Professional Documents
Culture Documents
TABLE OF CONTENTS
CONTENTS PAGE
i
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
ii
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
iii
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
iv
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
APPENDIX
v
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.1 Introduction
(a) Works contained in this document cover the Design and Build of a
new Waste Water Treatment Plant (WTP).
i Staff Quarters
S5-1
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(e) The locations of the new WTPs are as shown in drawings, and the
lands provided for the wastewater treatment plant are
approximate.
(f) The effluent generated from each facility will be delivered to the
treatment plant by pipelines, which will be aligned both above and
below ground depending on site conditions.
(g) The treated water must comply with “Sixth Schedule of the
Environmental Quality Act 1974”, which is noted to be very
stringent comparing with similar standards in the other countries.
See “the Sixth Schedule of the Environmental Quality Act 1974” in
Appendix 5.1.
(h) Since the proposed WTP will be located in the area as indicated in
the drawing, special design considerations should be given to its
aesthetic view, minimum emission of noise, fume and odour.
(i) The WTP shall be enclosed in a structure with proper access and
ventilation and in accordance with authorities requirement.
S5-2
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.2.1 Scope
The purpose of this specification covers the minimum requirement for the
design, supply, fabrication, installation, testing and commissioning,
warranty and maintenance provisions for the Wastewater Treatment
System. The Contractor, with the S.O., shall ensure full compliance with
authorities.
The system shall consists of (but not limited to) Oil and Grease
Separators, Holding Tank / Equalising Tank, Influent Tank, sludge tank,
Aeration, all mechanical and electrical system, associated works and etc.
S5-3
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Appendix 1 details the Effluent Quality Criteria for Discharge to Sewer. All
discharge to the sewer should meet the quality of the standard to comply
with Department of Environment.
(b) System shall have overflow by pass system which divert flow back
to inlet tank / sump
S5-4
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The design shall conform to the contemporary rules and regulations laid
out by the following authorities, standardization institution and utility
operators’ requirements:
S5-5
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
MCC will be provided near the respective plant equipment. The MCC shall
be type tested to form 4B construction. Busbar of the panel shall be
insulated by PVC sleeving with appropriate colour. The major components
for the MCC are as follow:
(h) Contactor
S5-6
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(j) MCCB
All the cable to plant equipment shall be armoured and installed on hot
dipped galvanized cable tray. For small power and lighting, the cable shall
be PVC insulated type in cable GI conduit or GI cable trunking. Cover
shall be provided for cable exposed to sunlight. The type of cables
proposed shall be as follows:
All the electrical installation shall be provided with will earthing system.
S5-7
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Keluar signs and emergency lights shall be provided for emergency and
during power failure. These will be of the self-contained type with nickel-
cadmium batteries providing 3 hours back up and automatic charging
facilities.
Local control panels shall be provided. The LCPs shall come with LED
type indicating light for monitoring and push button for control during LCP
mode. The material for the LCP panel shall be stainless steel.
The panel shall include PLC, UPS (2 hours back-up), MIMIC diagram,
alarm annunciator and marshalling compartment. All the equipment shall
be connected to PLC’s input and output points via the marshalling
compartment.
S5-8
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
i Manual operation
- Operator could control the individual equipment as per
local manual mode via the touch screen.
ii Semi-Auto operation
- Operator select the sequence shall be control by PLC.
All control and instrument cable be armoured type and installed on hot
dipped galvanized cable tray or cable trunking. Separate cable tray or
trunking from electrical cable shall be provided. Cover shall be provided
for cable exposed to sunlight. The type of cables proposed shall be as
follows:
S5-9
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
For data circuit (analogue signal only), lightning protection unit (LPU) shall
be provided at PLC end for indoor equipment installation. For outdoor
equipment installation, LPU shall be provided at equipment and PLC end.
The Contractor shall be responsible for all interfacing works within and
beyond the boundary of the project sites.
5.2.6 Miscellaneous
5.2.6.1 Training
S5-10
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.2.6.3 Spares
Contractor shall provide a spare parts catalogue complete with lead time
and prices and will provide revision services.
S5-11
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Upon expiration of warranty period, the Client shall have the option to
order spares directly from original equipment manufacturer or any local
agent.
(a) Training for local staff to operate and continue maintenance of the
system upon completion of 2 year maintenance service.
S5-12
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.2.6.6 Programme
The Contractor shall provide detailed procedures for the Testing and
Commissioning of the systems and equipment proposed by him.
5.3.1.1 General
If the S.O. is not satisfied with the pipe design calculations submitted by
the Contractor, the S.O. shall establish the test load for each pipe size
and class by physical testing as follows:-
S5-13
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(a) Upon the instruction and in the presence of the S.O., the
Contractor shall manufacture two (2) number standard pipes.
(b) All the pipes shall be suitably marked for identification, cured and
tested to failure to establish the respective crushing load strengths.
