Professional Documents
Culture Documents
Document No : NW000-S0071
Amendment No : 0
NETWORK Approved By : Head of AEP & S
Approval Date : 28/05/2015
Review Date : 31/03/2019
(Review Date Changed - 06.02.2019)
ISSUE
For issue to all Ausgrid and Accredited Service Providers’ staff involved with the design and installation of overhead lines, and is for
reference by field, technical and engineering staff.
Ausgrid maintains a copy of this and other Network Standards together with updates and amendments on www.ausgrid.com.au.
Where this standard is issued as a controlled document replacing an earlier edition, remove and destroy the superseded document
DISCLAIMER
As Ausgrid’s standards are subject to ongoing review, the information contained in this document may be amended by Ausgrid at
any time. It is possible that conflict may exist between standard documents. In this event, the most recent standard shall prevail.
This document has been developed using information available from field and other sources and is suitable for most situations
encountered in Ausgrid. Particular conditions, projects or localities may require special or different practices. It is the responsibility
of the local manager, supervisor, assured quality contractor and the individuals involved to make sure that a safe system of work is
employed and that statutory requirements are met.
Ausgrid disclaims any and all liability to any person or persons for any procedure, process or any other thing done or not done, as a
result of this Standard.
All design work, and the associated supply of materials and equipment, must be undertaken in accordance with and consideration
of relevant legislative and regulatory requirements, latest revision of Ausgrid’s Network Standards and specifications and Australian
Standards. Designs submitted shall be declared as fit for purpose. Where the designer wishes to include a variation to a network
standard or an alternative material or equipment to that currently approved the designer must obtain authorisation from the Network
Standard owner before incorporating a variation to a Network Standard in a design.
External designers including those authorised as Accredited Service Providers will seek approval through the approved process as
outlined in NS181 Approval of Materials and Equipment and Network Standard Variations. Seeking approval will ensure Network
Standards are appropriately updated and that a consistent interpretation of the legislative framework is employed.
Notes: 1. Compliance with this Network Standard does not automatically satisfy the requirements of a Designer Safety Report. The
designer must comply with the provisions of the Workplace Health and Safety Regulation 2011 (NSW - Part 6.2 Duties of designer
of structure and person who commissions construction work) which requires the designer to provide a written safety report to the
person who commissioned the design. This report must be provided to Ausgrid in all instances, including where the design was
commissioned by or on behalf of a person who proposes to connect premises to Ausgrid’s network, and will form part of the
Designer Safety Report which must also be presented to Ausgrid. Further information is provided in Network Standard (NS) 212
Integrated Support Requirements for Ausgrid Network Assets.
2. Where the procedural requirements of this document conflict with contestable project procedures, the contestable project
procedures shall take precedent for the whole project or part thereof which is classified as contestable. Any external contact with
Ausgrid for contestable works projects is to be made via the Ausgrid officer responsible for facilitating the contestable project. The
Contestable Ausgrid officer will liaise with Ausgrid internal departments and specialists as necessary to fulfil the requirements of this
standard. All other technical aspects of this document which are not procedural in nature shall apply to contestable works projects.
INTERPRETATION
In the event that any user of this Standard considers that any of its provisions is uncertain, ambiguous or otherwise in need of
interpretation, the user should request Ausgrid to clarify the provision. Ausgrid’s interpretation shall then apply as though it was
included in the Standard, and is final and binding. No correspondence will be entered into with any person disputing the meaning of
the provision published in the Standard or the accuracy of Ausgrid’s interpretation.
KEYPOINTS
This standard has a summary of content labelled “KEYPOINTS FOR THIS STANDARD”. The inclusion or omission of items in this
summary does not signify any specific importance or criticality to the items described. It is meant to simply provide the reader with a
quick assessment of some of the major issues addressed by the standard. To fully appreciate the content and the requirements of
the standard it must be read in its entirety.
Where there are changes to this standard from the previously approved version, any previous shading is removed and the newly
affected paragraphs are shaded with a grey background. Where the document changes exceed 25% of the document content, any
grey background in the document is to be removed and the following words should be shown below the title block on the right hand
side of the page in bold and italic, for example, Supersedes – document details (for example, “Supersedes Document Type
(Category) Document No. Amendment No.”). .
This standard is limited to scope identified This section provides details of major This section provides details of major This section provides details of major
below and provides controls for associated design requirements for CCT construction design requirements for bare conductor design requirements for SWER construction
risks as listed below: and includes the following: construction and includes the following: and includes the following:
Where to for more information? Where to for more information? Where to for more information?
Section 6 Section 7 Section 8 -14
Where to for more information? Tools and Forms Tools and Forms Tools and Forms
Section 1, 2, 5, Annexure A None None Annexure B Sample compliance checklist
Network Standard
NS126
Construction of High Voltage Overhead Mains
Contents
1.0 PURPOSE
This Network Standard is Ausgrid’s specification for the construction of 11kV, 22kV or 12.7kV
Single Wire Earth Return (SWER) Overhead lines within the Ausgrid Supply Network area.
