You are on page 1of 23

12/11/2009

CLAIMS &
DISPUTES RESOLUTION
UNDER FIDIC 99
REDBOOK

Suranga Jayasena
Senior Lecturer
Department of Building Economic
University of Moratuwa

CLAUSE 20

suranga@becon.mrt.ac.lk 1
12/11/2009

CLAUSE 20

... is all about Claims and Disputes Resolution

pages 58 to 62

CLAIM FLOWCHART

Claim Event, Clause 20.1


Circumstance Yes Contractor gives notice
arisen to the Engineer
describing the event or
circumstance giving
No rise to the Claim,
within 28 days
Contractor becomes
aware or should have
No Claim
become aware of the
Claim

suranga@becon.mrt.ac.lk 2
12/11/2009

Clause 20.1 Clause 20.1


Contractor gives notice Contractor provides
to the Engineer Engineer with detailed
describing the event or particulars and within
circumstance giving 42 days and final claim
rise to the Claim, Yes within 28 days after
within 28 days end of effect if
Contractor becomes continuing event and
aware or should have complies with other
become aware of the contractual
Claim requirements

No No

Clause 20.1 Clause 20.1


Claim Fails Claim approved may be
The Employer is limited, if failure has
discharged from all prevented or prejudice
liability in connection the proper
with the Claim investigation of Claim

Clause 20.1
Contractor provides
Engineer with detailed
particulars and within
42 days and final claim
within 28 days after
Dispute end of effect if
continuing event and
complies with other
contractual
No requirements

No

Clause 20.1
Clause 20.4 Claim approved is
Contractor is satisfied limited, if failure has
Yes
with Engineer’s prevented or prejudice
decision the proper
investigation of Claim

suranga@becon.mrt.ac.lk 3
12/11/2009

Clause 20.1
Clause 20.1 Contractor provides
The Engineer Engineer with detailed
(dis)approves, or gives Yes particulars and within
opinion on the Claim 42 days and final claim
within 42 days within 28 days after
end of effect if
continuing event and
complies with other
contractual
requirements

Clause 20.1 Clause 20.4


The Engineer Yes Contractor is satisfied
(dis)approves, or gives with Engineer’s
opinion on the Claim decision
within 42 days

No No

Contractor does not


tolerate Engineer’s Yes Dispute
delay in decision

No
No No

Clause 20.1 Clause 20.4


The Engineer Yes Contractor is satisfied
(dis)approves, or gives with Engineer’s
opinion on the Claim decision

suranga@becon.mrt.ac.lk 4
12/11/2009

20.4
Determination

Certification

Instructions Dispute

Valuations
Opinion

Recall...

CLAUSE 20

... is all about Claims and Disputes Resolution

However ... Typical sequence shown in


beginning of the document is useful

suranga@becon.mrt.ac.lk 5
12/11/2009

TYPICAL SEQUENCE OF DISPUTE EVENTS


ENVISAGED IN CLAUSE 20

8.1 20.2 20.4 20.4 20.6


Commencement Parties appoint A Party refers a A Party issues a A Party initiate
Date the DAB dispute to the “notice of arbitration
DAB dissatisfaction”

Parties present
submissions to the Amicable settlement
DAB

<28d <84d <28d >56d

DAB gives Arbitrators


its decision appointed

20.2
PARTIES APPOINT THE DAB

 Within 28 days of Date of Commencement?

 ... by the date stated in Appendix to Tender.


(28 days in example in sample forms)

 Guidance for Particular Conditions – “It is preferable,


but not essential, to agree before the Letter of
Acceptance”

 A list of potential members may be included in tender

suranga@becon.mrt.ac.lk 6
12/11/2009

20.2
PARTIES APPOINT THE DAB ... CONTINUED ...

 Parties jointly appoint a DAB

 DAB comprises one or three member stated in Appendix

 If not stated nor agreed, it shall be three

 If three, each party nominate one member for


approval of other party, two members appoint
chairman

 Each part pay one-half of DAB remuniration

20.2
PARTIES APPOINT THE DAB ... CONTINUED ...

 What if parties fail to agree DAB?

 An appointing entity is named in Appendix to Tender 20.3

 What if date of appointment not stated in Appendix?

 Might go for “ad-hoc” DAB > i.e. only appointed if and


when a particular dispute arises.

 What if appointing entity not stated in Appendix?

