Professional Documents
Culture Documents
HANDBOOK
&
GUIDELINES
Prepared by:
Date
Approved by:
Date
Date
You have joined a highly dynamic team. You will handle more projects from cradle to
grave in a year than some project engineers do in a lifetime. You may be expected
to manage up to 20 projects at a time. This highly motivated team responds quickly
to the plant needs for fast track projects, especially those related to unit turnarounds.
Job satisfaction comes from doing several good jobs safely, all at one time, and
working with a small tight knit group.
The minor project tool box is a set of standard templates and guidelines specifically
designed for the requirements of minor projects. Other templates, procedures and
guidelines are referenced which are to be used on all projects, details are given in
the reference section of this guideline.
This Guideline Handbook is provided to assist you in your new assignment. It is not
meant to shortcut Jacobs JSTEPs, as adapted to the Huntsman project execution
processes, which are the bases of our procedures and methods. Where it is agreed
that the efficiency of the Minor Projects Team can be improved without compromise
to quality or safety then the basic procedures used for major projects have been
simplified. Never lose sight of the fact that the “Best Practices” of Huntsman
procedures and JSTEPs shall be maintained as you execute projects in the minor
project environment.
Every project team member is willing to assist you in making the right choices and
finding information you need to be successful. You should have been assigned a
mentor. If you don’t know who your mentor is, contact the minor project team
Leader. Your mentor is an experienced professional project engineer who will be
available to help you in your transition period.
This manual covers several topics. It starts with Safety and ends with Safety. There
is no other way to complete a small project. If you are starting your first day you
probably already know that. You have completed your Huntsman induction and will
be aware of the emphasis both Huntsman and Jacobs put on safety. All project
activity will support and promote the principles of Zero Harm.
Other sections of this manual will walk you step by step through execution of a minor
project. In addition to this manual, you will be issued with a set of procedures and
guidelines. These procedures, which have minor project sections within them where
applicable, shall be followed at all times. These guidelines are a supplement that
gives you the basics for handling a minor project within the context of all Alliance
Procedures.
If you have any questions on any of the subjects, contact your mentor or the minor
projects manager.
Welcome again,
TABLE OF CONTENTS
1. Safety
3. Project Initiation
5. Project Estimate
6. Project Schedule
8. Construction
9. Constructability
18. References
Attachments
The Minor Project Toolkit is supported by a set of folders and templates that are to be
downloaded from the Huntsman network to be numbered and populated with information for a
new project, hence every new project will start with a ready made set of documentation.
The folders are located at X:\nnnnnnnn (Provide link)
2 Project Initiation
Idea form, template ref. Capx PF 22
CER input form, template ref. nnn
4 Project Schedule
No company standard template
6 Cost Reports
Management summary and cost status, template ref. Capx PF 12
Capital Cost Report – summary, template ref. Capx PF 13
8 Construction
Tie in/cutover procedure, template ref. Capx PF 15
9 Project Closure
Transfer of Responsibility Certificate 1 template ref. Capx PF 25
Transfer of Responsibility Certificate 2 template ref. Capx PF 26
Project Closure Notice, template ref. Capx PF 27
PER record, template ref. Capx PF 29
10 Resource summaries
Minor Project Resource Summaries (two pages), template ref. Capx PF 18
11 Compliance Report
Streamlined Compliance Report, template ref. Capx PF 19
1. SAFETY
Safety is your first priority as a Project Manager (PM) or Project Engineer (PE) in the
minor projects team. Every other Tuesday, the minor projects team Project
Engineers along with the Huntsman Team Lead perform safety audits at one or more
project construction sites as time allows.
As the leader of many projects, the minor project engineer must set the example for
safe work. The Project Engineer shall review his/her projects with engineering,
construction, and subcontractors with an emphasis on Zero Accidents. Every
meeting will start with a Safety Minute. All projects will comply with Huntsman EHS
Considerations for Capital Projects EHS-707.
Any visit to the jobsite requires a Safe Plan of Action: Visit to Construction Site (see
attachments, template ref. Capx PF 28). There are two exceptions to this rule: an
SPA form is not required if site trip is for attending a meeting in a building, or on
Safety Audits when the jobsite SPA can be signed.
