CIVIL ENGINEERING DEPARTMENT

DIPLOMA IN CIVIL ENGINEERING


SESSION JUNE 2017

COURSE: DCC2073: CONTRACT AND ESTIMATING

ASSESMENT: END OF CHAPTHER

NAME REG. NO MARKS

INSTRUCTION: ANSWER ALL QUESTIONS.

QUESTION 1

CLO2 : C2 Pursuant to clause 44.0, the contractor is entitled to claim


payment for losses and expenses incurred.

i. Explain the losses and expenses that can be claim by 10 marks


the contractor.
ii. Explain the action can be taken by the contractor to 10 marks
claim payment for losses and expenses.

QUESTION 2

CLO 3: C3 R&R is a construction company which is carrying out the


construction of a vocational school, Sepanggar,Kota
Kinabalu. Recently, this company is faced with the problem
of lack of skilled workers and the work progress is behind 25 marks
the actual work schedule. Discuss the clause 23.0 with this ** rubric
situations and explain how this clause can help the LD 8
company to solve the problem.

NOTE:-
1. Group Assignment ( 3 persons)
2. Evaluation based on rubric (CLO 3: LD 8) for EOC GSA scoring.
3. Score table:
EOC CA EOC GSA
(35 MARKS) (25 MARKS)
Q1 + Q2 Q2
RUBRIC -LD 8: PROFESSIONALISM, ETHICS AND MORAL

STUDENT NAME REG NO SKILL ASPECT MARK TOTAL 100%


(25)
A B C D E