Professional Documents
Culture Documents
https://doi.org/10.1007/s40098-019-00391-5
ORIGINAL PAPER
Abstract Geosynthetics technology has been applied in Keywords Preloading Prefabricated vertical drain
Indonesia as early as 1983 where a high strength geotextile Vacuum preloading Geosynthetic-reinforced soils
of 200 kN/m was laid to help stabilize the highway built on
swampy land toward Jakarta International Airport. Since
then, geosynthetics have been gaining popularity in solving Introduction
various geotechnical problems, e.g., slope stabilization,
construction of retaining walls, acceleration of consolida- Indonesia, a country with over ten thousand islands, has
tion, lining of ponds, construction of breakwaters and shore various difficult ground conditions, such as soft clay, peats,
protection works, etc. Six case histories on the application expansive soils, loose sands, highly weathered and frag-
of geosynthetics technology are presented in this paper. mented rocks, and clay shales. Figure 1 shows the distri-
Three case histories on the application of prefabricated bution of soft ground in Indonesia. In addition to the
vertical drain with vacuum preloading to accelerate con- problematic soil conditions, the country is also located on
solidation process of very soft clay are discussed. The first the ring of fire, an area with high seismicity (Fig. 2),
case is a vacuum preloading on lowland area, just a few km making Indonesia prone to earthquake-induced geotechni-
from seashore. The second case was vacuum preloading on cal hazards such as liquefaction, slope failures and lateral
high ground of about 700 m from sea level. The third case spreading on loose sandy ground.
was vacuum preloading combined with surcharging. To mitigate all the potential geotechnical hazards arises
Another three case histories discussed the application of from the problematic soils as well as the problem of high
geosynthetic-reinforced soils in slope stabilization where, seismicity, many ground improvement techniques and
instead of granular material, cohesive materials were uti- geosynthetics technology have been implemented, e.g.,
lized as backfill. The first was its application for river dynamic and vibro-compaction [4–10], conventional
embankment stabilization. The second was a back-to-back preloading in combination with prefabricated vertical drain
13-m-high reinforced soil to support a railway on top of it. [11–13], and geosynthetic-reinforced soils [14–18].
The third was a 25–37 m high retaining structure devel- In the last 3 years, in line with the government initia-
oped on a problematic clay shale for a runway support. tives to provide better housing and infrastructures for
Despite the difficulties encountered, each of the projects peoples: housing, power plants, highways, railways, sea-
was finally executed safely and successfully. ports, and airports are being built. Many of those facilities
had to be built over swampy lands or soft clay soil regions
requiring consolidation acceleration. Owing to its faster
construction time as compared to conventional preloading
& Tjie-Liong Gouw
gtloffice@gmail.com
system with PVD, vacuum preloading techniques had been
applied. Some of the railways and airports had to be built
1
Department of Civil Engineering, Universitas Katolik over a hilly terrain requiring slope stabilization; in many of
Parahyangan, Bandung, Indonesia these cases geosynthetic-reinforced soils had been chosen
2
Jakarta, Indonesia to stabilize high man-made slopes.
123
Indian Geotech J
123
Indian Geotech J
This paper presents three case histories on the applica- Basically, vacuum pressure within the soil body is cre-
tion of vacuum preloading and another three case histories ated by pumping through an interconnected network of
on the application of geosynthetics in stabilizing high man- prefabricated vertical drain (PVD), horizontal filter pipes
made slopes. and sand blanket, forming a complete path for spreading
the vacuum pressure and facilitating water flow. To be
effective, an airtight isolation system is required to prevent
Case Histories on Vacuum Preloading leakage of water and air below it. The system consists of
geomembrane, and the soft clay itself. Figure 4 shows the
Vacuum preloading method utilized atmospheric pressure whole configuration of the vacuum network. When there
as surcharge load to accelerate soil consolidation. Its are sand lenses, vertical slurry wall may be required to cut
principle is presented in Fig. 3. Atmospheric pressure will off the continuous sand lenses or else the vacuum may not
pressurize the soft soils when vacuum is imposed within work.
the soil body.