Huntsman use a simple screening process to separate the project workload into
those projects that can be done in a streamlined mode, i.e. Minor Projects and those
that require a conventional project management, multi-discipline approach. For a
project to be placed into the Minor execution category it must meet the following
requirements:
The technical solution is straight forward; simple appraisal and selection will
define the project
If the Process Hazard Analysis Study Leader has classified the project as Minor
and hence PSM is limited to a Safety Assessment and hazard studies are not
required
Procurement is limited to Replacement in Kind items with a minimum of technical
input or assessment
The work can be defined by a simple, logical step by step process with a
minimum of complicated dependencies and where each activity the responsibility
of a single discipline or contractor
Construction is straight forward
Typically the project is less than USD $500,000 in value and meets ALL of the
above requirements
The minor project team manager will assign projects to project engineers. These
projects could be in various phases of engineering or construction. This means
some of the projects may already be in study phase or even fully funded and ready
for detail design.
Because of the smaller size and minimum discipline involvement for minor projects a
two stage gate front end process is used; the Huntsman front end execution process
for Major projects is a four stage gate process each of which leads to CER
submission.
Overall project execution for minor projects is a four stage process to Operations
whereas the Major Project Execution process is a six stage process to Operations
The 3 stages of the MPT Work Process are: “Front End Loading or
Appraise/Select/Define Stage”, “Execute Stage” and “Operate or Start-Up & Close
Out Stage”, this comparison is illustrated on the Major Minor Project Comparison
chart shown below:
-
0 1 2 3 4 5 6 7
Phase 0 Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Phase 6 Phase 7
Detailed Commission
Idea Feasibility Concept Design Construct Operations
Scope & Start up
3. PROJECT INITIATION
Please refer to the flow chart below. All projects begin with the completion of an Idea
Form (see standard form ref. Capx PF 22) which may be raised by any member of
the Alliance. The Idea will be assessed by the Works Engineer who may call for
assistance from the appropriate Area Manager, the Site Production Manager, the
Asset Improvement Manager, the Technology Manager and the EHSQ manager. The
Works Engineer will check the Idea Database and the Pending and Closed Project
Database to ensure that Idea has not been assessed previously and will include any
reasons and decisions previously given in his assessment.
Prepare
IDEA
form
Check
IDEA
Database
Out Select
In/Out
substitute
Of Budget
project
In
Approved Add
N
for Details Stop
Development To IDEA
Database
Y
Appoint
PM/PE Major
& nominate Minor Major
or
Support Minor Refer to Major
team Project Flowchart
Populate
CER
for sanction
PDRI 3
for Minor
Projects
Add N
To pending/ CER
closed approved
Database
Y
Execute
project
Close out
Stop
The Idea Form is single page statement of the suggested improvement to bring to
management attention any issue that will improve the performance of the plant.
Whilst the Idea should be clear from the information provided the form content should
be kept to a summary to minimise the work required to raise it. It is important that the
problem is accurately stated, the application of Root Cause Analysis techniques may
help.
If the Idea form is not approved for development details of the design must be added
to the Idea Database and the form is filed in the appropriate electronic document
folder.
If the Idea form is approved the Works Engineer will consult with the Manager of
Projects to appoint a Project Manager/Project Engineer. The Appointed Project
Manager/Project Engineer is responsible for mobilising the team and ensuring that
sufficient data is produced to support a Capital Expenditure Request (CER) and for
arranging an independent assessor to perform the PDRI assessment at gate 3.
The lack of complexity in Minor Projects means that the Feasibility, Concept and
Detailed Scope phases can be amalgamated into one phase and an accelerated
timescale will be possible.
Minor projects will be assessed using the CII PDRI checklist, (see section 15 of this
document) which is to be used in conjunction with Operating Procedure CapxP01 to
prepare the necessary documentation to allow the responsible Project
Manager/Project Engineer to complete the CER submission. The CER is a standard
document and its use is defined in Huntsman “Corporate Capital Investment
Guidelines” section 5.0.
