will calculate
the area of C50 concrete required to safely carry this load
Some of the horizontal force in the cable will be and make visual comparisons to the profile of the tower.
carried as compression in the deck. I have calculated the
horizontal force for all of the cables to find the 242.4
compression in the deck. 𝐴= = 4.85𝑚2
50
(12)
The total compression in the deck due to cable forces is The actual area of concrete appears to be much greater
200MN. To check this value against the strength of the than this throughout the whole profile of the tower. The
concrete deck, a stress value needs to be obtained. most critical condition for the tower may be uneven
loading, for instance full HA and HB on only one side,
𝐹 200 × 106 this will cause considerable moments at the base of the
𝜎= = = 27.7𝑀𝑃𝑎
𝐴 7.2 × 106 tower.
(9)
This compression is acceptable as the compressive
strength of concrete is between 50 and 60Mpa.
9.3 Bending bridge than a cable stayed bridge, giving unexpected load
conditions.
To calculate the bending moments in the bridge I BS5400 5.4 dictates that the bridge must be
have had to assume that the bridge is continuous over analysed for 2 conditions, overall temperature increases
piers and has non moment carrying connection at both and variations in temperature through the profile of the
ends. Due to the scale of the bridge it would be difficult bridge.
to clarify the distribution of moments for the bridge as a I will initially look at the stresses caused by
whole. For this reason I will display those for just the overall temperature increases. The design values for the
cable stayed section. temperature variation are unknown but for the climate in
India I would suggest a conservative value of ±25°.
Concrete has a thermal expansion of 12×106/°C. The
greatest distance between expansion joints is 500m.

𝜀𝑐 = 𝛼∆𝑇
𝜀𝑐 = (12 × 10−6 ) × 25
𝜀𝑐 = 300𝜇𝜀
𝛿 = 𝜀𝑐 𝑙
𝛿 = 300 × 10−6 × 500000 = 150𝑚𝑚
(14)
The apparent stress in the deck can then be found:
𝑎𝑝𝑝𝑎𝑟𝑒𝑛𝑡
𝜎𝑐 = 𝐸𝜀𝑐
Figure 14: Bending Moment and Shear Force Diagram
𝑎𝑝𝑝𝑎𝑟𝑒𝑛𝑡
for Cable Section 𝜎𝑐 = 210000 × 300 × 106 = 63𝑁/𝑚𝑚2
(15)
Fig. 14 shows the bridge under combination 1
loading. The deck is continuous and is supported by
cables which are assumed to take all of the loads, any
support from piers has been neglected. There are
movements at each end of the cable stayed section of the
bridge and there is no moment carried. The bending and
shear diagram above shows just a small section but due
to the symmetrical and orthotropic nature of the cable
stayed section of this bridge the values will be concurrent
for the whole length of the cable stayed section. The
maximum sagging moment is 2.27MNm and the Figure15: Temperature Gradient and Associated Strains
maximum hogging is 9.09NMm.
This produces a stress of: Using Fig. 9 in BS5400 to obtain the expected
temperature gradient over the depth of the bridge.
𝑀𝑦 9.09 × 109 × 1500 Clearly these values will have to be adapted somewhat to
𝜎= = = 0.8𝑁/𝑚𝑚2 < 1 allow for the different temperatures in India. The
𝐼 17 × 1012
(13) corresponding values for strain are also shown. Stress in
10 Temperature Effects the deck can also be found and used to confirm the
capacity of the deck.
Effective temperature fluctuations and a severe
temperature gradient over the profile of a bridge can The maximum stress due to temperature effects will
cause deformations in the members. These deformations occur when the strain is 240µε. In this instance the
must be accommodated in design to avoid high levels of associated stress, assuming E of concrete is 30GPa is
stress being induced in the structure. For example, the 7.2N/mm2.
designer needs to provide bearings with adequate
displacement and rotation capacities. [7] For cable 11 Creep Effects
stayed bridges it is extremely important that temperature
changes will not cause the cables to slacken thus One of the most critical factors in the assessment of
reducing their tension and load carrying capacity a bridge is how the structure will perform and change
resulting in the large span section acting more as a beam with time. There are a number of parameters which can
affect the loading on the bridge such as, stress relaxation,
settlement and earth pressure. Possible shrinkage and must also allow inspection of the cables passage into the
creep effects are two of the most important and need to socket using an endoscope. Other methods of inspection
be incorporated into the design. are available such as electromagnetic and x-ray
The effects of creep are inevitable in concrete inspection which allow for examination of internal steel.
structures, to a certain degree. “Due to the effect of The sockets for the cables are located on the soffit of the
creep, a structure tend to amplify its deformation under a deck to aid inspection [9].
given load condition over time” [8]. These changes can Mitigation is a more effective solution but is not
substantially effect the stresses and strains calculated wholly reliable in all cases and does not remove the need
throughout this paper, which have neglected the effects for inspection. A number of measures have been taken in
of creep. The interaction between deformations of this case to improve durability and reduce the amount of
different portions of the structural system can cause required maintenance such as having glavanised strands
difficulties in design, for example “increase in the with a protective coating and covering the whole cable
deformations of the deck and pylons over time leads to with a polyethylene sheath. Microsillica and other
an increase in the initial tension in the stays” [8]. admixtures have been added to the concrete creating a
It is therefore important to counter these effects by denser, stronger and less permeable material which is
putting some initial prestress into the cables to reduce the less likely to require maintenance during construction.
effect that the creep in the concrete has on the cables. The bridge has been designed with contingency for
The amount of creep must be known in order to be able increase in traffic anticipated in Mumbai and no changes
to adjust the level of prestress accordingly. At the are anticipated in the near future.
Bandra Worli Sea Link O-Cells are used which are able
to output data about creep behaviour at various points 13 Conclusion
along the bridge, these can remain in-situ post
construction. “The bridge will be tested for reference Having studied the Bandra Worli Sea Link in depth I
geometry after 200 days in service stage which requires a can appreciate that it is a worthy representation of current
detailed analysis of the time dependant factors.” bridge engineering technology and a good example of
what is possible in the current climate. The optimised
execution of the inverted Y design of the pylon is a
solution that is both aesthetically and technically
successful. The use of tensioning mechanisms has
provided an efficient compromise between deck sizing
and costly strengthening methods.

