You are on page 1of 8

SPE 24065

SPE
Gas-Lift-Valve Test Rack Opening Design Methodology for Extreme
Kickoff Temperature Conditions
D.L. Lagerlef, W.H. Smalstig, and M.D. Erwin, ARCO Alaska Inc.
SPE Members

Copyright 1992, Society of Petroleum Engineers Inc.

This paper was prepared for presentation at the Western Regional Meeting held in Bakersfield, California, March 30-April 1, 1992.

This paper was selaoted for presentation by an SPE Program Comminee following review of information contained in an abstract submined by the author@). Contents of the paper,
as present&, have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the suthorfs). The material, as presented, does not necessarily reflect
any p o s i f i of the Society of Petroleum Engineers, its oificers. or members. Papers presented at SPE meetings are subjaot to publication review by Editoriar Committees of the Society
of PetroleumEngineers. Permissionto copy is restrictedto an abstractof not more than 300 words. Illustrationsmay not be repied.Th8 abstractshould contain consptcuousacknowledgment
of where and by whom the paper is presented. Write Librarian Manager, SPE, P.O. Box 833836, Richardson, TX 750853838. Telex, 730989 SPEDAL.

1900 to 2000 psi (13.10 to 13.79 MPa). Due to the kick-off


pressures and temperatures, valve dome pressures above 2000 psi
The objective of unloading valves in a gas lift string is to (13.79 MPa) are common.
transfer gas to the lift point. Normally, the valve test rack
opening (TRO) for nitrogen charged dome pressure valves is The top gas lift mandrels in Prudhoe Bay wells are normally
based upon the estimated flowing temperature profile. This is located between 2900 and 3400 ft TVD (883.9 to 1036.3 m),
appropriate for most situations. However, the valve settings we11 below the permafrost. Permafrost is essentially high water
may not unload consistently when a significant difference exists content, frozen soil and extends from just below the 18 in (457
between the shut in, unloading, and producing temperature cm) of active soil to 2500 ft TVD (762.0 m). This temperature
gradients. Such temperature differences are very pronounced in sink creates a large differential temperature in the well bore
either high rate wells or in wells with a large upper well bore between shut-in and flowing conditions, especially for high nte
heat sink, such as when penetrating the Arctic permafrost, and in wells.
deep sea completio11~.
Prudhoe Bay wells with moderate to low PIShave been found to
A procedure has been developed to determine an appropriate TRO begin flowing while only lifting on upper valves and at very
for each valve to accommodate the range of temperature cool temperatures as they slowly warm up to flowing
conditions expected during kick-off operations. It reduces the temperature. Designs based only on full flowing temperature
likelihood of unloading valves operating out of sequence and p f d e s lifted from the orifice may incorrectly estimate the actual
improves efficient transfer of lift gas to the design l i t valve top valve operating temperame by as much as 15O F (-9 OC).
under a variety of well bore temperature gradients.
BACKGROUND

Bellows operated gas lift valves are tempetatw sensitive and it's
The Prudhoe Bay field is located on the edge of Alaska's Arctic important to understand their characteristics over the range of
Ocean. The primary producing interval, the Sadlerochit, is found well bore temperature gradient conditions. The difference between
at approximately 8850 ft SS (2698 m) with significant portions the unloading temperature gradient and the flowing temperature
of the oil field undergoing water flood. Seawater from the Arctic gradient has been well documented1. The use of flowing
Ocean is injected in addition to produced water. All produced gas temperature gradients273 in gas lift design techniques is
not consumed as fuel is injected into the gas cap for pressure common. However, the flowing gradient does not always result
maintenance. Well productivity index (PI) varies across the field in an optimal gas lift design. Jones and Brown found that
from slightly below 1.0 to above 30 BF'PD per psi drawdown setting gas lift valve dome pressures based on a linear
(23 to 692 (m3/d)/MPa). Water cuts currently average 60 temperature change from top to bottom was inadequate4.
percent. A range of tubing sizes are found in the producing Likewise, Laing pointed out that bear temperame gradients are
wells, with 4-112 and 5-112 in (114 and 140 cm) diameter an oversimplification in deep water offshore production areas and
prevalent. Gas lift is the predominant artificial lift mechanism. could result in unloading problems5.
Over 150 of the 300 ARCO operated producing wells in the
Eastern Operating Area of Prudhoe Bay are normally on gas lift Other methods have been proposed. One valve manufacturer's
utilizing ammximately 250 hlMSCFD (81935 Us) lift gas. gas Sit manual recommends using the geothermal gradient to
Gas lift valves are normally 1-112 in (38 cm) 0. D. The
manifold operating pressure for the gas lift supply system is provide some "safety factor"6. Yet another method of estimating

