You are on page 1of 31

Project:

Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 1 of 50
Design of Wuhama River Bridge Checked by: Date:

Design of Wuhama River Bridge


Materials:
1. Concrete: C30, f c'  24 MPa
2. Steel: fy = 400 MPa

Design Method: Load and Resistance Factor Design (LRFD) method according to
American Association of State Highway and Transportation Officials
(AASHTO) Code, SI Units, 3rd Edition, 2005 Interim Revisions.

1. SUPERSTRUCTURE
The superstructure consists of two 15.22m center to center span T-girders and one
33.51m center to center span box girder central span as shown in Fig.1.

Fig.1. Longitudinal section of Wuhama river bridge

T – Girders Design
1.1 Preliminary Design Dimensions
Depth of girders [Table Art. 2.5.2.6.3.1-1]
For simple span T- girders, D = 0.07L where L is span length = 15.22m
Dmin = 0.07 * 15.22 = 1.065m
Take D = 1.10m
Spacing between longitudinal girders, S:- varies from1.8 - 3.6m
C is 0.25S to 0.75S, 2C + 3S= 9.52, C = 0.5S , S + 3S = 9.52m, S = 2.38m
and C = 1.19m
Take S = 2.35m and C = 1.235m
Web width
Minimum thickness = 200mm without pre-stressing duct [Art 5.1.4.1.3.1c and C
5.1.4.1.3.1c]
But the width of the web has to satisfy the clear spacing between bars. The clear spacing
between bars in a row should not be less than 1.5 or the maximum aggregate size.
Minimum concrete cover = 50mm
Taking 32 bars and considering splice, 432 bars in a row
require a beam width of
bw > 3*1.5+ 6*+ cover > 3 * 48 + 192 + 2 * 50> 436mm
Take bw= 450mm

1
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 2 of 50
Design of Wuhama River Bridge Checked by: Date:

Slab thickness
( S  3000) (2350  3000)
tS    178.3mm [Table Art. 2.5.2.6.3-1]
30 30
Take ts = 200mm for structural thickness of the slab, 292mm at the middle to provide a
2.5% side slope(camber) for drainage.
Diaphragms
For T - Girder bridges, diaphragms should be provided at the ends and at one or more
points at spans. The purpose is to help in load distribution between the girders. Further,
finite element analysis shows that there is stress concentration at the supports due to the
big support reactions. Diaphragms reduce the stress concentration. Use 0.3m thick, 1.1m
deep diaphragms at the ends (at each support) and 0.3m by 750mm deep diaphragms at
third points of spans.
Posts and railings
Use continuous concrete barrier wall of height 850mm and thickness varying from
300mm to 200mm as shown in the cross section of the bridge in Fig.2. Pipe posts and
railings will be provided at the top.
Fig.2 shows plan of the bridge and section of the T-girder.

Fig.2. Plan of Wuhama river bridge and section of the T-girder


1.2 Design of Bridge Slab
1.2.1 Deck slab
Loads
a) Dead loads
 75mm future asphalt wearing surface = 0.075* 22.07 kN/m3 = 1.66 kN/m2
 RC slab = (0.2m + 0.292)/2* 22.76 kN/ = 5.6 kN/m2
 Overhang slab ( (0.25+0.35)/2 * 22.76 kN/m3 = 6.83 k N/m2
 Curb (250mm above slab) = 0.25 * 22.76 kN/m3 = 5.69 kN/m2
 Posts and railings = [(0.3*0.3 + 0.25*0.55)22.76 + 0.084 + 0.0096) = 5.27kN/m

2
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 3 of 50
Design of Wuhama River Bridge Checked by: Date:

Dead load moments (slab, curb and railing dead load moments)
An approximate analysis of strips perpendicular to girder will be considered [Art 9.6.1]
The extreme positive moment in any deck panel between girders shall be taken to apply to all
positive moment regions. Similarly, the extreme negative moment over any girder shall be
taken to apply to all negative moment regions [Art 4.6.2.1.1]
The strips shall be treated as continuous with span length equal to C/C distance of the girders.
1m strip width will be taken MEnd = 5.27*1.1 + 12.52* 1.2352 = 15.35kNm/m
2
Member end moments by cross method of moment distribution :
Half the structure will be used for the distribution due to symmetry as shown

K 0.75 0.5
DF 1 0.6 0.4
FEM -15.35 0 -5.01 3.34
15.35 7.675
-3.60 -2.40
f.m -15.35 15.35 -0.94 0.94

Reactions and moments at sections of maximum positive and negative live load moments

Reactions:
RA1= 5.27 + 12.52x1.235 = 20.73; RA2= (15.35+ 7.26x2.352x0.5 - 0.94)/2.35 = 14.66
RB1= 7.26x2.35-14.66 = 2.40; RB2=0.5x7.26x2.35 = 8.53kN
M0.4S = M0.94 = 14.66x0.94 - 15.35 – 7.26x0.942/2 = -4.78kNm
MFace. = M0.225 = 0.94 - 7.26x0.2252/2 – 2.40x0.225 = 0.22kNm

b) Live loads
i) Overhang live load moments
The critical placement of a single wheel load is 300mm from the face of the curb for
design of overhang slabs.

The equivalent width of a transverse strip is 1140 + 0.833x, where x is distance from the
wheel load to centerline of support. In our case it doesn’t produce negative moment.
Overhang negative moment due to horizontal vehicular collision force on railings will be used
to design the overhang slab (done towards the end of deck slab design).

ii) Maximum positive live load moment


For repeating equal spans, the maximum positive bending moment occurs near the 0.4

5.19kN 3
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 4 of 50
Design of Wuhama River Bridge Checked by: Date:

points of the exterior spans.


72.5kN 72.5kN
0.4*2.35 = 0.94 1.8m

A 1.41m B 0.39 C
K 0.75 1 0.75
DF 1 0.429 0.571 0.571 0.429 1
FEM 0 - 28.623 19.67 -3.91 0 0
3.841 5.11 2.56
0.385 0.77 0.58
-0.165 -0.22 -0.11
0.06 0.047
f.m 0 -24.945 24.945 -0.63 0.63 0

72.5kN 72.5kN

32.89 110.96 0.88 0.27

Mmaxp = 32.89*0.94 = 30.92kNm


E = 660+0.55S = 660 + 0.55 * 2350 = 1952.5mm [Table Art. 4.6.2.1.3-1]
Mmaxp = 1.2 * (30.92/1.9525) = 19.00 kNm/m
RB = 1.2 * (110.96)/ 1.9525 = 68.2 kN/m

iii) Maximum interior negative live load moment


The critical placement of live load for maximum negative moment is at the first interior
deck support with one lane loaded (m = 1.2).