123
Indian Geotech J
123
Indian Geotech J
Fig. 7 a Installation of PVD and horizontal drains, b installation of airtight system, c anchoring geomembrane along the perimeter, d starting the
vacuum pump, e the vacuum gauges
123
Indian Geotech J
123
Indian Geotech J
Fig. 10 Post-vacuum—
trenches were excavated with
ease (courtesy of PT.
Geotekindo)
water pressure decreases. The drop in vacuum pressure can experiencing progressive failures due to erosive actions of
be calculated as follows: The first backfill added was 0.6 m the river and heavy rainfalls which were saturating the
high, a pressure of around 0.6 m 9 18 kN/m3 & 11 kPa; reddish clay of the riverbank (Fig. 16). The project team
hence, it will reduce the vacuum pressure by around requires an environmentally friendly and cost-effective
11 kPa. Looking at the vacuum pressure chart, it can be retaining structure to stabilize the riverbank and henceforth
seen that the pressure was reduced from 80 to 69 kPa. The guarantee safe access to the residential area and safeguard
pore water pressure readings from different depth also the housing complex on the other side of the access road.
increased by about the same values. Therefore, it is a The first stage of the project involved 200 m of pro-
normal phenomenon and it shall have positive effects in tection between road station 1 ? 680 and 1 ? 480. The
accelerating the consolidation process. At the time of the total length of the access road is approximately 2 km. The
writing of this manuscript, the vacuum process is still most challenging aspects of the project were: the presence
ongoing. of the river flowing at the toe of the riverbank, the necessity
to build a steep retaining structure due to the lack of space
and the constraint set by the client to use residual soil as
Case Histories on Geosynthetic-Reinforced Soil filling structural material due to limited budget.
Structures Typical soil stratigraphy along the riverbank is shown in
Fig. 17. The upper part of the soil is a medium–high
Ever since geosynthetic technology was introduced in 1983 plasticity reddish clay soil (PI = 40–60%), followed by
to stabilize basal slope failure of the highway embankment medium to very dense sand. The reddish clay layer is a
toward Jakarta International Airport, geosynthetic-rein- residual soil derived from volcanic material, and it is
forced soils have been gaining popularity to replace the commonly found in Indonesia, especially in Java island. It
conventional gravity and cantilever retaining wall. Some of is locally known as tanah merah which literally means red
its applications are presented below. clay. Thanks to the presence of halloysite nanotubes in its
molecular structure instead of the normal plate-shaped
Citra Gran Cibubur Access Road structure of illite and montmorillonite, this tanah merah
has fairly good mechanical properties when properly
The Citra Gran Cibubur is a large-scale luxury residential compacted; therefore, it is often used as reinforced soil
development located to the south of Jakarta. The project backfill material. However, it is important to note that not
access road that runs along the Cikeas river was all the reddish and brown color soils can be classified as
123
Indian Geotech J
tanah merah; thus, the good mechanical properties of tanah Atterberg limits plays a key role in the assessment of the
merah cannot be assigned to other widely present clays suitability of a clay as fill for reinforced soil structures and
such as alluvial clays or highly expansive clays. in the assessment of whether the soil can be classified as
Figure 18 illustrates the typical Atterberg limits for a tanah merah or not.
number of clays, where red clay (halloysite) is tanah The proposed solution was a 3.5-m-high gabion wall to
merah. The determination of index properties and protect the riverbank against erosion with rock mattresses
123
Indian Geotech J
123
Indian Geotech J
123
Indian Geotech J
123
Indian Geotech J
Compared to RC retaining walls, MSE walls can tolerate the precast panels and unsightly face panel separation.