Once CER approval has been obtained and the project has been scheduled for
implementation the project leader (Project Manager/Project Engineer) will update the
Project Execution Plan and hold a project kickoff meeting. The purpose of this
meeting is to align project team members with the project objectives through review
of the scope of work, roles and responsibilities, and project deliverables.
It will be issued in draft form for CER submission and will be updated for the
execution phases ready for the project start. The PEP is the key to communicating
the project goals and objectives to the project team and will be updated and reissued
as necessary.
Guidelines and typical content to indicate the expected contents of each section are
given in the standard pro-forma in the Minor Project Tool Box.
As discipline and construction personnel join the project team and start to add detail
to the scope of work, the PEP document shall be updated. As a minimum an
updated PEP shall be reissued before the construction phase starts.
The Project Execution Plan in conjunction with the Plant Item List will describe the
scope of work for the project. From time to time during the project execution it may
be necessary to change the project scope; all such changes must be authorised
before implementation. Where change is proposed a member of the project team
must raise a Change Alert Sheet and have this approved by the Project Manager.
5. PROJECT ESTIMATE
Better quality estimates will lead to more efficient use of group capital and therefore
potentially additional investment funds to allow more projects to go ahead.
The estimate shall be compiled in accordance with the guidelines set down in
capexBPG012 and the associated procedures and templates. The project estimate
shall be prepared using the Project Estimating Template (ref. Capx PF 11). This
template is located in the minor project folder on the company computer network.
Always start a new estimate with a new estimate template do not re-use an
estimate form from a previous project.
Instructions for using the cost estimate form are provided in the same folder. The
estimate compiler needs to review the associated cost schedule often because they
are up dated at regular intervals. It is recommended that the mentor’s help is sought
when preparing the first estimate.
The estimating process used for Minor projects is a shortened version of the Major
Project procedure and will use simplified methods as defined in the Association for
the Advancement of Cost Engineering International (AACE) guidelines.
Estimates of increasing accuracy are required at each successive stage gate and in
order to expedite the estimating process for Minor Projects the estimate will be
generated using best available prices for equipment and standard rate multipliers for
Civil Structural and Architectural works, Piping and Electrical Instrument and control
items.
Therefore it is anticipated and accepted that estimate inaccuracy will arise in the
generation of Minor Project estimates by the use of the standard rates rather than
omissions from the scope of work, compensation for this inaccuracy will be made in
the risk provision applied to such estimates. If better quality estimates can be
generated without extra effort then risk provision can be adjusted to suit.
Note this is a summary of a more comprehensive guide included in the Capex Best
Practice Guideline ref. Capx BPG 02
The Basis of Estimate defines the scope of the project, and will provide any person
with capital project experience the ability to understand and assess the estimate. The
BOE states the purpose of the estimate being prepared, the project scope, pricing
basis, allowances, assumptions, exclusions, cost risks and opportunities, and any
deviations from standard practices. Additionally the BOE records communications
that have occurred and agreements that have been made between the compiler and
other project stakeholders.
The BOE establishes the context of the estimate, and supports review and validation.
Where no statement is included in the BOE on any given element of the estimate a
subsequent reviewer may make unfounded assumptions as to the basis of estimate;
statements that confirm no change to existing are as valuable as those that describe
change and hence cost. Where no information is given the design and procurement
team may engineer or purchase items not included or covered by the estimate
leading to cost and time overruns.
The following describes the suggested topics and contents included in a typical BOE.
PROJECT CONTEXT
The BOE should be put in context by including an opening statement that re-iterates
a summary of the business objectives and general principles that underpin the
project. These general principles will determine the features, execution and detailed
design of the plant and project to meet the defined business objectives, it follows
therefore they will have an influence on the cost of the project.
Operating philosophy - List the design principles that must be included to achieve the
nameplate plant performance such as service factor, on-stream time, availability etc.
Business Objectives - Reference any features of the business case that will influence
the estimated cost of the project.
Technology - The technology proposed for the plant will be identified in the Idea
Form, proven technology involves less risk than novel or experimental technology to
project cost and schedule, a statement should be included to confirm the status of
the technology.
