Project: 1443 – WK RTO

892 USA
Date: 09/07/2019

2019 Jul Aug Sep 2019


Today

Project Duration 40 days Jul 8 - Aug 31

Material D.O. 16 days Jul 10 - Jul 31

Fabrication
a) Cutting & Fit up 16 days Jul 17 - Aug 7

b) Welding 15 days Jul 22 - Aug 9

c) Tri-fit 6 days Aug 7 - Aug 14

Painting 6 days Aug 13 - Aug 20

ITP(FAT) 2 days Aug 21 - Aug 22

Insulation 6 days Aug 23 - Aug 30 Sep 9

Shipment
Project: 1444 – WK RTO
839 SG
Date: 09/07/2019

2019 Jul Aug Sep Oct Nov Dec 2020 2020


Today

Project Duration Jul 8 - Jan 20

Material D.O. Jul 23 - Aug 5

Fabrication
a) Cutting & Fit up Aug 7 - Aug 25

b) Welding Sep 19 - Oct 2

c) Tri-fit Oct 3 - Oct 17

Inspection Oct 18 - Oct 23

Painting Oct 4 - Nov 7

Insulation Nov 9 - Nov 23

Shipment Nov 25 - Dec 7