Professional Documents
Culture Documents
FIDIC Claims & Disputes Resolution Under FIDIC 99 REDBOOK PDF
FIDIC Claims & Disputes Resolution Under FIDIC 99 REDBOOK PDF
CLAIMS &
DISPUTES RESOLUTION
UNDER FIDIC 99
REDBOOK
Suranga Jayasena
Senior Lecturer
Department of Building Economic
University of Moratuwa
CLAUSE 20
suranga@becon.mrt.ac.lk 1
12/11/2009
CLAUSE 20
pages 58 to 62
CLAIM FLOWCHART
suranga@becon.mrt.ac.lk 2
12/11/2009
No No
Clause 20.1
Contractor provides
Engineer with detailed
particulars and within
42 days and final claim
within 28 days after
Dispute end of effect if
continuing event and
complies with other
contractual
No requirements
No
Clause 20.1
Clause 20.4 Claim approved is
Contractor is satisfied limited, if failure has
Yes
with Engineer’s prevented or prejudice
decision the proper
investigation of Claim
suranga@becon.mrt.ac.lk 3
12/11/2009
Clause 20.1
Clause 20.1 Contractor provides
The Engineer Engineer with detailed
(dis)approves, or gives Yes particulars and within
opinion on the Claim 42 days and final claim
within 42 days within 28 days after
end of effect if
continuing event and
complies with other
contractual
requirements
No No
No
No No
suranga@becon.mrt.ac.lk 4
12/11/2009
20.4
Determination
Certification
Instructions Dispute
Valuations
Opinion
Recall...
CLAUSE 20
suranga@becon.mrt.ac.lk 5
12/11/2009
Parties present
submissions to the Amicable settlement
DAB
20.2
PARTIES APPOINT THE DAB
suranga@becon.mrt.ac.lk 6
12/11/2009
20.2
PARTIES APPOINT THE DAB ... CONTINUED ...
20.2
PARTIES APPOINT THE DAB ... CONTINUED ...
?
suranga@becon.mrt.ac.lk 7
12/11/2009
20.2
PARTIES APPOINT THE DAB ... CONTINUED ...
20.2
PARTIES APPOINT THE DAB ... CONTINUED ...
suranga@becon.mrt.ac.lk 8
12/11/2009
A “FULL-TERM” DAB
20.2 Para 7 – “if at any time the Parties so agree, they may
jointly refer a matter to DAB for it to give its opinion. Neither
party shall consult DAB on any matter without the
agreement of the other party
suranga@becon.mrt.ac.lk 9
12/11/2009
20.4
OBTAINING ADB’S DECISION
20.4 Reads “if a dispute (of any kind whatsoever)
arises between the Parties ....
in connection with or arising out of the Contract
or the execution of the Works
including any dispute as to any certificate,
determination, instruction, opinion or valuation
of the Engineer ...
may refer the dispute in writing
20.4
OBTAINING ADB’S DECISION ... CONTINUED ...
No matter can be referred to DAB unless it is in
dispute
but, no formal notice of dispute required
If matter is still in discussion or only interim
determination given
other party may assert that “no dispute”
DAB to find if dispute has arisen – see if
agreement achieved under sc 3.5
suranga@becon.mrt.ac.lk 10
12/11/2009
When ...
Final determination rejected
Discussions discontinued without agreement
Party decline to participate in discussion
Party decline to reach agreement as per sc3.5
So little progress being achieved that it is clear
that agreement is unlikely
20.4
WRITTEN REFERENCE TO DAB
The Written Submission by Claimant
For the decision of DAB
Describes the situation
Sets out the principles of the matter in dispute
What Claimant wishes the DAB’s decision to be
suranga@becon.mrt.ac.lk 11
12/11/2009
20.4
DAB’S DECISION
within 84 days after receiving the original
reference, or
within such other period as may be proposed by
the DAB and approved by both parties
approvals must not be unreasonably withheld or
delayed
20.4
DAB’S DECISION ... CONTINUED ...