PROJECT SCOPE
Project Objectives Statement - Ensure that objectives stated in the Idea Form or
Business Case are catered for in the estimate.
Project Design Criteria - Cost will be determined in part by the standards that must
be met in the design of the plant and systems.
Site characteristics available vs required - The estimate must cover the cost of
improvement or upgrade of existing site utilities and support services if required.
VALUE ENGINEERING
Site location - The geographical location must be confirmed and documented, the
estimate must be underpinned by site details.
Surveys and soil tests - The estimate shall be supported by sufficient survey and soil
data to confirm what preparations must be made to make the proposed site suitable
for construction and that unforeseen costs have been minimised.
Permit requirements - A permitting plan for the plant must be in place to support the
estimate.
Utility sources with supply conditions - The estimate will require confirmation of
extent of work required to provide supply of utilities required to operate the
unit/facility.
Fire protection and safety considerations - A list of fire and safety provisions.
Process Flow Diagrams (to include Utility and Material Flow Diagrams) - ensure that
the flowsheets are developed and approved prior to the preparation of the cost
estimate. Estimates for renovation and revamp projects may be based on marked up
copies of existing drawings to show scope of work.
Piping and Instrument Diagrams (P&IDs) - Ensure that the P&IDs for the main
process, services and off-sites have been developed in sufficient detail to be
representative of the equipment, its interconnection and the control philosophy.
Estimates for renovation and revamp projects may be based on marked up copies of
existing drawings.
Component and material take offs - Confirm that the P & IDs have been sufficiently
developed to enable the preparation of:
- a valve take off
- a line list (size, outline specification and length)
- a piping specialty items (in-line equipment) take off e.g. steam traps,
strainers)
- an instrument schedule.
Process Safety Management - Confirm if the project documents have been subject to
safety assessment or HAZOP. Where such assessments or reviews are incomplete
sufficient allowance should be made in the costs to cater for additional safety
measures that may be required as a result of the reviews.
Utility Flow Diagrams, Material Flow Diagrams, (UFDs, MFDs) - UFDs are similar in
nature to P&IDs in that they show utility equipment and pipelines from generation of
supply to user points.
Specifications and data sheets - Confirm that the process specification is firm and
process data sheets have been prepared for all the MPIs including those for services
and offsites. Estimates for renovation and revamp projects may be based on marked
up copies of existing documents.
Plot plan - The plot plan will show the location of new plant in relation to surrounding
plant or offsite areas and shall be complete with sufficient detail to ensure the
estimate compiler will have a sound basis for the estimate. This layout may be in the
form of a drawing or 3D model. Estimates for renovation and revamp projects may be
based on marked up copies of existing documents.
Mechanical Equipment List (MEL) - The mechanical Equipment list shall identify all
mechanical equipment by tag number to ensure the estimate compiler has a
complete scope of work. Estimates for renovation and revamp projects may be based
on marked up copies of existing documents.
Line list - The pipe line list designates pipelines to be included in the scope of work.
Estimates for renovation and revamp projects may be based on marked up copies of
existing documents.
Tie in list (also known as termination point schedule) - All tie-ins or fluid supply
terminations shall be listed so that cost of making connections can be included in the
estimate. Estimates for renovation and revamp projects may be based on marked up
copies of existing documents.
Piping specialty items list (inline equipment) - This list summarises pipe line specialty
items. Estimates for renovation and revamp projects may be based on marked up
copies of existing documents.
EQUIPMENT SCOPE
etc. Estimates for renovation and revamp projects may be based on marked up
copies of existing documents.
Control philosophy - The control philosophy describes the general nature of the
process and identifies overall control systems.
Logic diagrams - Logic diagrams should be developed. Estimates for renovation and
revamp projects may be based on marked up copies of existing documents to show
scope of work.
Electrical area classification - Electrical area classification shall be marked on the plot
plan.
Electrical Single Line Diagrams (SLDs) - SLDs indicates the components, devices or
parts of an electrical power distribution system. Estimates for renovation and revamp
projects may be based on marked up copies of existing documents.