Ausgrid’s requirements for Low Voltage overhead mains are detailed in NS125 Specification for
Low Voltage Overhead Mains. Ausgrid’s requirements for subtransmission voltage overhead mains
are detailed in NS135 Specification for the Design & Construction of Overhead Sub-transmission
Lines. For other system voltages design and construction documentation will be issued by Ausgrid
on a project specific basis.
2.0 SCOPE
This Network Standard together with other referenced standards and guidelines describes
Ausgrid’s construction requirements for 11kV, 22kV and SWER High Voltage (HV) Overhead (OH)
mains.
The following types of HV OH mains systems are currently in use in the Ausgrid 11kV distribution
network:
3.0 REFERENCES
All work covered in this document shall conform to all relevant Legislation, Standards, Codes of
Practice and Network Standards. Current Network Standards are available on Ausgrid’s Internet
site at www.ausgrid.com.au.
4.0 DEFINITIONS
Accredited Service An individual or entity accredited by the NSW Department of Planning and
Provider (ASP) Environment, Energy, Water and Portfolio Strategy Division, in accordance
with the Electricity Supply (Safety and Network Management) Regulation
2014 (NSW).
Business An Ausgrid internal integrated policy and procedure framework that contains
Management the approved version of documents.
System (BMS)
Bare conductor In this standard a bare conductor refers to a conductor (manufactured to
(BC) AS1222, AS3607, AS1531 or AS1746) which is not covered or insulated.
Covered Conductor An unscreened conductor around which is applied a specified thickness of
Thick (CCT) insulating material for the nominal working voltage of 11kV.
Customer A customer is an individual or an entity that is an end-user of electricity.
Document control Ausgrid employees who work with printed copies of document must check
the BMS regularly to monitor version control. Documents are considered
“UNCONTROLLED IF PRINTED”, as indicated in the footer.
HDPE High-density Polyethylene.
High Voltage, Aerial A screened cable system used by Ausgrid for the high voltage overhead
Bundled Cable distribution system. The high voltage cable system consists of three
compacted stranded hard-drawn aluminium conductors individually insulated
with black cross-linked polyethylene (XLPE) and a steel support catenary
wire.
High Voltage In this document the term High Voltage Distribution System means all mains
Distribution System and apparatus operating at nominal voltage of 11kV or single wire earth
return (SWER) operating at 12.7kV.
Low Voltage All mains and apparatus operating at nominal voltages above 50 V (extra low
Distribution System voltage) and up to and including 1000 V.
Network Standard A document, including Network Planning Standards, that describes the
Company's minimum requirements for planning, design, construction,
maintenance, technical specification, environmental, property and metering
activities on the distribution and transmission network. These documents are
stored in the Network Category of the BMS repository.
Phasing (Phased) Means a test to determine whether energised conductors of phase A, B or C
of one section of a polyphase system may be satisfactorily connected to the
corresponding phases of another section of polyphase system.
PCC Peak Consultative Committee.
Project Officer Employees who review network standards as directed by section managers
from Engineering, Network.
Review date The review date displayed in the header of the document is the future date
for review of a document. The default period is three years from the date of
approval however a review may be mandated at any time where a need is
identified. Potential needs for a review include changes in legislation,
organisational changes, restructures, occurrence of an incident or changes in
technology or work practice and/or identification of efficiency improvements.
SWER Single Wire Earth Return. A HV distribution system consisting of a single
active wire, and using the earth as the return path.
XLPE Cross-linked Polyethylene.
5.0 INTRODUCTION
This Network Standard together with other referenced standards and guidelines describes
Ausgrid’s construction requirements for 11kV, 22kV and Single Wire Earth Return (SWER) High
Voltage (HV) Overhead Mains.
Three types of High Voltage overhead mains systems are currently in use in the Ausgrid 11kV
distribution network.
All contestable works on or near Ausgrid Transmission and/or Distribution system falls under the
category of Authorised Work and shall only be performed by an Accredited Service Provider and in
accordance with the requirements of ES4 Service Provider Authorisation. Accredited Service
Providers shall ensure that any person carrying out the above work is duly authorised. (Refer to
ES4 and NS104 Specification for Electrical Network Project Design Plans).
Refer to Policy for ASP/1 Premises Connections for details of Ausgrid’s overhead and underground
mains policy.
The general guidelines for the form of construction for each development shall be determined by
Ausgrid and shall be in accordance with the prevailing policy of the time. The final interpretation
and decision as to the type of construction to be used shall be Ausgrid’s. Notification of the type of
construction shall be issued in the preliminary design brief.