The width of the equivalent transverse strip is, E = 1220 + 0.25s = 1220+0.25(2350) =
1807.5mm
72.5kN 0.9 0.9m 72.5kN

K 0.75 1 0.75
DF 1 0.429 0.571 0.571 0.429 1
FEM 0 - 32.55 24.84 -15.42 0 0
3.31 4.40 2.20
3.77 7.55 5.67
-1.62 -2.16 -1.08
0.31 0.62 0.46
- 0.133 -0.177 -0.089
0.05 0.038
f.m 0 -30.99 30.99 -6.17 6.17

72.5 kN 0.9 0.9 m 72.5 kN

14.58 113.22 kN 19.83 kN 2.63

Mmaxn = 1.2 * (30.99/1.8075) = -20.57 kNm/m [Art 4.6.2.1.1]


MFace = 30.99-55.3x0.225 = 18.55kNm/m
MFace = 1.2 * (18.55/1.8075) = -12.32 kNm/m
RB = 1.2 (113.22)/1.8075 = 75.17 kN/m

4
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 5 of 50
Design of Wuhama River Bridge Checked by: Date:

iv) Maximum live load reaction on exterior girder


The exterior wheel is placed 300mm from curb. E = 660 + 0.55*2350 = 1952.25

72.5 kN 72.5 kN
0.165m 1.8m 0.385

73.07 kN
K 0.75 1 0.75
DF 1 0.429 0.571 0.571 0.429 1
FEM 0 - 27.38 0 0 0 0
0 11.745 15.634 7.817
-2.23 -4.46 -3.35
0.96 1.274 0.64
-0.183 -0.365 -0.27
0.078 0.104 0.052
-0.03 -0.022
f.m 0 -14.60 14.60 3.64 -3.64 0

RA = 1.2 * 73.07/1.9525 = 44.91 kN/m

Gravity load combination


iQi = [pDC + pDW + 1.75(LL + IM)]
 = D * R * I >0.95
D = 0.95 ductility factor [Art 1.3.4]
R = 0.95 continuity factor for continuous span [Art 1.3.5]
I = 1.05 importance factor for operationally important bridges
 = D * R * I >0.95
 = 0.95 * 0.95 * 1.05 = 0.95

Action DC LL
RA 35.39 44.91
MA -15.35 0
RB 10.93 75.17
MB -0.22 -12. 32
MMaxp -4.78 19

Reactions and maximum moments for strength I limit state


RA = 0.95 [1.25(RA-DC) + 1.5(RA-DW) + 1.75 * 1.33 (RA-LL)
RA = 0.95[1.25(35.39) + 1.5(0) + 1.75 * 1.33 (44.91)] = 141.33 kN/m
MA = 0.95 [1.25(-15.35) + 1.5(0) + 1.75 (1.33)(0)] = -18.23 kNm/m
Mmaxp = 0.95 [1.25(-4.78) + 1.5 (0) + 1.75 * 1.33 * 19)] = 36.34 kNm/m
MB = 0.95 [1.25(-0.94) + 1.5 (0) + 1.75 * 1.33 (-12. 32)] = -28.36 kNm/m> MA

Strength I limit State


Reinforcement
fc’ = 24 MPa , fy = 400 MPa

Using 14 bars


dneg = 267.7 - 60 - 14/2 = 200.7mm for negative reinforcement.
dpos = 225 - 25 - 14/2 = 193 for positive reinforcement

5
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 6 of 50
Design of Wuhama River Bridge Checked by: Date:

Positive moment reinforcement


Maximum reinforcement is limited by ductility requirement, which is given by
C < 0.42d, a =1C, a<0.421d, 1 = 0.85, a < 0.357d
Mu = 0.85fc'ab (d-a/2) =0.2244 fc'bd2,  = 0.9

Mu 35.98 * 106
d   81.73 mm  193 mm 0k
0.2244 f c ' b 0.2244* 1000* 24
    
  1  1  2.352 * 36.34 *10  
' 6
2.352 M u  fc 24
  1  1  
'   
bd f c  1.176 f y  
2  
0.9 *1000 *193 * 24  1.176 * 400 
2

0.03 f c'
 0.00279   min   0.0021,   0.00279
fy

AS= bd = 0.00279*1000*193 = 537.7mm2

 (7)2  1000  (7) 2  1000 2


S   286 mm , Provide 14C/C200mm, Asprovided = 769.7 mm
As 537.7

Negative moment reinforcement


Mu = 28.36 kNm/m

 2.352M u   fc '   2.352* 28.36 *106  


  1  1     1  1  24

  bd 2
f '  1.176 f y   0.9 *1000* 200.7 * 24 
2
 1.176* 400 
 c    
  0.002   min  0.0021

As = bd = 0.0021 * 1000 * 200.7 = 421.47 mm2

, Provide 14 C/C 200mm, As provided = 769.7 mm2

Distribution reinforcement
Secondary reinforcement is placed at the bottom of the slab in the longitudinal direction to
distribute wheel loads on the bridge to the primary reinforcement in the transverse direction.
The required area as a percentage of the primary reinforcement is:

3840
%  67%   Se = 2350 - 450 = 1900 - clear span between girders
Se
3840
%  88.1  67%, take 67%
1900
As = 0.67 * 769.7 = 515.7 mm2
 (6) 2  1000 113.1  1000
Using 12, S    219.3mm ,
As 515.7
Provide 12 C/C 200 mm

6
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 7 of 50
Design of Wuhama River Bridge Checked by: Date:

Shrinkage and temperature reinforcement


The minimum amount of reinforcement in each direction will be
Ag 246  1000
AS  0.75  0.75   461.25mm2
fy 400

For members greater than 150mm in thickness the shrinkage and temperature reinforcement is
to be distributed equally on both faces. But the primary and secondary reinforcements
provided are more than this amount. This reinforcement will be provided on top face in the
longitudinal direction only.
AS 461.25
  230.63mm2
2 2
 (6) 2  1000 113.1  1000
Using 12, S    490.4mm  450mm or 3  180mm
As 230.63

Provide 12 C/C 400mm at top in the longitudinal direction to place every other bar with the
bottom distribution reinforcement, ASprov. = 282.7mm2

Service I limit state


a) Control of cracking
Cracking is controlled by limiting the spacing in the reinforcement under service
loads

123000 e dc
S  2d c , s 1 [Art. 5.7.3.4]
s fs 0.7(h  d c )
Where dc = depth of concrete measured from extreme tension fiber to center of bar
or wire located closest there to (mm). For calculation purpose, the actual
thickness of clear concrete cover shall be used.
γe = exposure factor, 1 for class 1 exposure and 0.75 for class 2. Class 1
exposure applies when cracks can be tolerated due to reduced concerns
for appearance/corrosion. Class 2 is used when there is an increased
concern for appearance/corrosion.
h = overall depth or thickness of component (mm).
βS is a geometric relationship between crack width at the tension concrete
face and crack width at the level of reinforcement

Es = 200Gpa
Ec  0.043K1 c f c '  0.043 (2400)1.5 24  24.77GPa
1.5

K1 - is correction factor for source of aggregate to be taken as 1 unless


determined by physical test
ES 200
n   8.07 take n = 8
EC 24.77

7
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 8 of 50
Design of Wuhama River Bridge Checked by: Date:

Load combination for service I limit state is


D = R = I= 1.0 =1.0

M  M DC  M LL IM

Check positive moment reinforcement

Mmaxp = -4.78 + 1.33 * 19 = 20.49 kNm/m


Assuming the N.A is above the top reinforcement, i.e.,
top reinforcement also in tension zone

bx2 *0.5= nA’S (d’ - x) + n AS (d-x)


1000x2 *0.5 = 8 * 769.7 (67 - x) + 8 * 769.7 (193 - x)
x2 + 24.63x –3201.95 = 0
x = 45.6mm < 67 Ok!

1000 45.6 3
I cr   8  769.7(67  45.6) 2  8  769.7(193  45.6) 2  168.21 106 mm4
3
nMy 8  20.49  106  (193  45.6)
fS    143.64MPa
Ic r 168.21  106

The contribution of the upper steel is very small and hence can be neglected.

