Professional Documents
Culture Documents
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 1 of 50
Design of Wuhama River Bridge Checked by: Date:
Design Method: Load and Resistance Factor Design (LRFD) method according to
American Association of State Highway and Transportation Officials
(AASHTO) Code, SI Units, 3rd Edition, 2005 Interim Revisions.
1. SUPERSTRUCTURE
The superstructure consists of two 15.22m center to center span T-girders and one
33.51m center to center span box girder central span as shown in Fig.1.
T – Girders Design
1.1 Preliminary Design Dimensions
Depth of girders [Table Art. 2.5.2.6.3.1-1]
For simple span T- girders, D = 0.07L where L is span length = 15.22m
Dmin = 0.07 * 15.22 = 1.065m
Take D = 1.10m
Spacing between longitudinal girders, S:- varies from1.8 - 3.6m
C is 0.25S to 0.75S, 2C + 3S= 9.52, C = 0.5S , S + 3S = 9.52m, S = 2.38m
and C = 1.19m
Take S = 2.35m and C = 1.235m
Web width
Minimum thickness = 200mm without pre-stressing duct [Art 5.1.4.1.3.1c and C
5.1.4.1.3.1c]
But the width of the web has to satisfy the clear spacing between bars. The clear spacing
between bars in a row should not be less than 1.5 or the maximum aggregate size.
Minimum concrete cover = 50mm
Taking 32 bars and considering splice, 432 bars in a row
require a beam width of
bw > 3*1.5+ 6*+ cover > 3 * 48 + 192 + 2 * 50> 436mm
Take bw= 450mm
1
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 2 of 50
Design of Wuhama River Bridge Checked by: Date:
Slab thickness
( S 3000) (2350 3000)
tS 178.3mm [Table Art. 2.5.2.6.3-1]
30 30
Take ts = 200mm for structural thickness of the slab, 292mm at the middle to provide a
2.5% side slope(camber) for drainage.
Diaphragms
For T - Girder bridges, diaphragms should be provided at the ends and at one or more
points at spans. The purpose is to help in load distribution between the girders. Further,
finite element analysis shows that there is stress concentration at the supports due to the
big support reactions. Diaphragms reduce the stress concentration. Use 0.3m thick, 1.1m
deep diaphragms at the ends (at each support) and 0.3m by 750mm deep diaphragms at
third points of spans.
Posts and railings
Use continuous concrete barrier wall of height 850mm and thickness varying from
300mm to 200mm as shown in the cross section of the bridge in Fig.2. Pipe posts and
railings will be provided at the top.
Fig.2 shows plan of the bridge and section of the T-girder.
2
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 3 of 50
Design of Wuhama River Bridge Checked by: Date:
Dead load moments (slab, curb and railing dead load moments)
An approximate analysis of strips perpendicular to girder will be considered [Art 9.6.1]
The extreme positive moment in any deck panel between girders shall be taken to apply to all
positive moment regions. Similarly, the extreme negative moment over any girder shall be
taken to apply to all negative moment regions [Art 4.6.2.1.1]
The strips shall be treated as continuous with span length equal to C/C distance of the girders.
1m strip width will be taken MEnd = 5.27*1.1 + 12.52* 1.2352 = 15.35kNm/m
2
Member end moments by cross method of moment distribution :
Half the structure will be used for the distribution due to symmetry as shown
K 0.75 0.5
DF 1 0.6 0.4
FEM -15.35 0 -5.01 3.34
15.35 7.675
-3.60 -2.40
f.m -15.35 15.35 -0.94 0.94
Reactions and moments at sections of maximum positive and negative live load moments
Reactions:
RA1= 5.27 + 12.52x1.235 = 20.73; RA2= (15.35+ 7.26x2.352x0.5 - 0.94)/2.35 = 14.66
RB1= 7.26x2.35-14.66 = 2.40; RB2=0.5x7.26x2.35 = 8.53kN
M0.4S = M0.94 = 14.66x0.94 - 15.35 – 7.26x0.942/2 = -4.78kNm
MFace. = M0.225 = 0.94 - 7.26x0.2252/2 – 2.40x0.225 = 0.22kNm
b) Live loads
i) Overhang live load moments
The critical placement of a single wheel load is 300mm from the face of the curb for
design of overhang slabs.