The use of overhead 11kV mains in non-urban areas shall be in accordance with Policy for ASP/1
Premises Connections. Where overhead mains are used, CCT should be used in the following
situations:
Where there is a significant risk of tree branches falling onto the mains or wind-blown debris
may come into contact with the mains, and disrupt supply or initiate bushfires etc.
Where reduced phase separation is required in narrow easements, or to reduce tree trimming.
Where conductor clashing is a problem and wider phase separation of BC is not practicable.
In all other cases BC shall be used.
CCT is manufactured to comply with AS 3675 Conductors - Covered overhead - For working
voltages 6.35/11(12) kV up to and including 19/33(36) kV.
6.1.1 Covering
CCT shall have an inner insulating covering of cross-linked polyethylene (XLPE) and an outer
sheath of black, UV stabilised, high-density polyethylene (HDPE) about 1 mm thick. The outer
sheath has a high resistance to abrasion. Grey CCT is supplied with Schneider reclosers and
enclosed high voltage switches.
For example:
The choice of conductor material depends on site conditions and mechanical load considerations.
Ausgrid uses three conductor sizes: CCT80, CCT120, CCT180 (see Table 1 below for details).
Conductor
CCT80 CCT120 CCT180
Cable Code (As per NS100)
Stockcode 144519 147421 176311
Number of strands/wire diameter 7/3.75 7/4.75 19/3.50
Alloy type/grade AAAC/1120 AAAC/1120 AAAC/1120
Cross sectional area (mm2) 77.3 124.0 182.8
Equivalent alum. area (mm2) 73.7 118.2 173.5
Minimum breaking load (kN) 17.6 27.1 41.7
DC resistance at 20°C (Ω/km) 0.383 0.239 0.163
Note: CCT180 current rating (Normal) under above conditions is 470 A. If larger loads are to be
met (e.g. in place of Pluto which has a current rating (Normal) of approximately 600 A
under similar conditions) multiple parallel conductors will be used, e.g. 2xCCT120 per
phase.
6.2.1 Phasing
The configuration of phases shall be according to the particular installation requirements as
specified by Ausgrid. Where there are no installation constraints, the following configuration shall
be used:
6.2.2.3 Separation between covered conductors and low voltage aerial bundled cable or LV bare
conductors
The separation between the CCT and LV ABC or LV bare conductors at the pole construction
depends on whether the HV network can be worked on using live line techniques. Refer to NS 220
Overhead Design Manual - Section 10 for live-line circuit to circuit clearances. Midspan separation
must not be less than that specified in AS7000 Overhead line design - Detailed procedures.
Note: Spur lines should always be designed and constructed with live-line circuit to circuit
separations.
For further live-line design principles refer to NS214 Guide to Live Line Design Principles.
6.3 Insulators
For line construction, solid-core type pin post insulators must be used. Standard pin insulators must
not be used since they do not offer satisfactory lightning or electrical tracking performance which
can damage and lead to the burn-down of the CCT. Solid-core type pin post insulators are
available with long or short studs to suit crossarm or bracket mounting respectively.
Note: Conductor insulation must not be removed at the pin or post insulator.
Solid-core strain rod insulators and strain clamps must be used at termination points and with high
angle deviation (>50° for horizontal configuration or >30° for vertical configuration). The strain rod
insulator currently available has a tongue and clevis designed to attach to a strain clamp.
The following three types of insulators are available to suit different construction purposes:
Short stud Z = 45 mm
Long stud Z = 145 mm
Short stud Z = 45 mm
Long stud Z = 145 mm
Additionally, surge arresters must be installed at CCT-BC transition points to prevent surges due to
lightning strikes originating in the BC system entering the CCT system. If the transition point is an
ABS the surge arresters should be installed one span away from the ABS on the CCT side.
Surge arresters shall be earthed in accordance with Ausgrid Network standard NS116 Design
Standards for Distribution Earthing and shall be designed and constructed in accordance with the
relevant drawings listed in Clauses 6.14 and 7.13.
The earth leads on S&C IntelliRupters shall be designed and constructed in accordance with the
relevant drawings listed in Clauses 6.14 and 7.13.
If the design involves crossarms and the insulators are upright (e.g. reconstruction of an existing
bare OH line) polymeric surge arresters should be used.
For vertical construction or where the insulators are not upright, the Current Limiting Arcing Horn
(CLAH) arrangement should be used.
11kV Polymeric Arrester, complete with insulated mounting bracket, galvanised steel support
bracket, ground lead disconnect device, bird cap, insulated aluminium stranded phase lead and
copper stranded earth lead (stockcode 150383).
11kV Current Limiting Arcing Horn (CLAH) (stockcode 144659) complete with Discharge
Connector (stockcode 144667 for 120 mm2 cables, 144675 for 80 mm2 cable and 176322 for
180mm2).
Note: Arrestors should be class NS to AS 1307.2.