PROCUREMENT STRATEGY
Identify long lead items/critical items and materials - Identify engineered items with
lead time that will impact the detailed engineering because of receipt of vendor
information or impact the construction schedule because of long lead times.
Identification of long delivery times and critical materials is especially important for
renovation and revamp projects where plant shutdown may be involved.
complete. Estimates for renovation and revamp projects may be based on marked up
copies of existing documents.
DELIVERABLES
CAD/3D model requirements - Advise the extent of CAD and 3D modeling proposed.
PROJECT CONTROL
Project control requirements - The estimate shall include provisions for planning, cost
control and estimating effort.
Risk analysis - All projects shall have a risk analysis performed and provisions
included in the estimate.
6. PROJECT SCHEDULE
The importance of a project schedule is that all project team members understand
the sequence of events and therefore they can coordinate their own contribution with
others because they may depend on others to provide information or they may
provide information to others so that work can proceed in the correct sequence.
In general it is expected that the responsible project engineer will schedule the work.
An electronic programming tool is the planning tool to be used for Minor Projects
unless a simple ordered list with dates and resources will suffice, however, a
software application is preferred because of the ease with which progress can be
shown graphically.
Once the project moves from the Detailed Scope phase to the Design and Construct
phase, the site Planner/Scheduler will integrate the Minor project into the overall site
schedule.
The overall project schedule shows all active minor projects and is updated bi-weekly
by the minor project planner. It is used to coordinate details of required resources for
each engineering discipline as well as the construction group. As new projects are
added or implementation dates proposed the overall schedule will determine best
use of resource and will confirm achievable implementation dates.
1 Make a list of all the activities or items that need to be done, made and installed to
achieve the project objectives.
2 Make an estimate of the time needed to do, make or install the activities listed, note
you will have to take into account the resource required to do the activities.
3 List the activities in a reasonably logical order on the Project Programme template.
4 Make any links between activities where one activity must be completed before
another one can start, or where activities must start together or where they must
finish together.
6 The project will only have so much of each of the resources (people, materials,
equipment) it requires available to it, make sure you have scheduled activities so that
resources are not overloaded. The consequence will be that some activities can’t be
started as soon as the earlier listing; this is known as resource leveling.
7 The result of the steps listed above will be to generate an end date for the project
which may or may not coincide with the required delivery date. Some projects will
have a fixed end date and resources may have to be increased to allow activities to
be done at the same time.
8 Adding large amount of resource has its limits; don’t plan on increasing to
unfeasible levels. Adding more resource at the latter stages of a project to recover a
late delivery will often delay the project further because people need to be trained,
supervised and will demand increased communication effort when they first start on a
project hence diverting the attention of the existing team and reducing the overall
efficiency.
9 An assessment by McKinsey indicated that projects that finish on time but over
budget are 140% more profitable than if they had finished on budget but six months
late. It is received wisdom that if a project ends on time it will generally be on budget
or within the contingency allowed in the budget.
10 Whilst the Project Manager/Engineer will be concerned with delivery on time and
on budget the business is concerned with delivering the promised benefit of doing the
work. An on time on budget project will only realise the return on investment if it
accomplishes what the company needed in the first place.
11 The best estimated and planned project can be disrupted by changes to the scope
or specification while it is in progress. Generally major changes are readily identified
and managed, however, the phenomenon known as ‘scope creep’ where small
increments in quality or scope, each of which appears inconsequential in itself, cause
overruns when they are all added together. This tendency is made worse because
delays and increased costs are largely undetected until a major milestone is missed
or the estimate to complete suddenly jumps up in value; by this time it is generally
too late to take corrective action.
Project risk management shall be carried out using the guidelines set out in capex
Best Practice Guideline 017.
Project risk is mostly concerned with cost, some projects may be time sensitive and
hence activity duration may pose a risk, however most schedule risks translate into
cost risks eventually; equally quality issues are generally resolved by additional cost.
Risk Management should be implemented from the start of the project but must be
formalised and documented whenever funding is requested; for Minor projects this
may be after approval of the IDEA form but will certainly be necessary as part of the
CER application.
