You are on page 1of 5

2016 Second International Conference On Science Technology Engineering and Management(ICONSTEM)

Relay Coordination for Distribution System

Anupreyaa K Sabari karthiga T C


Power system, Dept. of electrical sciences,
St.Joseph’s college of engineering, St.Joseph’s college of engineering,
Chennai, India. Chennai, India.
preyaaanu@gmail.com

Abstract— In power system protection relay and circuit causing a minimum disturbance to the system. The
breakers is the major instrument for large interconnected protective relay should be able to discriminate between
power system. We need proper protection to isolate the faulted normal, abnormal and fault conditions. The term called
region from healthier network. When two protective apparatus relay coordination covers the concept of discrimination,
installed in series have certain characteristics, which provide a
specified operating sequence, they are said to be coordinated or
selectivity and backup protection. In case of failure of
selective. The objective of protective relay coordination is to primary protection, there should be a backup protection for
achieve selectivity without loosening sensitivity and quick fault which proper relay co-ordination is necessary. Relay
clearance time. Relay coordination is an important aspect in coordination is essential to obtain continuous of system, to
the protection system design as coordination schemes must obtain maximum returns, to provide best service to the
guarantee fast, selective, and reliable relay operation to isolate consumer and earn the most revenue. Absolute freedom
the power system faulted sections. Thus the relay coordination from the failure of the plant cannot be guaranteed, even
problem is formulated, for a real time distribution system is though the risk of failure of the each item may be small; but
simulated using ETAP. the risk factors of such items, if multiplied together go high.
Keywords—plug multiplier setting; time setting; relay
Larger system has more chances for the fault occurrence and
coordination;short circuit analysis. cause disturbances due to the fault.
ETAP performs the numerical calculations with
tremendous in speed, it can automatically applies industry
I. INTRODUCTION
accepted standards, and provides easy to follow output
In modern era, the demand for electrical power reports. ETAP, while capable of handling 1000 buses,
generally is increasing at a faster rate in economically contains a load schedule program which tracks more than
emerging countries. The networks of the electricity 10,000,000 load items, and reports the voltage flow and
companies become most complicated. A Power System short circuit current at the terminals of each load item. The
consists of various electrical components such as Generating 100% of the Top 10 electrical design firms relays on ETAP
units, transformers (Power and Distribution), circuit (ECM Magazine). This capability makes ETAP suitable for
breakers, bus bars, cables, relays, instrument transformers, large industrial facilities, as well as utility systems [1]
transmission lines, isolators, distribution feeders, and This paper proposes a novel method to determine the
various types of loads. optimal settings of the Relays for the distribution network
Moreover faults may occur in any part of power system. To have a proper protection on the distribution side
system such as short circuit or earth fault. Faults may be of even if they are any changes in the power system. And to
the following types-Single Line to Ground, Double Line to develop a relay setting considering future generator
Ground, Line to Line, three phase short circuit etc. This planning scenarios. The relays in the power system are to be
results in the flow of heavy fault current through the system. coordinated properly and to provide the primary as well as
The fault level also depends on the fault impedance which it the backup protection, and at the same time it has to avoid
depends on the location of fault referred from the source mal function in power system.
side. Then to calculate the fault level at various points in the
power system, fault analysis is necessary.
In any power system network, protection should be II. OPERATION OF POWER SYSTEM
designed such that protective relays isolate the faulted Power system protection performs the function of
portion of the network at the earliest, to prevent equipment fault detection and clearing it as soon as possible, and
damage, injury to operators and by that to ensure minimum isolating whenever possible but only the faulted component
system disruption enabling continuity of service to healthy or a minimal set of the components in any other case. Since
portion of the network. The operation of the protection the main protection system may fail (relay fault or breaker
system should be as fast as and the selective i.e. it must fault), protections should act as backup either in the same
isolate only the faulty section in the shortest possible time station or in the neighbouring lines with time delay