The equivalent width of a transverse strip is 1140 + 0.833x, where x is distance from the
wheel load to centerline of support. In our case it doesn’t produce negative moment.
Overhang negative moment due to horizontal vehicular collision force on railings will be used
to design the overhang slab (done towards the end of deck slab design).
5.19kN 3
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 4 of 50
Design of Wuhama River Bridge Checked by: Date:
A 1.41m B 0.39 C
K 0.75 1 0.75
DF 1 0.429 0.571 0.571 0.429 1
FEM 0 - 28.623 19.67 -3.91 0 0
3.841 5.11 2.56
0.385 0.77 0.58
-0.165 -0.22 -0.11
0.06 0.047
f.m 0 -24.945 24.945 -0.63 0.63 0
72.5kN 72.5kN
The width of the equivalent transverse strip is, E = 1220 + 0.25s = 1220+0.25(2350) =
1807.5mm
72.5kN 0.9 0.9m 72.5kN
K 0.75 1 0.75
DF 1 0.429 0.571 0.571 0.429 1
FEM 0 - 32.55 24.84 -15.42 0 0
3.31 4.40 2.20
3.77 7.55 5.67
-1.62 -2.16 -1.08
0.31 0.62 0.46
- 0.133 -0.177 -0.089
0.05 0.038
f.m 0 -30.99 30.99 -6.17 6.17
4
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 5 of 50
Design of Wuhama River Bridge Checked by: Date:
72.5 kN 72.5 kN
0.165m 1.8m 0.385
73.07 kN
K 0.75 1 0.75
DF 1 0.429 0.571 0.571 0.429 1
FEM 0 - 27.38 0 0 0 0
0 11.745 15.634 7.817
-2.23 -4.46 -3.35
0.96 1.274 0.64
-0.183 -0.365 -0.27
0.078 0.104 0.052
-0.03 -0.022
f.m 0 -14.60 14.60 3.64 -3.64 0
Action DC LL
RA 35.39 44.91
MA -15.35 0
RB 10.93 75.17
MB -0.22 -12. 32
MMaxp -4.78 19
5
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 6 of 50
Design of Wuhama River Bridge Checked by: Date:
Mu 35.98 * 106
d 81.73 mm 193 mm 0k
0.2244 f c ' b 0.2244* 1000* 24
1 1 2.352 * 36.34 *10
' 6
2.352 M u fc 24
1 1
'
bd f c 1.176 f y
2
0.9 *1000 *193 * 24 1.176 * 400
2
0.03 f c'
0.00279 min 0.0021, 0.00279
fy
AS= bd = 0.00279*1000*193 = 537.7mm2
Distribution reinforcement
Secondary reinforcement is placed at the bottom of the slab in the longitudinal direction to
distribute wheel loads on the bridge to the primary reinforcement in the transverse direction.
The required area as a percentage of the primary reinforcement is:
3840
% 67% Se = 2350 - 450 = 1900 - clear span between girders
Se
3840
% 88.1 67%, take 67%
1900
As = 0.67 * 769.7 = 515.7 mm2
(6) 2 1000 113.1 1000
Using 12, S 219.3mm ,
As 515.7
Provide 12 C/C 200 mm
6
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 7 of 50
Design of Wuhama River Bridge Checked by: Date:
For members greater than 150mm in thickness the shrinkage and temperature reinforcement is
to be distributed equally on both faces. But the primary and secondary reinforcements
provided are more than this amount. This reinforcement will be provided on top face in the
longitudinal direction only.
AS 461.25
230.63mm2
2 2
(6) 2 1000 113.1 1000
Using 12, S 490.4mm 450mm or 3 180mm
As 230.63
Provide 12 C/C 400mm at top in the longitudinal direction to place every other bar with the
bottom distribution reinforcement, ASprov. = 282.7mm2
123000 e dc
S 2d c , s 1 [Art. 5.7.3.4]
s fs 0.7(h d c )
Where dc = depth of concrete measured from extreme tension fiber to center of bar
or wire located closest there to (mm). For calculation purpose, the actual
thickness of clear concrete cover shall be used.
γe = exposure factor, 1 for class 1 exposure and 0.75 for class 2. Class 1
exposure applies when cracks can be tolerated due to reduced concerns
for appearance/corrosion. Class 2 is used when there is an increased
concern for appearance/corrosion.
h = overall depth or thickness of component (mm).