 ?

suranga@becon.mrt.ac.lk 7
12/11/2009

20.2
PARTIES APPOINT THE DAB ... CONTINUED ...

 Parties may appoint members to be available to


replace members resign or be terminated

 Otherwise, replacement be similar to new


appointment

 Termination shall only be by mutual agreement of


Parties

 usually DAB expires when discharge become effective

20.2
PARTIES APPOINT THE DAB ... CONTINUED ...

 DAB members must be selected carefully, because

 Parties empowers the DAB to reach decisions with which


they undertake to comply, and

 A DAB member cannot normally be removed except with


the agreement of both parties (20.2 last para)

suranga@becon.mrt.ac.lk 8
12/11/2009

A “FULL-TERM” DAB

 Appointed before Contractor commence Works

 Visit the Site on a regular basis

 Also available to assist in avoiding disputes during


these visits

 20.2 Para 7 – “if at any time the Parties so agree, they may
jointly refer a matter to DAB for it to give its opinion. Neither
party shall consult DAB on any matter without the
agreement of the other party

DAB: “FULL-TERM” OR “AD-HOC”


 Red Book General Conditions are for “full-term” – see 20.2

 Parties may decide on appropriate model by


considering (among other things):

 Extent of Contractor’s Activities off-site – paying DAB may not


economical

 Extent of uncertainties in scope of works – underground


tunnelling – a full-term DAB most appropriate

 Extent of Variations expected – full-term

 Magnitude of the Contract – No. of DAB members 1 or 3

suranga@becon.mrt.ac.lk 9
12/11/2009

20.4
OBTAINING ADB’S DECISION
 20.4 Reads “if a dispute (of any kind whatsoever)
arises between the Parties ....
 in connection with or arising out of the Contract
or the execution of the Works
 including any dispute as to any certificate,
determination, instruction, opinion or valuation
of the Engineer ...
 may refer the dispute in writing

 to the DAB for decision”

20.4
OBTAINING ADB’S DECISION ... CONTINUED ...
 No matter can be referred to DAB unless it is in
dispute
 but, no formal notice of dispute required
 If matter is still in discussion or only interim
determination given
other party may assert that “no dispute”
 DAB to find if dispute has arisen – see if
agreement achieved under sc 3.5

suranga@becon.mrt.ac.lk 10
12/11/2009

THE MATTER HAS DEVELOPED INTO A


DISPUTE

When ...
 Final determination rejected
 Discussions discontinued without agreement
 Party decline to participate in discussion
 Party decline to reach agreement as per sc3.5
 So little progress being achieved that it is clear
that agreement is unlikely

20.4
WRITTEN REFERENCE TO DAB
The Written Submission by Claimant
 For the decision of DAB
 Describes the situation
 Sets out the principles of the matter in dispute
 What Claimant wishes the DAB’s decision to be

 A copy must be passed to the other party


(Respondent) and Engineer

suranga@becon.mrt.ac.lk 11
12/11/2009

20.4
DAB’S DECISION
 within 84 days after receiving the original
reference, or
 within such other period as may be proposed by
the DAB and approved by both parties
 approvals must not be unreasonably withheld or
delayed

 for complex matters DAB may propose to give


decisions in stages

 shall be reasoned and stated that it given under


sub-clause 20.4

20.4
DAB’S DECISION ... CONTINUED ...
 Note that DAB decision shall be admissible in
evidence in arbitration. sc 20.6
 Therefore well reasoned decision preferred

 The Contractor shall execute the Works while


DAB proceeding.

 The decision shall be binding on both parties

suranga@becon.mrt.ac.lk 12
12/11/2009

20.4
DISSATISFACTION ON DAB’S DECISION

 The Party must give a formal “notice of


dissatisfaction” within 28 days.
 It establishes the claimant the right to commence
arbitration.
 Unless the notice given within 28 days, decision
become final and binding.

20.5
AMICABLE SETTLEMENT
 During first 56 days after notice
 Parties should attempt amicable settlement
 DAB should not get involve in amicable
settlement procedure.
 If no amicable settlement (or attempt thereto),
.....
the dispute shall be finally settled by
international arbitration sc 20.6

suranga@becon.mrt.ac.lk 13
12/11/2009

20.7
WHAT IF...
 Formal notice of dissatisfaction NOT given,
 DAB decision became final and binding
 a Party FAILS to comply with decision

 Other Party may refer THIS FAILURE directly


to arbitration,

without having to refer again to DAB or try


amicable settlement

20.8
WHAT IF...
 a dispute occurs, but
no DAB is in place, either by
the word ‘otherwise’ shall be used to
 expiry or otherwise cover failure of appointing DAB due to
defect in document. E.g. “the
appointing entity is non-existent”

 the dispute may be referred directly to


arbitration under sc 20.6

 However, there is still room for amicable


settlement

suranga@becon.mrt.ac.lk 14
12/11/2009

20.6
ARBITRATION
 Unless otherwise agreed by both parties
 Rules of International Chamber of Commerce

 Three arbitrators

 Language be language defined in 1.4

 Shall commence before or after completion


 Shall not prevent executing obligation of contract
during the proceedings

::: BREAK :::

We’ll try something practical now

1101001011010110101010101010100100010111010011001100110
0101010010100101010011110101011101010110110101000101001
0110010101001111010010011011010111010111100010110011101
1001010010101001010100101111101001101010100100101001111
1001110101001001011111100010101111111001101001010100101
011110100101010100101010110100 0 1 0 0 0 0

suranga@becon.mrt.ac.lk 15
12/11/2009

CASE
PROPOSED SCHOOL BUILDING FOR SEEVALI COLLEGE

Variation Instructions were issued changing the Ground Floor


walls to block work from brick work which was in original
contract. No block work was found in ground floor level in the
original contract but upper floor partition walls in the original
contract was similar type.