337
978-1-5090-1706-5/16/$31.00©2016 IEEE
2016 Second International Conference On Science Technology Engineering and Management(ICONSTEM)

according to the selectivity requirement. The determination Failure in the main protection may be due to any of the
of the time delays for all the backup relays is known as following reasons:
coordination of the protection system. 1) D.C supply to the tripping circuit fails
Coordination of protective relays is mainly 2) Current or voltage supply to the relay fails
necessary to obtain selective tripping in the relays. The first 3) Tripping mechanism of the circuit breaker fails
rule of protective relaying is that the relay should trip for a 4) Circuit breaker fails to operate
fault in its zone. And the second rule is that the relays The Backup protection may be provided either by
should not trip for a fault outside its zone, except to back up the same circuit breakers which will be opened by the main
a failed relay or circuit breaker. To coordinate this backup protection or may use different circuit breakers. Usually,
Protection with the primary relay characteristic will ensure more than the faulty section is isolated when the backup
that the backup relay must have sufficient time delay to protection operates. Mostly the main protection of a circuit
allow the primary relay (and its breaker) to clear the fault. acts as back up protection for the adjacent circuit. The
backup protection is provided where the main protection of
2.2 Working of Power System the adjacent circuit fails to back up the given circuit. For the
In Normal Condition the power is generated by generator, simplification, back up protection can have the lower
acting as a source. This voltage is stepped-up with the help sensitivity factor and be operative over a limited back up
of step-up transformer up or higher to reduce transmission zone i.e. be operative only for the part of the protected
losses. Then that power is transmitted over the transmission circuit. Relay coordination is done by doing load flow
lines. Again the voltage is stepped down to a level, as it is analysis, short circuit analysis and CT analysis. CT’s are
desired by the loads, with the help of step-down selected according to the full load amper.
transformer. In Abnormal Condition or fault is nothing but a
defect in electrical circuit of the electrical equipment due to
which current is diverted from intended path. If the fault III. SHORT CIRCUIT ANALYSIS
impedance is low, then the fault currents are relatively high. In short circuit analysis we consider three phase
During the time of faults, the power flow is diverted towards short circuit as it is the most severe fault amongst all the
the fault and so the supply to the neighboring zone is faults. We are going to assume three phase short circuit on
affected. Therefore to isolate the faulty section from the various locations from 11kV to 415V level it is shown in
healthy part and by this we can maintain the continuity of Fig.1.and the impedances of certain generators,
supply, circuit breakers are employed in power system. transformers, cables and motors are contributing to the
change in fault level at different locations.
2.3 Need for Protection of Power System
The Modern power systems are growing with more 3.1 Formulae of Short Circuit Analysis
equipments such as generators, transformers and large
network in the systems. For the system protection, a high base MVA
degree of reliability is required. In order to protect the Z pu = % Z ×
system from damage, due to fault currents and/or abnormal transformer rating
voltages caused by the faults, needed for reliable protective base MVA
devices, such as relays and circuit breakers arises. The most Fault MVA =
common electrical hazard is the short circuit for which Z pu
protection is needed. Also the protection is required against
Fault MVA
the overloads, over-voltage, under-voltage, open-phase, Fault current =
power swings, under and over-frequency, instability etc. 3 × voltage
2.4 Primary and Back-up Protection For relay coordination
For attaining higher reliability, quick action and voltage between healthy and fault phase
improvements in the operating flexibility of the protection FPC =
schemes, and separate the elements of a power system, in normal phase voltage
addition to main or primary protection, are provided with a desired pick _ up current
back-up and auxiliary protection. First in line of defense is plug setting =
the main protection which ensures quick action and it is CTR
selectively clearing of faults within the boundary of the primary operation current = CTR × ps
circuit section or the element it protects. Main protection is
the essential one it is provided as a rule. Back up protection FI
plug setting multiplier =
which provides back up to the main protection, and when actual POC
the main protection fails to operate or is cut out for repairs
etc. Were FCL = First pole clear
POC = primary operation current

338
978-1-5090-1706-5/16/$31.00©2016 IEEE
2016 Second International Conference On Science Technology Engineering and Management(ICONSTEM)