βS is a geometric relationship between crack width at the tension concrete
face and crack width at the level of reinforcement
Es = 200Gpa
Ec 0.043K1 c f c ' 0.043 (2400)1.5 24 24.77GPa
1.5
7
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 8 of 50
Design of Wuhama River Bridge Checked by: Date:
M M DC M LL IM
1000 45.6 3
I cr 8 769.7(67 45.6) 2 8 769.7(193 45.6) 2 168.21 106 mm4
3
nMy 8 20.49 106 (193 45.6)
fS 143.64MPa
Ic r 168.21 106
The contribution of the upper steel is very small and hence can be neglected.
32
S 1 1.237
0.7(225 32)
123000 x0.75
S 200 2 x32 455.2 Ok!
1.237 x143.64
123000 * 0.75
S 200 2 * 67 402.6mm Ok!
1.477 *116.4
8
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 9 of 50
Design of Wuhama River Bridge Checked by: Date:
Ft = Rw
Where
Rw is the resistance or capacity of barrier
2 M L2
Rw 8M b 8M w c c
2lc Lt H
L 8H M b M w H
2
L
Lc t t
2 2 Mc
Mb is moment strength of beam at top of wall,
Mb=0 in our case
Mw is moment strength of wall about vertical axis
Mc is moment strength of wall about horizontal axis
H is height of wall, H=1100mm in this case.
Lt longitudinal distribution length of impact force
Lc critical wall length of yield line pattern
Try 12 C/C 200 mm for barrier wall reinforcement vertically so that it will be tied to
deck slab reinforcement. Try 12 C/C 200mm reinforcement horizontally also.
a As f y 565.5 400
M c As f y d , a 11.09mm
2 0.85 f c b 0.85 24 1000
'
11.09
M c 1.0 565.5 * 400 * (269 ) 59.6kNm / m ,
2
11.09
M w1 1.0 565.5 * 400 * (257 ) 56.9kNm / m
2
11.09
M w2 1.0 565.5 * 400 * (157 ) 34.26kNm / m
2
(56.9 34.26)
M wavg 45.58kNm / m
2
9
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 10 of 50
Design of Wuhama River Bridge Checked by: Date:
Overhang slab moment and reinforcement – the overhang moment will not be
bigger than that which requires 14mm bars which continue from the interior support.
10
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 11 of 50
Design of Wuhama River Bridge Checked by: Date:
Interior giders with concrete decks [Table art 4.6.2.2b and b-1]
Girder distribution factor with multiple presence factor included, g is taken the
smaller of the one obtained from empirical formulae for Nb = 4 or that obtained from
the lever rule.
One lane loaded
gSIM = 0.06 + (S/4300)0.4 * (S/L) 0.3 (kg/Lts3)0.1
gSIM = 0.06 + (2350/4300) 0.4 * (2350/15220) 0.3 = 0.508
SI = single lane loaded, interior; M = moment
res = 1.2*0.5P (85 + 1885)/2350 = 0.503P res exterior girder reaction for single
lane loading
Two or more lanes loaded
gMEM = e * gMI ,
where e = 0.77 + de/2800 = 0.77 + 135/2800 = 0.818
e = 0.818 < 1.0 use e = 1.0 gMEM = 0.682
11
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 12 of 50
Design of Wuhama River Bridge Checked by: Date:
145kN
110kN
145kN 35kN 110kN
Exterior girder
One lane loaded---lever rule with m = 1.2
g SEv = 1.2*0.5P*(85 + 1885)/2350 = 0.503P
It is necessary to construct factored moment and shear envelope equations for both Service I
and Strength I limit states. Truck governs for both shear and moment.
