Professional Documents
Culture Documents
SPE
Gas-Lift-Valve Test Rack Opening Design Methodology for Extreme
Kickoff Temperature Conditions
D.L. Lagerlef, W.H. Smalstig, and M.D. Erwin, ARCO Alaska Inc.
SPE Members
This paper was prepared for presentation at the Western Regional Meeting held in Bakersfield, California, March 30-April 1, 1992.
This paper was selaoted for presentation by an SPE Program Comminee following review of information contained in an abstract submined by the author@). Contents of the paper,
as present&, have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the suthorfs). The material, as presented, does not necessarily reflect
any p o s i f i of the Society of Petroleum Engineers, its oificers. or members. Papers presented at SPE meetings are subjaot to publication review by Editoriar Committees of the Society
of PetroleumEngineers. Permissionto copy is restrictedto an abstractof not more than 300 words. Illustrationsmay not be repied.Th8 abstractshould contain consptcuousacknowledgment
of where and by whom the paper is presented. Write Librarian Manager, SPE, P.O. Box 833836, Richardson, TX 750853838. Telex, 730989 SPEDAL.
Bellows operated gas lift valves are tempetatw sensitive and it's
The Prudhoe Bay field is located on the edge of Alaska's Arctic important to understand their characteristics over the range of
Ocean. The primary producing interval, the Sadlerochit, is found well bore temperature gradient conditions. The difference between
at approximately 8850 ft SS (2698 m) with significant portions the unloading temperature gradient and the flowing temperature
of the oil field undergoing water flood. Seawater from the Arctic gradient has been well documented1. The use of flowing
Ocean is injected in addition to produced water. All produced gas temperature gradients273 in gas lift design techniques is
not consumed as fuel is injected into the gas cap for pressure common. However, the flowing gradient does not always result
maintenance. Well productivity index (PI) varies across the field in an optimal gas lift design. Jones and Brown found that
from slightly below 1.0 to above 30 BF'PD per psi drawdown setting gas lift valve dome pressures based on a linear
(23 to 692 (m3/d)/MPa). Water cuts currently average 60 temperature change from top to bottom was inadequate4.
percent. A range of tubing sizes are found in the producing Likewise, Laing pointed out that bear temperame gradients are
wells, with 4-112 and 5-112 in (114 and 140 cm) diameter an oversimplification in deep water offshore production areas and
prevalent. Gas lift is the predominant artificial lift mechanism. could result in unloading problems5.
Over 150 of the 300 ARCO operated producing wells in the
Eastern Operating Area of Prudhoe Bay are normally on gas lift Other methods have been proposed. One valve manufacturer's
utilizing ammximately 250 hlMSCFD (81935 Us) lift gas. gas Sit manual recommends using the geothermal gradient to
Gas lift valves are normally 1-112 in (38 cm) 0. D. The
manifold operating pressure for the gas lift supply system is provide some "safety factor"6. Yet another method of estimating
During initial start-up of the Prudhoe Bay artificial lift system, A temperature model is used which simulates the thermal regime
designs were based on the expected flowing temperature gradient expected, assuming the flow rates calculated as the well unloads
(Fig. 1). However, it was discovered that some Prudhoe Bay at each valve. Arco uses an in-house model for this purpose but
wells experienced difficultly unloading to the operating valve. In several similar models have been published, including one
some cases, it took excessive amounts of lift gas, much more developed by shiul1. A temperature estimate is made for each
than any one valve could pass, to accomplish the unloading upper valve with the well unloading only from that valve.
sequence. Other wells could only be unloaded after waiting for
production, initiated with limited drawdown from lifting off the The resulting kick-off temperature profile reflects the expected
top valve alone, to warm up the well bore and upper valves. reservoir inflow as drawdown is increased by kicking to lower
valves. The actual initial kick-off gradient is much colder, but
The poor kick-off characteristics of designs based on flowing valves designed for cooler gradients would not function properly
temperature conditions alone were unexpected. It resulted in if required to unload the well after only a brief shut-in period.
multi-point lifting, which occurs as valves open and close out of This results from the warmer well bore temperatures increasing
the intended sequence. These unloading difficulties prompted the bellows pressure. The kick-off temperature gradient is used
closer evaluation of gas lift design assumptions and to design the opening and closing pressure for the three upper
methodology. valves, while the flowing gradient is appropriate kor the lower
valves.
Based on the operational problems associated with the flowing
temperature gradient, a modified technique was developed. The However, the upper valve performance under flowing temperature
next approach used a linear gradient beginning from 30 OF (-1 OC) gradient conditions must be evaluated to ensure sufficient kick-
at the base of the permafrost to the static bottom hole off pressure is available. Failure to complete this final check can
temperature (Fig. 1). The new design methodology eliminated require additional shut-in time for the well bore to cool after brief
many of the operational problems previously encountered but shut downs, such as for choke changes, sub-surface safety valve
resulted in new difficulties. The unloading process, after brief checks, miscellaneous wire line or slick line work, etc.
shut-in periods, often resulted in the inability to inject lift gas.