32
S 1  1.237
0.7(225  32)

123000 x0.75
S  200   2 x32  455.2 Ok!
1.237 x143.64

Check negative moment reinforcement


M = (0.22 + 1.33x12.32) = 16.61 kNm
0.5bx2 + (n-1) As’ (x - d’) = nAs(d-x)
500x2 + 7 * 769.7 (x-32) =8 * 769.7 (200.7- x)
x2 + 23.09x – 2816.49 = 0
x=42.77mm > 32mm Ok.
1000 42.77 3
I cr   7 * 769.7(42.77  32) 2  8 * 769.7(200.7  42.77) 2  180.29 *106 mm4
3
nMy 8  16.61  106  (200.7  42.77)
fS    116.40 MPa
Icr 180.29  106
67
S 1  1.477
0.7(267.7  67)

123000 * 0.75
S  200   2 * 67  402.6mm Ok!
1.477 *116.4

8
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 9 of 50
Design of Wuhama River Bridge Checked by: Date:

Fatigue limit state


Fatigue need not be investigated in multi girder applications. [Art. 9.5.3]

1.2.2 Design of deck overhang and barrier wall


Two limit states must be investigated: Strength I and Extreme Event II. The strength
limit state considers vertical gravity loads and it seldom governs unless the cantilever
span is large. The extreme event limit state considers forces in the following table for
test level 4, which is the case for bridges on highways conveying heavy vehicles
mixed with automobiles with maximum velocity of 100km/hr.

Design forces for a TL-4 barrier


Direction Force (kN) Length (m)
Transverse (Ft) 240 1.07
Longitudinal (Fl) 80 1.07
Vertical (Fv) 80 5.5

Ft = Rw
Where
Rw is the resistance or capacity of barrier
2  M L2 
Rw   8M b  8M w  c c 
2lc  Lt  H 

 L  8H M b  M w H 
2
L
Lc  t   t  
2 2 Mc
Mb is moment strength of beam at top of wall,
Mb=0 in our case
Mw is moment strength of wall about vertical axis
Mc is moment strength of wall about horizontal axis
H is height of wall, H=1100mm in this case.
Lt longitudinal distribution length of impact force
Lc critical wall length of yield line pattern
Try 12 C/C 200 mm for barrier wall reinforcement vertically so that it will be tied to
deck slab reinforcement. Try 12 C/C 200mm reinforcement horizontally also.
 a As f y 565.5  400
M c  As f y  d  , a   11.09mm
 2 0.85 f c b 0.85  24  1000
'

11.09
M c  1.0  565.5 * 400 * (269  )  59.6kNm / m ,
2
11.09
M w1  1.0  565.5 * 400 * (257  )  56.9kNm / m
2
11.09
M w2  1.0  565.5 * 400 * (157  )  34.26kNm / m
2
(56.9  34.26)
M wavg   45.58kNm / m
2

9
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 10 of 50
Design of Wuhama River Bridge Checked by: Date:

 Lt  8H M b  M wavg H  1070  1070  8 *11000  45580


2 2
Lt
Lc            3183.8mm
2 2 Mc 2  2  59.6
2  M L2  2  59.6 * 3183.82 
Rw   8M b  8M wavg  c c    0  8 * 45580  
2 Lc  Lt  H  2 * 3183.8  1070  1100 

Rw  345.0kN  240kN Ok.

Overhang slab moment and reinforcement – the overhang moment will not be
bigger than that which requires 14mm bars which continue from the interior support.

1.3. Design of Girders


Summary of DL slab reactions transferred to girders
DC: rA = 20.73 + 14.66 = 35.39 kN/m rB = 2.40 + 8.53 = 10.93 kN/m
Dead load effect due to dead load of web and diaphragm
-3
D = 1.1m, w = 0.45 * (1.1-0.246) * 2320 * 9.81 * 10 = 8.75 kN/m

Diaphragm load on girders (acting at span third points)


exterior girder = (0.75-0.246) * 0.30 * (2.35-0.45)*0.5* 22.76 = 3.27 kN = FDiaphExt
interior girder = 3.27*2 = 6.54 kN = FDiaphInt

DL moment and shear functions:


exterior girders: wDCExt = 35.39 +8.75 = 44.14
x: 0 – 5.073m: V(x) = 339.18 – 44.14x = RADLExt - wDLExtx
2
M(x) = 339.18 x – 22.07x = RADLExtx - wDLExt*x2/2
x: 5.073 – 10.146m: V(x) =335.91 – 44.14x = RADLExt- FDiaphragExt - wDLExtx
2
M(x) = 335.91 x – 22.07x = (RADLExt- FDiaphragExt )x - wDLExt*x2/2
interior girders: wDCInt = 10.93 +8.75 = 19.68
x: 0 – 5.073m: V(x) = 156.31 – 19.68x = RADLInt - wDLIntx
2
M(x) = 156.31x – 9.84x = RADLIntx - wDLInt*x2/2
x:5.07–10.146m:V(x) = 149.77 – 19.68x = RADLInt- FDiaphragInt - wDLIntx
2
M(x) = 149.77 x – 9.84x = (RADLInt- FDiaphragInt )x - wDLInt*x2/2

Select resistance factors, 


i) Strength limit state
Flexural and tension = 0.9
Shear and torsion = 0.9
ii) Non-strength = 1.0

10
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 11 of 50
Design of Wuhama River Bridge Checked by: Date:

Select load modifiers


Strength I Service I Fatigue AASHTO 2005 Art. No
Ductility, D 0.95 1.0 1.0 Art 1.3.3
Redundancy, R 0.95 1.0 1.0 Art 1.3.4
Importance, I 1.05 N/A N/A Art 1.3.5
 = D * R *I 0.95 1.0 1.0

Select applicable load combinations


Strength I U =0.95[1.25 DC + 1.5DW + 1.75 (LL + IM) + 1.0 (WA + FR)
Service I U = 1.0[DC + DW + 1.0(LL + IM) + 1.0 WA + 0.3 (WS + WL)
Fatigue U = 0.75(LL + IM)

Live load force effects


Number of lanes = 2. m = 1.2 for one lane loaded, m = 1.0 for two lanes loaded.
IM = 15% for fatigue and IM = 33% for all other limit states

Distribution factors for moments [Art 4.6.2.2.2]


This is applicable if all have constant deck width, at least four parallel beams and if
overhang is part of roadway.
 Cross section type is e in Table Art 4.6.2.2.2b-1, Nb = 4, ts = 246mm,
S=2350mm

Interior giders with concrete decks [Table art 4.6.2.2b and b-1]
Girder distribution factor with multiple presence factor included, g is taken the
smaller of the one obtained from empirical formulae for Nb = 4 or that obtained from
the lever rule.
One lane loaded
gSIM = 0.06 + (S/4300)0.4 * (S/L) 0.3 (kg/Lts3)0.1
gSIM = 0.06 + (2350/4300) 0.4 * (2350/15220) 0.3 = 0.508
SI = single lane loaded, interior; M = moment

Two or more lanes loaded


gMIM = 0.075 + (S/2900)0.6 * (S/L)0.2 (kg/Lts3)0.1
gMIM = 0.075 + (2350/2900)0.6 * (2350/15220)0.2 = 0.682
where (kg/Lts3) = 1.0 for preliminary design, MI = multiple lanes loaded, interior; M
= moment

Exterior girders [Table art 4.6.2.2.2d and d-1]


One lane loaded - lever rule with m = 1.2

res = 1.2*0.5P (85 + 1885)/2350 = 0.503P res exterior girder reaction for single
lane loading
Two or more lanes loaded
gMEM = e * gMI ,
where e = 0.77 + de/2800 = 0.77 + 135/2800 = 0.818
e = 0.818 < 1.0 use e = 1.0 gMEM = 0.682

11
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 12 of 50
Design of Wuhama River Bridge Checked by: Date:

Distributed live load moments


ILS for truck and tandem IL for Tandem

145kN
110kN
145kN 35kN 110kN

3.77 3.223 3.8


1.826
1.414

8.338 6.882 7.91 7.31

M(LL + IM) = g [ (MTr or MTan) (1+IM) + MLn]


MTr = 145(1.826 + 3.77) + 35(1.414) = 860.88 kNm ------ governs
MTan = 110 (3.223 + 3.8) = 772.50 kNm

Distribution factor for shear [Art 4.6.2.2.3]


Interior girder
One lane loaded: mg SI v = 0.36 +S/7600 = 0.669
Two lanes loaded: mg MI v = 0.2 + S/3600 - (S/10700)2 = 0.805

Exterior girder
One lane loaded---lever rule with m = 1.2
g SEv = 1.2*0.5P*(85 + 1885)/2350 = 0.503P

Two or more lanes loaded


gMEv = e* gMIv = (0.6 + 135/3000)*0.805 = 0.52 – this governs
Distributed live load shears
VLL + IM = g [1.33(VTr or VTa) + VLn]
IL for truck IL for tandem
145 110 110
35
0.921
0.717
0.435 1
1

VTr = 145(1 + 0.717) + 35 * 0.435= 264.19 kN, governs


VTan = 110 (1 + 0.921) = 211.31 kN

It is necessary to construct factored moment and shear envelope equations for both Service I
and Strength I limit states. Truck governs for both shear and moment.