Surge arresters must be compatible with the covered conductor system. The surge arrester, must
be the polymeric type rather than the porcelain type, for safety and insulation integrity reasons.
The line connection cable should be connected to the CCT conductor via a Parallel Groove
connection or other suitable CCT IPC as discussed in Clause 6.5.3.
Note: Polymeric surge arresters must be handled in accordance with NSA 1494.
The Current Limiting Arcing Horn (CLAH) is a composite surge arrester comprising an arcing horn
and a current-limiting non-linear resistor in series. Under no-surge conditions the full phase voltage
appears across the external air gap and the current limiting element is not electrically stressed.
When an arc is produced due to a surge, the current limiting element allows the surge current to
pass through the non-linear resistor to ground. As soon as the abnormal surge voltage subsides,
the non-linear resistor regains its high resistance and helps extinguish the power follow arc in the
arcing horn which could have otherwise continued for a longer time.
The two electrodes of the arcing horn are the discharge connector fitted on to the CCT and the
horn fitted on to the current-limiting element. The air gap can be adjusted to suit the system voltage
and the insulation co-ordination guidelines by using the slide mechanism of the horn. Under normal
conditions a gap of 20 mm is specified for 11kV CCT lines.
The discharge connector is an ultraviolet resistant, track resistant, hinged moulding of insulating
material with a thick mastic coating on the inside for waterproofing the connection. The connector
has a plastic bolt with a metal pin embedded at the end. While the point of the metal pin extends
out of the plastic bolt the head of the pin is located halfway inside the plastic bolt. A narrow hole
extends from the head of the plastic bolt to the head of the metal pin. When the bolt is screwed in,
the metal pin pierces the insulation of the CCT and contacts the conductor. The hole in the plastic
bolt acts as a chute for the arc between the head of the pin and the horn during flashover. This
arrangement maintains the integrity of the covered system by preventing exposure of the
conductor. Also, the chute helps control the variation of the flashover voltage by providing a
sheltered chamber for ionisation of air prior to flashover.
The metal oxide element used for the CLAH is similar to a polymeric arrester but is moulded in
rubber, which is ultra-violet resistant, track resistant, and waterproof. The CLAH has a lower
voltage rating and fault capacity than polymeric arresters.
The strain clamp cover folds over the unit and is locked together with tags. It is difficult to remove
the covers after installation.
144568 144576
The PG cover has tapered conductor entries, which are trimmed to size depending on the size of
CCT conductor used.
Alternatives to PG clamps such as CCT insulation piercing connections (IPCs) may also be used
subject to approval by Ausgrid in accordance with NS181 Approval of Materials and Equipment and
Network Standard Variations.
Where pole mounted equipment such as reclosers requires that access permit earths or working
earths be installed from an elevating work platform, they shall be placed at least one metre from
the vertical projection of the nearest energised conductor. To accommodate this, the earthing point
shall be established at least one metre from the dropper cable.
Such standard earthing points are created by removing 125mm of the insulation on the CCT at
each nominated point. An earthing point cover shall be installed at each earthing point. The cover
is moved along the conductor to reveal the earthing point by tapping with an earthing stick. The
cover must be returned to its correct position after removal of the earths. Table 5 shows the
stockcode for the earthing point cover.
144741
Alternatives to the standard earthing points described above such as CCT insulation piercing
stirrup connections may also be used subject to approval by Ausgrid in accordance with NS181.
80mm² 144618
120mm² 144600
180mm² 176312
conductor covering and care must be taken in the placement of joints to ensure that they are not
subjected to abrasion.
Note 1. The thread diameter of BC insulator pins is 24mm (requiring 26mm crossarm hole),
whereas the thread diameter of CCT post insulators is 16mm (requiring 18mm crossarm
hole). Therefore when converting BC to CCT the crossarms should also be changed,
unless approved otherwise by Ausgrid, since the use of the 16mm threads in 26mm
crossarm holes is not mechanically sound and can lead to crossarm fires.
Note 2. In some rural lines, with long spans where constraints such as way-leave and tree-
trimming are minimal, longer crossarms may be used subject to Ausgrid approval
provided the documentation demonstrating that proper clearances are maintained is
submitted with the request.
Standard earthing points and covers shall be provided on both sides of each operating device.
6.9 Regulators
Pole mounted regulators shall be constructed in accordance with the latest amendment of Drawing
No 224227.
6.10 Capacitors
Pole mounted capacitors shall be constructed in accordance with the latest amendment of Drawing
No 162475.
taken when working on CCT lines. Before working on a CCT line (except when using live line
procedures) steps must be taken to ensure the line has been isolated, proven de-energised, short-
circuited and earthed in accordance with the Ausgrid Electrical Safety Rules.
Note: Before commencing work at a worksite from which the Access Permit earths at the
isolation points are not visible, the line must be positively identified as described in
Clause 6.11.3.