The risk team should review the list generated and assess risk into three classes:
Unmanageable: Those risk that if they occur cannot be mitigated by any
action or provision available to the project team, e.g. the whole of the site,
including the work area, is flooded; a fire in an existing plant that damages the
work area; a 747 falls from the sky onto the plant.
Day to Day problems: Those risks that should be controlled if all project
members do their jobs well and on time e.g. project documentation is late,
installation involves a heavy lift.
Project risks: Those risks that are specific to this project and can be
managed by including provisions in the estimate and hence in the budget
and/or additional time in the overall duration or promised delivery date, e.g.
quality of information used to generate quotations, a specialist item of
equipment may be late because of unavailability of exotic material.
Risk shall be summarised on the risk register, a template is included in the minor
project tool box.
8. CONSTRUCTION
The involvement of the construction engineer at all of the phases of the project will
ensure that construction is not neglected during design and procurement. The
construction phase is always the most costly of any phase of a project and any
construction cost that can be saved by good design or procurement will be repaid
tenfold in construction.
An estimate is prepared for budget and cost control purposes; the estimate must be
prepared including input from the construction department. This detailed line item
estimate is formatted to indicate what is to be included in subcontract packages
(mechanical, civil, etc.). A construction schedule should be prepared after the
definitive estimate is approved by the PM/PE and issued prior to funding and
included in the overall project schedule. All parties that will form the construction
team should have walked the project site with Engineering and Operations and have
copies of any preliminary data such as the PEP, marked up P&IDs, Plant Layouts or
model shots that the PE can provide to them.
9. CONSTRUCTABILITY
The Project Engineer is responsible for constructability on the project through the
creation of a constructability team. This effort will vary, depending upon the overall
size and scope of the project. The main focus is to ensure that the design package
will provide the information necessary for safe, efficient procurement and
construction planning and will provide construction continuity through planned
delivery of materials and efficient deployment of site supervision and labour.
Each Business shall ensure that Capital Project Processes and Procedures are in
place. These procedures shall include appointment of key project personnel and
technical authorities; relevant engineering and design standards; statutory approvals;
EHS studies and reviews, which must include Hazard Identification and Analysis as
well as occupational health and environmental impact assessments. These studies
and reviews shall consider the entire life of the project, including design,
procurement, construction, commissioning, operation and decommissioning phases.
Each Business / Facility shall maintain business ownership and overall responsibility
for ensuring the project follows the capital project process. In doing so, the Senior
Manager or Business Line Managers shall ensure that a Project Sponsor and/or a
Venture Manager shall be appointed for each Capital Project.
The Project Sponsor / Venture Manager shall ensure that the following key
appointments are made at an appropriate time in the project process:
a) A Project Manager
b) Commissioning Manager
The Project Manager shall ensure during the Design Phase capital projects are
designed, built and commissioned in accordance with local regulatory requirements
and EHS Policies and Standards; particularly those shown below:
EHS-708 Electrical Safety
EHS-516 Lifting Equipment
EHS-703 EHS Critical Mechanical & Pressurized Systems Integrity
EHS-704 Structural & Civil Systems Integrity
EHS-705 Critical Control & Instrumented Systems Integrity
Appointments required by the EHS Standards and other key appointed project team
members must be made in writing. It is essential that those appointed clearly
understand their EHS responsibilities and accountabilities.
All processes shall be engineered with the lowest practicable Risk and the necessary
Hazard Identification and Analysis Studies are carried out. (Ref: EHS - 706), EHS
Critical plant, equipment, structures, instrumented systems and control systems,
including software, are identified and the design intent / function of all EHS Critical
equipment and systems shall be considered, achieved and recorded for use by plant
operating personnel.
During the Procurement and Construction Phases the purchase and supply of
materials, equipment and services must be specified and checked so that the EHS
requirements are achieved. Inspections and tests during manufacture shall be carried
out as per design specification, recorded and records are handed over to the
appropriate facility.