P
0.2414P P P P
0.2414P

x
x L-x
L-x

12
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 13 of 50
Design of Wuhama River Bridge Checked by: Date:

Moment:
M ( x) Ln 
1
* 9.3 * x *
L  x  * L  4.65( Lx  x 2 )
2 L
x: 0 4.3m (0.2414P axle load outside span, i.e., not on bridge)
x L  x  x 2P 2 P
M ( x)Tr  P  P( L  x  4.3)   x  (2L  4.3) x
L L L L
M LL  IM  g m 1.33M Tr  M Ln 
  2P 2 P  
M LL  IM  g m 1.33 x  (2 L  4.3) x   4.65( Lx  x 2 )
  L L  
 2.66 P 
M LL IM  g m  (  4.65) x 2  (2.66 P  4.65L  4.3) x
 L 

x: 4.3 L-4.3 ( All the three axle loads on bridge)


M ( x)Tr  0.2414 P
x  4.3L  x   P xL  x   P ( L  x  4.3) x
L L L
P 2 P
M ( x)Tr  2.2414 x  (2.2414 L  3.262) x  1.038P
L L
M LL IM  g m 1.33M Tr  M Ln 
  P P  
M LL IM  g m 1.33 2.2414 x 2  (2.2414 L  3.262) x  1.038P   4.65( Lx  x 2 )
  L L  
 2.9811P P 
M LL IM  g m  (  4.65) x 2  (2.9811P  4.65L  4.3385 ) x  1.3805P 
 L L 

Shear:
X: 0 L-8.6 (All the three axles on bridge)
V ( x)Tr  P
L  x   P L  x  4.3  0.2414P L  x  8.6  P  2.2414 x  (2.2414L  6.376)
L L L L

 L  x ( L  x)  4.65
V ( x) Ln 
1
* 9.3 *    
( L  x) 2  
4.65 2

L  2 xL  x 2 
2  L  L L

VLL  IM

 gV 1.33 *  2.2414  (2.2414L  6.376) 
P 4.65 2
 
L  2 Lx  x 2  
 L L 
 4.65 2 P P 
VLL  IM  gV  x  (2.9811  9.3) x  (2.9811P  8.48  4.65L)
 L L L 

Corresponding moment is (x: 0 L - 8.6m)


x L  x  L  x  4.3x  0.2414P( L  x  8.6) x  P  2.2414 x2  (2.2414L  6.376) x
M ( x)Tr  P
L
P
L L L
 
M ( x) Ln 
1
* 9.3 * x *
L  x  * L  4.65( Lx  x 2 )
2 L

13
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 14 of 50
Design of Wuhama River Bridge Checked by: Date:

 P
  
M LL  IM  g m 1.33 *  2.2414 x 2  (2.2414 L  6.376) x  4.65( Lx  x 2 )
 L 
 P P 
M LL IM  g m  (2.9811  4.65) x 2  (2.9811P  8.48  4.65L) x
 L L 

X: L-8.6 L – 4.3 (0.2414P axle load outside bridge)


V ( x)Tr  P
L  x   P L  x  4.3  P 2L  2 x  4.3
L L L
 L  x ( L  x)  4.65
1
V ( x) Ln  * 9.3 *    
( L  x) 2  
4.65 2

L  2 xL  x 2 
2  L  L L

VLL  IM  gV 1.33 * 2 L  2 x  4.3 
P 4.65 2
 
L  2 Lx  x 2  
 L L 
 4.65 2 P P 
VLL  IM  gV  x  (9.3  2.66 ) x  5.719  2.66 P  4.65L
 L L L 
Corresponding moment is (x: L – 8.6 L - 4.3m)
x L  x  L  x  4.3x  P  2 x 2  (2L  4.3) x
M ( x)Tr  P
L
P
L L
 
M ( x) Ln 
1
* 9.3 * x *
L  x  * L  4.65( Lx  x 2 )
2 L
 P
  
M LL  IM  g m 1.33 *  2 x 2  (2 L  4.3) x  4.65( Lx  x 2 )
 L 
 P P 
M LL  IM  g m  (2.66  4.65) x 2  (2.66P  5.719  4.65L) x
 L L 

Strength I limit state

Envelope equations for strength I limit state

U = [1.25DC + 1.5DW + 1.75(LL + IM)

Moments

a) Exterior girder
x: 0 4.3m, wDLExt = 44.14, RADLExt = 339.18, FDiaph = 3.27kN,
gmext
 0.682
 w  2.66 P 
M U  0.951.25( RADLExt x  DLExt x 2 )  1.75 * g mext  (  4.65) x 2  (2.66 P  4.65L  4.3) x
 2  L 
 wDLExt 4.655P ext 
 (1.25  * g m  8.1375 g mext ) x 2  
MU    2 L 
(1.25R 
ADLExt  4.655P * g m  8.1375 g m * L  7.525 g m ) x 
ext ext ext

14
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 15 of 50
Design of Wuhama River Bridge Checked by: Date:

MU  60.21x2  915.46 x
x: 4.3 5.073m
 wDLExt 2 
1.25( RADLExt x  2 x )  
M U  0.95 
1.75 * g mext  ( 2.9811P  4.65) x 2  (2.9811P  4.65L  4.3385 P ) x  1.3805P 
  L L 
 wDLExt 5.217 P ext 
 (1.25  * g m  8.1375 g mext ) x 2  
MU    2 L 
(1.25R  ext
 ext
 ext
 ext 
 ADLExt 5.217 P * g m 8.1375 g m * L 7.592 g m ) x 2.416 Pg m 

MU  63.68x2  968.215x  238.92


x: 5.073m 10.14m
 wDLExt 2 
1.25(( RADLExt  FDiaph ) x  2 x )  
M U  0.95 
1.75 * g mext  ( 2.9811P  4.65) x 2  (2.9811P  4.65L  4.3385 P ) x  1.3805P 
  L L 
 wDLExt 5.217 P ext 
 (1.25  * g m  8.1375 g mext ) x 2  
MU    2 L 
(1.25( RADLExt  FDiaph )  5.217 P * g mext  8.1375 g mext * L  7.592 g mext ) x  2.416 Pg mext 
 
MU  63.68x2  964.332 x  226.97
dM u
0, x = 7.572m, Mumax = 3423.85 kNm
dx

b) Interior girder
x: 0 4.3m, wDLInt = 19.68, RADLExt = 156.31, FDiaph = 6.54kN,
g m  0.682
int

 w  2.66 P 
M U  0.951.25( RADLInt x  DLInt x 2 )  1.75 * g mint  (  4.65) x 2  (2.66 P  4.65L  4.3) x
 2  L 
 wDLInt 4.655P int 
 (1.25  * g m  8.1375 g mint ) x 2  
MU    2 L 
(1.25R 
ADLExt  4.655P * g m  8.1375 g m * L  7.525 g m ) x 
int int int