References and figures at end of paper.


2 Gas Lift VaIve Test Rack Design Methodology SPE 24065
for Extreme Kick-off :mperature Condition
the valve temperature was suggested by ~ o c h t ~ He. proposed, short shut-in periods).
but did not elaborate, that the operating valve temperature should
be based on the anticipated reservoir feed-in rate when lifting The procedure utilizes a multi-phase flow model to estimate fluid
from the unloading valve. rates and a well bore temperature prediction model to estimate the
temperature at each of the upper three valves under kick-off
One of the most detailed techniques published for gas lift design conditions. A multi-phase model is used to determine the
utilizing a temperature gradient other than the flowing gradient is anticipated fluid rates while unloading at each valve. Several
found in a 1981 ptent8. The patent describes a design technique multi-phase models are available for this purpose, including
which corrects gas lift valve spacing and reopening pressures to those developed by Hagedom and Brown and ~ r k i s z e w s k i ~ s ~ ~ .
the lowest temperature expected while lifting from the next lower Fluid rates are calculated assuming the PI is 50% of the well's
valve. expected productivity index, a maximum lift gas rate 500 to
1000 MSCFD (164 to 327 L/s), and expected gas oil ratio and
water cut. The calculated fluid rates are then input in a
temperam model.

During initial start-up of the Prudhoe Bay artificial lift system, A temperature model is used which simulates the thermal regime
designs were based on the expected flowing temperature gradient expected, assuming the flow rates calculated as the well unloads
(Fig. 1). However, it was discovered that some Prudhoe Bay at each valve. Arco uses an in-house model for this purpose but
wells experienced difficultly unloading to the operating valve. In several similar models have been published, including one
some cases, it took excessive amounts of lift gas, much more developed by shiul1. A temperature estimate is made for each
than any one valve could pass, to accomplish the unloading upper valve with the well unloading only from that valve.
sequence. Other wells could only be unloaded after waiting for
production, initiated with limited drawdown from lifting off the The resulting kick-off temperature profile reflects the expected
top valve alone, to warm up the well bore and upper valves. reservoir inflow as drawdown is increased by kicking to lower
valves. The actual initial kick-off gradient is much colder, but
The poor kick-off characteristics of designs based on flowing valves designed for cooler gradients would not function properly
temperature conditions alone were unexpected. It resulted in if required to unload the well after only a brief shut-in period.
multi-point lifting, which occurs as valves open and close out of This results from the warmer well bore temperatures increasing
the intended sequence. These unloading difficulties prompted the bellows pressure. The kick-off temperature gradient is used
closer evaluation of gas lift design assumptions and to design the opening and closing pressure for the three upper
methodology. valves, while the flowing gradient is appropriate kor the lower
valves.
Based on the operational problems associated with the flowing
temperature gradient, a modified technique was developed. The However, the upper valve performance under flowing temperature
next approach used a linear gradient beginning from 30 OF (-1 OC) gradient conditions must be evaluated to ensure sufficient kick-
at the base of the permafrost to the static bottom hole off pressure is available. Failure to complete this final check can
temperature (Fig. 1). The new design methodology eliminated require additional shut-in time for the well bore to cool after brief