Qualified contractors, sub-contractors and suppliers shall be selected and are given
sufficient site information to protect the safety and health of their employees,
construction work associated with the project must meet EHS requirements, and
contractor’s EHS standards shall be no less rigorous than Huntsman Standards.
The Commissioning Manager shall ensure that the equipment is checked and its
installation complies with the design intent, and that equipment is appropriately
tested to demonstrate that it is working properly; operating instructions are written in
accordance with EHS 111 (Operating Procedures); new or modified plant, equipment
and systems are commissioned in accordance with EHS requirements and
standards; people who will operate and maintain the plant, equipment and systems
are qualified and have documented training.
Relevant EHS information relating to the project shall be retained for future reference
once the project is completed.
It should be noted that the appointed Project Manager and Commissioning Manager
mentioned are not job titles they describe job functions for a single project. The
Project Sponsor / Venture Manager must be a Huntsman Associate. Where the
Huntsman Project Manager is not a Huntsman Associate, the Project Sponsor /
Venture Manager accountable for the Project shall have responsibility for compliance
with this Standard. The Project Manager is normally responsible for the Capital
Project until the end of commissioning unless otherwise agreed with the Project
Sponsor / Venture Manager.
The completed CER package is the mechanism used to allocate funding from central
funds. The CER includes a Financial Summary. The methods to calculate the various
financial components are given in Corporate Capital Expenditure Guidelines.
Once CER approval has been gained the PM/PE must confirm the project budget
based on the CER estimate unless this has been modified by the CER approval
process.
The execution phase kick-off meeting will be chaired by the PE and attended by the
following:
All engineering and support personnel
Construction personnel
Operations
The project kickoff meeting will use the Project Execution Plan as its agenda. This
meeting like all meetings will start with a safety minute and a quality minute each of
which is of relevance to the project.
The team will review scope, schedule and budgets with everyone involved. This is
the time to set up review meetings if required. The project engineer will point out any
key milestones in the schedule that must be met; any long lead items that need to be
placed on order by a specific date and any turn around associated with the overall
schedule of work. The team will also discuss any permits required to complete the
work and make sure they are shown on the project schedule. Other items, which
need to be discussed, include: review of the budgets; setting expectations for
progress; Value Enhancing Practices applicable to the project which will be
implemented; and emphasizing Value Plus. Value Plus can be used as the quality
topic to help the team become aligned with the concept of adding value to the
project. The team shall also agree on the calendar for the future meetings.
The full JVEP list extends to twenty two practices, however, because of the nature of
Minor Projects four are considered of primary importance:
Class of Plant Quality JVEP-13
Constructability JVEP-3
Design to Capacity JVEP-4
Project Definition Rating Index (PDRI) JVEP-9
The minor project team will hold weekly meetings chaired by the Minor Project Team
Manager and attended by all the Project Managers, Project Engineers, Cost
Engineer, Construction, Inspection, Operations, (and Discipline Leads by invitation).
The cost engineer will issue cost reports for all projects. These reports will be
generated in part from the company accounting system; however, the responsible
Project Managers and Project Engineers must update the forecast column. The
responsible Project Engineer shall review these reports regularly and follow up with
the cost engineer to ensure accuracy of the report as well as to provide an updated
cost forecast.
In addition, the Project Engineer shall also review the resource allocation reports to
verify new costs being charged to his/her project(s), for example if the project is not
in construction phase, then there should not be any construction work hours. For
construction labour hours as well as design man hours which include quality
assurance/quality control, construction staff and engineering personnel, the Project
Engineer shall verify that those personnel who charged to his/her project have in fact
charged their time correctly and if not contact them and have charges reversed.
In order to maintain this aspect of control it is vital that all team members charge their
time accurately and do so by the time sheet deadline each week.
Actions:
All “As Built” marked up documentation shall be completed and handed over
to the appropriate groups in the drawing office to allow asset records to be
updated.
The Project Manager /Project Engineer with Field Quality Assurance/Quality
Control engineer shall assemble all system inspection certificates where
these are carried out or verified by Huntsman personnel and the contractor’s
system inspection certificates where these are carried out by the
subcontractor’s representative.