Covered conductors cannot be proven de-energised by stabbing. There is no earthed screen in the
cable and stabbing must not be attempted.
Proving de-energised must be carried out with an approved HV testing device at standard earthing
points, or at a termination or transition where exposed conductors are available, then tracing the
line to the work site.
6.11.3 Identification
After the Access Permit earths have been fitted and an Access Permit issued on the line, the line
must be positively identified at the worksite. This must be done by visually tracing the line from a
point of isolation to the worksite. A marker should be attached to the line using HV live line working
methods.
A second person must independently verify the visual tracing. The verification must be carried out
in the opposite direction - from the mark on the cable to the earth at the point of isolation.
Poles shall be located in accordance with NS167 Positioning of Poles and Lighting Columns.
Covered conductors are to be erected using the pulling in (or tension stringing) method. The
paying-out method can also be used, provided precautions are taken not to damage the CCT.
When tensioning a new conductor a suitable allowance shall be made for the initial stretch (“creep”)
of the conductor.
Refer to NS220 Overhead Design Manual and AS/NZS 7000 Overhead line design - Detailed
procedures for further information.
6.12.1 Precautions
The following precautions shall be taken when working with CCT:
Where insulation is to be removed from CCT conductor, it must be removed using tools and
procedures specifically designed for this purpose. The conductor MUST NOT be damaged
(nicked) during stripping. The use of incorrect tools and procedures can lead to premature
failure of the conductor.
Vertical construction 10 - 30 deviation Post insulator on angle bracket. (stockcode: 144634)
Vertical construction > 30° deviation Strain clamp and strain rod arrangement.
Horizontal construction > 50° Strain clamp and strain rod arrangement.
Delta Construction 0 - 25 deviation Post insulators on single cross arm and one pole raiser.
Delta Construction 25 - 50 deviation Post insulators on double cross arms and two pole raisers.
Delta Construction > 50 deviation Strain clamp and strain rod arrangement.
NS177 11kV Joints (including Transition Joints) & Terminations - Polymeric Insulated Cables,
or
NS129 11kV Joints and Terminations – Paper Insulated Lead Covered Cables,
depending on the type of UG cable to which the overhead conductors are to be connected.
Refer to Drawing No. 160354 regarding the preferred and alternative methods of bonding the
UGOH to the OH mains.
11kV UGOH must never be constructed on concrete or steel poles which also carry
subtransmission (i.e. 33kV, 66kV or 132kV) mains. This is due to the transferred voltage and earth
potential rise (EPR) hazards associated with faults on the subtransmission mains which may affect
the 11kV mains.
Note 1: Stainless steel conical (volute) washers shall be used on all bolts used to secure
crossarms to a pole or equipment to a crossarm or pole. The approved method for a
crossarm attached to a pole is to use a bolt fitted with a square washer, through the pole,
gain block and crossarm then use 1 x square washer, 1 x SS conical washer, 1 x round
washer (galv) and finally the nut.
Note 2: Equipment mounted on a crossarm similarly requires either 2 x square washers, or the
steelwork substituting 1 x square washer, plus 1 x SS conical washer, 1 x round washer
and a nut. Both cases require a large surface area in contact with the timber to prevent
indentation. The conical washer is used to allow for shrinkage of the timber.
Construction Drawing
Description
Number Number
Standard Construction 2 Unit 11kV Pole Mounted Regulator
224401
with Ground Mounted Control Panel
Standard Contruction 3 Unit 11kV Pole Mounted Regulator
224229
with Ground Mounted Controllers
6/4.74 +
Number of strands/wire diameter 7/4.50 19/3.75 6/1/3.00
7/1.6
Where bare conductor is used, specific effort must be made during design and construction
activities to avoid any possibility of conductor clashing throughout the life of the overhead line.
For this reason delta (small) is the preferred construction for all intermediate structures. Flat pin
construction shall be used only when under-building the circuit or for under-crossing structures. For
longer spans, delta (medium) and large delta constructions are available and other construction
types (e.g. horizontal offset, etc) may be used under specific circumstances and subject to
approval of Ausgrid. Details of approved designs for such construction types may be obtained by
contacting Ausgrid.
6.16.1 Phasing
The configuration of phases shall be according to the particular installation requirements as
specified by Ausgrid. Where there are no installation constraints, the following configuration shall
be used:
In the case of horizontal construction, crossarms on alternate poles with flat pin construction should
be fitted with reverse orientation to achieve improved mid-span clearance (ie. the centre conductor
alternates from one side of the pole to the other).
6.16.2.2 Separation between Bare Conductors (BC) and Low Voltage (LV) Aerial Bundled Cable
(ABC) or LV BC
The separation between the BC and LV ABC or LV bare conductors at the pole construction
depends on whether the HV network can be worked on using live line techniques. Refer to NS 220
Overhead Design Manual - Section 10 for live-line circuit to circuit clearances. Midspan separation
must not be less than that specified in AS7000.
