Professional Documents
Culture Documents
Owner’s Engineer
Contractor
Sub-Supplier
Project
Document No.
J910-DH02-P0ZEN-049003
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
RECORD OF REVISION
Rev. Date Page Affected Description of Revision
Rev.B 2 of 14
Jawa 9&10 Coal Fired Steam Power Plant_ITP Comment Sheet
From : O/E Mr. - -
To : HK Mr. I Made Japasunu j_japasunu@yahoo.com Comment Sheet Document No : J910-DH02-P0ZEN-049003_CS
cc : IRT Mr. Steve Adrianto Steve.adrianto@irt.co.id
Doc Title : ITP FOR INSTALLATION OF STORM WATER
Doc No : J910-DH02-P0ZEN-049003
Purpose : FA
Review Category
A = Approved
B = Approved with comments, forward final document C
C = Not Approved
I = Accepted for reference (For information only)
No. Rev. Sheet/ Page/ Sect. O/E Comments Consortium Response Status
1. Update the legend
2. Additional Point for Preparation Works
1 A 7-8/14/- It is applied on Rev. B. Closed
3. Correction on CONTROL DOCUMENT, ACCEPTANCE CRITERIA and
VERIFYING DOCUMENT.
It is applied on Rev. B. We changed Oreintation of spools into Orientation
2 A 12/14/- What is the meaning of Oreintation of spools? Change Slop to Slope Closed
as per drawing.
3 A 14/14/- Ask for Concrete ITP If necessary, ITP for Concrete Work will be applicable. Closed
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
TABLE OF CONTENTS
I. INTRODUCTION…………………………………………………………………. 4
1.1.Inspection and Test Plan (ITP)
1.2.Acceptance Conditions
1.3.Request for Inspection and Test (RFI)
1.4.Documentation
Rev.B 3 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
I. INTRODUCTION
Rev.B 4 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
H : Hold Point
Consortium shall also send a notification to the Owner prior to perform the related
test or inspection. If the Owner fails to be present, any construction activities shall
not be proceeded by Consortium without attendence or any written approval of the
Owner.
1.4. Documentation
a. The results of inspections and tests shall be documented in writing and signed by the related
parties as a token of approval
b. Signed documents shall be controlled as a QA records in accordance with the related procedure.
Rev.B 5 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
II. FLOW CHART OF SITE MATERIAL INSPECTION
SITE
Rev.B 6 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
1 Preparation
1.1 Comply with
Material for Drainage System (U-Ditch, Contract Book 4.3.5 and MAR Document/Vendor Data
Specification, Method I/R SW -
Cover, and Box Culvert, ect.) Drawing or broschure, shop visit
B Statement, and Drawing
Comply with
Contract Book 4.4.2 and
1.2 Warehouse/Receiving Point at Site Specification, Drawong, Inspection Report I/R V -
Storage Instruction
List of Material
2 Earth Work
2.1 Setting out and positioning Approved Drawing Comply with Drawing ITP-C-0001-30 I/R V -
Rev.B 7 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
3 Erection / Installation
Approved Method
3.1 Setting out and positioning Comply with Method Statement ITP-C-0001-31 I/R V -
Statement
Approved Method
3.2 U-Ditch handling Comply with Method Statement ITP-C-0001-31 I/R V -
Statement
Approved Method
3.3 Alignment / Center Point Comply with Method Statement ITP-C-0001-31 I/R SW -
Statement
3.4 Cast-in-site Concrete for U-Ditch and Approved Method
Comply with Method Statement ITP-C-0001-31 I/R SW -
Box Culvert Joints Statement
4 Non-Destructive Testing
Approved Method
4.1 Surface cleanliness Comply with Method Statement ITP-C-0001-32 I/R V -
Statement
5 Joint Grouting
Approved Method
5.1 Surface cleanliness Comply with Method Statement ITP-C-0001-32 I/R V -
Statement
Approved Method
5.2 Grouting mixing and pouring Comply with Method Statement ITP-C-0001-32 I/R V -
Statement
6 Backfilling
Approved Method
6.1 Sand filling and Compacting Comply with Method Statement ITP-C-0001-33 I/R V -
Statement
Approved Method
6.2 Native Soil Filling and Compacting Comply with Method Statement ITP-C-0001-33 I/R V -
Statement
Rev.B 8 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
IV. APPENDICES
APPENDIX 1
Form No. ITP-C-0001-10
Inspection Result
No. Description Remarks
Accept Reject
13 Quality of Cleaning
Rev.B 9 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
APPENDIX 2
Form No. ITP-C-0001-11
Inspection Result
No. Description Remarks
Accept Reject
1 Material for backfill are suitable and approved
Note :
Rev.B 10 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
APPENDIX 3
Form No. ITP-C-0001-30
Inspection Result
No. Description Remarks
Accept Reject
1 Conformity to mute coordinated and elevation in the plan Drawing
Note :
Rev.B 11 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
APPENDIX 4
Form No. ITP-C-0001-31
INSPECTION FOR ERECTION / INSTALLATION
REPORT
Inspection Result
No. Description Remarks
Accept Reject
1 Checklist for box culvert and u-ditch joint
Note :
Rev.B 12 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
APPENDIX 4
Form No. ITP-C-0001-32
Inspection Result
No. Description Remarks
Accept Reject
1 Preparing for equipment testing Refer to the mixture requirement As per Specification
a. CEMENT Sulphate resisting PORTLAND cement
b. SAND
c. ADMIXTURE SIKA LATEX
d. WATER
2 Surface cleanliness
3 Formwork
Note :
Rev.B 13 of 14
ITP FOR INSTALLATION OF STORM WATER WORK
J910-DH02-P0ZEN-049003
APPENDIX 4
Form No. ITP-C-0001-33
Inspection Result
No. Description Remarks
Accept Reject
1 Backfilling material as per specification As per Specification
5 Tolerance by successive layers with the excavated materials deprived As per Specification
Note :
Rev.B 14 of 14