Professional Documents
Culture Documents
Flow Chart Perhitungan Struktur Beton
Flow Chart Perhitungan Struktur Beton
(BENDING MOMENT)
Start
Load, Mu
Mn = Mu / f
Mn2 = Mn - Mn1
yes no
es' < ey
AS1 = Cc max / fy
AS' = CS required / (f s' - 0,85.f c')
AS = AS1 + AS' .f s' / fy
Stop
www.sarjanateknik.com
FLOW CHART - BEAM With T-SECTION
(BENDING MOMENT)
Start
Load, Mu
r min = 1,4/fy
0,85.f c'.600
r max = 0,75.b2.
fy. (600 + fy)
Assume c < hf
Cc = 0,85.f c'. bf.a
Mu = Cc. (d - a/2)
Calculate c
c > hf
f c' bf a Calculate a
rw = 0,85.b1 ---.---.---
fy bw d Cc1 + Cc2
rw=
fy.bw.d
No
r w < r max
Yes
No
r w > r min
r w = r min
Yes
As = r w.bw.d
Stop
www.sarjanateknik.com
FLOW CHART SEISMIC DESIGN - LIMITED DUCTILITY
Start
General
Information
Preliminary Design
Size Estimation
Dynamic Analysis
Time Period
Seismic load
(K >= 2)
Gravity load VE
NE
VD, VL, (Vg)
Ng
MD, ML
NE
MU, Beam
= 1,2 MD, b + 1,6 ML, b Mu, Column
= 1,05 (MD, b + ML, b + ME, b) = 1,05 (MD, K + ML, K +
= 0,9 MD, b + ME, b WdME, K)
NU, Column
Column Reinforcement
VU, Beam
VU, Column
= 1,05 (VD, b + VL, b + 4/KVE, b) = 1,05 (VD, K + VL, K + Wd VE, K)
STOP
www.sarjanateknik.com
FLOW CHART TORSION REINFORCEMENT OF BEAM
Start
1/15. fc'.Ex2y
Tc =
1 + (0,4.Vn/Ct.Tu)2
1/6. fc'.bw.d
Vc =
1 + (2,5.Ct.Tu/Vu)2
yes
Tu/f > 5.Tc
no
Tu/f > 1/24. fc'.Ex y 2
Only shear reinforcement
yes
no
Vu/f < Vc/2 Only torsion reinforcement
yes
no
Vu/f > Vc Av/S = bw/(3.fy)
yes
(Vu/f - Vc)
Av/S =
fy.d
no
Tu/f > Tc Av/S + 2.At/S = bw/ (3.fy)
yes
www.sarjanateknik.com
FLOW CHART SHEAR REINFORCEMENT OF BEAM
Start
Vc = 1/6. fc .bw.d (shear & bending) Vc = 1/7 ( fc' + 120. r w.Vu.d/Mu)bw.d < 0,3 fc.bw.d (shear & bending)
Vc = [1+(Nu/14.Ag)].1/6. fc'.bw.d (shear & compression axial load) Vu.d/Mu < 1
Vc = 0 (shear & tension axial load) Vc = 1/7 ( fc' + 120.rw.Vu.d/Mu)bw.d < 0,3 fc.bw.d 1+0,3.Nu/Ag (shear & compression axial load)
Mm = Mu-Nu [(4.h - d) / 8]
Vc = (1-0,3.Nu/Ag).1/6. fc'.bw.d (shear & tension axial)
yes no no
Vu/f > Vc Vu/f > 1/2.Vc Shear reinforcement : No required
yes
S = Av.fy.d/Vs
S = 3.Av.fy/bw
yes no
Vu/f - Vc > ( fc'/3).bw.d
Determine S
Stop
www.sarjanateknik.com
2
no
Vu / f > Vc/2 Shear reinforcement not required
yes
no
Vu / f > Vc Av / S = bw / (3.fy)
yes
(Vu/f - Vc)
Av/S =
fy.d
yes