Note that DAB decision shall be admissible in
evidence in arbitration. sc 20.6
Therefore well reasoned decision preferred
suranga@becon.mrt.ac.lk 12
12/11/2009
20.4
DISSATISFACTION ON DAB’S DECISION
20.5
AMICABLE SETTLEMENT
During first 56 days after notice
Parties should attempt amicable settlement
DAB should not get involve in amicable
settlement procedure.
If no amicable settlement (or attempt thereto),
.....
the dispute shall be finally settled by
international arbitration sc 20.6
suranga@becon.mrt.ac.lk 13
12/11/2009
20.7
WHAT IF...
Formal notice of dissatisfaction NOT given,
DAB decision became final and binding
a Party FAILS to comply with decision
20.8
WHAT IF...
a dispute occurs, but
no DAB is in place, either by
the word ‘otherwise’ shall be used to
expiry or otherwise cover failure of appointing DAB due to
defect in document. E.g. “the
appointing entity is non-existent”
suranga@becon.mrt.ac.lk 14
12/11/2009
20.6
ARBITRATION
Unless otherwise agreed by both parties
Rules of International Chamber of Commerce
Three arbitrators
1101001011010110101010101010100100010111010011001100110
0101010010100101010011110101011101010110110101000101001
0110010101001111010010011011010111010111100010110011101
1001010010101001010100101111101001101010100100101001111
1001110101001001011111100010101111111001101001010100101
011110100101010100101010110100 0 1 0 0 0 0
suranga@becon.mrt.ac.lk 15
12/11/2009
CASE
PROPOSED SCHOOL BUILDING FOR SEEVALI COLLEGE
Contractor asked for the same rate from the upper floor block
work but the Engineer rejected it and approved rate of his own
schedule of prices (used for Engineer’s Estimate) which is less
than claimed rate.
TASK 01
suranga@becon.mrt.ac.lk 16
12/11/2009
Dear Sirs,
REFERENCE TO ADJUDICATION
...............
.....
We are not in agreement with the rates determined by the Engineer for
Block work (varied item) at Ground Floor Level we carried out under the
above contract. Therefore a dispute has arisen between the parties to the
above Contract and pursuant to Sub-clause 20.4 we refer the dispute to
DAB for its decision. The detail claim is attached herewith.
Thank you.
Yours faithfully,
suranga@becon.mrt.ac.lk 17
12/11/2009
TASK 02
TASK 02 - TIPS
How much to write - Keep it short but clear
Format – Not strict, but you may use something similar to
arbitration submissions
Order –
Introduce parties and contract
DAB appointed
Contractual provision 1,
Contractual provision 2,
Occurance, your statement
........
Dispute
Your claim for decision by DAB
suranga@becon.mrt.ac.lk 18
12/11/2009
ABC Construction,
No 9, Road Lane
Colombo 20
Contractor/Claimant
and
Seevali College,
111/1, Lane Road
Colombo 19.
Employer/Respondent
STATEMENT OF CLAIM
........
measure and pay basis without price fluctuation adjustment for the
priced bills of quantities bid by the contractor, at the time and in the
suranga@becon.mrt.ac.lk 19
12/11/2009
Variation changing all ground floor walls to block work from brick
suranga@becon.mrt.ac.lk 20
12/11/2009
Engineer gives oral instructions the Contractor shall confirm the said
instruction by writing.
Evaluation].
rate for an item shall be the rate specified for similar work.
10. The Contractor confirmed the Variation instructions and notified the
Item 2.34: Block Work Walls at Second Floor level, by his letter to the
suranga@becon.mrt.ac.lk 21
12/11/2009
11. The Contractor included the block work quantity with applicable rate
12. Sub-clause 14.6 of the FIDIC Conditions provides that the Engineer
13. The Engineer, in the Interim Payment Certificate, had not certified
the rate applied for Variation and had determined a lower rate.
PARTICULARS
<<< Include a brief calculation here, annex if there are detailed calculations>>
percentage points above the discount rate of the Central Bank of Sri
Contract.
suranga@becon.mrt.ac.lk 22
12/11/2009
16. I certify on behalf of the Contractor that the facts stated in this
..........................................................
Muralitharan, M.
Project Coordinator
ABC Construction
No 9, Road Lane
Colombo 20
WELL--DONE
WELL
suranga@becon.mrt.ac.lk 23