DSI - Running Completion Tubings
DSI - Running Completion Tubings
“All personnel has the authority to stop the job if any issue or problems arises –
take Time Out for Safety when required”
RUNNING IN BP COMPLETION
Following well control items need to be prepared prior to RIH completions
Drillers to Prepare / Check Tick
FOSV+ Key
Well control X-over from tubing to FOSV connection
Fluid on the active tank
5. P/U and M/U 2.7/8” EUE pin x 3.1/2” EUE Box c/w H/Drain.
6. Continue RIH completion strings in single from deck as per given running list.
Ensure torque are calibrated and witness by drillers to achieve Optimum torque
7. P/U hanger and land hanger to set S/V at 887mbthf.
8. Fill up tubing with water and observed fluid level.
9. Screw in tie down bolt.
10. Install BPV inside hanger profile. Review SOP prior to install BPV.
11. R/D handling gear. Remove Working floor.
12. N/D 7.1/16” annular BOP and N/U x-mass tree. Retrieved BPV and install TWCV.
13. P/T X-mass tree to 2800kPa in stages from LOW 1400kPa to High 2800kPa for 15mins. Record P/T.