MU  45.69 x2  698.30 x

15
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 16 of 50
Design of Wuhama River Bridge Checked by: Date:

x: 4.3 5.073m

 wDLInt 2 
1.25( RADLInt x  2 x )  
M U  0.95 
1.75 * g mint  ( 2.9811P  4.65) x 2  (2.9811P  4.65L  4.3385 P ) x  1.3805P 
  L L 
 wDLInt 5.217 P int 
 (1.25  * g m  8.1375 g mint ) x 2  
MU    2 L 
(1.25R int 
ADLInt  5.217 P * g m  8.1375 g m * L  7.592 g m ) x  2.416 Pg m 
int int int

MU  49.16 x 2  751.06 x  226.97

x: 5.073m 10.14m
  2.9811P 
  (  4.65) x 2  
wDLInt 2  L
M U  0.951.25(( RADLInt  FDiaph ) x  x )  1.75 * g mint  
 2 (2.9811P  4.65L  4.3385 P ) x  1.3805P 
  L 
 wDLInt 5.217 P int 
 (1.25  * g m  8.1375 g mint ) x 2  
MU    2 L 
(1.25( RADLInt _ FDiaph )  5.217 P * g mint  8.1375 g mint * L  7.592 g mint ) x  2.416 Pg mint 
 
MU  49.16 x 2  743.29 x  226.97
dM u
0, x = 7.56m, Mumax = 2582.63 kNm
dx

Shear Forces
a) Exterior girder
x: 0 5.073m, wDLExt = 44.14, RADLExt = 339.18, FDiaph = 3.27kN,
g v  0.52
ext

 4.65 2 P P 
VU   1.25( RADLExt  wDLExt x)  1.75 * g vext x  (2.9811  9.3) x  (2.9811P  8.48  4.65L) 
 L L L 

 8.1375 ext 2 P ext 


 L g v x  (1.25wDLExt  5.217 L g v  13.95 g v ) x  
ext

VU    
(1.25R P ext
 ADLExt  5.217 Pg v  14.84
ext
g v  8.1375Lgv ) 
ext

L 
VU  0.264 x 2  83.86 x  767.31

16
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 17 of 50
Design of Wuhama River Bridge Checked by: Date:

x: 5.073 L- 8.6
 4.65 2 P P 
VU   1.25( RADLExt  FDiaph  wDLExt x)  1.75 * g vext x  (2.9811  9.3) x  (2.9811P  8.48  4.65L) 
 L L L 

 8.1375 ext 2 P ext 


g x  (1.25 w  5.217 g v  13.95 g vext ) x 
 L v DLExt
L 
VU    
(1.25( R P ext ext 
 ADLExt  F Diaph )  5 .217 Pg ext
v  14 .84 g v  8 .1375 Lg v ) 
L
VU  0.264 x 2  83.86 x  763.42

The corresponding moments are:

x: 0 5.07
 w P P 
M C  0.951.25( RADLExt x  DLExt x 2 )  1.75 * g mext  (2.9811  4.65) x 2  (2.9811P  8.48  4.65L) x 
 2 L L 
 wDLExt 5.217 P ext 
 (1.25 2  L * g m  8.1375 g m ) x 
ext 2

MC  
(1.25R P ext
 ADLExt  5.217 P * g m  14.84
ext
g m  8.1375 g m * L) x
ext

L 
M C  63.68x 2  881.53x
x: 5.073 L – 8.6
 w P P 
M C  0.951.25( RADLExt x  FDiaphx  DLExt x 2 )  1.75 * g mext  (2.9811  4.65) x 2  (2.9811P  8.48  4.65L) x 
 2 L L 
 wDLExt 5.217 P ext 
 (1.25 2  L * g m  8.1375 g m ) x 
ext 2

MC  
(1.25( R P ext
 ADLExt  FDiaph )  5.217 P * g m  14.84
ext
g m  8.1375 g m * L) x
ext

L 
M C  63.68x 2  877.65x

b) Interior girder
x: 0 5.073m, wDLInt = 19.68, RADLExt = 156.31, FDiaph = 6.54kN,
g v  0.805
int

 4.65 2 P P 
VU   1.25( RADLInt  wDLInt x)  1.75 * g vint x  (2.9811  9.3) x  (2.9811P  8.48  4.65L) 
 L L L 

17
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 18 of 50
Design of Wuhama River Bridge Checked by: Date:

 8.1375 int 2 P int 


g x  (1.25 w  5.217 g v  13.95 g vint ) x  
 L v DLInt
L 
VU    
(1.25R P int 
 ADLInt  5.217 Pg int
v  14.84 g v  8.1375 Lg v
int
) 
L
VU  0.41x 2  72.05x  750.72

x: 5.073 L- 8.6
 4.65 2 P P 
VU   1.25( RADLExt  FDiaph  wDLExt x)  1.75 * g vext x  (2.9811  9.3) x  (2.9811P  8.48  4.65L) 
 L L L 

 8.1375 ext 2 P ext 


 L g v x  (1.25wDLExt  5.217 L g v  13.95 g v ) x 
ext

VU    
(1.25( R P ext ext 
ADLExt  FDiaph )  5.217 Pg v  14.84 g v  8.1375Lgv )
ext
 L 
VU  0.41x 2  72.05x  742.95

The corresponding moments are:

x: 0 5.073
 w P P 
M C  0.951.25( RADLInt x  DLInt x 2 )  1.75 * g mint  (2.9811  4.65) x 2  (2.9811P  8.48  4.65L) x 
 2 L L 
 wDLInt 5.217 P int 
 (1.25 2  L * g m  8.1375 g m ) x 
int 2

MC  
(1.25R P int
 ADLInt  5.217 P * g m  14.84
int
g m  8.1375 g m * L) x
int

L 
M C  49.16 x 2  664.38x
x: 5.073 L – 8.6
 w P P
M C  0.951.25( RADLExt Inx  FDiaphx  DLInt x 2 )  1.75 * g mint  (2.9811  4.65) x 2  (2.9811P  8.48  4.65L) x
 2 L L
 wDLInt 5.217 P int 
 (1.25 2  L * g m  8.1375 g m ) x 
int 2

MC  
(1.25( R P int 
 ADLInt  FDiaph )  5 .217 P * g int
m  14 . 84 g m  8.1375 g int
m * L ) x 
L
M C  49.16 x 2  656.61x

Check adequacy of section for compression in concrete


c < 0.42d, a = 1c a  0.421d 1 = 0.85 [Art 5.7.3.3]
a< 0.85 * 0.42d
a< 0.357d ------------- (a)

18
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 19 of 50
Design of Wuhama River Bridge Checked by: Date:

From the moment equation


M = (0.85fc’ab)(d - a/2) -------- (b)
From equations (a) and (b) above
M = 0.2244fc’bd2
MU
d
0.2244bf C'
1 15220
Leff   3805
4 4
bi  12t s  bw  12(246)  450  3402
S  2350
1 15220
Leff   1902.5
8 8
b b 450
be  i  6t s  w  6(246)   1701
2 2 2
Overhang  1235

bi = 2350 mm taking the minimum


be = 1235 + 0.5*2350 = 2410 mm

Exterior girder
MU 3423.85 *106
d   513.6mm  1100  146  954mm ok!
0.2244bfC' 0.2244  2410 * 24
Interior girder
MU 2582.63 *106
d   451.73  1100  106  994mm ok
0.2244bfC' 0.2244 * 2350 * 24