Pipes sizes stated in the Drawing and Bill of Quantities refer to nominal
internal diameters. The plastic liner plate and high alumina lining are
additional requirements to those specified in the above-mentioned
Standards and hence the finished internal diameters shall not be reduced
accordingly as shown in the table below:
---------------------------------------------------------------------------------------------
Nominal Internal Minimum Finished Internal
Diameter (mm) Diameter (mm)
Class Y/Class Z/Class ZZ/Class 1.5Z
---------------------------------------------------------------------------------------------
375 375
450 450
525 525
600 600
675 675
750 750
900 900
975 975
1050 1050
1200 1200
1350 1350
1500 1500
1650 1650
------------------------------------------------------------------------------------------
(a) The load test shall be conducted in accordance with the methods
described in para 4.22 and Appendix B of Australian Standard AS
1342:1973.
S5-14
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Concrete pipes shall have spigot and socket rubber ring joints to BS 2494.
5.3.2.1 General
Vitrified clay pipes, bends and fittings shall be obtained from a approved
manufacturer and shall comply in all respects with BS 65 and BS 2494.
The S.O. may require these tests to be carried out in his presence or
alternatively properly substantiated test certificates for each batch of
consignment of pipes shall be submitted for approval. The pipes shall not
be dispatched from the place of manufacture until the approval of the
pipes has been given by the S.O. following whatever test or inspection the
S.O. may have called for. Notwithstanding the approval of the pipes at
the place of manufacture by the S.O., the Contractor shall be responsible
for the fault that may be found in the pipes on sites.
S5-15
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The joints shall be of a type which can remain completely watertight while
accommodating a deflection of 5 degrees in any direction.
5.3.4 General
All Ductile iron pipes and fittings shall conform to BS 4772. Ductile iron
pipes with flexible joints or welded flanges shall be Class K9. Fittings
without branches and screwed-on flanges shall be Class K12. Fittings with
branches shall be Class K14.
(a) Flexible Joint for Ductile Iron Pipes shall be K-Type unless
otherwise approved by the S.O. and shall employ the circular
rubber gasket for sealing purposes unless specified otherwise.
The gasket shall be of such size and shape that, when jointed in
accordance with the manufacturer’s instructions, it provides a
positive seal within the manufacturer’s range of maximum joint
deflection and withdrawal under all combinations of joint and
gasket dimensional tolerances, and in the range of pressure likely
to occur in the pipeline.
(b) Flanged Joints shall be used in all cases when sewers are laid
above ground. They shall have faces that are at right angles to an
concentric with the axis of the bore. The faces of the flanges on
fittings shall be at right angles to the directional axes. Flanges
shall be faced over the jointing surface with a tool mark finish
having a pitch of 1 + 0.33mm; serrations may be spiral or
concentric. Pipes having screwed on flanges shall be sealed at the
S5-16
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
All ductile iron pipe and fittings shall be lined with sulphate resisting
cement mortar to the thickness shown in Table 49 of BS 4772. The
surface of the lining shall be substantially smooth but “fine crazing”
associated with cement rich surfaces shall be permitted. Isolated
shrinkage cracks shall be acceptable provided their width does not
exceed 0.8mm. The surface shall be substantially free from laitance and
any sand segregation present shall be minimal.
All pipes and fittings shall be factory-coated internally and externally with
a corrosion resistant coal tar pitch varnish to a type and grade generally
used for ductile iron pipe or bitumen complying with the requirements of
BS 3416. The coating may be applied by dipping, spray, brush or roller
but coating that does not bond firmly or shows voids or holidays shall be
rejected. The internal coating shall be applied while the cement mortar
lining is still moist.
All pipes, specials, fittings, etc. shall be carefully inspected for damages
which may have been caused during loading, transit and unloading before
lowered into the trench. Damaged pipes shall not be used in the Works.
S5-17
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) Steel and ductile iron pipes shall also be 150mm compacted
sandfill with at least 150mm sandfill cover all over or as shown on
the drawing.
5.3.7 Pipelaying
5.3.7.1 General
Pipes shall be laid only after the trench has been inspected and approved
by the S.O. on site. The trench shall be kept sufficiently firm and dry for
making joints.
5.3.7.2 Handling
Pipes shall be inspected for defects before being gently lowered into the
trench by means of a crane or suitable shear logs and chain blocks with
rope slings. Pipes shall be laid true to invert, alignment and fall. Care shall
be exercised to ensure that the barrel of every pipe is evenly bedded
throughout, with suitable excavation to receive the socket or collar.
S5-18
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The Contractor shall provide and fix at such points as may be directed,
properly painted, black and white sight rails set to correct levels. At least 3
such rails shall always be in position for each length of sewers. Pipes
shall be accurately boned and laid to even gradients, centered and in
straight lines between manholes. Sight rails shall be 1.8m long and
painted black and white. Such rails shall be fixed and maintained at the
changes in grade or lines at not more than 15m apart. Invert levels to be
set out shall be referred to protected level pegs near such manhole and
change of grade or line. Boning rods shall be designed to show the pipe
line invert level below the sight rails. When excavation is completed and
before any further work commenced wooden pegs shall be driven into the
bottom of the trench at not more than 4m centres, the level of each peg
being adjusted to the proposed sewer invert by the use of the sight rails
and boning rods.
5.3.7.5 Cleaning
Temporary stops for effectively closing the open ends of the mains shall
be used to prevent rain water from washing earth and other foreign matter
into the main. These stops shall be used at all times and shall be moved
forward as the work of laying and jointing progresses.