Spur lines should always be designed and constructed with live-line circuit to circuit separations.
For further live-line design principles refer to NS214 Guide to Live Line Design Principles.
6.17 Insulators
The insulators used for all 11kV and 22kV BC mains shall be 22kV rated.
Identification numbers of pin and pin threads shall be stamped on the pin collar (C/200/11)
indicating the following:
Insulators shall be 22kV, type ALP 22/450 and manufactured in accordance with AS/NZS 2947
Insulators - Porcelain and glass for overhead power lines - Voltages greater than 1000 V a.c. - Test
methods.
Note: Polymeric insulators must be handled in accordance with NSA 1494 Polymeric Insulator
Handling Guide.
Surge diverters shall be located at all pole substations, enclosed load break switches, reclosers
and UGOH connections.
Surge diverters shall be earthed in accordance with NS116 Design Standards for Distribution
Earthing and shall be designed and constructed in accordance with the relevant drawings listed in
Clauses 6.14 and 7.13.
The earth leads on S&C IntelliRupters shall be designed and constructed in accordance with the
relevant drawings listed in Clauses 6.14 and 7.13.
Note: Polymeric surge arresters must be handled in accordance with NSA 1494.
6.19 BC Fittings
6.19.1 Parallel Groove (PG) clamp
PG clamps shall comply with the requirements of AS 1154.1.
The die size, and number and location of crimps should be marked on the sleeve. If not, they shall
be returned to the store for return to the supplier.
6.20 Crossarms
Crossarms shall be in accordance with Ausgrid’s current specification. Refer to Drawing Nos
514373 and 514374 as appropriate.
All ABSs shall be mounted on poles in accordance with the latest amendment of Drawing No.
175902.
All pole mounted circuit breakers shall be mounted on poles in accordance with the latest
amendment of Drawing Nos. 127318, 220041 or 220251 as appropriate.
Three types of 11kV drop-out fuses are currently used, depending on the fault level, as shown in
Table 12 below. Where necessary, fault level shall be specified in the Design Information. Fuse
ratings shall be in accordance with TS4200 Fuse Standard.
6.23 Regulators
Pole mounted regulators shall be constructed in accordance with the latest amendments of
Drawing No 224227.
6.24 Capacitors
Pole mounted capacitors shall be constructed in accordance with the latest amendment of Drawing
No. 162475.
Poles shall be located in accordance with NS167 Positioning of Poles and Lighting Columns.
The two principle methods of erection are paying-out and pulling-in. Of the two, pulling-in is the
preferred method as it minimises the likelihood of damage to the conductor during the installation
process.
When tensioning a new conductor a suitable allowance shall be made for the initial stretch (“creep”)
of the conductor.
NS177 11kV Joints (including Transition Joints) & Terminations - Polymeric Insulated Cables,
or
NS129 11kV Joints and Terminations – Paper Insulated Lead Covered Cables,
depending on the type of UG cable to which the overhead conductors are to be connected.
Refer to Drawing No. 160354 regarding the preferred and alternative methods of bonding the
UGOH to the OH mains.
11kV UGOH must never be constructed on concrete or steel poles which also carry
subtransmission (i.e. 33kV, 66kV or 132kV) mains. This is due to the transferred voltage and earth
potential rise (EPR) hazards associated with faults on the subtransmission mains which may affect
the 11kV mains.
Note 1: Stainless steel conical (volute) washers shall be used on all bolts used to secure
crossarms to a pole or equipment to a crossarm or pole. The approved method for a
crossarm attached to a pole is to use a bolt fitted with a square washer, through the pole,
gain block and crossarm then use 1 x square washer, 1 x SS conical washer, 1 x round
washer (galv) and finally the nut.
Note 2: Equipment mounted on a crossarm similarly requires either 2 x square washers, or the
steelwork substituting one square washer, plus 1 x SS conical washer, 1 x round washer
and a nut. Both cases require a large surface area in contact with the timber to prevent
indentation. The conical washer is used to allow for shrinkage of the timber.
Notes:
1. Construction 2-5 is the preferred construction for all intermediate structures in urban
areas.
2. Construction 2-1 is to be used only when under-building the circuit or for under-crossing
structures.
3. Constructions 2-6, 2-7, 2-31, 2-37, 2-38 are for use with longer spans only.
7.1.2 Advantages
SWER systems have a number of advantages. SWER lines utilise the same components as
normal 3-wire/3-phase or 2 wire/1 phase BC systems. SWER systems are quicker to build and
have lower construction costs compared to the normal 3-wire/3-phase or 2 wire/1 phase systems,
through the use of one wire instead of three or two, and also because of the reduced quantities of
pole fittings (crossarms, insulators, etc.). Similarly SWER systems can have lower maintenance
costs due to the fewer components involved. SWER systems can also reduce the risk of initiating
bushfires because conductor clashing cannot occur in high winds.
