Scope of Services
Collect data on existing conditions
Develop a Concept of Operations
ITS device build-out
Identify needs
• Evaluate alternatives
Traffic signal timing pilot
• Training for traffic signal technicians
• Develop ITS Master Plan
• Recommend projects for CIP
• Develop City Standards
Concept Of Operations
Defines in Concept
what the future ITS
will look like.
Goals of the Project
Beckham Avenue
Significant Improvements
Beckham:
Gentry to 5th
Broadway:
LP 323 to Chimney Rock/
Donnybrook
Loop 323
Loop 323:
Broadway to Old Bullard
Beckham Corridor
Example: Beckham, Northbound
Before
After
AM MD PM
17% 21% 15%
Beckham Corridor
Example: Beckham, Southbound
Before
After
AM MD PM
24% 23% 26%
Benefits of Optimizing
Traffic Signals
Corridor Beckham Broadway Loop 323
Reduction in
19% 17% 16%
Travel Time
Annual Cost
$5.7 $6.0 $3.4
Savings in Delay
Detector Type
Fixed Time 5 4% Good detection.
Loops 15 11% Look to upgrade
Radar 8 6% older
Video 103 75%
installations
None 6 4%