S5-19
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
In the event obstructions not shown on the plans are encountered during
the progress of the work which requires alterations to the proposed works,
the S.O. shall have the authority to change Drawings and order the
necessary deviation from the line or grade shown. Contractor shall not
make any deviation from the specified line or grade without approval of
the S.O..
5.3.8 Jointing
S5-20
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Pipes shall be bedded, true to line and grade with uniform bearing for the
entire barrel length. All materials shall be removed from the interior of the
pipe and the inner surface of the bell or socket and the other surface of
the spigot end shall be thoroughly cleaned so that good joints can be
made. Pipe sections shall be laid such that the offset of the inside of the
pipes at any joint will be held to a minimum at the invert. The maximum
offset at the invert of pipe shall be one percent of the inside diameter of
the pipe or 10mm, whichever is smaller. Unavailable offsets shall be
distributed around the circumference of the pipe such that the minimum
offset occurs at the invert. After the joints have been made the pipe shall
not be disturbed in any manner. The interior of each pipe, after being laid,
shall be thoroughly cleaned.
The jointing of spigot and socket shall be done with approved flexible
rubber ring joints.
The spigot and socket of each pipe shall be thoroughly brushed clean
before laying. The pipes shall then be laid to line and level and secured in
position with the socket ready to receive the next pipe. The rubber ring
shall be fixed properly onto the spigot of the next pipe and this shall be
pushed into the socket of the laid pipe. It shall be checked that the rubber
ring has properly "rolled" into place and that the joint is tight. Otherwise
the pipe shall be refixed.
Rubber sealing rings for pipe jointing shall comply with BS 2494 and shall
in addition contain anti-ozonants. The hardness of the rubber shall be
such that the joint when made on the installed pipes will be watertight as
specified under any combination of working or test loads. Immediately
before assembling each joint incorporating a rubber ring seal, the rubber
shall be inspected for cracks, every part of the ring being deformed by
S5-21
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
hand to about 15cm radius. If under this deformation any cracks appear or
are revealed, the ring shall be rejected, cut through completely to prevent
inadvertent use, and the matter reported forthwith to the S.O.. If more than
three successive rings inspected in this way are rejected the Contractor
shall on the instruction of the S.O. stop all pipe jointing until the cause of
the defect has been proved and remedied to his satisfaction.
The mechanical joints are flexible joints and shall conform to BS 4772.
They are used for Ductile Iron pipe unless otherwise shown on the
Drawings or instructed by the S.O.. They shall employ the circular rubber
gasket for sealing purpose unless specified otherwise. The seal is
affected by compressing a rubber gasket, onto the jointing surface in the
pipe socket and the outside of the pipe spigot by means of a pressure
gland and a series of T-head bolts and nuts. When jointed in accordance
with the manufacturer’s instructions, it provides a positive seal under all
combinations of joint and gasket dimensional tolerances, and in the range
of pressure likely to occur in the pipeline. It is capable of axial movement.
Certain portions of sewer pipelines may not be heavy enough to resist the
possible uplift due to water pressure until the pipelines have been properly
covered. The Contractor shall make adequate arrangement to keep the
excavation dry until the filling of the pipelines is completed or shall adopt
other approved means of ensuring the stability of the Works.
The material for granular bedding shall meet the following requirements:
S5-22
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
20 mm 100 -
9.5 mm 80 90
4.75 mm 10 25
2.36 mm 0 15
28 mm 100 -
20 mm 80 90
9.5 mm 10 25
4.75 mm 0 15
S5-23
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
in the location of lines will be permitted by the S.O.. The Contractor shall
make all closures with suitable pipe and approved connections to
compensate for cumulative errors in pipeline installation. The cutting of
reinforced spun concrete pipes for inserting specials, fittings or closure
pieces shall be carried out in a neat and workmanlike manner with an
approved cutting machine without damage to the pipe and so as to leave
a smooth end at right angles to the axis of the pipe. Cast and ductile iron
pipes may be cut by hand, using a hacksaw or may be machine cut. Only
experienced men shall be employed by the Contractor on this work. Steel
pipes shall be machine cut at the maker's works or the Contractor may
make arrangements for them to be cut by an approved local engineering
firm. Flame cutting of pipes on Site will not be permitted. After making any
cut to steel pipes the cut end shall be fettled and all damaged portions of
lining and sheathing shall be cleaned from the pipe which shall be
scraped and wire brushed to bare metal in areas stripped and then primed
with a rust inhibitor, the lining and sheathing being then made good to the
full original thickness. The Contractor shall take every precaution to
ensure that both the measurements and the cutting of pipes are to the
accuracy required and should any errors occur the Contractor shall
remedy the same at his own expense and as the S.O. directs.
S5-24
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The Contractor shall agree with the S.O. the programme for all interim and
final inspection. The necessary form requesting such inspections will be
prepared by the S.O. for formal submission by the Employer but all fees
and costs of such inspection are to be borne by the Contractor.