References

[1] HCC. Bandra Worli Sea Link Project - Construction


Methods. HCC India Website. [Online] 2008.
Figure 16: Effect of Pre-stress on cable tension with
[2] Dar Consultants. Bandra Worli Sea Link. [Online]
2008.
12 Durability and Maintenace
[3]Bandra-Worli Sea Link - Mumbai, India.
Waymarking. [Online] April 2009.
Due to this bridge being a new build it is unlikely
that there will be any durability or serious maintenance [4] Walther, Rene, et al. Cable Stayed Bridges. s.l. :
issues for some time, however the these issues must be Thomas Telford, London, 1988.
accounted for and any possible inadequacies in durability [5] Drilled Shaft Construction For the Bandra Worli Sea
Link Project. Conrad, W. Felice and Brenniman,
highlighted so that there is a prior awareness of any
Henry. 2004, pp. 84-95.
shortfalls. It is useful to look to precedents prior to
design to see if there is a trend in the type of damage [6] Bridge Construction Paper - Cable Stay
caused to cable stayed structures over time which can be Construction . VSL.
alleviated through design. [7] Effects of Temperature Variations on Precast,
It is important to undertake comprehensive Prestressed. Barr, P. J., Stanton, J. F. and Eberhard,
M. O. 2005, Jounal of Bridge Engineering.
inspections both periodically and after extreme events
[8] Long Term Behaviour of Cable Stayed Bridges.
such as floods or storms. In cable structures critical
damage to the cables themselves must be prevented. The Scotti, Andrea. 2003.
[9] LaViolette, Mike et al. 2007, Bridge Construction
cable anchorages at Bandra Worli have been designed to
allow full access and a thorough inspection. The design Practices.

You might also like