P
0.2414P P P P
0.2414P
x
x L-x
L-x
12
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 13 of 50
Design of Wuhama River Bridge Checked by: Date:
Moment:
M ( x) Ln
1
* 9.3 * x *
L x * L 4.65( Lx x 2 )
2 L
x: 0 4.3m (0.2414P axle load outside span, i.e., not on bridge)
x L x x 2P 2 P
M ( x)Tr P P( L x 4.3) x (2L 4.3) x
L L L L
M LL IM g m 1.33M Tr M Ln
2P 2 P
M LL IM g m 1.33 x (2 L 4.3) x 4.65( Lx x 2 )
L L
2.66 P
M LL IM g m ( 4.65) x 2 (2.66 P 4.65L 4.3) x
L
Shear:
X: 0 L-8.6 (All the three axles on bridge)
V ( x)Tr P
L x P L x 4.3 0.2414P L x 8.6 P 2.2414 x (2.2414L 6.376)
L L L L
L x ( L x) 4.65
V ( x) Ln
1
* 9.3 *
( L x) 2
4.65 2
L 2 xL x 2
2 L L L
VLL IM
gV 1.33 * 2.2414 (2.2414L 6.376)
P 4.65 2
L 2 Lx x 2
L L
4.65 2 P P
VLL IM gV x (2.9811 9.3) x (2.9811P 8.48 4.65L)
L L L
13
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 14 of 50
Design of Wuhama River Bridge Checked by: Date:
P
M LL IM g m 1.33 * 2.2414 x 2 (2.2414 L 6.376) x 4.65( Lx x 2 )
L
P P
M LL IM g m (2.9811 4.65) x 2 (2.9811P 8.48 4.65L) x
L L
Moments
a) Exterior girder
x: 0 4.3m, wDLExt = 44.14, RADLExt = 339.18, FDiaph = 3.27kN,
gmext
0.682
w 2.66 P
M U 0.951.25( RADLExt x DLExt x 2 ) 1.75 * g mext ( 4.65) x 2 (2.66 P 4.65L 4.3) x
2 L
wDLExt 4.655P ext
(1.25 * g m 8.1375 g mext ) x 2
MU 2 L
(1.25R
ADLExt 4.655P * g m 8.1375 g m * L 7.525 g m ) x
ext ext ext
14
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 15 of 50
Design of Wuhama River Bridge Checked by: Date:
MU 60.21x2 915.46 x
x: 4.3 5.073m
wDLExt 2
1.25( RADLExt x 2 x )
M U 0.95
1.75 * g mext ( 2.9811P 4.65) x 2 (2.9811P 4.65L 4.3385 P ) x 1.3805P
L L
wDLExt 5.217 P ext
(1.25 * g m 8.1375 g mext ) x 2
MU 2 L
(1.25R ext
ext
ext
ext
ADLExt 5.217 P * g m 8.1375 g m * L 7.592 g m ) x 2.416 Pg m
b) Interior girder
x: 0 4.3m, wDLInt = 19.68, RADLExt = 156.31, FDiaph = 6.54kN,
g m 0.682
int
w 2.66 P
M U 0.951.25( RADLInt x DLInt x 2 ) 1.75 * g mint ( 4.65) x 2 (2.66 P 4.65L 4.3) x
2 L
wDLInt 4.655P int
(1.25 * g m 8.1375 g mint ) x 2
MU 2 L
(1.25R
ADLExt 4.655P * g m 8.1375 g m * L 7.525 g m ) x
int int int
MU 45.69 x2 698.30 x
15
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 16 of 50
Design of Wuhama River Bridge Checked by: Date:
x: 4.3 5.073m
wDLInt 2
1.25( RADLInt x 2 x )
M U 0.95
1.75 * g mint ( 2.9811P 4.65) x 2 (2.9811P 4.65L 4.3385 P ) x 1.3805P
L L
wDLInt 5.217 P int
(1.25 * g m 8.1375 g mint ) x 2
MU 2 L
(1.25R int
ADLInt 5.217 P * g m 8.1375 g m * L 7.592 g m ) x 2.416 Pg m
int int int
MU 49.16 x 2 751.06 x 226.97
x: 5.073m 10.14m
2.9811P
( 4.65) x 2
wDLInt 2 L
