Professional Documents
Culture Documents
INFORMATION
RFI No. Manufacturer
Serial No Ref. Drawing nos.
Valve size kW/HP Rating
Overload setting
Punch
No. Items to be Checked OK N/A
List no.
Documents required for verification.
a. MOV Datasheet
1 b. Completed and signed-off pre-com check-sheet for the subject
MOV and punch list status
c. FAT report / Routine test report
2 Verify the operation of limit switch.
3 Verify the operation of torque switch.
Start Current:
4
______ Amps
5 Running Current:
______ Amps
6 Total stroke time:
______ Seconds
7 Record any defects/shortcomings in the system punch-list.
COMMENT(S) / ADDITIONAL INFORMATION:
Completed by Verified by PMT/OWNER Accepted by
CONTRACTOR Commissioning OWNER/OPERAT
Designation
Company
Name
Signature
Date