of the projects and for some other purposes. Following is the explanation of some Pc’s forms
along with the propose of its usage and Importance.
PC-1 FORM
(Social SECTORS)
This form/proforma is used for Development projects (social sectors).which includes
Education, Training and Manpower, Health, Nutrition, Family Planning & Social Welfare,
Science & Technology, Water Supply & Sewerage, Culture, Sports, Tourism & Youth, Mass
Media, Governance Research. It is revised in 2005 by Government of Pakistan Planning
commission. It has several contents which is necessary for the investor or any person who
wants to invest or start their projects on the above mentioned social sectors must be filled.
Following are the contents of the pc-1 form(Social sector):
Page | 1
After fulfilling these requirements it must be signed by following persons/authorities along
with their designations, name and phone number.
i. Prepared by _______________________
Name, Designation & Phone #
Page | 2
PC-1 FORM Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PC-1 FORM
(Production SECTORS)
It is another type of pc-1 form. This form/proforma is used for Production sectors which
include Agriculture Production, Agriculture Extension, Industries, Commerce and Minerals.
It also have several contents which are necessary for the investor or any person who wants to
invest or start their projects on the above mentioned Production sectors that must be filled.
Following are the contents of the pc-1 form (Production sectors):
Name of the project
Location
Authorities responsible for:
i. Sponsoring
ii. Execution
iii. Operation and maintenance
iv. Concerned federal ministry
Plan provision
Project objectives and its relationship with sector objectives
Description, justification, technical parameters and technology transfer aspects
(enclose feasibility study for projects costing Rs 300 million and above)
Capital cost estimates
Annual operating and maintenance cost after completion of the Project
Demand and supply analysis
Financial plan and mode of financing
Project benefits and analysis
i) Financial
ii) Economic
iii) Social benefits with indicators
iv) Employment generation (direct and indirect)
v) Environmental impact
vi) Impact of delays on project cost and viability
(a)Implementation schedule
b) Result Based Monitoring (RBM) Indicators.
Management structure and manpower requirements including specialized skills during
construction and operational phases
Additional projects/decisions required to maximize socio-economic benefits from the
proposed project
Page | 3
Certified that the project proposal has been prepared on the basis of Instructions
provided by the Planning Commission for the preparation of PC-I for production
sector projects.
i. Prepared by _______________________
Name, Designation & Phone #
These are some requirements of pc-1 forms that should be filled. If it cannot be filled
the no one can legally start their project on these areas.
Page | 4
PC-1 FORM Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PC-1 FORM
(Infrastructure SECTORS)
It is another type of pc-1 form. This form/proforma is used for Infrastructure sectors which
includes Transport & Communication,Telecommunication,Information Technology ,Energy
(Fuel & Power),Housing, Government Buildings &Town Planning, Irrigation, Drainage &
Flood Control. Any person who wants to invest or start their projects on the above mentioned
Infrastructure sectors must filled some requirements. Following are the contents/requirements
of the pc-1 form (Infrastructure sectors):
i. Sponsoring
ii. Execution
iii. Operation and maintenance
iv. Concerned federal ministry
Plan provision
Project objectives and its relationship with sector objectives
Description, justification, technical parameters and technology transfer aspects
(enclose feasibility study for projects costing Rs. 300 million and above)
Capital cost estimates
Annual operating and maintenance cost after completion of the Project
Demand and supply analysis
Financial plan and mode of financing
Project benefits and analysis
i) Financial
ii) Economic
v) Environmental impact
Page | 5
vi) Impact of delays on project cost and viability
Implementation schedule
b) Result Based Monitoring (RBM) Indicators
Management structure and manpower requirements including specialized skills during
construction and operational phases
Additional projects/decisions required to maximize socio-economic benefits from the
proposed project
Certified that the project proposal has been prepared on the basis of instructions
provided by the Planning Commission for the preparation of PC-I for Infrastructure
sector projects.
