For the next monthly planned accomplishment we’re needing of 35% to be accomplish for now

we have already 8% accomplishment. These are the list that we’re targeting for the next 3 weeks.

Activity Current Target % Difference


Concretingworks 17.13% 24.63% 7.5%
Reinforcement 5.78% 8.08% 2.3%
Reinforcement 10.01% 22.37% 6.39%
Repair of Inside property 0% 3.91% 3.91%
Steel Grating 0% 0.3% .3%
Excavation 1.9% 2.24% .34%
Access Lader .19% 0.23% .04%
Temporary 7.15% 7.21% .06%
Safety 4.09% 5.26% 1.17%
TOTAL 22.01%

For this activities we need to accomplish 9m for the box culvert complete sidings and slabs
included the excavation, 8m for the top slab of already concreted part and the installation of steel
gratings. We can’t move on the phase 2 because we don’t still have the permit from the DPWH .