larger total and differential deformation. However, the Therefore, for the area where 6–13-m-high embankment
amount of total and differential deformation that can be has to be built, flexible welded wire gabion facings com-
tolerated by an MSE structure depends on the wall facing bined with the geogrids reinforcement (known as Ter-
material, configuration, and timing of facing construction. ramesh system) as shown in Fig. 26 are adopted. The
An MSE wall with precast concrete panels facing cannot tensile element used in this project is high strength
tolerate as much deformation as welded or double-twisted polyester geogrids coated with LLDPE for the best long-
wire mesh gabion facing because of its potential damage to term performances and has an ultimate tensile strength
123
Indian Geotech J
equal to 300 kN/m (Paralink 300). The geogrids are laid overall and the internal stability of the structure, thanks to
continuously from one side of the embankment to the other the high tensile forces developed when they are intercepted
side with no mechanical or frictional joints. The geogrids by a potential slip surface, whereas the wire mesh units,
vertical spacings are 1 m, and the maximum width of the which are produced with a ‘‘tail’’ of double-twisted wire
embankment body is 16 m at the base. mesh, are considered a secondary reinforcement and act as
This type of MSE structure is also known as hybrid fascia providing the local stability at the facing, ensuring
MSE structure since it combines metallic and polymeric that no local mechanism of direct sliding, pull-out or
reinforcements. Both of the components act as reinforce- rotational failure can occur. The steel wire mesh facing
ments and as stabilizing elements. Geogrids are considered units can provide the structure with a stone facing reaching
to work as primary reinforcements since they guarantee the inclination to the horizontal up to almost 90. The stability
123
Indian Geotech J
123
Indian Geotech J
technically reliable and economically feasible retaining of 500 years, and the presence of clay shale foundation
structures have to be built. soils which easily lose its strength when exposed to
The first stage of the Tana Toraja runway construction atmosphere.
was undertaken in 2015. It involved the design and the Clay shale is a fine-grained sedimentary rock formed by
execution of a 100-m-long and 15-m-high retaining struc- clays hardened due to long-term pressure deep in the
ture as runway support. The retaining structure had to be ground. Over time geological events brought the clay shale
erected in between two hills. Afterward, during a second formation to near-surface. These clay shales, when dry and
later stage, the retaining structure will be topped with an undisturbed, are hard and show high shear strength. How-
additional 10-m-high structure in order to reach the final ever, when unloaded and exposed to the atmosphere, they
runway elevation. The total height of the mentioned easily degrade and dramatically lose their shear strength.
structure will be 25 m. The main technical issues related to Gartung [22] reported unweathered clay shale can have an
the design and the execution of this works were: the high effective cohesion as high as 85 kPa with internal friction
seismicity of the area with PGA = 0.3 g for a return period angle of 41. However, when exposed to atmosphere, it
123
Indian Geotech J
123
Indian Geotech J
123
Indian Geotech J
• Construction schedule: the structure shall be con- Based on all the above criteria, hybrid reinforced soil
structed in 2-month time; slope (RSS) combining anchored gabion units and geogrids
• Overall cost; is selected as the best suitable solution. The main compo-
• Local manpower: the construction method shall max- nents of the proposed hybrid RSS are illustrated in Fig. 37.
imize the employment of locally available unskilled The first stage retaining structure construction height is
manpower. equal to 15 m, but it has to be designed for a final target
123
Indian Geotech J
123
Indian Geotech J
Concluding Remarks
123
Indian Geotech J
123
Indian Geotech J
123
Indian Geotech J
123
Indian Geotech J
Acknowledgements The author would like to thank PT. Geotekindo, 11. Gouw TL (1992) Satisfactory performance of monolithic vertical
PT. Geosystem Teknindo Unggul, and PT. Maccaferri Indonesia for drain. In: International symposium on the applications of
giving permission in using the project data to write this paper. geosynthetic technology, Jakarta