CTR = current transformer ratio


ps = plug setting

Fig.2. Short Circuit Analysis Report


IV. RELAY COORDINATION
Relay co-ordination plays an important role
in the protection of power system. For the proper
protection, we must have proper co-ordination of
relays with appropriate relay setting is to be done.
Relay settings is done in such a way that the proper co-
ordination is achieved along various series network.
Coordination of relays in a modern power system is a
challenging task for the protection engineers. However the
review of Co-ordination is always essential since various
Fig.1. Online Diagram of Short Circuit Analysis additions / deletion of feeders and equipments will occur
after the initial commissioning of plants. As the power can
be received from the generators of captive power plant, the
analysis becomes complex. Lager the systems, more will be
the chances of the fault occurrence and disturbances due to
the fault.
Stages for fault clearance:
1) Occurrence of fault
2) Measurement by instrument transformer
3) Analysis by protection relay for initiating selective
tripping
4) Switchgear to clear the fault
5) Relays are installed not to prevent the faults but to isolate
the faults and to minimize the damage.
Relay co-ordination it can be done by selecting a
proper plug setting and the time multiplication setting of the
relay, considering maximum fault current at the relay
locations. After the selection of plug setting and time
multiplier setting, the co-ordination can be checked
graphically. When plotting co-ordination curves, certain
time intervals must be maintained between the curves of the
various protective device in order to ensure the correct

339
978-1-5090-1706-5/16/$31.00©2016 IEEE
2016 Second International Conference On Science Technology Engineering and Management(ICONSTEM)

sequential operation of the device when co-coordinating


inverse time over current relays. For a given fault current,
the operating time of relay is jointly determined by its plug
and time multiplier settings. Thus theses type of relay which
is mostly suitable for proper coordination. Operating
characteristics of this relay are usually given in the form of a
curve with the operating current of plug setting multiplier
along the X axis and operating time along Y axis during
representation.
Calculation of the relay operating time:
To calculate the actual relay operating time, the following
parameters is needed
1) Time / PSM Curve
2) Plug Setting
3) Time Setting
4) Fault Current
5) Current Transformer Ratio Fig.3. Sequences of Operation of the Relay and Circuit
The process for calculating the actual relay operating time is Breaker
as the follows:
1) Convert the fault current into the relay coil current by
using the current transformer ratio.
2) Express the relay current as a multiple of current setting,
i.e. calculate the PSM
3) From the Time/PSM curve of the relay, with the
calculated PSM the corresponding time of operation can be
obtained.
4) Determine the actual time of operation by multiplying the
above time of the relay by time-setting multiplier in use.

V. RESULTS AND DISCUSSION


Fig.4. Relay Operating Time
Let us consider a real time system which is consisting of
more than 30 bus systems for relay coordination using
ETAP software. In ETAP we have to design the circuit by
calculation for certain values in the system and some will be
taken from the IEC standards. In the designed system we
need to run the following analysis for relay coordination.
They are
1) Load flow analysis
2) Short circuit analysis
3) CT Selection
4) Relay coordination
By this we can have proper sequential operation of the relay
by this we can isolate the fault position for the healthier
network.

Fig.5. Relay Coordination

VI. CONCLUSION
The fault current it is inversely proportional to the fault
impedance up to the location of fault and the voltage level.
In low voltage side of distribution transformers the voltage
level is significantly lower than high voltage side as the

340
978-1-5090-1706-5/16/$31.00©2016 IEEE
2016 Second International Conference On Science Technology Engineering and Management(ICONSTEM)

transformation ratio is high. The effect of low voltage level


is more than the effect of increase in fault impedance which
causes the fault level to rise. We can coordinate the relay by
injecting fault at various bus of the system. Even though the
fault level is maximum that fault will be cleared without any
damage. The relays (phase and earth fault) are the major
protection devices in distribution system. The relay
coordination in radial network is highly constrained
optimization problem. The relays in the power system are to
be coordinated properly so as to provide primary protection
as well as back up protection, and the same time avoid mal
function and hence avoid the unnecessary outage of healthy
part of system.

VII. REFERENCES
[1] Hima a. Patel, vaibhav m. Sharma, anuradha
deshpande “relay coordination using etap”
international journal of scientific &engineering
research, volume 6, issue 5, may-2015.
[2] H.h.zeineldin, y.r.mohamed, v.khadkikar, and
v.pandi, “a protection coordination index for
evaluation distributed generation impacts on
protection for meshed distribution systems,” ieee
trans.smart grid,[1] vol.4, no.3, pp. 1523-1532,
sep:2013.
[3] Dharmendra Kumar Singh, Dr. S. Gupta
“Protection Of Power System By Optimal Co-
ordination of Directional Overcurrent Relays Using
Genetic Algorithm” International Journal of
Modern Engineering Research (IJMER) Vol. 2,
Issue.1, pp. 326-331, Jan-Feb 2012.

341
978-1-5090-1706-5/16/$31.00©2016 IEEE

You might also like