After fulfilling these requirements it must be signed by following persons/authorities along
with their designations, name and phone number.
i. Prepared by _______________________
Name, Designation & Phone #
These are some requirements of pc-1 forms that should be filled. If it cannot be filled the no
one can legally start their project on these areas.
Page | 6
PC-IIFORM Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PC-II FORM
Expected outcome of the survey feasibility study and details of projects likely to be
submitted after the survey.
i. Prepared by _______________________
Name, Designation & Phone #
Page | 7
PC-III (a) Form
(Revised – 2005)
Government of Pakistan
Planning Commission
Implementation of Development Projects
(Physical Targets based on PSDP allocation)
To be furnished by 1st July of each year
This PC III form is given by planning commission of Pakistan. This form/proforma is used
for Implementation of Development Projects (Physical Targets based on PSDP allocation) to
be furnished by 1st July of each. It has some requirements which must be filled.Following \re
the Requirements:
Page | 8
Cash Plan (Rs.Millions)
Ist Quarter 2nd Quarter 3rd Quarter 4th Quarter
Output indicators:
These are some requirements of PC III form that is necessary to be filled .If it is not filled
properly then it has no worth.So its necessary that fill the above requirements properly.
PCIII (B)
(Revised 2005)
Government of Pakistan
Planning Commission
Implementation of developments projects
(To be furnished 5th day of Each Month)
This PC III (B) form is given by planning commission of Pakistan. This form/proforma is
used for Implementation of Development Projects to be furnished by 5th day of each month. It
has some requirements which must be filled. Without filling this form a penalty has been
charged by pc.
Page | 9
PC - IV
PROJECT COMPLETION REPORT
(PROFORMA FOR DEVELOPMENT PROJECTS)
PCR – 01
(Revised-2010)
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
******
(PC – IV PROFORMA)
It is another type of form which is issued or given by planning commission of Pakistan. This
form/proforma is used for the Project completion..Following are some requirements of this
form
.
To be furnished immediately after completion of the project regardless the project
accounts have been closed or not.
Location
2. Sector
Sub-Sector
3. Sponsoring Ministry/Agency
Page | 10
6. Date of Approval & Approving Forum (DDWP/CDWP/ECNEC/PDWP/Other)
• Original
• Revised
7. Date of
a) Implementation Period Date of Completion
Commencement
• As per PC-I
• Actual
(Rs. Million)
• Original
• Revised
(Rs. Million)
9. FE/Loan/*
Financing of the Project Local Total
Grant
Federal Share
Provincial Share
Donors/Others
Total:
Page | 11
10. Project Accounts
PLA
Assignment Account
Current Account
Saving Account
Other
(Rs. Million)
1 2 3 4 5 6 7 8 9
Total
Page | 12
12. Physical Targets and Achievements
(Rs. Million)
Total:
(Rs. Million)
Page | 13
Total:
* Mention source and agency responsible for financing the recurring cost after
completion of the project
(Rs. Million)
Page | 14
17. RBM Indicators as given in the PC-I
Outcome
Targeted
S.No. Input Output Baseline Targets after Completion Impact
Indicator of Project
Indicate Agency
List of Assets (Moveable/Immoveable)
a) Financial
b) Economic
c) Technological
d) Social (Education, Health, Employment, area Development, etc.)
e) Environmental
f) Any other
Page | 15
21. Mechanism for Sustainability of Activities after Completion
Indicate mechanism how the project activities will be continued on sustainable basis
a) Financial
b) Economic
Organizational Management
Capacity of the department concerned
Decision making process
Any other
a) Project identification
b) Project preparation
c) Project approval
d) Project financing
e) Project implementation
Page | 16
25. Suggestions for Future Planning & Implementation of Similar Projects
Name &
Designation
Telephone No.
E-mail Address
Date
Page | 17
Revised 2005
PC-V FORM
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PROFORMA
These are some requirements of PCV form that is necessary to be filled .If it is not filled
properly then it has no worth.So its necessary that fill the above requirements properly.
Page | 18