Reinforcement
Flexure
a) Exterior girder
Assuming two rows of 32 bars, d =954mm, Mumax = 3423.85 kNm

 2.352 M  fc '   2.352 * 3423.85 *10 6  24 


     1  
1  1  b d 2 f ' 1 
u
 1.176 f   0.9 * 2410 * 954 2 * 24  1.176 * 400 
 e c  y   
  0.0045

s = bed = 0.0045* 2410* 954 = 10346.1mm2 , 1332 bars



Provide 1432 bars in four rows.

y = 4 *(50 +16) + 4 * (50 + 3 * 32) + 4*(50 + 5.5*32)+2*(50+8*32) = 168.86


14

19
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 20 of 50
Design of Wuhama River Bridge Checked by: Date:

y = 4 *(66) + 4 * (146) + 4*(226)+2*(306) = 168.86


14

d = 1100 – 168.86 = 931.14 mm,

revise ,
 2.352 * 3423.85 *10 6  24 
  1  1   
 0.9 * 2410 * 931.14 2 * 24  1.176 * 400 
 
  0.0048

s = bed = 0.0048* 2410* 931.14 =10771.43mm2, 13.432 bars,

Provide 1432 bars in four rows, 4 bars in each row and 2 bars in the fourth row
Asprov.= 11259.5 mm2

This area of reinforcement is required to resist moment at section of maximum


moment. Moment decreases as we go away from this point and so bars that are not
needed have to be curtailed.

Cutting off the two bars in row 4, moment capacity of section with 1232 bars is
9650.97 * 400
As = 12(16)2 = 9650.97 mm2, c   92.38
0.7225 * 24 * 2410
M = Asfy(d - 0.425c),
M = (0.9)(9650.97)(400)(954 - 0.425 * 92.38) = 3178.13 kNm
Assuming x: 5.073 – 10.14m
3178.13 kNm = – 63.68x2 + 964.332x-226.97
x = 5.61m and 9.53m. Length of the two bars in row 4, l1 = 9.53 - 5.61 + 2ld

Development length
Basic tension development length, ldb [Art 5.11.2]
0.02 Ab f y
l db   0.06d b f y
f c'
Modification factor do not apply to this girder [Art 5.11.2.1.2and 3]
ldb = 1215.91mm
1800 hook anchorage is provided for bars that continue to the support as per AASHTO
Art. 5.11.2.4.

Provide ld = 1220mm
l1 = 9.53 - 5.61 + 2ld = 3.92 + 2*1.22 = 6.36m

Then two bars will be terminated from row 3, capacity of section with 10  32 bars
(8042.5mm2) assuming x: 4.3 – 5.073m: y =130mm, d=970, c=76.98,
M=2713.72kNm = -63.68x2 + 968.215x – 238.92, x=4.22 outside assumed range

20
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 21 of 50
Design of Wuhama River Bridge Checked by: Date:

Assuming x: 0 – 4.3m: M=2713.72 kNm = -60.21x2 + 915.46x, x = 4.04m (and 15.22-


4.04=11.2m)

l2 = 11.2 - 4.04 + 2ld = 7.16 + 2*1.22 = 9.6m

Then the rest 2 bars in the third row will be terminated where they are no more
needed, capacity of section with 8  32 bars (6433.98mm2): y =106mm, d=994,
c=61.58, M=2241.7kNm=-60.21x2 + 915.46x, x=3.07 and (15.22 – 3.07) 12.15m

l3 = 12.15 - 3.07 + 2ld = 9.08 + 2*1.22 = 11.52m

Then two bars will be terminated from row 2, capacity of section with 6  32 bars
(4825.5mm2) assuming x: 0 – 4.3m: y = 92.67mm, d= 1007.3mm, c=46.2,
M=1730.2kNm = -60.21x2 + 915.46x, x=2.21m (and 15.22-2.21=13.01m)

l4 = 13.01 - 2.21 + 2ld = 10.8 + 2*1.22 = 13.24m, two bars of 12m length lapped with
two bars of length 1.24 + 1.22 = 2.46m.

Then the rest 2 bars in the second row will be terminated where they are no more
needed, capacity of section with 4  32 bars (3217mm2): y =66mm, d=1034mm,
c=30.79, M=1182.34kNm = -60.21x2 + 915.46x, x=1.425 and (15.22 – 1.425)
13.795m

l4 = 13.795 - 1.425 + 2ld = 12.37 + 2*1.22 = 14.81m, two bars of 12m length lapped
with two bars of length 2.81 + 1.22 = 4.03m.

Finally, 4  32 bars in the first row will continue to the support.

b) Interior girder
Assuming two rows of 32 bars, d =954mm,, Mumax = 2582.63 kNm
 2.352 M u     6 
  1  1   fc '   1  1  2.352 * 2582.63 *10  
24 

  1.176 f   
 
2 2
 be d f c '  y   0.9 * 2350 * 994 * 24 1.176 * 400
  0.0032

s = bed = 0.0032* 2350 * 994 = 7474.88 mm2, 9.332, Asprovided= 6433.98mm2



Provide 1032 bars, 4 bars in rows 1 and 2, and 2 bars in row 3. 

y = 4 *(50 +16) + 4 * (50 + 3 * 32) + 2*(50 + 5.5*32)= 130, d = 970,


10

s = mm2, 1032 bars

Cutting the top 2 bars, moment capacity of section with 832 bars (6433.98mm2)

21
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 22 of 50
Design of Wuhama River Bridge Checked by: Date:

As = 8(16)2 = 6433.98 mm2, y = 106mm, d=994mm,


6433.98 * 400
c  63.16
0.7225 * 24 * 2350
M = Asfy(d - 0.425c),
M = (0.9)(6433.98)(400)(994 - 0.425 * 63.16) = 2240.16 kNm
Assuming x: 5.073 – 10.14m
2240.16 kNm = – 49.16x2 + 743.29x-226.97 , x = 4.91 outside assumed range

Assume x:4.3 – 5.073 m, 2240.16 kNm = – 49.16x2 + 751.06x - 226.97 , x = 4.78 and
(15.22 – 4.78) 10.44m

Development length
The same as for exterior girders.

l1 = 10.44 - 4.78 + 2ld = 5.66 + 2*1.22 = 8.1m

Then two bars will be terminated from row 2, capacity of section with 6  32 bars
(4825.5mm2) assuming x: 0 – 4.3m: y = 92.67mm, d= 1007.3mm, c=47.37,
M=1714.89kNm = -45.69x2 + 698.3x, x=3.07m (and 15.22-3.07=12.146m)

l2 = 12.146 - 3.07 + 2ld = 9.08 + 2*1.22 = 11.52m

Then the rest 2 bars in the second row will be terminated where they are no more
needed, capacity of section with 4  32 bars (3217mm2): y =66mm, d=1034mm,
c=31.58, M=1181.95kNm = -45.69x2 + 698.3x, x=1.942 and (15.22 – 1.942) 13.278m

l3 = 13.278 - 1.942 + 2ld = 11.336 + 2*1.22 = 13.78m, two bars of 12m length lapped
with two bars of length 1.78 + 1.22 = 3.0m.

Finally, 4  32 bars in the first row will continue to the support, to which is provided
1800 hook anchorage.