many of the operational problems previously encountered but shut downs, such as for choke changes, sub-surface safety valve
resulted in new difficulties. The unloading process, after brief checks, miscellaneous wire line or slick line work, etc.
shut-in periods, often resulted in the inability to inject lift gas.
It was determined that the valve dome pressures were higher than High productivity wells with high water cut exhibit the greatest
the available casing pressure as a result of the higher flowing difference between their static and flowing temperamre gradients.
temperatures, forcing the valves to remain shut Shut-in periods By contrast, low productivity wells, particularly low water cut
were extended to allow the well bore to further cool, reducing the wells, exhibit the greatest difference between their kick-off and
lift valve temperatures and the bellows pressure, allowing the flowing temperature gradients. Typical flowing, shut-in, and
well to be kicked off. But the associated production loss was kick-off gradients estimated using the reduced productivity index
unacceptable. methodology are shown in Figure 1. Table 1 displays the
general trend for the kick-off gradient and the flowing gradient.
The design methodology was revised to average the expected Below 6000 ft SS (1829 m), or the third valve, the difference is
flowing wellhead temperature and the permafrost gradient of 30 negligible as the gradients converge.
OF (-1 "C). This approach appeared to result in fewer kick-off
problems but was still unreliable in certain situations; valves
locking out or operating out of sequence continued to occur with EXAMPLE:
unacceptable fresuency
Given:' Top valve with R= 0.0614 a't 3013 ft TVD (918.4 m),
maximum available kick-off pressure = 1850 psi (1276 MPa),
design kick-off pressure = 1815psi (12.51 MPa), Ptmin = 1218
psi (8.40 MPa), gas gradient = 0.055 psi/ft (.0012 MPaIm).
The design methodology now involves two steps: (1) designing Design PI = 3.0 BFPD/apsi (69 (m3/D)/IWa), liquid rate = 5885
the upper three valves based on a kickoff temperature gradient, BFPD (935.6 m3/d), water cut = 70%, GOR=1400 SCFISTB
and (2) determining if the upper valves will operate properly (896400 L/m3), lift gas rate = 4000 MSCFD (1311 L/s) injected
under flowing temperature gradient conditions (occurring after at 8326 ft TVD(2537.8 m).
SPE 24065 D.L. Lagerlef. W.H.Smalstig. M.D.Erwin 3

off temperature conditions can be opened with the maximum


First, a two phase model is used to determine the flow rates available design kick-off gas lift pressure under flowing
lifting from the top valve at 3013 ft TVD (918.4 m) with 1000 temperature conditions. Continuing the example above, the
MSCFD (327 Lls) lift gas and the given formation GOR and, flowing temperature at the top valve = 159 OF:
water cut. A flow rate of 2303 BFPD (366.1 m3/d) is estimated. 1
The temperature model is then used to predict a kick-off The dome pressure at flowing temperature can be calculated using
' temperature at the top valve of 140 OF (60 OC). The next step is equation (5).
to determine the valve opening pressure conditions, and then
determine the dome setting pressure.

The casing pressure at valve depth is the valve opening pressure


desired and can be found by: The valve opening pressure at depth can then be calculated using
equation (2).

Pvo = Pcsg = 1981psi (13.66 MPa)


Using a rearrangement of equation (I), replacing Pcsg with Pvo.
The dome pressure at valve depth and temperature can be found the surface pressure required to open the valve under flowing
by: tempemure conditions is:

Pdome - Ptmin*R
Pvo =
1-R
.............(2)
Rearranging terms;
= 1848 psi (12.74 MPa)

This is the minimum casing pressure required to overcome the


temperature affected bellows pressure, and it is below the design
maximum kick-off pressure of 1850 psi (12.76 MPa).