S5-25
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
i General inspection
iv Level checks
S5-26
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(a) The test pressure for gravity pipelines up to and including 750mm
nominal bore shall be not less than 1.2m head of water above the
pipe soffit or ground water level, whichever is the higher at the
highest point, and not greater than 6m head at the lowest point of
the section. Steeply graded pipelines shall be tested in stages in
cases where the maximum head, as stated above, would be
exceeded if the whole section were tested in one length.
(b) The pipeline shall be filled with water and a minimum period of 2
hours shall be allowed for absorption, after which water shall be
added from a measuring vessel at intervals of 5 minutes and the
quantity required to maintain the original water level noted. Unless
otherwise specified, the length of pipeline shall be accepted if the
quantity of water added over 30 minutes period is less than 0.5
litre per linear metre per metre of nominal bore.
S5-27
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) The intensity of illumination within the pipe and the rate of draw of
the camera shall be such as to allow a proper examination of the
inside of the pipe. Provision shall be made for the movement of the
camera to be stopped and its position recorded and for permanent
photographs to be taken at any point requested by the S.O..
5.3.12.6 Infiltration
S5-28
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The water used in the test shall be of fair quality, reasonably free
from sediment and from a source approved by the S.O..
S5-29
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
the escape of air. Any vent hole drilled shall be plugged and
saddled before the test is applied. Where the main runs up-hill
the pressure gauge shall be situated at the bottom of the section
as otherwise excessive pressure may be imposed upon the lower
part of the pipeline with a risk of damage to anchorages designed
to withstand the specified test pressure. Pressure for the test
shall be applied by means of an approved force pump at the
highest convenient point on the main so as to minimise the
pressure against which the pump will have to be operated. The
test section shall be completely filled with water for at least 24
hours prior to testing to allow for absorption of water into the
pipes and/or jointing materials.
Water shall be pumped into the main rising the pressure slowly in
increments of 10.0 m head of water with pauses of one minute
between each increment. When any appreciable drop in pressure
is noted during one of these pauses the test shall be stopped
until the cause of the pressure drop has been investigated and
rectified. The pipes shall be tested to the pressure of 1.5 times
maximum working pressure head to be determined by the S.O..
The leakage test shall follow after the pressure test. The
pressure in the pipes shall be maintained to the maximum
S5-30
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.13.1 Cleaning Up
All water retaining and other structures shall be pumped dry and washed
and swept out free of all debris mud dirt and construction materials.
All equipment and fittings shall be cleaned, greased and oiled and all
necessary adjustments made to ensure their full working efficiency.
All site roads, paths and drains shall be swept clean and dry and all
construction plant and materials removed from site.
Following the cleaning up of the whole or a section of the Works for the
taking over by the Employer, a detailed inspection shall be carried out by
the appropriate Authority together with the S.O. who shall be
accompanied by the Contractor or his Representative.
S5-31
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Any defects found during the detailed inspection of the Works shall be
rectified, as required by the appropriate Authority. The works shall then
be cleaned again and re-inspected. The cost of making good any defect
shall be borne by the Contractor.
5.3.13.3 Maintenance
One month before the end of the Defects Liability Period the Contractor
shall inform the S.O. of the expiry date and arrange for the cleaning up
and ventilation of the Works and the provision of all necessary ladders
etc., required for inspection of the works by the S.O. accompanied by
the Contractor or his Representative. Any default resulting from faulty
material or workmanship used in the execution of the works shall be
rectified by the Contractor at his own cost to the satisfaction of the
S.O./Authority.
5.3.14 Manholes
S5-32
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
S5-33
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
End of pipes shall be built into the walls of manholes and finished off in
cement mortar.
Manhole covers and frames shall comply with BS 497: Part 1 and be of
the type and size specified in the Drawings.
The heavy duty type shall be used in roadways and paved areas unless
otherwise directed by the S.O.. The medium duty type shall be used in
public areas inaccessible and unlikely to be inaccessible to vehicular
traffic, while the light duty type shall be installed in household manholes
within owner's properties.
Manhole covers and frames shall be well fitting, flush at the top and
should not rock. Where required by the S.O., the covers and frames
shall be tested in accordance with BS 497, the cost of which shall be
deemed to be included in the cost of the manhole covers.
S5-34
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.14.5 Ladder
5.3.15.1 General
All service sewer pipes between local reticulation sewer and household
manhole in owner's premise shall be of the type and size as shown on
the Drawing. All materials and workmanship shall comply with all the
provisions of this Specification.
S5-35
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
S5-36
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
concerned with the minimum interference to the free flow of water in the
watercourse. Details of any temporary works which may affect the
watercourse shall be submitted to the S.O. at least 14 days before
starting work. Where the pipelines passes underneath a river, stream,
canal or ditch, unless otherwise detailed on the Drawings it shall be
encased in concrete. The minimum thickness shall be 150mm. Unless
otherwise shown, the depth of cover shall be not less than 60cm from
the bed of the river, stream or ditch to the top of the concrete. The
Contractor shall fill the trench in both banks with rockfill or concrete up to
levels as shown on the Drawings or as directed by the S.O.. The extent
of this work may be varied to suit each individual crossing. Unless
otherwise ordered, the concrete encasement of the pipe shall extend at
least to a section vertically below the tops of the banks. Provide
protection against erosion to the banks by means of stone pitching or
riprap.