M U 0.951.25(( RADLInt FDiaph ) x x ) 1.75 * g mint
2 (2.9811P 4.65L 4.3385 P ) x 1.3805P
L
wDLInt 5.217 P int
(1.25 * g m 8.1375 g mint ) x 2
MU 2 L
(1.25( RADLInt _ FDiaph ) 5.217 P * g mint 8.1375 g mint * L 7.592 g mint ) x 2.416 Pg mint
MU 49.16 x 2 743.29 x 226.97
dM u
0, x = 7.56m, Mumax = 2582.63 kNm
dx
Shear Forces
a) Exterior girder
x: 0 5.073m, wDLExt = 44.14, RADLExt = 339.18, FDiaph = 3.27kN,
g v 0.52
ext
4.65 2 P P
VU 1.25( RADLExt wDLExt x) 1.75 * g vext x (2.9811 9.3) x (2.9811P 8.48 4.65L)
L L L
VU
(1.25R P ext
ADLExt 5.217 Pg v 14.84
ext
g v 8.1375Lgv )
ext
L
VU 0.264 x 2 83.86 x 767.31
16
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 17 of 50
Design of Wuhama River Bridge Checked by: Date:
x: 5.073 L- 8.6
4.65 2 P P
VU 1.25( RADLExt FDiaph wDLExt x) 1.75 * g vext x (2.9811 9.3) x (2.9811P 8.48 4.65L)
L L L
x: 0 5.07
w P P
M C 0.951.25( RADLExt x DLExt x 2 ) 1.75 * g mext (2.9811 4.65) x 2 (2.9811P 8.48 4.65L) x
2 L L
wDLExt 5.217 P ext
(1.25 2 L * g m 8.1375 g m ) x
ext 2
MC
(1.25R P ext
ADLExt 5.217 P * g m 14.84
ext
g m 8.1375 g m * L) x
ext
L
M C 63.68x 2 881.53x
x: 5.073 L – 8.6
w P P
M C 0.951.25( RADLExt x FDiaphx DLExt x 2 ) 1.75 * g mext (2.9811 4.65) x 2 (2.9811P 8.48 4.65L) x
2 L L
wDLExt 5.217 P ext
(1.25 2 L * g m 8.1375 g m ) x
ext 2
MC
(1.25( R P ext
ADLExt FDiaph ) 5.217 P * g m 14.84
ext
g m 8.1375 g m * L) x
ext
L
M C 63.68x 2 877.65x
b) Interior girder
x: 0 5.073m, wDLInt = 19.68, RADLExt = 156.31, FDiaph = 6.54kN,
g v 0.805
int
4.65 2 P P
VU 1.25( RADLInt wDLInt x) 1.75 * g vint x (2.9811 9.3) x (2.9811P 8.48 4.65L)
L L L
17
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 18 of 50
Design of Wuhama River Bridge Checked by: Date:
x: 5.073 L- 8.6
4.65 2 P P
VU 1.25( RADLExt FDiaph wDLExt x) 1.75 * g vext x (2.9811 9.3) x (2.9811P 8.48 4.65L)
L L L
x: 0 5.073
w P P
M C 0.951.25( RADLInt x DLInt x 2 ) 1.75 * g mint (2.9811 4.65) x 2 (2.9811P 8.48 4.65L) x
2 L L
wDLInt 5.217 P int
(1.25 2 L * g m 8.1375 g m ) x
int 2
MC
(1.25R P int
ADLInt 5.217 P * g m 14.84
int
g m 8.1375 g m * L) x
int
L
M C 49.16 x 2 664.38x
x: 5.073 L – 8.6
w P P
M C 0.951.25( RADLExt Inx FDiaphx DLInt x 2 ) 1.75 * g mint (2.9811 4.65) x 2 (2.9811P 8.48 4.65L) x
2 L L
wDLInt 5.217 P int
(1.25 2 L * g m 8.1375 g m ) x
int 2
MC
(1.25( R P int
ADLInt FDiaph ) 5 .217 P * g int
m 14 . 84 g m 8.1375 g int
m * L ) x
L
M C 49.16 x 2 656.61x
18
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 19 of 50
Design of Wuhama River Bridge Checked by: Date:
Exterior girder
MU 3423.85 *106
d 513.6mm 1100 146 954mm ok!