Therefore, the valve TRO set at 1720 psi (11.86 MPa) will
The Non-Ideal Gas Law can be used to determine the dome function under cool kick-off conditions and under a warmer
pressure to be set at 60 OF (30 OC) in the shop; flowing temperature gradient also. If there was not enough
pressure available, the cool kick-off design would have to be
recalculated assuming a lower kick-off gas lift supply pressure.
Table 2 shows the spreadsheet developed to perform the various
TRO calculations for both cool kick-off temperature and flowing
temperature conditions.
Since for the bellows we assume Vl=V2, solve for the dome
pressure at any temperature given another known operating
pressure and associaad temperame at depth; CASE HISTORY

Well 13-28 was squeezed with cement on January 3, 1990 to


reduce water production from a confirmed channel. Following
the squeeze the well was reperforated and a deep gas lift design
installed on February 10, 1990. A schematic of the well is
1934 460t60 *Ieo=1615 psi (11.14 Mh) shown in Figure 2. The well initially produced 1600 BFPD
860 OF= ((4d(l4O)* l . k 8 (254.4 m31d) at a 90% water cut and 800 SCFISTB (511200
~ l m GLR~ ) but by September 1990 the rate had declined to
Then the TRO pressure can be determined from the following approximately 375 BFPD (59.6 m3ld). A production profile and
formula: gas lift survey on September 27, 1990 indicated the gas lift
design was functioning properly with the well lifting from the
orifice in station #12 located at 8910 ft MD (2715.8 m). The
TRO = P me 60 OF.............(6) well's production decline was apparently not related to gas lift
performance.
1720 psi (11.86 m a )
= (1 - 0.0614) = A further decrease in liquid production led to additional trouble
shooting. A liquid level survey in April, 1991 indicated the well
It must then be determined whether the valve designed for kick- was no longer lifting at the orifice. Well tests reported a
wellhead temperature of 53 OF (12 OC). Due to the well's
4 Gas Lift Valve Test Rack 0 ning Design Methodology SPE 24065
for Extreme Kick-off mperature Condition
relatively low flow rate and the cooling effect of permafrost, temperature gradient, there may not be enough kick-off pressure
hydrates readily formed in the well. Methanol injection into the available to open upper valves nor inject gas past them after the
production casing was attempted but failed to mitigate hydrate well has been temporarily shut-in following a long producing
formation. It was postulated that the gas lift valves were interval. Therefore an approach which considers a practical range
improperly sequenced, due to cold well bore temperatures, and of temperatures in the well bore is needed for designing gas lift
that the low production rates were insufficient to warm the upper valves.
valves and allow the well to unload down to the orifice.
Attempts to increase the artificial lift rate through each unloading A new gas lift design methodology has been developed for
valve also failed as hydrates quickly formed. Figure 3 shows the evaluating the temperature conditions each valve will experience
casing and tubing pressure trend for the well while trying to during the unloading process. This enables unloading valves to
"fog" lift gas to the well. The well eventually had to be shut-in effectively kick-off wells under a broader range of well bore
and treated with a hot oil pump down to thaw the hydrates. temperature conditions. The methodology is based on proven
gas lift concepts and has been field tested.
A gas lift survey run on April 17,1991 confirmed that the well
was lifting at the top valve in station #1, located at 2888 ft MD Designing wells with the cool kick-off temperature gradient has
(880.3 m). Extremely cold well bore temperatures were recorded the additional advantage of increasing gas lift performance
with the temperature tool. Figure 4 shows the temperature flexibility. Wells will unload as intended even when the flowing
profiles from the April 1991, and the previous September's gas temperature is lower than expected. In other words, if the
lift surveys. production rates are lower than design assumptions, the well can
be kicked-off with less difficulty after a short shut-in duration.
The April survey indicated the temperature was 37 OF (3 OC) An associated benefit is that gas lift designs are more forgiving
cooler at the top valve than the September survey. The cold well as productivity declines.
bore kick-off temperatures resulted in the top valves remaining
open and the lower bellows valves remaining closed. The The cool kick-off gas lift design methodology should be
reduced flow rate from lifting on the upper valves was unable to implemented for the design of bellows operated, gas lift
raise the well bore temperature enough to encourage the lift point unloading valves in any area where well bore temperatures vary
to sequentially transfer down to the orifice. Table 3 summarizes significantly with well conditions. The methodology can be
the gas lift design in place at the time of these problems. easily incorporated into existing gas lift design procedures.

