Professional Documents
Culture Documents
36 Japan Railway & Transport Review • December 1997 Copyright © 1997 EJRCF. All rights reserved.
Figure 2 Typical (top) and Geosynthetic-Reinforced Embankments (bottom)
Typical embankment collapsed during Great Hanshin Earthquake (RTRI) Geosynthetic-reinforced embankment with vertical concrete facing wall undam-
aged by Great Hanshin Earthquake (RTRI)
Copyright © 1997 EJRCF. All rights reserved. Japan Railway & Transport Review • December 1997 37
Technology
Steel bridges
(d) Finished viaduct
Steel railway bridges can roughly be di-
vided into plate girder bridges (bridges
with rails above the girders are called
deck plate girder bridges and those with
rails under the girders are called through
Scaffold shoring for rigid frame viaduct (RTRI) Completed viaduct (RTRI)
38 Japan Railway & Transport Review • December 1997 Copyright © 1997 EJRCF. All rights reserved.
Figure 4 Cable-Stayed PC Bridge Construction using Cantilever Method
Mountain Tunnels
Constructing cable-stayed bridge (RTRI) Chain of bridges joining Honshu and Shikoku over Seto Inland Sea—upper deck
for motorway and lower deck for railway (Honshu-Shikoku Bridge Authority)
Copyright © 1997 EJRCF. All rights reserved. Japan Railway & Transport Review • December 1997 39
Technology
(a) Earth-retaining (b) Covering ground (c) Constructing (d) Back filling,
wall surface, protect- underground removing cover
ing utilities, station plate, restoring
excavating ground surface
Cover plate
Plate girder bridge (RTRI) Supports
placing the conventional steel and used for relatively shallow tunnels and water supply, sewage, and gas pipes.
pile supports. This has become the where there are no existing structures on After the station is built, the above space
standard method since it was first or under the ground. However, the shield is back-filled to restore the ground sur-
used for the Nakayama Tunnel on the method, which permits deep tunnels to face.
Joetsu Shinkansen (completed in be dug horizontally, is widely used to-
1982). day. Shield method
Recently, the tunnel excavation has be- In the shield method, a shield (steel shell)
come increasingly automated and some Cut-and-cover method with a cutter at the front is used to tunnel
tunnels have been constructed using Complex underground stations are through the ground. The excavated
shield tunnelling machines. chiefly constructed using the cut-and- ground is prevented from collapsing by
cover method (Fig. 5). the pressure of slurry, etc., pumped back
First, an earth-retaining structure of steel to the work face. Segment concrete
Subways piles, concrete, etc., is constructed from blocks prefabricated elsewhere are as-
ground level, then the open cut is cov- sembled automatically inside the shield
For some time after the construction of ered so as not to interfere with the above behind the work face to finish the tunnel
the first tunnel, subways were built us- ground traffic. Next, the ground is exca- (Fig. 6). Shield tunelling permits fast, rela-
ing exclusively the cut-and-cover vated to the required depth using suit- tively safe construction work, and nei-
method. In this method, the ground is able supports and taking care not to ther interferes with traffic above ground
cut to the tunnel depth, so it can only be damage underground utilities, such as nor adversely affects nearby underground
Jack
Cutter disk P Pump
Erecting prefabricated segments behind shield in Tokyo’s new Subway Line No. 7
of Teito Rapid Transit Authority (M. Shimizu)
40 Japan Railway & Transport Review • December 1997 Copyright © 1997 EJRCF. All rights reserved.
structures.
In recent years, since shallow under- Figure 7 Longitudinal Cross Section of Seikan Tunnel
ground space in big cities is almost fully
used, more subway stations are being Tunnel length (53.8km)
constructed deeper underground, using Underground section Underwater section Underground section
(13.55km) (23.3km) (17.0km)
the shield method.
Tunnel Portal
(m) at Yunosato,
400
Tunnel portal
at Hamana, Shirenai-cho,
Smoke extraction Hokkaido
300 Imabetsu-cho, machine room Smoke extraction
Seikan Tunnel 200
Honshu machine room Shaft to side
side Shaft to Ventilator surface
machine room Ventilator
100 surface machine room
Tsugaru Strait
With a length of 53.8 km, the Seikan Tun- 0
l
nel connecting Honshu and Hokkaido -100 Main 140m
tunne
tunne
l
Servic
e tunn e tunne
l Main
-200 el 100m Servic
is the world’s longest tunnel (Fig. 7). Inspection Inspection point
-300 point Pilot tunnel Pilot tunnel Water
Construction started in 1971 and was drainage
Water drainage area
completed in 1988. Because of the ex- area
ceptional length, pilot and service tun-
0 5 10 15 20 25 30 35 40 45 50 (km)
nels were also dug. The pilot tunnel was
used mainly for geological surveys, and
the service tunnel alongside the main
tunnel was used as a passage for con-
Figure 8 Seikan Tunnel between Honshu and Hokkaido
struction workers and for removal of ex- showing main, service and pilot tunnels
cavated rock.
The main tunnel diameter is 9.6 m to al- Main tunnel
low passage of shinkansen in the future. 30.00m
Service 0~
The submarine section is 23.3-km long 0.7 90m
Shotcrete thickness 0.12m~0.15m 0.
tunnel
and the deepest point is 240 m beneath 0m
4.8
sea level. Construction proceeded with s of 600m)
necting gallery (at interval
4.10m
Con
3.47~
Copyright © 1997 EJRCF. All rights reserved. Japan Railway & Transport Review • December 1997 41