0.2244bfC' 0.2244 2410 * 24
Interior girder
MU 2582.63 *106
d 451.73 1100 106 994mm ok
0.2244bfC' 0.2244 * 2350 * 24
Reinforcement
Flexure
a) Exterior girder
Assuming two rows of 32 bars, d =954mm, Mumax = 3423.85 kNm
19
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 20 of 50
Design of Wuhama River Bridge Checked by: Date:
revise ,
2.352 * 3423.85 *10 6 24
1 1
0.9 * 2410 * 931.14 2 * 24 1.176 * 400
0.0048
Provide 1432 bars in four rows, 4 bars in each row and 2 bars in the fourth row
Asprov.= 11259.5 mm2
Cutting off the two bars in row 4, moment capacity of section with 1232 bars is
9650.97 * 400
As = 12(16)2 = 9650.97 mm2, c 92.38
0.7225 * 24 * 2410
M = Asfy(d - 0.425c),
M = (0.9)(9650.97)(400)(954 - 0.425 * 92.38) = 3178.13 kNm
Assuming x: 5.073 – 10.14m
3178.13 kNm = – 63.68x2 + 964.332x-226.97
x = 5.61m and 9.53m. Length of the two bars in row 4, l1 = 9.53 - 5.61 + 2ld
Development length
Basic tension development length, ldb [Art 5.11.2]
0.02 Ab f y
l db 0.06d b f y
f c'
Modification factor do not apply to this girder [Art 5.11.2.1.2and 3]
ldb = 1215.91mm
1800 hook anchorage is provided for bars that continue to the support as per AASHTO
Art. 5.11.2.4.
Provide ld = 1220mm
l1 = 9.53 - 5.61 + 2ld = 3.92 + 2*1.22 = 6.36m
Then two bars will be terminated from row 3, capacity of section with 10 32 bars
(8042.5mm2) assuming x: 4.3 – 5.073m: y =130mm, d=970, c=76.98,
M=2713.72kNm = -63.68x2 + 968.215x – 238.92, x=4.22 outside assumed range
20
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 21 of 50
Design of Wuhama River Bridge Checked by: Date:
Then the rest 2 bars in the third row will be terminated where they are no more
needed, capacity of section with 8 32 bars (6433.98mm2): y =106mm, d=994,
c=61.58, M=2241.7kNm=-60.21x2 + 915.46x, x=3.07 and (15.22 – 3.07) 12.15m
Then two bars will be terminated from row 2, capacity of section with 6 32 bars
(4825.5mm2) assuming x: 0 – 4.3m: y = 92.67mm, d= 1007.3mm, c=46.2,
M=1730.2kNm = -60.21x2 + 915.46x, x=2.21m (and 15.22-2.21=13.01m)
l4 = 13.01 - 2.21 + 2ld = 10.8 + 2*1.22 = 13.24m, two bars of 12m length lapped with
two bars of length 1.24 + 1.22 = 2.46m.
Then the rest 2 bars in the second row will be terminated where they are no more
needed, capacity of section with 4 32 bars (3217mm2): y =66mm, d=1034mm,
c=30.79, M=1182.34kNm = -60.21x2 + 915.46x, x=1.425 and (15.22 – 1.425)
13.795m
l4 = 13.795 - 1.425 + 2ld = 12.37 + 2*1.22 = 14.81m, two bars of 12m length lapped
with two bars of length 2.81 + 1.22 = 4.03m.
b) Interior girder
Assuming two rows of 32 bars, d =954mm,, Mumax = 2582.63 kNm
2.352 M u 6
1 1 fc ' 1 1 2.352 * 2582.63 *10
24
1.176 f
2 2
be d f c ' y 0.9 * 2350 * 994 * 24 1.176 * 400
0.0032
Cutting the top 2 bars, moment capacity of section with 832 bars (6433.98mm2)
21
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 22 of 50
Design of Wuhama River Bridge Checked by: Date:
Assume x:4.3 – 5.073 m, 2240.16 kNm = – 49.16x2 + 751.06x - 226.97 , x = 4.78 and
(15.22 – 4.78) 10.44m
Development length
The same as for exterior girders.
Then two bars will be terminated from row 2, capacity of section with 6 32 bars
(4825.5mm2) assuming x: 0 – 4.3m: y = 92.67mm, d= 1007.3mm, c=47.37,
M=1714.89kNm = -45.69x2 + 698.3x, x=3.07m (and 15.22-3.07=12.146m)
Then the rest 2 bars in the second row will be terminated where they are no more
needed, capacity of section with 4 32 bars (3217mm2): y =66mm, d=1034mm,
c=31.58, M=1181.95kNm = -45.69x2 + 698.3x, x=1.942 and (15.22 – 1.942) 13.278m
l3 = 13.278 - 1.942 + 2ld = 11.336 + 2*1.22 = 13.78m, two bars of 12m length lapped
with two bars of length 1.78 + 1.22 = 3.0m.