Theoretical surface opening and closing pressures for the well


bore conditions logged during the September 27, 1990 gas lift
survey with the lift point at the orifice are presented on Table 4.
It also shows the theoretical surface opening and closing BFPD = Barrels of fluid per day
pressures for the April 17, 1991 gas lift survey conditions, Gg = Gas gradient, psi/foot
operating with the lift point at the top unloading valve. The GLR = Gas to liquid ratio, SCFISTB
opening and closing sequence is improper under both flowing GOR = Gas to oil ratio, SCFISTB
conditions. The pressures need to decrease from top to bottom. H = Depth of valve, TVD feet
The sequence is actually reversed under both flowing conditions, MD = Measured depth, ft
meaning the top valves remain open and make it impossible to O.D. = Outer diameter
kick the gas lift down to the orifice without letting the well bore Pcsg = Casing pressure at valve depth, psi
cool down. Pdome = Nitmgen dome charge, psi
Pk0 = Kick-off pressure, psi
Later in April, the top two valves were redesigned to account for Psc = Surface casing pressure required to close valve, psi
the extremely cold well bore temperatures logged during the Pso= Surface casing pressure required to open valve, psi
April, 1991 gas lift survey. The new design is shown in Table
5. The top two unloading valves were replaced by valves with Punin=Design minimum tubing pressure at valve depth, psi
much higher TRO pressures. This raised the closing pressure PVo= Valve opening pressure at valve depth, psi
and allowed lift gas to transfer to the deeper valves. A liquid R = Ratio of port area to bellows area
level survey in May, 1991 confirmed that the well successfully SS = Vertical depth in feet subsea
transferred gas to the orifice. The casing and tubing pressure T = Temperature, O Rankine
trend following installation of the new design is shown in Figure TRO = Test rack opening pressure at 60 OF, psi
5. TVD= True vertical feet
Z = Compressibility factor for nitrogen
apsi = drawdown at perforations, psi
i3P = casing pressure drop taken at unloading valve above, psi

Gas lift designs based on a single temperature gradient are prone


to function improperly in well bores with extreme temperature AUTHORS' NOTE
conditions. Designing solely on the flowing temperature
gradient can lead to upper valves remaining out of sequence under The techniques and/or conclusions are those of the authors and
cool well bore conditions which occur after extended shut-in are not necessarily shared by Prudhoe Bay Working Interest
periods. In wells with designs using the coolest expected Owners.
SPE 24065 D.L. Lagerlef, W.H.Smalstig. M.D. k i n 5

The authors wish to thank the ARC0 Alaska hvdhoe Bay


Operations Engineering group for contributing to the
developmentof the methodology presented.

REFERENCES
1. Winkler, H. W.: "Gas Lift", Petroleum Engineering
Handbook, SPE (1987) Chapter 5 5-23 and 5-26.
2. Winkler, H. W., and Smith, S. S.: "Gas Lift Manual,"
Camco, Inc., Houston, Texas (1962).
3. Brown, K. E.: "The Technology of Artificial Lift Methods,"
Vol. 2a, Petroleum Publishing Co., Tulsa, Oklahoma
(1980) 224 and 233.

4. Jones, D. L.: "How Needed Changes Can Hike Gas Lift Oil
Production," Oil and Gas J. (June 25,1973) 100.
5. Laing, C. M.: "Gas Lift Design Performance Analysis in
the North Hutton Field," J. Pet. Tech. (January. 1991) 97.