7.1.3 Disadvantages
SWER systems also have a number of disadvantages. SWER lines typically have a “spur” (linear)
layout with no alternative means of supply and therefore a single-point failure can cause lengthy
interruptions to supply to all customers further down the line. Since SWER lines tend to be long, the
voltage drop along the line is often a problem, causing poor power quality. Also, significant earth
return currents flowing through the ground near the customer substations can pose a safety risk,
and particular care must therefore be taken to ensure good, low impedance, earth connections.
7.1.4 Use
SWER systems shall be used only under specific circumstances and subject to the approval of
Ausgrid.
Note 1: Stainless steel conical (volute) washers shall be used on all bolts used to secure
crossarms to a pole or equipment to a crossarm or pole. The approved method for a
crossarm attached to a pole is to use a bolt fitted with a square washer, through the pole,
gain block and crossarm then use 1 x square washer, 1 x SS conical washer, 1 x round
washer (galv) and finally the nut.
Note 2: Equipment mounted on a crossarm similarly requires either 2 x square washers, or the
steelwork substituting one square washer, plus 1 galvanised conical washer, 1 x round
washer and a nut. Both cases require a large surface area in contact with the timber to
prevent indentation. The conical washer is used to allow for shrinkage of the timber.
Table 14 – SWER Lines Standard Construction Drawings
Designs shall also be in accordance with the specific requirements indicated in NS 220 Pole
Mounted Substation Construction.
Poles should be located in the road or private property either side of a rail crossing, provided
RailCorp’s technical requirements, on maximum span lengths and the like, etc permit this.
Where new works on existing crossings permit, advantage should be taken of the opportunity to
relocate poles where this is appropriate. Any such projects should be referred to Ausgrid for
decision on what work should be included in these cases.
Further information concerning the construction of new facilities within railway corridors may be
obtained by contacting Ausgrid.
The assessment of waterway crossing risks as required by the above code shall be undertaken in
accordance with NEG OH14 Guide to the Assessment of Waterway Crossing Risks.
All necessary consents, e.g. Local council development consent, State Rail Infrastructure
Corporation crossing approval, Waterways Authority water crossing approval, RMS road
crossing approval.
All relevant data regarding the existence of other installations in the vicinity of the work site and
their relative locations, such as water, sewer, gas and telecommunications installations.
The original copy of the agreement to pay street lighting alteration and annual charges by Local
Council/RMS/SRA, etc.
Profiles of overhead designs showing poles, ground and conductor profiles at maximum
operating temperature. (Profiles may not be required for low voltage lines in urban streets,
however, details should be provided to indicate the minimum ground clearances).
A report on the mid span clearances between circuits at worse case conditions for each span.
The conductor temperature of the higher circuit shall be the Maximum Design Temperature, as
nominated by Ausgrid. The conductor temperature of the lower circuit shall be 15°C.
Pole loading and details of ground strengths used for calculations. Pole loading shall include
the load cases prescribed above.
Any approval for constructions in/on classified roads (ie either RMS or local council).
The basic safety principle for high voltage work is that all exposed high voltage mains and
apparatus must be treated as alive until they have been isolated, proved de-energised, earthed and
short-circuited by approved means.
Work or testing must not be done on or near high voltage mains and apparatus until an operator
has completed the procedures documented in Clause 8.1 of Ausgrid’s Electrical Safety Rules.
Refer also to Clause 7.1 of Ausgrid’s Electrical Safety Rules, where the work is on or near low
voltage mains and apparatus.
After testing the line to prove it is de-energised, the line must be earthed and short-circuited
between all points of isolation and the work site. Earthing and short-circuiting must be carried out
using the appropriate equipment.
Where isolation is by opening high voltage dropout fuses, the fuse carriers must be completely
removed.
10.0 CLEARANCES
10.1 Clearance Criteria
Clearances from ground, structures and vegetation shall be in accordance with Section 10 of
NS220 Overhead Design Manual.
It should be noted that whilst clearances specified in NS 220 are based on AS/ NZS 7000
Overhead line design - Detailed procedures, the ground clearance values specified in NS 220
Section 10 are more stringent.
Where poles need stays due to unbalanced loads which would exceed the permissible design load
limits of the pole, they must be stayed in accordance with NS 220 Section 7, prior to attaching the
unbalanced loads to the pole.
The insulation resistance (IR) test measures the insulation resistance of the installation using an
insulation resistance tester (e.g. Megger). It involves measuring both the phase-to-phase and
phase-to-earth insulation resistances.
For 11kV installations, a 1000 V insulation resistance tester with a measurable range of at least
100 Megohms marked in numbers on the graduated scale must be used. A measurable range of at
least 400 Megohms marked in numbers on the graduated scale is preferred.