Shear reinforcement
Nominal shear resistance Vn is the lesser of

Vn = Vc + Vs + Vp or
Vn = 0.25fc’bvdv + Vp

In which the nominal shear resistance of concrete Vc is


Vc = 0.083 f c' bvdv, traditional value of  = 2.0
Nominal stirrup shear resistance, Vs is

22
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 23 of 50
Design of Wuhama River Bridge Checked by: Date:

Av f y d v (cot   cot  ) sin 


Vs 
S

For vertical stirrups,  = 900 (angle of inclination of transverse reinforcement to


longitudinal axis) and
Av f y d v cot 
Vs 
S
bv = effective web width taken as the minimum web width with in the depth dv
dv = effective shear depth taken as the distance measured perpendicular to the NA
between the resultants of the tensile and compressive forces due to flexure

> 0.9de or 0.72D = 0.9*(1100-126.8) or 0.72*1100 = 875.88 for exterior girder and
the larger of 0.9*994 or 0.72*1100 = 894.6mm or 792mm = 894.6mm
S = spacing of shear reinforcement
Vu < 0.1fc’bvdv S  0.8dv  600mm
Vu > 0.1fc’ bvdv S  0.4dv  300mm
Vp = component of pre stressing force in the direction of shear (N)

Vu
Nominal shear stress in concrete  u 
bv d v

Tensile strain in the longitudinal reinforcement


MC
 0.5Vu cot 
dv
x   0.001
2 Es As

Shear causes tension in the longitudinal reinforcement that must be added to flexural
tension force.

M C  Vu 
As f y     0.5Vs  cot  [Art 5.8.3.5]
d v  v 
If this equation is not satisfied either the tensile reinforcement As must be increased or
the stirrups must be placed closer together to increase Vs. Vu is shear envelope for
strength I limit state which will be taken with MC.

The shear envelopes and the corresponding moments and are:

a) Exterior girder
X: 0 – 5.073m
VU  0.264 x2  83.86 x  822.79
M C  63.68x2  881.53x

23
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 24 of 50
Design of Wuhama River Bridge Checked by: Date:

x: 5.073 L- 8.6
VU  0.264 x2  83.86 x  763.42
M C  63.68x2  877.65x

b) Interior girder
x: 0 5.073m
VU  0.41x2  72.05x  750.72
M C  49.16 x2  664.38x
x: 5.073 L- 8.6
VU  0.41x  72.05x  742.95
2

M C  49.16 x2  656.61x

Reinforcement As at tenth points:

Exterior Girder Reinforcement (mm2) Interior Girder Reinforcement ( mm2)


dv 6Φ32 = 4825.5 dv 6Φ32 = 4825.5
0.1L=1.522 m 8Φ32 = 6433.98 0.1L=1.522 m 6Φ32 = 4825.5
0.2L=3.044 m 10Φ32 = 8042.48 0.2L=3.044 m 8Φ32 = 6433.98
0.3L=4.566 m 14Φ32 = 11259.5 0.3L=4.566 m 10Φ32 = 8042.5
0.4L=6.088 m 14Φ32 = 11259.5 0.4L=6.088 m 10Φ32 = 8042.5
0.5L=7.61 m 14Φ32 = 11259.5 0.5L=7.61 m 10Φ32 = 8042.5

a) Exterior Girder

Step 1
Determine Vu and MC at distance dv from the support
632 bars, As = 4825.5 mm2, bv = 450mm, be = 2410

As f y 4825.5  400
a   39.26 mm
0.85 f b'
c ee 0.85  24  2410

d = 1007.3 mm = de
 a 39.26
 d  2  1007.3  2  987.7 mm

d v  max of  0.9d  0.9 1007.3  906.6 mm
0.72 D  0.72 1100  792mm

dv = 987.7 mm, Vu = 684.71, Mc = 808.79

Step2

24
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 25 of 50
Design of Wuhama River Bridge Checked by: Date:

Calculate the shear stress ratio u/fc’

Vu 684.71 103
u    1.712
bv d v 0.9  450  987.7

 1.712
'
  0.071
f c 24

Step 3
Estimate an initial value of and calculate x
first trial  = 35 0, cot = 1.428, Es = 200GPa
MC
 0.5Vu cot 
dv
x   0.001 
2 Es As

 0.5Vu cot  808.79 10  0.5  684.71 103 1.428
MC 6

d 987.7
x  v   0.678 10 3 
2 Es As 2 * 200 10  4825.5
3


Step 4
Use the calculated values of u/fc’ and x to determine  from Table 5.8.3.4.2-1 of
AASHTO 2005 and compare with the value estimated in step 3. If different,
recalculate x and repeat step 4 until the estimated value of  agrees with the value
from Fig 5.8.3.4.2-1 of AASHTO 98. When it does, take the corresponding value of
.

 = 33.7, cot = 1.499, x = 0.69*10-3  = 33.7 is okay.


 = 2.38

Vc  0.083bv d v f c'  0.083  2.38  450  987.7  24  430.13 kN

Vu 684.71
Vs   Vc   430.13  330.66
 0.9

Using 10, Av = 2**(5)2 = 157.08 mm2

Av f y d v cot  157.08  400  987.7  cot 33.7


s   281.4 mm
Vs 330.66 103
Av f y 157.08  400
s   343.4 mm
0.083bv f c' 0.083  450  24
Vu  0.1 f c'bv dv  0.1 24  450  987.7  1066.7, s  0.8  987.7mm  790.2 mm

25
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 26 of 50
Design of Wuhama River Bridge Checked by: Date:

Check T in longitudinal reinforcement


M V
T  As f y  C  ( u  0.5Vs ) cot 
d v 
808.79 *106 684.71*103
4825.5 * 400  (  0.5 * 330.66 *103 ) cot 33.7
0.9 * 987.7 0.9
1930.2kN  1802.7kN okay.

Provide 10 C/C 280 mm

At x = 1.522m, Vu = 640.36, Mc = 1194.17, a = 52.35, d = 994, dv = 967.8 mm, u


=1.634, u/fc’ = 0.068 and x = 0.66*10-3 from table,  = 33.7, cot = 1.499, x =
0.659*10-3,  = 33.7 is okay,  = 2.38, S = 343.4mm, T = 2573.6kN > 2273.65kN.

Provide 10 C/C 340 mm

At x = 3.044m, Vu = 514.5, Mc = 2093.32, a = 65.43, d = 970, dv = 937.3 mm, u


=1.355, u/fc’ = 0.056 and assuming  = 33.7, x = 0.814*10-3 from table,  = 36.4,
cot = 1.356, x = 0.803*10-3,  = 36.4 is okay,  = 2.23, S = 343.4mm,
T = 3217.0kN > 3167.3kN okay.

Provide 10 C/C 340 mm

At x = 4.566m, Vu = 389.91, Mc = 2697.4, a = 91.61, d = 931.1, dv = 885.3 mm, u


=1.087, u/fc’ = 0.045 and assuming  = 36.4, x = 0.735*10-3 from table,  = 33.7
okay, x = 0.74*10-3,  = 33.7,  = 2.23, S = 343.4mm T = 4508.8kN > 3953.3kN
okay.

Provide 10 C/C 340 mm afterwards

b) Interior girder

Step 1
Determine Vu and MC at distance dv from the support, Vu = 680kN, MC =607.97kNm
632 bars, As = 4825.5 mm2, bv = 450mm, bi = 2350

As f y 4825.5  400
a   40.26 mm
'
0.85 f b
c ee 0.85  24  2350

d = 1007.3 mm = de

26
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 27 of 50
Design of Wuhama River Bridge Checked by: Date:

 a 40.26
 d  2  1007.3  2  987.2 mm

d v  max of  0.9d  0.9 1007.3  906.6 mm
0.72 D  0.72 1100  792mm


Take dv = 987.2 mm
Step2
Calculate the shear stress ratio u/fc’

Vu 680.0 103
u    1.70
bv d v 0.9  450  987.2

u 1.70
'
  0.071
f c 24

Step 3
Estimate an initial value of and calculate x first trial  = 33.7 0, cot = 1.499,
Es = 200GPa
MC
 0.5Vu cot 
dv
x   0.001 
2 Es As

 0.5Vu cot  607.97 10  0.5  680 103 1.499
MC 6

d 987.2
x  v   0.583 103 
2 Es As 2 * 200 10  4825.5
3


Step 4
Use the calculated values of u/fc’ and x to determine  from Table 5.8.3.4.2-1 of
AASHTO 2005 and compare with the value estimated in step 3. If different,
recalculate x and repeat step 4 until the estimated value of  agrees with the value
from Fig 5.8.3.4.2-1 of AASHTO 98. When it does, take the corresponding value of
.