5.3.17.1 General
The Contractor shall satisfy himself as to the soil conditions along the
pipe jacking route and if he consider it to be necessary, he shall carry
out further soil investigations at his own cost.
S5-37
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
S5-38
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Stainless Steel collars shall be installed between the sections of the pipe
to permit proper joining of the pipe sections.
S5-39
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Before starting work, the Contractor shall submit to the S.O. for
approval, a detailed schedule of the entire jacking operation. Approval of
such schedule shall not relieve the Contractor of his responsibility to
provide a fully satisfactory installation. The Contractor shall include with
his submission evidence that he has successfully completed a jacking
installation using the procedures similar to those proposed.
After the jacking operation has begun, the Contractor shall work
continuously and expeditiously in accordance to programme until the
complete length of jacked pipes is installed. This continuous work where
required shall not be construed as overtime work.
The pipes for the jacking operation shall be 3.05m long and shall be
jacked into place to line and level.
The Contractor shall be required to furnish and install and remove to the
extent required, thrust blocks or whatever provisions that may be
required for backing up the jacks employed in jacking the pipe forward.
The jacking pit shall also be equipped with steel rails or beams
embedded in concrete for placement and alignment of each pipe during
the jacking operation.
The Contractor shall be fully responsible for the design and construction
of the jacking and receiving pits, thrusting wall, installation of jacking
equipment, sheeting, bracing, etc and for the efficient execution of the
S5-40
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The Contractor shall provide all plant and equipment for mixing and
injecting grout. The apparatus shall be of a type approved by the S.O.
and shall be capable of mixing effectively and stirring the grout and then
forcing it into the grout connections in continuous uninterrupted flow.
Grout pipes shall be secured to the grout holes in such a manner that no
leakage shall occur during grouting. After completion of grouting,
pressure shall be maintained by means of polyvinyl chloride stop plugs
or other suitable devices until the grout has set sufficiently. The grout
holes shall then be completely filled with dense concrete and finished
neatly without voids and projections.
The Contractor shall ensure that fouling of the equipment and lines is
prevented by constant circulation of grout and by periodic flushing out of
S5-41
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
the system with water. Flushing shall be undertaken with the grout
intake valve closed, the water supply valve open, and the pump running
at full speed.
S5-42
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.17.9 Grouting
The void at the joint between two adjacent pipes and the steel thrust
collar shall be completed by pressure grouting and finished neatly
without voids and projections to ensure a smooth continuous surface
throughout the pipeline. The composition of the grout shall consist of
Portland cement and sand slurry, the crushing strength of which when
set shall be equal to that of the pipe.
The connections at the two ends of the jacked pipeline shall be made at
the jacking and receiving pits. The Contractor shall maintain and keep
these pits intact and in a safe condition to facilitate the connections. The
Contractor shall remove all other temporary works and any concrete
blocks including cutting and removing part of the walls of the pits that
are in the way of the pipework connections.
5.3.17.11 Safety
The minimum of plant shall be used in the pits, and any which produces
noxious gases or is operated by electricity at a greater voltage than
240V shall be permanently outside the pit at ground level.
S5-43
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
All persons entering the pits shall wear safety helmets constantly, and
shall leave the pits for meal breaks, rests and the like.
At the beginning of each shift and after any break for refreshment or
other reason, the Contractor shall provide and use an approved
instrument to check for noxious gases before anyone re- enters either
pit.
The Contractor shall ascertain for himself and comply with all the
requirements of KTMB in connection with the pipe jacking work under
the railway line and within the railway reserve. The Contractor shall pay
particular attention to the high fill embankment of the railway line and
shall ensure that the stability of the embankment will be safe-guarded in
connection with his pipe jacking work. No heaving of the ground beneath
the railway tracks shall be permitted during the duration of the pipe
jacking operation.
S5-44
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The Contractor may use alternative methods of pipe jacking other than
as detailed above. The alternative method shall be submitted to the S.O.
for approval with a description of the proposed method of operations
before proceeding with the construction. Approval of the alternative
method by the S.O. shall not relieve the Contractor of the responsibility
for making satisfactory installation meeting the criteria set herein above.
The Contractor shall construct all anchors and thrust blocks as required
and where directed by the S.O. and as shown on the Drawings. In
general, thrust blocks will be placed at all changes in pipe direction
greater than seven (7) degrees. Each thrust block shall be designated to
have a sufficient bearing area and shall be placed to safely transmit to
the surrounding point. Thrust devices shall be cast-in-place concrete
metal harness, or other suitable devices. Thrust blocks shall be
constructed of Grade 20/20 concrete and shall be placed between fitting
and trench wall or trench bottom, as the case may be. The bearing faces
of the block shall be placed against freshly cut and undisturbed trench
wall or bottom of sound material. If the thrust exceeds the bearing value
of the surrounding soil, the soil shall be pre-compacted before placing
concrete. All concrete shall be kept behind the bells of fittings. Formwork
shall be constructed wherever necessary to confine the concrete to the
prescribed dimensions for the block. All form lumber shall be removed
prior to testing.