no
Tu / f > 1/24. fc' bw. d Torsion reinforcement not required
no
Tu / f < 5.Tc Av/S + 2.At/S = bw / (3.fy)
yes
At (Tu / f - Tc)
---- = ----------------
S fy.st.x2.y2
Avt = 2.At / S + Av / S
Al = 2.At / S. (x2 + y2)
2,8.x Tu 2.At
Al = [ ------- ( ------------------------- ) - -----] (x2 + y2)
fy Tu + Vu / (3.Ct) S
2,8.x Tu bw
Al < [ ------- ( ------------------------ ) - ----- ] (x2 + y2)
fy Tu + Vu / (3.Ct) 3.fy
Stop
www.sarjanateknik.com
1
At (Tu / f - Tc)
---- = ----------------
S fy.f t.x2.y2
Stop
1/15. fc'.Ex2y
Tc =
1 + (0,4.Vu/Ct.Tu)2
1/6. fc'.bw.d
Vc =
1 + (2,5.Ct.Tu/Vu)2
no
Tu / f < 5.Tc A
yes
2
www.sarjanateknik.com
FLOW CHART COLUMN REINFORCEMENT
Start
Load :
Pu = 1,2.Pd + 1,6.Pl
Mu = 1,2.Md + 1,6.Ml
e = Mn / Pu
no
e > 0,1.h concentric column
yes
no yes
Es' Es' < Ey Es' = Ey
yes no
Tension failure Pn < Pbal Compression failure
Pn = 0,85.fc'a.b + As' (fs - 0,85.fc') - As.fy) Pn = 0,85.fc'a.b + As' (fc' - 0,85.fc') - As.fs)
Pn.e = 0,85.(c'.a.b.(d - a/2 -d") + As.fy.d" + Pn.e = 0,85.(c'.a.b.(d - a/2 -d") + As.fy.d" +
As'(fs - 0,85.fc') (d - d' - d") As'(fc' - 0,85.fc') (d - d" - d")
AS
f = As / (b.h)
no
0,001 < f < 0,008
yes
Stop
www.sarjanateknik.com
2
bd = 1,2.Pd/(1,2.Pd + 1,6.Pl
Pc = x2.EI/(k.ln)2
tidak
M2b = Pu.e min M2b/Pu > e min = (15+0,03.h)mm
ya
Mc = db.M2b + ds.M2a
1 Selesai
www.sarjanateknik.com
DIAGRAM ALIR PERENCANAAN KOLOM
Mulai
Tentukan dimensi
Agr = b.d untuk penampang persegi
Agr = 1/4.x.d2 untuk penampang bulat
ya tidak
kolom dengan pengaku
Kolom pendek :
tidak Hitung tulangan kolom tidak
untuk Pu dan Mu
ya Direncanakan menurut
k.ln/r > 100 SKSNI 3.3.10-1
tidak
1
Analisa kolom panjang
dengan faktor pembesaran
dinamis
www.sarjanateknik.com
FLOW CHART SEISMIC CAPACITY DESIGN (FULL DUCTILITY)
Start
General
Information
Preliminary Design
Size Estimation
Time Period
Seismic load
VE, 4,0 VE
Gravity load
ME, 4,0 ME
VD, VL, (Vg)
Ng
MD, ML
ME, 4,0 ME
MU, Beam
= 1,2 MD, b + 1,6 ML, b Mu, Column
= 1,05 (MD, b + ML, b + ME, b) = 0,7.Ev.EM kap, b/lb) + 1.05 Ng, k
= 0,9 MD, b + ME, b > 1,05 (Ng, k A 4/K NE, k
MU, Column
Column Reinforcement
M kap, b = fo M nak, b
Upper : Stop
Beam Reinforcement (shear) = (Mu, k, a + M kap, k, b) / Ln
= 1,05 (VD, k + VL, k f 4 / K.VE, k
www.sarjanateknik.com
www.sarjanateknik.com