Finally, 4 32 bars in the first row will continue to the support, to which is provided
1800 hook anchorage.
Shear reinforcement
Nominal shear resistance Vn is the lesser of
Vn = Vc + Vs + Vp or
Vn = 0.25fc’bvdv + Vp
22
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 23 of 50
Design of Wuhama River Bridge Checked by: Date:
> 0.9de or 0.72D = 0.9*(1100-126.8) or 0.72*1100 = 875.88 for exterior girder and
the larger of 0.9*994 or 0.72*1100 = 894.6mm or 792mm = 894.6mm
S = spacing of shear reinforcement
Vu < 0.1fc’bvdv S 0.8dv 600mm
Vu > 0.1fc’ bvdv S 0.4dv 300mm
Vp = component of pre stressing force in the direction of shear (N)
Vu
Nominal shear stress in concrete u
bv d v
Shear causes tension in the longitudinal reinforcement that must be added to flexural
tension force.
M C Vu
As f y 0.5Vs cot [Art 5.8.3.5]
d v v
If this equation is not satisfied either the tensile reinforcement As must be increased or
the stirrups must be placed closer together to increase Vs. Vu is shear envelope for
strength I limit state which will be taken with MC.
a) Exterior girder
X: 0 – 5.073m
VU 0.264 x2 83.86 x 822.79
M C 63.68x2 881.53x
23
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 24 of 50
Design of Wuhama River Bridge Checked by: Date:
x: 5.073 L- 8.6
VU 0.264 x2 83.86 x 763.42
M C 63.68x2 877.65x
b) Interior girder
x: 0 5.073m
VU 0.41x2 72.05x 750.72
M C 49.16 x2 664.38x
x: 5.073 L- 8.6
VU 0.41x 72.05x 742.95
2
M C 49.16 x2 656.61x
a) Exterior Girder
Step 1
Determine Vu and MC at distance dv from the support
632 bars, As = 4825.5 mm2, bv = 450mm, be = 2410
As f y 4825.5 400
a 39.26 mm
0.85 f b'
c ee 0.85 24 2410
d = 1007.3 mm = de
a 39.26
d 2 1007.3 2 987.7 mm
d v max of 0.9d 0.9 1007.3 906.6 mm
0.72 D 0.72 1100 792mm
Step2
24
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 25 of 50
Design of Wuhama River Bridge Checked by: Date:
Vu 684.71 103
u 1.712
bv d v 0.9 450 987.7
1.712
'
0.071
f c 24
Step 3
Estimate an initial value of and calculate x
first trial = 35 0, cot = 1.428, Es = 200GPa
MC
0.5Vu cot
dv
x 0.001
2 Es As
0.5Vu cot 808.79 10 0.5 684.71 103 1.428
MC 6
d 987.7
x v 0.678 10 3
2 Es As 2 * 200 10 4825.5
3
Step 4
Use the calculated values of u/fc’ and x to determine from Table 5.8.3.4.2-1 of
AASHTO 2005 and compare with the value estimated in step 3. If different,
recalculate x and repeat step 4 until the estimated value of agrees with the value
from Fig 5.8.3.4.2-1 of AASHTO 98. When it does, take the corresponding value of
.