S5-45
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.19.1 General
All protection coatings shall be non-toxic and shall not impart any odour
or taste to the water. All ferrous surfaces in contact with water shall be
given two coats of epoxy coal tar bitumastic paint. The external surfaces
shall be painted with two coats of approved zinc rich epoxy paint.
Valves flanges shall conform to ANSI B16.1 Class 125. They shall be of
the raised face type, square to the longitudinal axis and truly faced over
their whole width. Bolt holes shall be drilled off centre lines and shall be
truly in line end to end with the longitudinal axis.
S5-46
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.19.3 Inspection
Unless otherwise specified, all valves shall be cleaned and painted with
2 coats of coal tar epoxy paint with a resin base after installation.
S5-47
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
delivery. All valves shall be body tested to one and half the working
pressure. Seat tests to the working pressure as specified or as required.
i. With the edge or disc closed and with the valve fixed at
one end only, the test pressure shall be applied to that
face of the wedge or disc, the other face being at
atmospheric pressure.
With the wedge or disc open the test pressure (gauge) specified
shall be applied to the whole body of the valve. There shall be no
visible leakage through the metal, the flanged joint or the valve
packing gland nor shall any part be permanently deformed.
The test durations for all tests shall be as in the table below:
150 mm 1 1
200 mm to 300 mm 2 2
350 mm and above 5 2
S5-48
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.21 Materials
5.3.21.1 Castings
5.3.21.2 Forgings
S5-49
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.21.3 Workmanship
5.3.21.4 Lubrication
The Contractor shall submit full details of the method of lubrication for
valves to be supplied under the Contract. He shall supply all necessary
lubricating equipment, grease and other lubricants for setting valves to
work, of which the cost of supply shall be included for in the Contract
Rates.
Vales supplied shall be of the appropriate grade and quality for and
adequately protected against the climatic conditions in Malaysia. Valves
found to be unsuitable for use under these conditions shall be removed
and replaced by suitable ones by the Contractor at his own expense.
Valves bodies, surface boxes and all other castings shall be coated in
accordance with BS 5163 for tropical conditions. Where this is not
applicable, they shall be thoroughly cleaned and be given two coats of
coal tar epoxy with a resin base. Machined surfaces shall be covered by
a suitable rust inhibitor, such as a high melting point grease of approved
quality.
All submerged moving parts of the valves, including pins, spindles, face
rings, etc. shall be of non-corrodible materials. Any parts that show signs
of corrosion or wear during the Defects Liability Period shall be replaced
by non-corrodible material of special quality for the purpose at the
Contractor’s expense. Care shall be taken in selection of metals for use
S5-50
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
S5-51
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.23.1 General
All sluice valves shall be of approved made and suitable for the intended
use. They shall generally be to BS 5163, of double flange, parallel seat,
non rising spindle type and shall be of the inside non-rising screw
wedge-gate type. The valves gates shall be double faced cast iron made
in one piece. The wedge seats (ring faces) and corresponding body
seats shall be gunmetal, machined and having broad bearing surfaces
securely and accurately fitted and faced to machined recesses to give a
watertight bearing. The recesses for the spindle nuts shall be smooth
and even so that on opening or closing the valve stresses are evenly
distributed over the bearing areas. Internal surfaces of the valves shall
be smooth and clear.
S5-52
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The valves shall be so designed that the gates may be removed without
removing the bodies from the connecting pipework. The gate guides
shall be cast integrally with the valve bodies and be of adequate
strength and of sufficient length to guide the gates throughout their full
travel. In the fully open positions, the gates shall be fully withdrawn well
clear of the stream and the spindles shall not protrude into the bores of
the valves.
Flanges shall be to BS 4504 PN 16 and to match with the flanges for the
steel pipes.
5.3.23.2 Material
The body shall be of closed grained, high duty, grey cast iron to BS
1452 Grade 220 (minimum). The wedge shall also be cast iron to BS
1452 with ample guides and gunmetal rings. For valve with resilient
seat, the wedge facing shall be of resilient nitrile rubber bonded to the
cast iron wedge using the latest rubber technology.
The spindles shall be of the inside screw non-rising type of high tensile
brass or bronze to BS 2872 CZ114/CZ116 with machined square or
acme threads. They shall be truly circular throughout their lengths and
be of such lengths that when the valves are closed the bottom ends of
the spindles engage fully in the spindle nuts. The spindle collars or
thrust plates shall be concentric and machined suitable for the specified
test pressure. The spindle nut shall be gunmetal to BS 1400 LG2,
square or acme threaded to suit the spindles. The thickness and bearing
areas of the nut shoulders shall be adequate to resist operating thrusts.
All spindle contacting surfaces in the gland and neck of stuffing box shall
be bushed with gunmetal. Packed gland shall be arranged for easy
replacement of the packing. The valves shall be replaced with valve
wedge fully open and valves under pressure.
S5-53
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
the valves and suitable for operation by one man with a mild steel tee
key and bar under the maximum working pressure. Gears and bearings
shall be protected by suitable water-tight enclosures permanently
packed with grease. Gearing assemblies shall be enclosed in boxes or
corrosion resistant material.
5.3.23.3 Pressure
All valves shall be subject to a minimum body test pressure of 150m (15
bar) and seat test pressure of 100m (10 bar). Valve pressure rating shall
equal the class of pipe unless otherwise specified.