Contractor asked for the same rate from the upper floor block
work but the Engineer rejected it and approved rate of his own
schedule of prices (used for Engineer’s Estimate) which is less
than claimed rate.

TASK 01

Write the cover letter for referring the matter to DAB

You may make necessary assumptions

suranga@becon.mrt.ac.lk 16
12/11/2009

<< Date >>

<< Adjudicator1 >> - chairman (member)


<< Adjudicator2 >> - member
<< Adjudicator3 >> - member

Dispute Adjudication Board


Proposed School Building for Seevali College
<< Address >>

Dear Sirs,

REFERENCE TO ADJUDICATION

...............

.....
We are not in agreement with the rates determined by the Engineer for
Block work (varied item) at Ground Floor Level we carried out under the
above contract. Therefore a dispute has arisen between the parties to the
above Contract and pursuant to Sub-clause 20.4 we refer the dispute to
DAB for its decision. The detail claim is attached herewith.
Thank you.

Yours faithfully,

<< Contractor >>

cc: << Employer >>


<< Engineer >>

suranga@becon.mrt.ac.lk 17
12/11/2009

TASK 02

Write the Adjudication Submission

You may make necessary assumptions

TASK 02 - TIPS
How much to write - Keep it short but clear
Format – Not strict, but you may use something similar to
arbitration submissions
Order –
Introduce parties and contract
DAB appointed
Contractual provision 1,
Contractual provision 2,
Occurance, your statement
........
Dispute
Your claim for decision by DAB

suranga@becon.mrt.ac.lk 18
12/11/2009

In the matter of Adjudication


Dispute Between

ABC Construction,
No 9, Road Lane
Colombo 20
Contractor/Claimant

and

Seevali College,
111/1, Lane Road
Colombo 19.
Employer/Respondent

STATEMENT OF CLAIM

........

1. The Contractor is a civil engineering contractor registered under

ICTAD as a Grade C-5. The Employer is a public school in Colombo.

2. By a contract dated 09th October 2009 (‘the Contract’), The Contractor

undertook to construct and complete certain building works, namely

“the Construction of Proposed School Building for Seevali College”

(‘the Works’) in consideration for payment by the Employer on

measure and pay basis without price fluctuation adjustment for the

priced bills of quantities bid by the contractor, at the time and in the

manner prescribed by the contract.

suranga@becon.mrt.ac.lk 19
12/11/2009

3. The Contract Incorporates the FIDIC Conditions of Contract for

Construction, First Edition 1999 (‘the FIDIC Conditions’).

4. The Dispute Adjudication Board (‘the DAB’) was appointed by a

tripartite agreement signed on 15th October 2009.

5. Sub-clause 13.1 of the FIDIC Conditions provides that Variations may

be initiated by the Engineer and the Contractor shall execute and be

bound by each Variation.

6. On 28th October during a site visit, the Engineer instructed a

Variation changing all ground floor walls to block work from brick

work specified in the Contract.

suranga@becon.mrt.ac.lk 20
12/11/2009

7. Sub-clause 3.3 of the FIDIC Conditions provides that in the event

Engineer gives oral instructions the Contractor shall confirm the said

instruction by writing.

8. Sub-clause 13.3 of the FIDIC Conditions provides that each Variation

shall be evaluated in accordance with Clause 12 [Measurement and

Evaluation].

9. Sub-clause 12.3 of the FIDIC Conditions provides that the appropriate

rate for an item shall be the rate specified for similar work.

10. The Contractor confirmed the Variation instructions and notified the

applicable rate to be the rate of similar work in the Contract – BOQ

Item 2.34: Block Work Walls at Second Floor level, by his letter to the

Engineer dated 01st November 2009.

suranga@becon.mrt.ac.lk 21
12/11/2009

11. The Contractor included the block work quantity with applicable rate

to its Interim Statement dated 31st December 2009.

12. Sub-clause 14.6 of the FIDIC Conditions provides that the Engineer

shall issue an Interim Payment Certificate which shall state the

amount which the Engineer fairly determines to be due.

13. The Engineer, in the Interim Payment Certificate, had not certified

the rate applied for Variation and had determined a lower rate.

14. The Engineer failed to certify payment to the Contractor of sums to

which it is entitled pursuant to the said Sub-clause 12.3; which sums

amount to Rs. 115,000.00.

PARTICULARS

<<< Include a brief calculation here, annex if there are detailed calculations>>

15. Accordingly, the Contractor claims Rs. 115,000.00 under Sub-clause

12.3 of the Contract, plus interest thereon at the rate of three

percentage points above the discount rate of the Central Bank of Sri

Lanka, compounded monthly, pursuant to Sub-clause 14.8 of the

Contract.

suranga@becon.mrt.ac.lk 22
12/11/2009

16. I certify on behalf of the Contractor that the facts stated in this

Statement of Claim are true to the best of my knowledge and belief.

..........................................................

Muralitharan, M.

Project Coordinator

ABC Construction

No 9, Road Lane

Colombo 20

WELL--DONE
WELL

suranga@becon.mrt.ac.lk 23

You might also like