The responsible Project Manager /Project Engineer will complete a Project
Closure Folder and will obtain signatures required from various stakeholders
to ensure that the project is ready to be closed.
Safety clearance will have been obtained during the commissioning and
handover process, in order to close the project from this point of view the
Area Engineers signature on the Transfer of Responsibility Certificate 2 will
confirm compliance with the relevant Safety requirements.
The PDRI manual and the tool are located in Add file reference
The Excel workbook that accompanies the CII Implementation Resource should be
used during the assessment meeting to score the project elements and record notes
as the review proceeds. The Instruction sheet form the Workbook is given below:
REQUIREMENTS
Office 2003 or greater.
INSTRUCTIONS:
Session Assesment Process:
-Introductions: Name, Company, Role (pass attendance sheet around)
-Ask if anyone present has not been through a PDRI. If yes, briefly explain PDRI
-Explain ground rules and scoring.
-Begin PDRI Section I
-Repeat process for each new PDRI.
Toolkit Security Issue:
Due to the presence of macros in this toolkit package, ensure that the security setting before use is set to
"LOW" and afterwards, re-start the toolkit package. This can be done by using the "Security Level" button to
change and check present settings.
How to use:
Start by entering information on PDRI Cover Page
Select project status (i.e., Conceptual, Feasibility, etc.) and then press on the corresponding PDRI sheet (i.e.,
PDRI1, PDRI 2, PDRI 2i, or PDRI 3). Pressing different PDRI buttons, will activate different sets of PDRI
tabs.
Make sure you document the participants by completing the Attendance Sheet tab
Enter basic information on the summary Final Results page for the corresponding PDRI and then press the
button for Section I - Unweighted sheet.
Complete the questions for the section and then proceed to the next section.
NOTE: with this spreadsheet, you cannot score elements through the weighted sheets and update the
Unweighted sheets.
In each section, double click on any element name to display the official element description and dialog box
for scoring. You can also enter comments to each element. Make sure the comments are entered first
before entering the score. The form will change to the next question as soon as you enter a score.
YOU MUST DOUBLE CLICK on any of the element words to get the dialog box to appear. If the text for
the individual element is longer then a single screen, click on the text and you will get the scroll bar. You will
only have to do this on the first long one, after that the scroll bars will show up automatically. For the revision,
the element box is larger and will automatically take you to the next box, when you choose a definition.
Click on the Low definition items at any time to see a summary of all elements with a score higher than the
one predetermined on the page. By default all elements with a score higher than 3 will be displayed. You can
change the Low Definition threshold by selecting the value from the pull-down menu.
TO REFRESH THE LIST AFTER YOU CHANGE THE LOW DEFINITION LEVEL you must first click on any
other tap and then return to the Low Definition sheet for the changes to take effect.
Save frequently to insure that you do not lose any information, using the "Save As" button and a file name
that is unique to your project.
To see the results go to the Final Score page.
You can use the same worksheet to record the results of different PDRI conducted on the same project. The
PDRI Score Chart page will graphically display the results of up to four PDRIs conducted on the same project.
The developers of this freeware program do not warrant its usage or guarantee that it is error free.
This freeware is provided solely to facilitate the use of conducting the PDRI that is provided in the
official printed document provided by CII in Research Team 242. The product is provided "as-is" in
an unsupported basis. The worksheets are protected for the purpose of preventing accidental
damage of the formulas. However, the protected worksheets do not have a password.
CII would like to acknowledge the contributions of and express appreciation to Eskil Carlsson at CSA Group
for the development of this program.
This is a good time to walk the finished project with some of the team to look at the
site and see if safety was appropriately addressed during the design and construction
of the project. Are there places or items that could be improved upon? Is there
something that needs corrective action to prevent a future injury due to the design?
The project team shall verify that no one could be injured because of something that
might have been overlooked or missed during design or construction. Which
processes and activities went particularly well and should be encouraged on future
projects. This verification will provide the project team with a better foundation of
information for design of the current and future projects.
It’s easy to skip this step. But this is one of the most important steps that the Project
Engineer can implement to assure that future projects are better than prior ones.
18. REFRENCES
Capex Procedures