5.3.24.1 General
Check valves shall be of approved made, suitable for their intended use
and generally to BS 5153. They shall have an unrestricted opening with
non-slam closure upon instantaneous power failure or pump shut-off.
Valves shall preferably be mounted horizontally and suitable for
velocities up to 5.0m/s.
Check valves shall be of the swing type, full body flanged type, with a
top access cover and only one moving part, the valve disc.
The valve body shall have 100 percent pipe flow area, with no
restrictions at any point, through the valve. The seating surface shall be
on a 45 degree angle to minimise disc travel. The top access port shall
S5-54
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
be full size, allowing removal of the disc without removing the valve from
the pipeline.
The access cover shall be domed in shape, to allow the disc to fully
open should waste solid get collect behind the disc.
The valve function is to permit flow in only one direction, close tightly
when its discharge side pressure exceeds its inlet pressure and to close
without a slam or bang.
All internal parts shall be replaceable without removing the valve body
from pipeline.
5.3.24.2 Material
The valve body and cover shall be cast iron ASTM A 126, Class B
internally coated with two parts hi-build epoxy suitable for sewerage
service. The exterior shall be primed coated with a universal base
primer.
5.3.24.3 Pressure
All valves shall be subject to a minimum body test pressure of 150m (15
bar) and a working pressure of 100m (10 bar).
S5-55
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.25.1 General
Plug valves shall be of approved made with handwheel, suitable for their
intended use and resilient seated eccentric and non-lubricated type
capable of handling abrasive and raw sewage. The plug valve shall have
flanged ends as shown.
They shall have round ports with a flow area not less than 90 percent of
the connecting pipe area or rectangular ports equal to the pipe area.
Valves pressure rating shall be rated for 120m (12 bar) up to 300mm
diameter and 100m (10 bar) for sizes 350mm diameter and larger. Drop
tight shut-off shall be provided at full rated working pressure in the
standard flow direction and 35m (3.5 bar) in reverse flow direction. Full
pressure rating in reverse flow shall be provided when indicated in the
valve schedule. An adjustable close position stop shall be provided for
field adjustment. The seat end and standard flow direction shall be cast
on valve body.
5.3.25.2 Material
The shaft seal shall comply with AWWA specification C504-80, section
3.7 and be of either the bronze cartridge type with two O-rings, V-type or
pull down packing. If V-type or pull down packings are utilised, they shall
be self adjusting. All shaft seals shall be replaceable without
disassembling the valve and while the valve is under system operating
pressure.
The plug shall be of a one piece with a precision molded resilient facing.
Resilient body seats are not acceptable. The resilient seating surface
shall not be in the flow way pattern when the valve is in the open
position. The body seating surface shall be welded nickel overlay
containing a minimum of 90 percent nickel and machined to a 16 micro-
inch finish contained no stress cracks.
S5-56
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The valve interior shall be coated with 4-6 mil of a two part hi-built epoxy
suitable for sewerage service. The exterior of the flanged valves shall be
prime coated with a universal base primer. The exterior of the
mechanical joint valves are to be coated with asphalt varnish.
5.3.26.1 General
The Contractor shall install at each location in the force main shown on
the Drawings the valve assemblies as detailed.
5.3.26.2 Definitions
For the purpose of this construct, the valves shall be defined as follows:
S5-57
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The Contractor shall submit to the S.O. the following information before
provision of the valves:
S5-58
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(b) Venting
Inlet and outlet ports. The body inlet port and the cover outlet
port for air/vacuum valves and combination air valves shall be
sized such that the minimum flow area of each port shall be
equal to or greater than the flow area of circle of diameter equal
to the nominal valve size.
S5-59
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(e) Floats
For valves with inlet size less than 4 in. (100mm), the float shall
be capable of withstanding a collapse pressure of 1000 psig
(6900kPa [gauge]). For inlet sizes 4 in (100mm) and larger, the
float shall be capable of withstanding collapse pressures of 750
psig (5180kPa [gauge]).
(f) Gaskets
(g) Orifices
S5-60
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(i) Seat
S5-61
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
At each low point in the force main the Contractor shall install a scour
valve assembly as detailed on the Drawings. Valves and fittings shall
equal or exceed the pressure rating of the pipe to which they are
attached.
5.3.28 Penstocks
5.3.28.1 General
5.3.28.3 Faces
5.3.28.4 Spindles
All spindles shall be of the inside screw non-rising type suitably size for
the intended duty and shall be of stainless steel with gun metal nuts on
top.
S5-62
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Headstock and handwheels with gun metal index and pointer shall be
provided for operation of the penstock. This shall be manual or electric
driver as specified or as shown on the Drawings.
(a) General
S5-63
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.29.1 Submittals
S5-64
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
S5-65
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
All anchor bolts, nuts and washers, including anchor bolts used
in the installation and assembly of the equipment shall be
stainless steel, Type 316, (unless specified otherwise herein) and
of ample size and strength for the purpose intended. All bolt
heads and nuts shall be hexagonal. Anchor bolts shall be
furnished with 2 nuts to facilitate installation and alignment.