 = 33.7 is okay.
 = 2.38

Vc  0.083bv dv f c'  0.083  2.38  450  987.2  24  429.91 kN

Vu 680
Vs   Vc   429.91  325.64
 0.9

Using 10, Av = 2**(5)2 = 157.08 mm2

27
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 28 of 50
Design of Wuhama River Bridge Checked by: Date:

Av f y d v cot  157.08  400  987.2  cot 33.7


s   283.8 mm
Vs 325.64 103
Av f y 157.08  400
s   343.4 mm
0.083bv f c
'
0.083  450  24
Vu  0.1 f c'bv dv  0.1 24  450  987.2  1066.7, s  0.8  987.7mm  790.2 mm

Check T in longitudinal reinforcement


M V
T  As f y  C  ( u  0.5Vs ) cot 
d v 
607.97 *106 680 *103
4825.5 * 400  (  0.5 * 250.09 *103 ) cot 33.7
0.9 * 987.2 0.9
1930.2kN  1314.8kN okay.

Provide 10 C/C 280 mm

At x = 1.522m, Vu = 642.0, Mc = 897.31, a = 52.35, d = 1007.3, dv = 987.2 mm, u


=1.606, u/fc’ = 0.0669 and assuming  = 34.6, x = 0.696*10-3 from table,  = 33.7
is okay,  = 2.38, VC = 402.82, VS = 239.18, S = 343.4mm, T = 1930.2kN >
1815.06kN.

Provide 10 C/C 340 mm

At x = 3.044m, Vu = 535.2, Mc = 1566.86, a = 53.68, d = 994, dv = 967.16 mm, u


=1.355, u/fc’ = 0.057 and assuming  = 36.4, x = 0.77*10-3 from table,  = 36.4 is
okay,  = 2.23, VC = 394.64, VS = 140.56, S = 343.4mm,
T = 2573.6kN > 2511.14kN okay.

Provide 10 C/C 340 mm afterwards

Summary of Shear Reinforcement:


Exterior Girder
Location   Sreqiured [mm] Sprovided [mm]
dv = 0.988 m 33.7 2.38 281.4 280
0.1L = 1.522 m 33.7 2.38 343.4 340
0.2L = 3.044 m 36.4 2.28 343.7 340
0.3L = 4.566 m 36.4 2.28 343.4 340
0.4L = 6.088 m 36.4 2.28 343.4 340
0.5L = 7.61 m 36.4 2.28 343.4 340

Interior Girder
Location   Sreqiured [mm] Sprovided [mm]
dv = 0.988 m 33.7 2.38 283.8 280
0.1L = 1.522 m 36.4 2.28 343.4 340
0.2L = 3.044 m 36.4 2.28 343.4 340

28
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 29 of 50
Design of Wuhama River Bridge Checked by: Date:

0.3L = 4.566 m 36.4 2.28 343.4 340


0.4L = 6.088 m 36.4 2.28 343.4 340
0.5L = 7.61 m 36.4 2.28 343.4 340

Service I Limit State


Load Combination for Service I limit state is:

M  M DC  M LL IM

a) Durabiilty
It is assumed that concrete materials and construction procedures provide adequate
concrete cover, nonreactive aggregates, thorough consolidation, adequate cement
content, low water/cement ratio and thorough curing. If these conditions are satisfied,
it is sufficient to provide minimum cover provision of AASHTO Table Art. 5.12.3-1,
which are provided in here.

b) Crack control
i) Positive bending moment reinforcement – exterior girder
x:5.073 - 10.146m
M = MDC + MLL+IM
 wDLExt 2 
(( RADLExt  FDiaph ) x  2 x )  
M  
 g mext  ( 2.9811P  4.65) x 2  (2.9811P  4.65L  4.3385 P ) x  1.3805P 
  L L 
 wDLExt 2.9811P ext 
 ( 2  L
g m  4.65 g mext ) x 2  
M  
(( R P ext 
 ADLExt  FDiaph )  g m (2.9811P  4.65L  4.3385 L )) x  1.3805Pg m 
ext

M C  44.61x2  650.79 x  136.52


dM/dx = 0, x = 7.29 m, Mmax = 2236.98 kNm
Assuming the section cracks and j = 0.875, fs = 0.6fy = 0.6*400 = 240MPa
d = 1100 – 130 = 970 mm

M 2236.98 *106
As    10981.7mm2 , 12 32 less than the area provided.
f s jd 240 * 0.875 * 970
( )√ = 24.77GPa, , take n = 8

Effective flange width is [Art 4.6.2.6.1]

Assuming neutral axis is in flange, depth of neutral axis x is

29
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 30 of 50
Design of Wuhama River Bridge Checked by: Date:

2
 nA  2nAs d
2
nA 8(11259.5)  8 *11259.5  2(8)(11259.5)(931.1)
x   s   s       
be  be  be 2410  2410  2410
 229.08 mm  t s  246mm assumption okay

bx 3 2410  229.083
I cr   nAs (d  x) 2   8 11259.5(931.1  229.08) 2  5.405 1010 mm4
3 3
nM (d  x) 8(2236.98 *106 )(702.02)
fs    232.44MPa
I cr 5.405 *1010

ii) Positive bending moment reinforcement – interior girder

 wDLExt 2 
(( RADLExt  FDiaph ) x  2 x )  
M  
 g mext  ( 2.9811P  4.65) x 2  (2.9811P  4.65L  4.3385 P ) x  1.3805P 
  L L 
 wDLExt 2.9811P ext 
 ( 2  L
g m  4.65 g mext ) x 2  
M  
(( R P ext 
 ADLExt  F )  g ext
( 2.9811P  4 .65 L  4.3385 )) x  1.3805 Pg m 

Diaph m
L
M C  32.38x 2  464.65x  136.47
dM/dx = 0, x = 7.175 m, Mmax = 1530.45 kNm

Assuming the section cracks and j = 0.875, fs = 0.6fy = 0.6*400 = 240MPa


M 1530.45 *106
As    7513.3mm2 , less than the rows area provided
f s jd 240 * 0.875 * 970

Assuming neutral axis is in flange, depth of neutral axis x is

2 2
nA  nA  2nAs d 8(8042.5)  8(8042.5)  2(8)(8042.5)(970)
x s   s        204.71 mm
b  b  b 2350  2350  2350
x  flange thickness, assumption is ok

30
Project:
Client:
Mille-Chifra-Alewuha Road
Consultant:
Upgrading Project
Calculation for: Date: 13/ 01/’11 Sheet Nr
Designed by: Fekadu Melese 31 of 50
Design of Wuhama River Bridge Checked by: Date:

The actual steel stress must be compared to the allowable steel stress for crack control

bx 3 2350  204.713
I cr   nAs (d  x) 2  I cr   8  8042.48(970  204.71) 2  4.44 1010 mm4
3 3
nM (d  x) 8(1530.45 *10 )(765.29)
6
fs    211.03MPa
I cr 4.44 *1010

S< spacing of flexural reinforcement.

31

You might also like