Vu 684.71
Vs Vc 430.13 330.66
0.9
25
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 26 of 50
Design of Wuhama River Bridge Checked by: Date:
b) Interior girder
Step 1
Determine Vu and MC at distance dv from the support, Vu = 680kN, MC =607.97kNm
632 bars, As = 4825.5 mm2, bv = 450mm, bi = 2350
As f y 4825.5 400
a 40.26 mm
'
0.85 f b
c ee 0.85 24 2350
d = 1007.3 mm = de
26
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 27 of 50
Design of Wuhama River Bridge Checked by: Date:
a 40.26
d 2 1007.3 2 987.2 mm
d v max of 0.9d 0.9 1007.3 906.6 mm
0.72 D 0.72 1100 792mm
Take dv = 987.2 mm
Step2
Calculate the shear stress ratio u/fc’
Vu 680.0 103
u 1.70
bv d v 0.9 450 987.2
u 1.70
'
0.071
f c 24
Step 3
Estimate an initial value of and calculate x first trial = 33.7 0, cot = 1.499,
Es = 200GPa
MC
0.5Vu cot
dv
x 0.001
2 Es As
0.5Vu cot 607.97 10 0.5 680 103 1.499
MC 6
d 987.2
x v 0.583 103
2 Es As 2 * 200 10 4825.5
3
Step 4
Use the calculated values of u/fc’ and x to determine from Table 5.8.3.4.2-1 of
AASHTO 2005 and compare with the value estimated in step 3. If different,
recalculate x and repeat step 4 until the estimated value of agrees with the value
from Fig 5.8.3.4.2-1 of AASHTO 98. When it does, take the corresponding value of
.
= 33.7 is okay.
= 2.38
Vu 680
Vs Vc 429.91 325.64
0.9
27
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 28 of 50
Design of Wuhama River Bridge Checked by: Date:
Interior Girder
Location Sreqiured [mm] Sprovided [mm]
dv = 0.988 m 33.7 2.38 283.8 280
0.1L = 1.522 m 36.4 2.28 343.4 340
0.2L = 3.044 m 36.4 2.28 343.4 340
28
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 29 of 50
Design of Wuhama River Bridge Checked by: Date:
M M DC M LL IM
a) Durabiilty
It is assumed that concrete materials and construction procedures provide adequate
concrete cover, nonreactive aggregates, thorough consolidation, adequate cement
content, low water/cement ratio and thorough curing. If these conditions are satisfied,
it is sufficient to provide minimum cover provision of AASHTO Table Art. 5.12.3-1,
which are provided in here.
b) Crack control
i) Positive bending moment reinforcement – exterior girder
x:5.073 - 10.146m
M = MDC + MLL+IM
wDLExt 2
(( RADLExt FDiaph ) x 2 x )
M
g mext ( 2.9811P 4.65) x 2 (2.9811P 4.65L 4.3385 P ) x 1.3805P
L L
wDLExt 2.9811P ext
( 2 L
g m 4.65 g mext ) x 2
M
(( R P ext
ADLExt FDiaph ) g m (2.9811P 4.65L 4.3385 L )) x 1.3805Pg m
ext
M 2236.98 *106
As 10981.7mm2 , 12 32 less than the area provided.
f s jd 240 * 0.875 * 970
( )√ = 24.77GPa, , take n = 8
29
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 30 of 50
Design of Wuhama River Bridge Checked by: Date:
2
nA 2nAs d
2
nA 8(11259.5) 8 *11259.5 2(8)(11259.5)(931.1)
x s s
be be be 2410 2410 2410
229.08 mm t s 246mm assumption okay
bx 3 2410 229.083
I cr nAs (d x) 2 8 11259.5(931.1 229.08) 2 5.405 1010 mm4
3 3
nM (d x) 8(2236.98 *106 )(702.02)
fs 232.44MPa
I cr 5.405 *1010
wDLExt 2
(( RADLExt FDiaph ) x 2 x )
M
g mext ( 2.9811P 4.65) x 2 (2.9811P 4.65L 4.3385 P ) x 1.3805P
L L
wDLExt 2.9811P ext
( 2 L
g m 4.65 g mext ) x 2
M
(( R P ext
ADLExt F ) g ext
( 2.9811P 4 .65 L 4.3385 )) x 1.3805 Pg m
Diaph m
L
M C 32.38x 2 464.65x 136.47
dM/dx = 0, x = 7.175 m, Mmax = 1530.45 kNm
2 2
nA nA 2nAs d 8(8042.5) 8(8042.5) 2(8)(8042.5)(970)
x s s 204.71 mm
b b b 2350 2350 2350
x flange thickness, assumption is ok
30
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 31 of 50
Design of Wuhama River Bridge Checked by: Date:
The actual steel stress must be compared to the allowable steel stress for crack control
bx 3 2350 204.713
I cr nAs (d x) 2 I cr 8 8042.48(970 204.71) 2 4.44 1010 mm4
3 3
nM (d x) 8(1530.45 *10 )(765.29)
6
fs 211.03MPa
I cr 4.44 *1010
31