Gate frames and guides shall be cast in one piece and shall be
flat back. The back of the frame shall be machined to a plane
and drilled to mate the thimble. The guides shall be extended for
full gate opening. Guide grooves shall be accurately machined to
provide free movement of the slide tongues and to insure proper
engagement of the wedging devices. Frames and guides shall be
cast-iron, ASTM Designation A 126-66 (Class B or C) or
equivalent BS Code.
S5-66
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The gate slides shall be cast in one piece with vertical and
horizontal ribs, pads for attaching wedging devices, a stem block
pocket and a reinforced section around the perimeter to provide
for mounting of the seating faces. The casting shall be of ample
section to safely withstand 6 metres unseating head. A stem
block shall be provided to attach the gate slide to the stem. It
shall be threaded and provided with a means of locking it to the
rising stem after it is installed. Pads for mounting wedging
devices shall be machined and drilled. A groove shall be cut in
each pad to receive the mounting tongue on the side wedge.
Slides shall be cast-iron, ASTM Designation A 126-66 (Class B
or C) or equivalent BS Code.
S5-67
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(f) Fasteners
S5-68
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(h) Stems
S5-69
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
a standard galvanised pipe cap, and the bottom shall screw into
a cast-iron housing mounted on top of the gate operator. The
inside of this housing shall be bored to the exact diameter of the
stem cover to assure accurate alignment of the cover.
5.3.29.4 Operators
The manual lift mechanism shall be the crank operated type with either a
single or double gear ratio, depending upon the lift load. Each type shall
have a cast bronze lift nut threaded to fit the operating stem. Ball thrust
bearings shall be provided, above and below the flange on the lift nut to
take the load developed in opening and closing the gate. Gears shall be
of cast iron or steel, accurately machined with cut teeth and smooth
running with suitable shafts running in bronze sleeve bearings or rollers
bearings of ample size. All geared lifts shall be suitable for auxiliary
motor operation. All gears and bearings shall be enclosed in a cast iron
housing. Fittings shall be provided so that all gears and bearings can be
periodically lubricated. The removable cast iron crank shall be fitted with
a rotating handle. The lift mechanism shall be supplied with a cast iron
pedestal, machined and drilled to receive the gear housing and suitable
for bolting to the operating floor. The design of the lift mechanism shall
be such that the slide can be operated with a 11.4Kg effort on the crank.
The maximum crank radius shall be 38cm. The direction of rotation to
open the gate shall be indicated on the lift mechanism. A cast iron stop
nut shall be provided for each lift. All exposed cast iron surfaces shall be
painted in accordance with these specifications. Each rising stems unit
shall be provided with a position indicator to show the position of the
gate at all times.
S5-70
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
5.3.29.5 Installation
(b) In-Place-Testing
S5-71
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
The frame and flap shall be cast iron to BS 1452 and seating faces shall
be bronze or stainless steel. It shall operate efficiently under the
designed hydraulic head.
5.3.32 Fittings
Cast iron fittings shall be of a strength equal or greater than the pipe to
be joined. Exterior surfaces shall be coated with coal tar pitch varnish.
S5-72
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Valve operating tee wrenches shall have a socket for a 50mm square
operating wrench. One wrench for each type of valve shall be supplied
to a height where it may be operated at waist level.
Valve bodies, surface boxes, fittings and all other castings shall be
coated in accordance with BS 4164 for tropical conditions. Where it is
not applicable, they shall be thoroughly cleaned and be given two coats
of coal tar epoxy with a resin base. Machined surfaces shall be covered
by a suitable rust inhibitor, such as a high melting point grease of
approved quality.
All submerged moving parts, or the pins, spindles and faces, etc in
contact with them, shall be of non-corrodile materials. Any parts that
show signs of corrosion or wear during the Defects Liability Period shall
be replaced with non-corrodible materials or special quality for the
purpose at no extra cost. Care shall be exercised in the choice of metals
for use in the valves to reduce the effects of bi-metallic corrosion to a
minimum. The foregoing shall apply also to the moving parts exposed to
the weather.
All flange bolts and nuts shall be lubricated and coated with protective
coating. Exposed ferrous metal surfaces in contact with the earth such
as valves, flanges, butt straps, and couplings shall be field coated in
accordance with the manufacturer's recommendations. Surface shall be
thoroughly cleaned prior to coating.
S5-73
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
(a) All rust, loose scale, and foreign matter shall be removed from
surfaces to be coated by wire brushing or sandblasting. Oil and
grease shall be removed with cleaning solvent, and surfaces
shall be dry.
(b) Surfaces which will be in contact with the earth and are to
receive a field applied coal-tar coating as specified elsewhere,
shall be shop painted as per specification Section 10.
Where pipes pass through concrete floor or other walls, suitable puddle
flange or collar shall be provided.
Hose valves shall be 20mm bronze with composition disc and with
screwed end installed 0.5mm above grade or attached to wall.
S5-74
Revised on 4 Oct. 2011
EDTP GEMAS-JOHOR BAHRU TECH. SPEC. FOR ARCH., C&S AND MEP
Appendix 5.1
SIXTH SCHEDULE
S5-75
Revised on 4 Oct. 2011