NUSANTARA TURBIN & PROPULSI PART NAME : Boost Comp C1604 Work Scope : Sermalon Coating

CUSTOMER : PT. Indoturbine Planned Time : 14 Days

MASTER PRODUCTION SCHEDULE WIP# : 451941 Date Started : 5 July 19


S/N : n/a Complete Target Date : 18 July 19

DATE
NO ACTIVITY June July 2019 REMARKS
26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

01 Incoming inspection n Cleaning

02 Impurities

03 masking

04 blasting 1 2 3

05 masking 1 2 3
06 coating 1460 1 2 3
07 curing 1 2 3
08 inspection 1 2 3
09 burnishing 1 2 3
10 inspection resist n cond 1 2 3
11 coating 1083 1 2 3
12 coating 1140 1 2 3
13 curing 1 2 3
14 Final inspection 1 2 3
15 Shipment

TURN AROUND TIME 1 2 3 4 5 6 7 8 9 10 11 12 13 14

NOTE :
ISSUED BY : CHECKED BY : APPROVED BY :
1: kelompok diffuser I C16,
2: kelompok diffuser II C16,
3: kelompok impeller C16

Endang Ruhimat Irwan Wahyu Ferry Surya K R0 DATE : 5 July 2019

FORM No. PC10-1R1