Because of capacitance effects, the insulation resistance tester must be applied for a minimum
period of one minute before taking each resistance reading.
If any test readings are less than those indicated above, Ausgrid must be consulted before any
further work proceeds.
To purchase materials from Ausgrid, the Project Manager must contact the "Manger – Customer
Service - Logistics" on telephone number (02) 9394 6001. Materials will generally be made
available for the Accredited Service Provider to pick up from:
Central Warehouse
33 Kangoo Road
Somersby NSW 2250
Alternatively, the Accredited Service Provider may obtain material from other sources provided the
quality assurance and environmental management system requirements are met. Materials must
comply with Ausgrid's relevant specifications.
14.0 RECORDKEEPING
The table below identifies the types of records relating to the process, their storage location and
retention period.
Table 15 – Recordkeeping
Approved copy of the network BMS Network sub process Standard – Unlimited
standard Company
Draft Copies of the network TRIM Work Folder for Network Unlimited
standard during Standards (Trim ref. 2014/21250/125)
amendment/creation
* The following retention periods are subject to change eg if the records are required for legal
matters or legislative changes. Before disposal, retention periods should be checked and
authorised by the Records Manager.
A1 Assumptions
Calculations and the curves are for a line considered running horizontal and erected on a
horizontal ground plane. Approximate adjustment for a line inclined to the horizontal is also
given below.
Line height is less than 18m.
Only direct lightning strikes are considered.
Direction of the lightning discharge path up to the final return stroke is vertical.
Only trees greater than the line height are considered for calculations.
A2 Additional information
Usually lightning stroke currents range from 3kA to 200kA.
If a line is shielded (from direct strikes) for strikes lower than (for example) I kA then it is
shielded for all strikes greater than I kA. The calculations and the curves given below are for
potential strikes less than 5kA. The probability of occurrence of such strikes is less than one in
every 100 strikes.
It can also be shown that the probability of a direct lightning strike less than 5kA strength to an
open line of 20km length, with outer conductors 2.4m apart, is one per 10 years. (This
inference is arrived using the strike incidence equation by IEEE working group on “Lightning
Performance of Transmission Lines”).
Striking distance of a lightning stroke with a given stroke current ‘I’ is given by:
rc rg r 10I 0.65
[Love’s equation for striking distance for heights less than 18m]
Where rc and rg are the striking distances to conductor and ground respectively.
A3 Explanations of graphs
The following paragraphs explain the graph shown at the end of this section.
Figure A-3 give the minimum heights (above the line) required by the objects, corresponding to
different conductor heights, to provide complete shielding, at least, for some length of the line.
This extent of the line completely shielded by a close by object could be read from Figures A-4 to
A-8.
Figure A-8 is to estimate the level of shielding offered by the nearby objects to lightning originating
on the object side of the line. This is different from complete shielding, as in this case, the line
segment is slightly exposed to the lightning coming from the other side of the line unless there are
objects on the other side of the line to provide shielding.
As surge arresters are recommended for all CCT to BC transition points and either side of
switching poles, effort should be made to locate these poles in exposed areas if convenient.
A4 Inclined lines
Shielding length when the line is inclined to the horizontal by an angle α.
If the line is inclined to the horizontal by an angle then the shielded region is estimated as
follows.
When the graphs are read to estimate the shielding provided by an object for an inclined line, the
height (h) shall be multiplied by cos. This has the effect of a reduced height above the line equal
to hcos. The total protected length of the line is read from the graph for this new height. It should
be noted that:
Figure A-1 – Explanation about the geometry of the space near the inclined line.
The point (P) is on the line. Also, the point P is on the line of intersection of the vertical planes, one
through the line and the other through the object perpendicular to the former plane (or line L1L2).
The height (h) of the object above the line is defined as the, vertical height of the point (T2) under
consideration, above the point P.
This is the vertical distance PT2 in Figure A-1, above. Note that P is a point on the line and hence
PT2 is not a vertical line but h is the vertical distance between P and T2 as shown in Figure A-2
below.
Figure A-2 – Further explanation about the geometry of the space near the inclined line.
PP1T1T2 form a vertical plane perpendicular to the vertical plane through the line.
Figure A-3 – Minimum heights of objects for given conductor heights for complete protection
Figure A-4 – Shielding length for different heights (Height of the line 9.0m) for given horizontal
distance of the object for complete protection
Figure A-5 – Shielding length for different heights (Height of the line 10.5m) for given horizontal
distance of the object for complete protection
Figure A-6 – Shielding length for different heights (Height of the line 11.5m) for given horizontal
distance of the object for complete protection
Figure A-7 – Shielding length for different heights (Height of the line 13.0m) for given horizontal
distance of the object for complete protection
Figure A-8 – Shielding length for different heights for given horizontal distance of the object for
lighting originating from the same side of the line as the object