Catchup Plan
Catchup Plan
we have already 8% accomplishment. These are the list that we’re targeting for the next 3 weeks.
For this activities we need to accomplish 9m for the box culvert complete sidings and slabs
included the excavation, 8m for the top slab of already concreted part and the installation of steel
gratings. We can’t move on the phase 2 because we don’t still have the permit from the DPWH .