6. Teledyne Merla: "Gas Lift Manual," Garland, Texas (1980)


Section 2 pg. 27.
7. Focht, F. T.: "Trouble Shooting Gas Lift Wells," World Oil
(June, 1981) 160.
8. Raggio, I. J., U. S. Patent No. 4,392,532 [patented July 12,
1983, filed Mar. 16, 19811.
9. Hagedom, A. R., and Brown, K. E.: "Experimental Study of
Pressure Gradients Occurring During Continuous Two-phase
Flow in Small-diameter Vertical Conduits," J. Pet. Tech.
(April, 1965) 475-484.

10. Orkiszewski, J.: "Predicting Two-Phase Pressure Drops in


Vertical Pipes," J. Pet. Tech. (June, 1967) 829-838.

11. Shiu, K. C. and Beggs, H. D.: "Predicting Temperatures in


Flowing Oil Wells," J. of Energy Resources T. (March
1980) Trans. ASME.
I Table I. Normal Tem~erature 1
Variation
Statton VnlveDepth Temp
Tm.& aPi
3000 15 OF

Table 2. Gas Lift Valve Design Spreadsheet I


-
Daslgn Engr Valw I N D I Valve Tyw Cornmanv lVdm Sb. 1 PDtl SIzo I bIUPI (IR I Kv I F h l T m d KO Temp
L.(l.rl.f 1 3013 VRSm UcYurry 1 112 In. 114" 20 650 1.53 159.F 140 'F
Wdl 2 4868 VRm McMurry 1 112 in. 14" 40 750 1.55 169'F 157 'F
16-19 3 6765 V R m McMuny 1 112 In. SH6" 208 950 1.56 180.F 175 'F
CddKOPm 4 8326 CAMCO 1 112 In. 112" 10 1100 1.55 189'F 100 'F
1815 PSI 5 8850 102'F 192 'F
WHT
MW 6

Table 3. DS13-28 Old Design Summary


Station Fiowlna TRO
w & EeP ear UEE
I 150 1780 1731 1675
2 172 1750 1716 1686
3 186 1736 1701 1687
5 204 1723 1681 1750
12 21 6 Orifice Orifice Orifice

Table 4. DS 13-28 Calculated Valve Performance


I Warm Cold Cold Cold W a r m Warm

1568 1534 1675 1635 1688


148 1632 1597 1671 1634 1687
196 182 1689 1647 1688 1646 1750
12 21 6 214 Orifice Orifice Orifice Orlfice Orifice

Table 5.
Warm
DS13-28 New Design Summary
Cold Cold Cold Warm Warm I
I'Fn
Dealgn Derlgn Tamp Temp Temp Temp

108 70 1765 1716 1925 1867 1950


Temperature I F)
0 50 100 150 200 250

GLV
for

Figure 1 . T y p i c a l Prudhoe Bay Well


Max A n g l e
2 4 deg.

Figure 2.
7"
s
n w o o .
Sqz P e r f s
Open Perfs

Well Schematic
I

Increase A!L to

Well Shut in.


Hydrated off

-X
s
loo0
Q Valve#l @ ~a1ve#2

Casing Injection
E 800.- Pressure

: s o 0 --
m

400

200

0
a-

-.
4
-
Flowing Wellhead

I .
Pressure

I
0.00 2.00 4.00 6.00 8.00
Time, hrs
Figure 3. 13-28 Pressure Trend (4/9/91)
Temperature ( F)
0 50 100 150 200 250

Figure 4 . 13-28 Temperature Survey Results

1200
Casing Injection Pressure

-.1 0 0 0
.

Y
2
800 1 well operating smoothly with
the lift point at the orifice

400 +
Flowing wellhead pressure
"
200

Daya after 4/29/91 Survey


Figure 5 . 13-28 Pressure Trend with New
Valve Design I n s t a l l e d

You might also like