Situation I.

The table shown lists the activities for making up a network diagram for
a project together with the duration and the costs of carrying out the work.

Activity Duration (days) Cost


A (0-1) 5 ₱12,000.00 1. Draw a network diagram using AON approach
B (0-3) 3 ₱800.00 [2pts].
C (0-2) 8 ₱20,000.00 2. Determine the critical path [1pt].
D (2-3) 0 ₱0.00 3. Determine the number of days to complete
E (1-4) 4 ₱1,000.00 the project [1pt].
F (3-4) 4 ₱900.00 4. Determine the total cost of the project
G (3-5) 6 ₱14,000.00 [1pt].
H (2-6) 7 ₱16,000.00
I (4-7) 6 ₱15,000.00
J (5-7) 2 ₱800.00
K (5-6) 7 ₱18,000.00
L (6-7) 6 ₱17,000.00

Situation II. Given the list of activities of a network diagram for a dam construction
in Northern Luzon.

Activity Duration (days) Cost


A (4-5) 30 ₱36,000.00
1. Draw a network diagram using AOA. (limit
B (11-12) 4 ₱5,000.00 your use of dummy activity to 2 only) [2pts]
C (1-3) 40 ₱48,000.00 2. Give the number of days to finish the
D (1-6) 28 ₱33,000.00 job. [1pt]
E (2-4) 8 ₱9,000.00 3. Give the total cost of the project. [1pt]
F (3-6) 10 ₱14,000.00 4. Give the critical path. [1pt]
G (0-1) 10 ₱12,000.00
H (3-5) 0 ₱0.00
I (5-6) 14 ₱16,000.00
J (7-8) 12 ₱14,000.00
K (6-8) 10 ₱13,000.00
L (8-9) 0 ₱0.00
M (9-10) 6 ₱7,200.00
N (8-10) 10 ₱13,000.00
O (8-11) 6 ₱8,000.00
P (10-11) 4 ₱5,000.00
R (1-2) 20 ₱24,000.00
T (5-7) 24 ₱28,000.00