It was determined that the valve dome pressures were higher than High productivity wells with high water cut exhibit the greatest
the available casing pressure as a result of the higher flowing difference between their static and flowing temperamre gradients.
temperatures, forcing the valves to remain shut Shut-in periods By contrast, low productivity wells, particularly low water cut
were extended to allow the well bore to further cool, reducing the wells, exhibit the greatest difference between their kick-off and
lift valve temperatures and the bellows pressure, allowing the flowing temperature gradients. Typical flowing, shut-in, and
well to be kicked off. But the associated production loss was kick-off gradients estimated using the reduced productivity index
unacceptable. methodology are shown in Figure 1. Table 1 displays the
general trend for the kick-off gradient and the flowing gradient.
The design methodology was revised to average the expected Below 6000 ft SS (1829 m), or the third valve, the difference is
flowing wellhead temperature and the permafrost gradient of 30 negligible as the gradients converge.
OF (-1 "C). This approach appeared to result in fewer kick-off
problems but was still unreliable in certain situations; valves
locking out or operating out of sequence continued to occur with EXAMPLE:
unacceptable fresuency
Given:' Top valve with R= 0.0614 a't 3013 ft TVD (918.4 m),
maximum available kick-off pressure = 1850 psi (1276 MPa),
design kick-off pressure = 1815psi (12.51 MPa), Ptmin = 1218
psi (8.40 MPa), gas gradient = 0.055 psi/ft (.0012 MPaIm).
The design methodology now involves two steps: (1) designing Design PI = 3.0 BFPD/apsi (69 (m3/D)/IWa), liquid rate = 5885
the upper three valves based on a kickoff temperature gradient, BFPD (935.6 m3/d), water cut = 70%, GOR=1400 SCFISTB
and (2) determining if the upper valves will operate properly (896400 L/m3), lift gas rate = 4000 MSCFD (1311 L/s) injected
under flowing temperature gradient conditions (occurring after at 8326 ft TVD(2537.8 m).
SPE 24065 D.L. Lagerlef. W.H.Smalstig. M.D.Erwin 3
Pdome - Ptmin*R
Pvo =
1-R
.............(2)
Rearranging terms;
= 1848 psi (12.74 MPa)
Therefore, the valve TRO set at 1720 psi (11.86 MPa) will
The Non-Ideal Gas Law can be used to determine the dome function under cool kick-off conditions and under a warmer
pressure to be set at 60 OF (30 OC) in the shop; flowing temperature gradient also. If there was not enough
pressure available, the cool kick-off design would have to be
recalculated assuming a lower kick-off gas lift supply pressure.
Table 2 shows the spreadsheet developed to perform the various
TRO calculations for both cool kick-off temperature and flowing
temperature conditions.
Since for the bellows we assume Vl=V2, solve for the dome
pressure at any temperature given another known operating
pressure and associaad temperame at depth; CASE HISTORY
REFERENCES
1. Winkler, H. W.: "Gas Lift", Petroleum Engineering
Handbook, SPE (1987) Chapter 5 5-23 and 5-26.
2. Winkler, H. W., and Smith, S. S.: "Gas Lift Manual,"
Camco, Inc., Houston, Texas (1962).
3. Brown, K. E.: "The Technology of Artificial Lift Methods,"
Vol. 2a, Petroleum Publishing Co., Tulsa, Oklahoma
(1980) 224 and 233.
4. Jones, D. L.: "How Needed Changes Can Hike Gas Lift Oil
Production," Oil and Gas J. (June 25,1973) 100.
5. Laing, C. M.: "Gas Lift Design Performance Analysis in
the North Hutton Field," J. Pet. Tech. (January. 1991) 97.
Table 5.
Warm
DS13-28 New Design Summary
Cold Cold Cold Warm Warm I
I'Fn
Dealgn Derlgn Tamp Temp Temp Temp
GLV
for
Figure 2.
7"
s
n w o o .
Sqz P e r f s
Open Perfs
Well Schematic
I
Increase A!L to
-X
s
loo0
Q Valve#l @ ~a1ve#2
Casing Injection
E 800.- Pressure
: s o 0 --
m
400
200
0
a-
-.
4
-
Flowing Wellhead
I .
Pressure
I
0.00 2.00 4.00 6.00 8.00
Time, hrs
Figure 3. 13-28 Pressure Trend (4/9/91)
Temperature ( F)
0 50 100 150 200 250
1200
Casing Injection Pressure
-.1 0 0 0
.
Y
2
800 1 well operating smoothly with
the lift point at the orifice
400 +
Flowing wellhead pressure
"
200