12. Gouw TL (1995) Precompression by synthetic vertical drains.
Indonesian. Indones Geotech J I(01):43–64
13. Gouw TL (2014) A proposed Indonesian standard for design,
References execution, and installation of soft ground improvement by use of
prefabricated vertical drain. In: International conference on soft
1. Cox JB (1970) The distribution and formation of recent sediments soils 2014, Universitas Katolik Parahyangan dan Universiti Tun
in South East Asia. In: Proceeding 2nd South Asia conference on Hussein Onn Malaysia, Bandung
soil engineering, pp 30–47 14. Gouw TL (1990) Creep factor in the selection of geosynthetics
2. Indonesian Public Work Department (2002) Geoguide. Departe- for Earth reinforcement, in Indonesian. In: 4th Indonesian con-
men Pekerjaan Umum, Jakarta ference on geotechnical engineering, Bandung
3. Irsyam M (2012) Geotechnical engineering lecture notes. Institut 15. Gouw TL (1990) The application of geosynthetics in accelerating
Teknologi Bandung, Indonesia the construction of road embankment, in Indonesian. In: Seminar
4. Gouw TL (1989) Deep compaction for ground improvement and on reinforced embankments-theory and practice, Jakarta
for reduction of liquefaction potential in Sumatra, Indonesia, 16. Gouw TL, Lelli M, Meinata LE, Laneri R, Cerro M, Rimoldi P
M.Eng. Thesis, Asian Institute of Technology (AIT), Bangkok (2016) High hybrid reinforced soil slope as runway support—
5. Gouw TL (1990) Dynamic compaction for reducing earthquake Tana Toraja airport case study. In: 6th Asian regional conference
induced soil liquefaction, in Indonesian. In: 4th Indonesian con- on geosynthetics, November 8–11, 2016, New Delhi
ference on geotechnical engineering, Bandung 17. Lelli M, Gouw TL, Laneri R, Cerro M, Meinata LE (2016)
6. Gouw TL (1990) Vibro-compaction, some examples on the Design of Earth structures reinforced with polymeric and metallic
construction difficulties. In: 2nd short course and seminar on reinforcements using limit equilibrium methods. In: Indonesian
ground improvement—mechanically stabilized Earth and Its geosynthetics conference 2016, Indonesian chapter of Interna-
application, Jakarta tional Geosynthetics Society, Jakarta
7. Gouw TL (1991) Dynamic compaction on coraline soil. In: 9th 18. Lelli M, Gouw TL, Laneri R (2017) The important role of exe-
Asian regional conference on soil mechanics and foundation cution and CQA/CQC plans in building with geosynthetics. In:
engineering, Bangkok Geosintetik Indonesia 2017 seminar on quality in construction
8. Gouw TL (1997) Soil improvement on reclaimed lands—the using geosynthetics, by Indonesian chapter of International
indonesian experiences. In: 30th year anniversary symposium of Geosynthetics Society, Century Hotel, Jakarta
the Southeast Asian Geotechnical Society. Deep excavations, 19. Gouw TL, Liu Y (2013) Vacuum preloading for a power plant
ground improvements and tunneling, Bangkok, Thailand project in Southern Vietnam. In: 18th South East Asian
9. Gouw TL, Irsyam M, Gunawan A (2013) The application of geotechnical conference, Singapore
ground improvement techniques in Indonesia. In: 18th Southeast 20. Masse F, Spaulding CA, Wong PIC, Varaksin S (2011) Vacuum
Asian geotechnical conference, Singapore consolidation: a review of 12 years of successful development.
10. Gouw TL (2017) Proposed design guideline of dynamic com- Geo-Odyssey, ASCE/Virginia Tech, Blacksburg
paction for practicing engineers. In: 50th Anniversary celebration 21. Dobie M (2017) Considerations in the design and construction of
of the Southeast Asian Geotechnical Society, Asian Institute reinforced soil structures using clay fills with special reference to
Technology, Bangkok Indonesia. In: Proceeding geosintetik Indonesia 2017, INA-IGS,
Jakarta
123
Indian Geotech J
22. Gartung E (1986) Excavation in hard clays of the Keuper for- Publisher’s Note Springer Nature remains neutral with regard to
mation. In: Proceeding of symposium on geotechnical engineer- jurisdictional claims in published maps and institutional affiliations.
ing, Seattle, Washington
123